CN110792009A - Bridge head bump prevention and control structure based on concrete composite pavement and laying method thereof - Google Patents

Bridge head bump prevention and control structure based on concrete composite pavement and laying method thereof Download PDF

Info

Publication number
CN110792009A
CN110792009A CN201910988772.3A CN201910988772A CN110792009A CN 110792009 A CN110792009 A CN 110792009A CN 201910988772 A CN201910988772 A CN 201910988772A CN 110792009 A CN110792009 A CN 110792009A
Authority
CN
China
Prior art keywords
bridge
bridge head
pavement
filling
abutment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910988772.3A
Other languages
Chinese (zh)
Inventor
周萍儿
龚微
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Longde Construction Co Ltd
Original Assignee
Longde Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Longde Construction Co Ltd filed Critical Longde Construction Co Ltd
Priority to CN201910988772.3A priority Critical patent/CN110792009A/en
Publication of CN110792009A publication Critical patent/CN110792009A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01CCONSTRUCTION OF, OR SURFACES FOR, ROADS, SPORTS GROUNDS, OR THE LIKE; MACHINES OR AUXILIARY TOOLS FOR CONSTRUCTION OR REPAIR
    • E01C3/00Foundations for pavings
    • E01C3/04Foundations produced by soil stabilisation
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/08Damp-proof or other insulating layers; Drainage arrangements or devices ; Bridge deck surfacings
    • E01D19/083Waterproofing of bridge decks; Other insulations for bridges, e.g. thermal ; Bridge deck surfacings

Abstract

The invention discloses a structure for preventing and controlling vehicle bump at the bridge head based on a concrete composite pavement and a laying method thereof. The settlement difference value of the two ends of the bridge head is larger, so that the processing engineering amount is reduced, asphalt concrete bridge pavement with a certain thickness can be milled and planed, the processing thickness is reduced, the number of transverse joints is reduced, and the pavement evenness and straightness are improved.

Description

Bridge head bump prevention and control structure based on concrete composite pavement and laying method thereof
Technical Field
The invention relates to the field of road construction, in particular to a bridge head bump prevention structure based on a concrete composite pavement and a laying method thereof.
Background
At present, the construction of the highest-grade roads in China is in an important development stage with the same quality and quantity, adverse effects of position difference settlement on road surface structure of bridge head skip, high filling and emptying sections, filling and excavating joint parts and the like due to local conditions cause increasing attention of departments of road construction, design, supervision, construction and the like, the driving mechanism of automobiles at the bridge head is very complex, and the influence degrees of different access plate lengths, different yield values and different vehicle speeds of different models are different.
The main reason for the bump at the bridge head is the subsidence caused by poor soil quality. Bridges and culverts are usually positioned in gullies, the underground water level is high, the natural water content of the soil is greater than a limit value, the natural pores are large, the soil often contains organic substances, the compressibility is high, the shear strength is low, once disturbed, the natural structure is easy to damage, the strength is obviously reduced, the filling height of the bridge head roadbed is large, the generated foundation stress is relatively large, the foundation settlement is easy to cause under the action of vehicle load, and the deformation stability lasts for years or even longer. The problem can not be avoided even under the action of external load on some stable foundations.
Disclosure of Invention
The invention aims to provide a bridge head bump prevention structure based on a concrete composite road surface and a laying method thereof.
The technical purpose of the invention is realized by the following technical scheme:
the utility model provides a bridgehead prevention and cure structure of jumping of car and laying method thereof based on concrete combined type road surface, its characterized in that, including milling the bridgehead road surface, add and spread asphalt concrete and eliminate the settlement difference, mill and carry out ground reinforcement processing after the bridgehead road surface, carry out the bridge back of the body at the junction of bridge floor and ground and adopt conventional filler, the platform back of the body is backfilled including the layering and is backfilled and experimental detection, set up the changeover portion at the bridgehead after ground reinforcement, mill and mill the bridgehead road surface and adopt the measurement lofting earlier, use "dot matrix" to arrange the elevation measurement point, the bridge structure arrangement point that has telescoping device should not be less than 50m from the telescoping device, the bridge that does not have the telescoping device is counted from the seam, the bridge of no expansion joint.
By adopting the technical scheme, although the settlement difference value of the two ends of the bridge head is larger, in order to reduce the processing work amount, the asphalt concrete bridge deck pavement with a certain thickness can be milled and planed, the processing thickness is reduced, the number of transverse joints is reduced, and the pavement evenness and the straightness are improved.
Preferably, the milled bridge head pavement is subjected to seam processing, the dislocation between the upper layer and the lower layer of the longitudinal seam is at least 200m, the dislocation between the lower layer and the longitudinal seam is at least 1m, and the dislocation between the adjacent layers is at least 1 m.
By adopting the technical scheme, the joint processing is carried out after the bridge head pavement is milled and milled, the two steps are staggered, the height difference at the later stage is increased, the adjustment is convenient, and meanwhile, a certain space is reserved for the adjustment at the later stage.
Preferably, before the abutment back is backfilled, scale marks are marked on the rear part of the abutment according to a layer of every 15cm, layered filling is carried out from the lowest part during backfilling, the layers are compacted layer by layer, the surface of each layer is flat, a road arch corresponding to a roadbed is formed, when the backfilling height of the abutment back of the abutment is more than 5m, in order to reduce uneven settlement, a layer of bidirectional geogrid is additionally arranged on the original ground and the top of the abutment back respectively, the geogrid is paved in a direction perpendicular to a route, the lap joint width is not less than 2O cm, and four corners are firmly fixed.
Adopt above-mentioned technical scheme, through the compaction of layering to increase the compactness between every layer, thereby increase the compressive strength of whole coating, cooperation building grid, thereby avoid the coating pressurized to remove towards both sides, the compressed effect of further whole dirt bed of increase also can avoid the soil layer pressurized to take place to remove.
Preferably, the rolling is preferably performed by stabilizing the pressure by using a vibratory roller, then performing low vibration for 2 times, and finally performing static pressure until the design requirement is met, a safe distance of 0.5m is reserved near the abutment during rolling, a small-sized tamping machine is adopted for tamping within the safe distance, and the aim of preventing any possible damage to the structure is fulfilled until the degree of compaction meets the design requirement.
By adopting the technical scheme, the strength of the whole soil layer is increased by double tamping and matching with a vibratory roller, and meanwhile, the safety distance of 0.5m is kept, so that the damage to peripheral objects and people during construction is avoided, and the safety of the whole operation is improved.
Preferably, the test detection is carried out according to layered filling, layered rolling and layered detection, filling is controlled not to exceed 4 layers every day, the compaction degree is detected according to the frequency of one point every 50m, at least one point is detected when the thickness is less than 50m, the compaction degree standard is more than 96% or the settlement difference is within 2mm, the construction procedure is strictly controlled, the previous procedure is unqualified, and the next procedure is strictly forbidden for construction.
Adopt above-mentioned technical scheme, be superior to earth at the first pressure-bearing after, need go to know the actual pressurized condition of earth through stewing to avoid carrying out the detection when exerting pressure once, the experimental data deviation can appear, thereby avoid the later stage to be superior to experimental data and cheat the problem that leads to and appear, through setting up a plurality of check points, make the stricter of whole data more afterwards.
Preferably, the concrete anisotropic precast block is paved on the surface layer of the transition section, the length of which is 10-50cm, of the transition section.
Adopt above-mentioned technical scheme, add transition section for the junction between bridge floor and the ground can slow down the difference in height between the two, thereby makes the height on whole bridge floor press close to the height on ground more.
Preferably, graded broken stones or gravel are adopted for a certain thickness of the filling in the filling process.
By adopting the technical scheme, through the structural characteristics of the material, the whole sedimentation can be completed in a short time, and the material has no capillary water effect, can prevent water and accelerate water drainage, thereby achieving the effect of preventing sedimentation.
Detailed Description
The following description is only a preferred embodiment of the present invention, and the protection scope is not limited to the embodiment, and any technical solution that falls under the idea of the present invention should fall within the protection scope of the present invention. It should also be noted that modifications and embellishments within the scope of the invention may occur to those skilled in the art without departing from the principle of the invention.
As shown above, the structure for preventing and controlling the bumping at the bridge head based on the concrete composite pavement and the paving method thereof are characterized by comprising the steps of milling the bridge head pavement, firstly adopting measurement lofting for milling the bridge head pavement, using a dot matrix to arrange elevation measurement points, arranging the points of a bridge and culvert structure with a telescopic device to be not less than 50m from the telescopic device, calculating the bridge and culvert without the telescopic device from a joint, paving a bridge without an expansion joint, adding asphalt concrete to eliminate settlement difference, performing joint processing on the milled bridge head pavement, wherein on a longitudinal joint, the dislocation between lower layers is at least 200m, the horizontal joint is at least 1m, and the dislocation between adjacent layers is at least 1 m.
As shown above, the foundation reinforcement treatment is carried out after the pavement of the bridge head is milled, then the conventional filling is adopted for the bridge back at the joint of the bridge deck and the ground, graded broken stones or gravels are adopted for filling with a certain thickness in the filling process, the layered filling is carried out from the lowest position when the back of the abutment is backfilled according to the scale mark of every 15cm layer at the back of the abutment before the abutment backfilling, the layer-by-layer compaction is carried out on each layer, the surface of each layer is flat, a road arch corresponding to the roadbed is formed, when the backfill height of the abutment back of the bridge is more than 5m, a layer of bidirectional geogrid is respectively additionally arranged on the original ground and the top of the abutment for reducing the uneven settlement, the geogrid is paved in the direction vertical to the route, the lap joint width is not less than 2O cm, the four corners are firmly fixed, the road roller compaction is preferably carried out by adopting a vibration machine for firstly stabilizing the pressure, then for 2, tamping is carried out within a safe distance using a small tamping machine, and care is taken to prevent any possible damage to the structure until the degree of compaction meets the design requirements.
As shown above, the abutment back filling comprises layered filling and test detection, the test detection is constructed according to layered filling, layered rolling and layered detection, the filling of every day is controlled not to exceed 4 layers, the compactness is detected according to the frequency of one point per 50m, at least one point is detected when the compactness is less than 50m2, the compactness standard is more than 96% or the settlement difference is within 2mm, the construction procedure is strictly controlled, the upper procedure is unqualified, the construction of the lower procedure is strictly forbidden, the abutment back construction is carried out firstly, the abutment back filling is timely, the abutment back filling construction, the cone and the slope protection are preferably carried out synchronously, the cone and slope protection cracking damage caused by uneven settlement is avoided as much as possible, and the heavy machinery is fully utilized to roll compactly.
As shown in the above, after the foundation is reinforced, a transition section is arranged at the bridge head, and a concrete anisotropic precast block is paved on the surface layer of the transition section with the length of 10-50 cm.

Claims (8)

1. The structure is characterized by comprising the steps of milling a bridge head pavement, paving asphalt concrete to eliminate settlement difference, carrying out foundation reinforcement treatment after the bridge head pavement is milled, carrying out bridge back filling at the joint of a bridge floor and the ground by adopting conventional filling materials, wherein the step of back filling comprises layered backfilling and test detection, and a transition section is arranged at the bridge head after the foundation reinforcement.
2. The structure for preventing and treating bump at bridge head based on concrete composite pavement as claimed in claim 1 and the laying method thereof are characterized in that the milled bridge head pavement is firstly subjected to measurement lofting, the elevation measurement points are arranged in a dot matrix manner, the arrangement of the bridge and culvert structure with the telescopic device is not less than 50m from the telescopic device, and the bridge and culvert without the telescopic device are not provided with expansion joints from the joints.
3. The structure for preventing and controlling vehicle bump at bridge head based on concrete composite pavement as claimed in claim 1, wherein the milled bridge head pavement is processed by seam processing, the upper layer and the lower layer are staggered by at least 200m in the longitudinal seam, the transverse seam is staggered by at least 1m in the adjacent layers.
4. The structure of claim 1, wherein the abutment is backfilled with a graduation mark on every 15cm layer at the rear of the abutment before the abutment is backfilled in a layered manner from the lowest position, each layer is compacted layer by layer to be flat, a road arch corresponding to a roadbed is formed, when the backfill height of the abutment is larger than 5m, a bidirectional geogrid is respectively added on the original ground and the top of the abutment to reduce uneven settlement, the geogrid is paved in a direction perpendicular to the route, the lap joint width is not smaller than 2O cm, and four corners are firmly fixed.
5. The structure for preventing and treating bump at bridge head based on concrete composite pavement as claimed in claim 4, wherein the rolling is preferably performed by a vibratory roller to stabilize the pressure, then the vibration is performed for 2 times, and finally the static pressure is performed until the design requirement is met, a safe distance of 0.5m is reserved near the abutment during the rolling, a small-sized tamping tool is used for tamping within the safe distance, and the structure is prevented from being damaged by attention until the degree of compaction meets the design requirement.
6. The structure for preventing and treating bump at bridge head based on concrete composite pavement and the laying method thereof according to claim 1, wherein the test detection is carried out according to layered filling, layered rolling and layered detection, filling of not more than 4 layers per day is controlled, the compaction degree is detected according to the frequency of one point per 50m, at least one point is detected when the thickness is less than 50m2, the compaction degree standard is more than 96% or the settlement difference is within 2mm, the construction procedure is strictly controlled, the previous procedure is unqualified, and the next procedure is strictly prohibited for construction.
7. The structure for preventing and treating bump at bridge head based on concrete composite pavement as claimed in claim 1, wherein the concrete anisotropic precast block is laid on the surface layer of the transition section with the length of 10-50 cm.
8. The structure for preventing and treating bump at bridge head based on concrete composite pavement as claimed in claim 5, wherein graded broken stone or gravel is adopted for certain thickness of the filling in the filling process.
CN201910988772.3A 2019-10-17 2019-10-17 Bridge head bump prevention and control structure based on concrete composite pavement and laying method thereof Pending CN110792009A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910988772.3A CN110792009A (en) 2019-10-17 2019-10-17 Bridge head bump prevention and control structure based on concrete composite pavement and laying method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910988772.3A CN110792009A (en) 2019-10-17 2019-10-17 Bridge head bump prevention and control structure based on concrete composite pavement and laying method thereof

Publications (1)

Publication Number Publication Date
CN110792009A true CN110792009A (en) 2020-02-14

Family

ID=69440374

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910988772.3A Pending CN110792009A (en) 2019-10-17 2019-10-17 Bridge head bump prevention and control structure based on concrete composite pavement and laying method thereof

Country Status (1)

Country Link
CN (1) CN110792009A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112391890A (en) * 2020-11-10 2021-02-23 桂林理工大学 Construction device and method for solving bump at bridge head
CN115324078A (en) * 2022-08-24 2022-11-11 中国二十冶集团有限公司 Rapid remediation treatment method for local uneven settlement of roadbed

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102839595A (en) * 2012-09-26 2012-12-26 江苏省交通科学研究院股份有限公司 Method for treating bump at bridge-head
CN102979021A (en) * 2012-11-21 2013-03-20 邢台路桥建设总公司 Construction method for treating vehicle jump at bridge head in highway
CN104746399A (en) * 2015-04-10 2015-07-01 成军 Construction method for preventing vehicle bump at bridge head
CN105113386A (en) * 2015-08-17 2015-12-02 苏州同尚工程设计咨询有限公司 Stage back suitable for preventing bridgehead bump on high filling subgrade

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102839595A (en) * 2012-09-26 2012-12-26 江苏省交通科学研究院股份有限公司 Method for treating bump at bridge-head
CN102979021A (en) * 2012-11-21 2013-03-20 邢台路桥建设总公司 Construction method for treating vehicle jump at bridge head in highway
CN104746399A (en) * 2015-04-10 2015-07-01 成军 Construction method for preventing vehicle bump at bridge head
CN105113386A (en) * 2015-08-17 2015-12-02 苏州同尚工程设计咨询有限公司 Stage back suitable for preventing bridgehead bump on high filling subgrade

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112391890A (en) * 2020-11-10 2021-02-23 桂林理工大学 Construction device and method for solving bump at bridge head
CN115324078A (en) * 2022-08-24 2022-11-11 中国二十冶集团有限公司 Rapid remediation treatment method for local uneven settlement of roadbed

Similar Documents

Publication Publication Date Title
CN101153475B (en) Redbeds mudstone filled high-speed railway subgrade and construction method thereof
CN111893827A (en) Construction process of urban trunk road
CN104358188A (en) Filling construction method for collapsible loess subgrade
CN111549598B (en) Construction method of highway reinforced bridgehead roadbed in collapsible loess region
CN111962350A (en) Geocell reinforced cement concrete pavement structure and method for calculating thickness of surface slab
CN103334357A (en) Viaduct road embankment structure with lower pile foundation bearing platform extending in roadbed, and construction method
Fattah et al. Stress distribution from railway track over geogrid reinforced ballast underlain by clay
CN110777588A (en) Pressure filling construction method for soil-stone mixed high-filling roadbed
CN204940030U (en) Reconstruction and extension project new-old concrete bond Pavement mosaic structure
CN101311418A (en) Exchange filling method for deep-foundation pit and large area equipment foundation
CN204570720U (en) A kind of widening of subgrade culvert foundation
CN103276649A (en) Method for constructing multi-thickness rockfill embankment with lateral confinement and layering functions
CN109680586A (en) A kind of pavement asphalt laying method
CN106894432A (en) A kind of pile variation rigidity reinforcement cushion composite foundation and its construction method
CN110761137B (en) Non-damage layered rolling construction method using cement-modified fine silt as roadbed filler
CN104863031B (en) A kind of karst area ductility anti-collapse road structure and construction method thereof
CN110792009A (en) Bridge head bump prevention and control structure based on concrete composite pavement and laying method thereof
CN116815733A (en) Construction process for quality control of high-fill roadbed in collapsible loess area
CN108193572A (en) A kind of method recycled to precast beam precasting yard hardened layer
Puppala et al. Recommendations for design, construction, and maintenance of bridge approach slabs.
CN110820456A (en) Anti-settling and replacement-filling alternate airport runway and construction method thereof
CN103276716B (en) A kind of changeover portion CFG stake and mattress layer composite foundation stabilization construction method
CN210946329U (en) High embankment structure of filling up in subway top
CN110804939A (en) Reinforced structure of abutment jump car
CN105113350A (en) Pier abutment roadbed structure and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200214