CN110777983A - Synchronous construction structure and method for concrete filled wall and cast-in-place structure - Google Patents
Synchronous construction structure and method for concrete filled wall and cast-in-place structure Download PDFInfo
- Publication number
- CN110777983A CN110777983A CN201911100129.9A CN201911100129A CN110777983A CN 110777983 A CN110777983 A CN 110777983A CN 201911100129 A CN201911100129 A CN 201911100129A CN 110777983 A CN110777983 A CN 110777983A
- Authority
- CN
- China
- Prior art keywords
- wall
- steel bars
- concrete
- bars
- vertical
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/74—Removable non-load-bearing partitions; Partitions with a free upper edge
- E04B2/82—Removable non-load-bearing partitions; Partitions with a free upper edge characterised by the manner in which edges are connected to the building; Means therefor; Special details of easily-removable partitions as far as related to the connection with other parts of the building
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/74—Removable non-load-bearing partitions; Partitions with a free upper edge
- E04B2/82—Removable non-load-bearing partitions; Partitions with a free upper edge characterised by the manner in which edges are connected to the building; Means therefor; Special details of easily-removable partitions as far as related to the connection with other parts of the building
- E04B2/828—Connections between partitions and structural walls
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/84—Walls made by casting, pouring, or tamping in situ
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
- E04G21/06—Solidifying concrete, e.g. by application of vacuum before hardening
- E04G21/08—Internal vibrators, e.g. needle vibrators
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Mechanical Engineering (AREA)
- Buildings Adapted To Withstand Abnormal External Influences (AREA)
Abstract
本发明公开了一种混凝土填充墙与现浇结构同步施工结构及方法,同步施工结构包括围绕填充墙上下的结构梁和两侧的剪力墙,填充墙中水平及竖向分布有钢筋,所述填充墙竖向两侧与剪力墙之间以及填充墙下侧与下侧结构梁之间分别通过设置塑料垫板形成分隔缝,填充墙上端与上侧结构梁之间不设分隔缝混凝土浇筑后连为一体,本发明填充墙与原结构之间通过结构分隔缝材料进行隔断以实现软连接,还原结构刚度。以顶部与混凝土结构相连的锚固钢筋和分隔缝材料作为阻尼装置实现抗震效果,其抗震方式类似于摇摆墙体系,对比砌体填充墙在抗震能力方面更有一定优势。
The invention discloses a synchronous construction structure and method of a concrete infill wall and a cast-in-place structure. The synchronous construction structure includes structural beams surrounding the infill wall and shear walls on both sides, and steel bars are distributed horizontally and vertically in the infill wall. Between the vertical sides of the infill wall and the shear wall, and between the lower side of the infill wall and the lower side structural beams, separate joints are formed by setting plastic backing plates, and there is no separation joint concrete between the top of the infill wall and the upper side structural beams. After pouring, they are connected as a whole, and the filling wall of the present invention is separated from the original structure by the structural separation joint material to realize the soft connection and restore the structural rigidity. The anti-seismic effect is achieved by using the anchoring steel bar and the separation joint material connected to the top of the concrete structure as the damping device.
Description
技术领域technical field
本发明涉及建筑施工,特别涉及一种混凝土填充墙与现浇结构同步施工The invention relates to building construction, in particular to a synchronous construction of a concrete filling wall and a cast-in-place structure
结构及方法。structure and method.
背景技术Background technique
填充墙是结构中重要的围护和分隔构件,传统填充墙常采用砌块进行砌筑,需要在混凝土结构全部或部分完成后实施,砌筑工程量大,其有水房间墙体底部混凝土反坎、构造柱或芯柱、圈梁、过梁、系梁、水平拉结筋等需要二次施工,电气导管、线盒等需要与填充墙砌体穿插作业,墙面往往需要抹灰等,不仅工序穿插繁琐,而且易出现质量通病。The infill wall is an important enclosure and separation component in the structure. Traditional infill walls are often built with blocks, which need to be implemented after the concrete structure is fully or partially completed. Sills, structural columns or core columns, ring beams, lintels, tie beams, horizontal tie bars, etc. require secondary construction, electrical conduits, junction boxes, etc. need to be interspersed with infill wall masonry, and walls often need plastering, etc. Not only is the process interspersed with cumbersome, but also prone to common quality problems.
近来虽有通过混凝土完成填充墙的方法,如公开号CN 107386502 A的“填充墙成型方法及填充墙”,该方法是在已浇筑成型的结构框架上再支撑模板浇筑填充墙,存在着需要设置与已浇筑成型的结构框架连接的钢筋,由于与结构框架不是同时浇筑,浇筑后存在与已浇筑成型的结构框架连接缝收缩不一致导致连接缝隙大的问题,为后续处理带来更多工作量。Although there is a method for completing the infill wall by concrete recently, such as the "Infill Wall Forming Method and the Infill Wall" of the publication number CN 107386502 A, the method is to support the formwork pouring the infill wall on the structural frame that has been poured and formed, there is a need to set Since the steel bars connected to the poured structural frame are not poured at the same time as the structural frame, there is a problem of inconsistent shrinkage of the connection joints with the poured structural frame after pouring, resulting in a large connection gap, which brings more workload for subsequent processing.
发明内容SUMMARY OF THE INVENTION
本发明的目的在于提出一种混凝土填充墙与现浇结构同步施工结构及The purpose of the present invention is to propose a synchronous construction structure of concrete infill wall and cast-in-place structure and
方法,混凝土填充墙与现浇结构同时浇筑,避免两种基体材料交接处的收缩裂缝,部分应力在结构分隔缝处得到释放,有效减少抹灰空鼓、开裂、外墙渗漏等质量通病。Method, the concrete infill wall and the cast-in-place structure are poured at the same time to avoid shrinkage cracks at the junction of the two base materials, and part of the stress is released at the structural separation joints, effectively reducing plastering hollowing, cracking, external wall leakage and other common quality problems.
为了实现上述目的,本发明的技术方案是:In order to achieve the above object, the technical scheme of the present invention is:
一种混凝土填充墙与现浇结构同步施工结构,包括围绕填充墙上下的结构梁和两侧的剪力墙,填充墙中水平及竖向分布有钢筋,所述填充墙竖向两侧与剪力墙之间以及填充墙下侧与下侧结构梁之间分别通过设置垫板形成分隔缝,填充墙上端与上侧结构梁之间不设分隔缝,混凝土同步浇筑后连为一体,在分隔缝垫板宽度方向两侧分别设置有填充墙定位固定钢筋,其中,水平定位固定钢筋分别伸入到填充墙和剪力墙中与填充墙与剪力墙中外侧竖向钢筋绑扎固定,竖向定位固定钢筋分别伸入到填充墙和下侧结构梁中与外侧水平钢筋绑扎固定,所述填充墙中分布的竖向钢筋伸入到上侧结构梁中形成锚固钢筋,锚固钢筋的锚固端与上侧结构梁中的水平钢筋绑扎在一起,在水平定位固定钢筋外侧设置有钢丝网,钢丝网伸入到填充墙与剪力墙中。A synchronous construction structure of a concrete infill wall and a cast-in-place structure includes structural beams around the infill wall and shear walls on both sides, steel bars are distributed horizontally and vertically in the infill wall, and the two sides of the infill wall are vertically connected with shear walls. Between the force walls and between the lower side of the filling wall and the lower structural beams, separate joints are formed by setting backing plates, and there is no separation joint between the top of the filling wall and the upper structural beams. The infill wall positioning and fixing steel bars are respectively arranged on both sides in the width direction of the joint plate, wherein the horizontal positioning and fixing steel bars extend into the infill wall and the shear wall respectively, and are bound and fixed by the vertical steel bars on the outer and middle sides of the infill wall and the shear wall. The positioning and fixing steel bars extend into the infill wall and the lower side structural beams respectively and are bound and fixed with the outer horizontal steel bars. The vertical reinforcement bars distributed in the infill wall extend into the upper side structural beams to form anchoring steel bars, and the anchoring ends of the anchoring steel bars are connected to The horizontal steel bars in the upper structural beam are bound together, and a steel wire mesh is arranged on the outside of the horizontally positioned and fixed steel bars, and the steel wire mesh extends into the filling wall and the shear wall.
方案进一步是:所述水平定位固定钢筋和竖向定位固定钢筋分别穿过所述垫板设置,或者,所述垫板的宽度小于填充墙的宽度,所述水平定位固定钢筋和竖向定位固定钢筋分别在所述垫板两侧外设置。The scheme is further: the horizontal positioning and fixing steel bars and the vertical positioning and fixing steel bars are respectively set through the backing plate, or the width of the backing plate is smaller than the width of the infill wall, and the horizontal positioning and fixing steel bars and the vertical positioning and fixing steel bars are respectively arranged through the backing plate. The reinforcing bars are respectively arranged outside the two sides of the backing plate.
方案进一步是:所述与上侧结构梁中的钢筋绑扎在一起的所述填充墙中的竖向钢筋是填充墙中分布的全部竖向钢筋,竖向钢筋伸入到上侧结构梁中的长度不小于锚固端长度。The scheme is further: the vertical reinforcing bars in the infill wall bound with the reinforcing bars in the upper structural beam are all vertical reinforcing bars distributed in the infilling wall, and the vertical reinforcing bars extend into the upper structural beam. The length is not less than the length of the anchoring end.
方案进一步是:所述钢丝网与水平定位钢筋通过绑扎固定。The solution is further: the steel wire mesh and the horizontal positioning steel bars are fixed by binding.
方案进一步是:所述填充墙中的竖向钢筋在填充墙厚度方向呈两排设置,两排竖向钢筋的底部呈U字形连接,水平钢筋间隔与竖向钢筋绑扎在一起。The scheme is further as follows: the vertical reinforcing bars in the infill wall are arranged in two rows in the thickness direction of the infilling wall, the bottoms of the two rows of vertical reinforcing bars are connected in a U-shape, and the horizontal reinforcing bars are bound together with the vertical reinforcing bars at intervals.
一种基于所述混凝土填充墙与现浇结构同步施工结构的施工方法,进行同层的剪力墙、填充墙、上侧结构梁钢筋绑扎,支撑同层的剪力墙、填充墙、上侧结构梁模板,其特征在于,在支撑好剪力墙、填充墙、上侧结构梁模板后,所述剪力墙、填充墙、上侧结构梁的混凝土同步浇筑完成。A construction method based on the synchronous construction structure of the concrete infill wall and the cast-in-place structure, the shear wall, infill wall, and upper side structural beams of the same layer are bound with steel bars, and the shear wall, infill wall, and upper side of the same layer are supported. The structural beam formwork is characterized in that, after the shear wall, the filling wall and the upper structural beam formwork are supported, the concrete of the shearing wall, the filling wall and the upper structural beam is synchronously poured.
方案进一步是:在剪力墙和填充墙的钢筋绑扎完成后插入分隔缝垫板,然后在进行水平定位固定钢筋的绑扎,在水平定位固定钢筋的绑扎完成后,进行钢丝网的固定绑扎。The plan is further as follows: after the reinforcement of the shear wall and the infill wall is bound, insert the spacer plate, and then perform the binding of the horizontally positioned and fixed steel bars, and after the binding of the horizontally positioned and fixed steel bars is completed, the steel mesh is fixed and bound.
方案进一步是:当所述水平定位固定钢筋穿过所述分隔缝垫板设置时,首先按照水平定位固定钢筋分布尺寸在所述分隔缝垫板上钻孔,剪力墙和填充墙的钢筋绑扎完成后插入分隔缝垫板后再将水平定位固定钢筋插入分隔缝垫板绑扎。The scheme is further as follows: when the horizontally positioned and fixed steel bars are set through the separation joint pad, firstly drill holes on the separation joint pad according to the distribution size of the horizontally positioned and fixed steel bars, and the reinforcement bars of the shear wall and the infill wall are bound. After the completion, insert the partition joint plate and then insert the horizontal positioning fixed steel bar into the partition joint plate to bind.
方案进一步是:所述填充墙中的竖向钢筋在填充墙厚度方向呈两排设置,两排竖向钢筋的底部呈U字形连接,所述填充墙中的水平钢筋从U字形端起50mm处起步分隔设置。The scheme is further as follows: the vertical reinforcing bars in the infill wall are arranged in two rows in the thickness direction of the infill wall, the bottoms of the two rows of vertical reinforcing bars are connected in a U shape, and the horizontal reinforcing bars in the infill wall are 50mm from the U-shaped end. Start separation settings.
方案进一步是:所述混凝土浇筑为分层浇筑,每一层浇筑厚度不大于振动棒作用部分长度的1.25倍,振动棒的前端插入前一层混凝土中,插入深度不小于50mm;振动棒垂直于混凝土表面并快插慢拔均匀振捣;当混凝土表面无明显塌陷、有水泥浆出现、不再冒气泡时,结束该部位振捣;振动棒接近模板时,振动棒与模板的距离不大于振动棒作用半径的50%;振捣插点间距不大于振动棒的作用半径的1.4倍。The plan is further: the concrete is poured in layers, the thickness of each layer is not greater than 1.25 times the length of the action part of the vibrating rod, the front end of the vibrating rod is inserted into the concrete of the previous layer, and the insertion depth is not less than 50mm; the vibrating rod is perpendicular to the The concrete surface shall be vibrated evenly by fast insertion and slow pulling; when there is no obvious collapse on the concrete surface, cement slurry appears, and no air bubbles appear, the vibration of this part shall be terminated; when the vibrating rod is close to the formwork, the distance between the vibrating rod and the formwork shall not be greater than the vibration 50% of the action radius of the rod; the spacing of the vibrating insertion points is not greater than 1.4 times the action radius of the vibrating rod.
本发明的有益效果是:The beneficial effects of the present invention are:
结构性能方面:本结构及方法填充墙与原结构之间通过结构分隔缝材料进行隔断以实现软连接,还原结构刚度。以顶部与混凝土结构相连的锚固钢筋和分隔缝材料作为阻尼装置实现抗震效果,其抗震方式类似于摇摆墙体系,对比砌体填充墙在抗震能力方面更有一定优势。In terms of structural performance: the structure and method are partitioned between the infill wall and the original structure through the structural separation joint material to achieve a soft connection and restore the structural rigidity. The anti-seismic effect is achieved by using the anchoring steel bar and the separation joint material connected to the top of the concrete structure as the damping device.
质量控制方面:本结构及方法填充墙与原结构均为混凝土材质且同步浇筑、一次成型,避免两种基体材料交接处的收缩裂缝,部分应力在结构分隔缝处得到释放,有效减少抹灰空鼓、开裂、外墙渗漏等质量通病。分隔缝采用PVC-U垫板材料时,“翼缘”加长水流的渗透路径,增强防水的效果。混凝土填充墙内电气导管(盒)同步预埋,有效避免砌体填充墙后期开槽现象。In terms of quality control: the structure and method infill wall and the original structure are both made of concrete and are simultaneously poured and formed at one time to avoid shrinkage cracks at the junction of the two base materials, and part of the stress is released at the structure separation joint, effectively reducing plastering voids Bulging, cracking, external wall leakage and other common quality problems. When the separation joint is made of PVC-U pad material, the "flange" lengthens the penetration path of the water flow and enhances the waterproof effect. The electrical conduits (boxes) in the concrete-filled wall are pre-buried synchronously, which can effectively avoid the later slotting phenomenon of the masonry-filled wall.
进度控制方面:本结构及方法与混凝土结构同步施工,无需后期插入作业;减少了砌筑、有水房间底部混凝土坎台、构造柱、过梁、圈梁、系梁、水平拉结筋、墙体抹灰等工序,减少了工序间的穿插,降低了管理难度,提高了生产效率,节约工期。In terms of schedule control: the structure and method are constructed simultaneously with the concrete structure, without the need for later insertion operations; it reduces the number of masonry, concrete sills at the bottom of water rooms, structural columns, lintels, ring beams, tie beams, horizontal tie bars, and walls. Body plastering and other processes reduce the interspersed between processes, reduce the difficulty of management, improve production efficiency and save construction time.
绿色安全施工方面:较砌体填充墙,不再需要外墙砌筑和抹灰,减少了外脚手架施工工程量,临边洞口数量降低,特别对于采用爬架的工程,外墙结构可随爬架一次完成,减少了危险源;较砌体填充墙,没有破损或边角料砌块,无砌筑砂浆落地灰问题,无填充墙多余养护用水流失,节省了物料运输的能源消耗,符合绿色施工的政策理念。成本控制方面:由于相应部位不再需要施工填充墙砌体,节省了砌块、砂浆等材料运输而占用的垂直运输设备的台班、外脚手架租赁费用、砌筑和配管等的人工工时,减少了质量缺陷修补工程量和临时用工,有效节约了施工成本。In terms of green and safe construction: Compared with masonry infill walls, external wall masonry and plastering are no longer required, which reduces the amount of external scaffolding construction works and reduces the number of side openings. Especially for projects using climbing frames, the external wall structure can be climbed along with it. The frame is completed at one time, which reduces the source of danger; compared with the masonry infill wall, there is no damage or leftover blocks, no masonry mortar landing ash problem, no excess maintenance water loss of the infill wall, saving energy consumption for material transportation, in line with green construction requirements policy concept. In terms of cost control: since the corresponding parts no longer need to construct infill wall masonry, it saves the time required for vertical transportation equipment, external scaffold rental costs, masonry and piping, etc., which are occupied by the transportation of blocks, mortar and other materials. The amount of repair work and temporary labor for quality defects are reduced, which effectively saves construction costs.
下面结合附图和实施例对本发明进行详细描述。The present invention will be described in detail below with reference to the accompanying drawings and embodiments.
附图说明Description of drawings
图1 是本发明结构示意图;Fig. 1 is the structure schematic diagram of the present invention;
图2是本发明填充墙横断面结构示意图;Fig. 2 is the cross-sectional structure schematic diagram of filling wall of the present invention;
图3是本发明填充墙与剪力墙分隔缝结构示意图;Fig. 3 is the structure schematic diagram of the separation joint between the filling wall and the shear wall of the present invention;
图4是本发明填充墙与下侧结构梁分隔缝结构示意图。FIG. 4 is a schematic structural diagram of the separation joint between the filling wall and the lower side structural beam according to the present invention.
具体实施方式Detailed ways
一种混凝土填充墙与现浇结构同步施工结构,如图1、图2、图3和图4所示,所述混凝土填充墙与现浇结构同步施工结构包括围绕填充墙1的上侧结构梁2、下侧结构梁3和两侧的左侧剪力墙4和右侧剪力墙5,图1示意了三层结构,包含了上层的填充墙和下层的填充墙,这里的上侧结构梁2、下侧结构梁3是相对于每一层而言,因此,作为中间层的上侧结构梁,在上层中就是上层填充墙的下侧结构梁,所述的上下侧结构梁包括边墙的上下侧结构梁以及在每一层中间的上下侧结构梁。如图2、图3和图4所示,填充墙中分布有水平钢筋6以及竖向钢筋7,所述填充墙竖向两侧与剪力墙之间以及填充墙下侧与下侧结构梁之间分别通过设置垫板8形成分隔缝,垫板的厚度根据现场分隔缝的大小确定,垫板使用塑料垫板,本实施例分隔缝要求20mm至25mm,因此,分隔缝由上下两层PVC塑料板加中间PVC骨架组合成为一体。填充墙上端与上侧结构梁之间不设分隔缝,混凝土同步浇筑后连为一体,所述同步浇筑是指连续浇筑。此结构具有抗震的作用,其抗震方式类似于摇摆墙体系,在分隔缝垫板宽度方向两侧分别设置有填充墙定位固定钢筋9,其中,水平定位固定钢筋分别伸入到填充墙和剪力墙中与填充墙与剪力墙中外侧竖向钢筋绑扎固定,竖向定位固定钢筋分别伸入到填充墙和下侧结构梁中与外侧水平钢筋绑扎固定,所述填充墙中分布的竖向钢筋伸入到上侧结构梁中形成直角折弯的L形锚固钢筋11(折弯由于是纵向的所以图4中并未显示出来),锚固钢筋直角折弯的锚固端与上侧结构梁中的水平钢筋绑扎在一起,并且,所述与上侧结构梁中的钢筋绑扎在一起的所述填充墙中的竖向钢筋是填充墙中分布的全部竖向钢筋,竖向钢筋伸入到上侧结构梁中的长度不小于锚固端长度。如图3所示,在水平定位固定钢筋外侧设置有钢丝网10,钢丝网伸入到填充墙与剪力墙中,所述钢丝网与水平定位钢筋通过绑扎固定。A synchronous construction structure of a concrete infill wall and a cast-in-place structure, as shown in Figure 1, Figure 2, Figure 3 and Figure 4, the synchronous construction structure of the concrete infill wall and the cast-in-place structure comprises an upper side structural beam surrounding the
其中:根据施工需要,垫板有两种宽度结构方式,一种是垫板的宽度等于填充墙的宽度,所述水平定位固定钢筋和竖向定位固定钢筋分别穿过所述垫板设置,另一种是所述垫板的宽度小于填充墙的宽度,所述水平定位固定钢筋和竖向定位固定钢筋分别在所述垫板两侧外紧贴垫板设置。Among them: according to the construction needs, the backing plate has two width structures. One is that the width of the backing plate is equal to the width of the filling wall, the horizontal positioning and fixing steel bars and the vertical positioning and fixing steel bars are respectively set through the backing plate, and the other is that the width of the backing plate is equal to the width of the filling wall. One is that the width of the backing plate is smaller than the width of the filling wall, and the horizontal positioning and fixing steel bars and the vertical positioning and fixing steel bars are respectively arranged close to the backing plate on both sides of the backing plate.
实施例中,如图4所示:所述填充墙中的竖向钢筋7在填充墙厚度方向呈两排设置,两排竖向钢筋的底部呈U字形连接,水平钢筋间隔与竖向钢筋绑扎在一起。其中,如图2所示,水平钢筋6在其一端呈L形与竖向钢筋绑扎在一起。In the embodiment, as shown in Figure 4: the vertical reinforcement bars 7 in the infill wall are arranged in two rows in the thickness direction of the infill wall, the bottoms of the two rows of vertical reinforcement bars are connected in a U-shape, and the horizontal reinforcement bars are spaced and bound with the vertical reinforcement bars. together. Among them, as shown in FIG. 2 , the
下面是基于上述混凝土填充墙与现浇结构同步施工结构的施工方法,分别进行同层的剪力墙、填充墙、上侧结构梁钢筋绑扎,支撑同层的剪力墙、填充墙、上侧结构梁模板,在支撑好剪力墙、填充墙、上侧结构梁模板后,所述剪力墙、填充墙、上侧结构梁的混凝土同步浇筑完成。The following is a construction method based on the above-mentioned synchronous construction of the concrete infill wall and the cast-in-place structure. The shear wall, infill wall, and upper side structural beams on the same layer are bound with steel bars to support the shear wall, infill wall, and upper side of the same layer. Structural beam formwork, after the shear wall, infill wall, and upper side structural beam formwork are supported, the concrete of the shear wall, infill wall, and upper side structural beam is synchronously poured.
在钢筋绑扎过程中:首先进行剪力墙和填充墙的钢筋绑扎,在剪力墙和填充墙的钢筋绑扎完成后插入分隔缝垫板,然后在进行水平定位固定钢筋的绑扎,在水平定位固定钢筋的绑扎完成后,进行钢丝网的固定绑扎。In the process of reinforcing steel bar binding: firstly bind the reinforcing bars of the shear wall and the infill wall, insert the spacer plate after the bar binding of the shear wall and the infill wall is completed, and then perform the horizontal positioning and fixing of the reinforcing bars, and then fix the horizontal positioning and fixing After the binding of the steel bars is completed, the fixed binding of the steel mesh is carried out.
当所述水平定位固定钢筋穿过所述分隔缝垫板设置时,首先按照水平定位固定钢筋分布尺寸在所述分隔缝垫板上钻孔,剪力墙和填充墙的钢筋绑扎完成后插入分隔缝垫板后再将水平定位固定钢筋插入分隔缝垫板绑扎。When the horizontally positioned and fixed steel bars are set through the separation joint pad, first drill holes on the separation joint pad according to the distribution size of the horizontally positioned and fixed steel bars, and then insert the partitions after the reinforcement of the shear wall and the infill wall is bound. After seam the backing plate, insert the horizontal positioning fixed steel bar into the separation seam backing plate and tie it.
其中:所述填充墙中的竖向钢筋在填充墙厚度方向呈两排设置,两排竖向钢筋的底部呈U字形连接,所述填充墙中的水平钢筋从U字形端起50mm处起步分隔设置。Wherein: the vertical reinforcement bars in the infill wall are arranged in two rows in the thickness direction of the infill wall, the bottoms of the two rows of vertical reinforcement bars are connected in a U shape, and the horizontal reinforcement bars in the infill wall are separated 50mm from the U-shaped end. set up.
在混凝土浇筑过程中:所述混凝土浇筑为分层浇筑,每一层浇筑厚度不大于振动棒作用部分长度的1.25倍,振动棒的前端插入前一层混凝土中,插入深度不小于50mm;振动棒垂直于混凝土表面并快插慢拔均匀振捣;当混凝土表面无明显塌陷、有水泥浆出现、不再冒气泡时,结束该部位振捣;振动棒接近模板时,振动棒与模板的距离不大于振动棒作用半径的50%;振捣插点间距不大于振动棒的作用半径的1.4倍。In the process of concrete pouring: the concrete is poured in layers, and the thickness of each layer is not greater than 1.25 times the length of the action part of the vibrating rod. The front end of the vibrating rod is inserted into the concrete of the previous layer, and the insertion depth is not less than 50mm; It is perpendicular to the concrete surface and vibrates evenly by fast insertion and slow pulling; when there is no obvious collapse on the concrete surface, cement slurry appears, and no air bubbles are formed, the vibration of this part is terminated; when the vibrating rod is close to the formwork, the distance between the vibrating rod and the formwork is not equal. It is greater than 50% of the action radius of the vibrating rod; the distance between the vibrating insertion points is not greater than 1.4 times the action radius of the vibrating rod.
本实施例通过在钢筋混凝土填充墙与结构体之间的下方和两侧的水平和竖向接缝部位设置柔性材料作为结构分隔缝,在竖向分隔缝两侧设置定位钢筋固定柔性材料,在与结构体的顶部设置定位锚固钢筋,填充墙内安装竖向和水平分布筋,结构分隔缝外侧绑扎铁丝网等技术工艺,达到了不影响结构刚度,满足抗震要求,减少荷载向下层的累积传递,实现了填充墙非结构体与结构体的同步施工,并具有抗裂防水的效果。In this embodiment, flexible materials are arranged at the horizontal and vertical joints below and on both sides between the reinforced concrete infill wall and the structure as structural separation joints, and positioning steel bars are arranged on both sides of the vertical separation joints to fix the flexible materials. The positioning and anchoring steel bars are arranged on the top of the structure, the vertical and horizontal distribution bars are installed in the filling walls, and the barbed wire is bound on the outside of the structural separation joints. It realizes the simultaneous construction of the non-structural body and the structural body of the infill wall, and has the effect of crack resistance and waterproofing.
实施例中填充墙与下侧结构梁的水平分隔缝垫板采用墙体竖向定位固定钢筋穿透固定的方式,首先根据定位固定钢筋间距,采用机械钻孔方式对结构分隔缝垫板进行开孔,孔洞直径应较钢筋直径大2~3mm,然后将垫板插入竖向定位固定钢筋,然后今次进行填充墙钢筋绑扎,对于预埋机电管线等按照管线位置及大小进行开槽、留洞。混凝土填充墙底部竖向钢筋为U型,首先将U型钢筋及第一道水平筋与定位固定钢筋进行绑扎,U型钢筋与定位固定钢筋搭接范围内不少于3个绑扎扣,采用八字扣,水平筋起步尺寸为50mm,再进行填充墙上部墙体钢筋绑扎。填充墙体钢筋绑扎过程中设置梯子筋,填充墙体水平钢筋在竖向结构分隔缝厚度方向两侧断开,绑扎墙体过程中注意相关专业的配合,及时进行水电预留预埋,在两侧墙体钢筋绑扎完成后,再将竖向分隔缝材料放入,避免钢筋绑扎过程中损坏材料。分隔缝材料宽度方向两侧绑扎定位固定钢筋,并与分隔缝宽度方向两侧第一排竖向钢筋进行八字扣绑扎,随后定位固定钢筋外侧绑扎通高镀锌钢丝网。对于外墙上下层水平施工缝处,模板需有防止错台、涨模的措施。对于内墙上下层水平施工缝处支模前在楼板上弹好的模板位置线外侧5mm处粘贴1cm厚3cm宽通长海绵条,防止模板与楼面接缝处缝隙漏浆。In the embodiment, the horizontal separation joint pad of the filling wall and the lower structural beam adopts the method of penetrating and fixing the vertical positioning and fixing steel bars of the wall. First, according to the spacing of the positioning and fixing steel bars, the structural separation joint pad is drilled by mechanical drilling. The diameter of the hole should be 2-3mm larger than the diameter of the steel bar, then insert the backing plate into the vertical positioning and fixing steel bar, and then tie the steel bar of the filling wall this time. . The vertical steel bars at the bottom of the concrete infill wall are U-shaped. First, bind the U-shaped steel bars and the first horizontal bar to the positioning and fixing steel bars. There are no less than 3 binding buckles within the overlapping range of the U-shaped steel bars and the positioning and fixing steel bars. Buckle, the starting size of the horizontal bar is 50mm, and then the reinforcement of the wall on the infill wall is bound. Ladder bars are set in the process of bundling the reinforcement of the infill wall, and the horizontal reinforcement of the infill wall is broken on both sides in the thickness direction of the vertical structure separation seam. During the process of bundling the wall, attention should be paid to the cooperation of relevant professionals, and the water and electricity reserves should be pre-buried in time. After the reinforcement of the side wall is bound, the vertical separation joint material is placed in to avoid damage to the material during the reinforcement of the reinforcement. The two sides of the width direction of the separation seam material are bound and positioned to fix the steel bars, and the first row of vertical steel bars on both sides of the width direction of the separation seam are bound with an eight-character buckle, and then the outer sides of the fixed steel bars are bound to a high galvanized steel wire mesh. For the horizontal construction joints on the lower layers of the outer wall, the formwork shall have measures to prevent misplacement and formwork expansion. For the horizontal construction joints on the inner wall, paste 1cm thick and 3cm wide and long sponge strips 5mm outside the position line of the elasticized formwork on the floor before the formwork is supported to prevent the gap between the formwork and the floor from leaking.
浇筑完成后,各构件模板拆除首先需满足拆模强度要求。常温状态下墙体模板拆除时,混凝土强度要不小于1.2MPa,使得混凝土强度能保证其表面及棱角不因拆除模板而损坏。使用撬棍时,应避免接触混凝土表面,不得使用锤子或其他工具剧烈敲打模板面,注意混凝土及分隔缝材料的成品保护。After the pouring is completed, the dismantling of each component formwork must first meet the requirements of dismantling strength. When the wall formwork is removed at normal temperature, the concrete strength should be no less than 1.2MPa, so that the concrete strength can ensure that its surface and edges and corners are not damaged due to the removal of the formwork. When using a crowbar, avoid contact with the concrete surface, do not use a hammer or other tools to violently hit the formwork surface, and pay attention to the finished product protection of concrete and separation joint materials.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201911100129.9A CN110777983A (en) | 2019-11-12 | 2019-11-12 | Synchronous construction structure and method for concrete filled wall and cast-in-place structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201911100129.9A CN110777983A (en) | 2019-11-12 | 2019-11-12 | Synchronous construction structure and method for concrete filled wall and cast-in-place structure |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN110777983A true CN110777983A (en) | 2020-02-11 |
Family
ID=69391755
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201911100129.9A Pending CN110777983A (en) | 2019-11-12 | 2019-11-12 | Synchronous construction structure and method for concrete filled wall and cast-in-place structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN110777983A (en) |
Cited By (14)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107503450A (en) * | 2017-08-22 | 2017-12-22 | 中建四局第六建筑工程有限公司 | A kind of cast-in-place hollow armored concrete filling wall and its construction technology |
| CN111335490A (en) * | 2020-03-13 | 2020-06-26 | 山西四建集团有限公司 | Crack-resistant structure at joint of filler wall and shear wall under full-concrete outer wall window and construction method of crack-resistant structure |
| CN111441499A (en) * | 2020-04-17 | 2020-07-24 | 中建一局集团第一建筑有限公司 | Joint structure and method for common concrete and iron ore sand concrete super-thick wall |
| CN112411816A (en) * | 2020-12-02 | 2021-02-26 | 安徽格构材料科技有限公司 | Assembled wallboard and connecting method |
| CN112575923A (en) * | 2020-12-09 | 2021-03-30 | 中机国际工程设计研究院有限责任公司 | Full-concrete outer wall structure rigidity reduction method and full-concrete outer wall with reduced structure rigidity |
| CN112709358A (en) * | 2020-12-25 | 2021-04-27 | 浙江东设建筑设计有限公司 | Shear force wall and integrative connection structure of pouring of infilled wall and template structure thereof |
| CN113006321A (en) * | 2021-03-12 | 2021-06-22 | 昆山市建设工程质量检测中心 | Construction method for connecting joints between combined precast concrete wall bodies |
| CN113863541A (en) * | 2021-09-29 | 2021-12-31 | 中国建筑第八工程局有限公司 | Construction method of ultra-long thin-wall clear water concrete wall |
| CN114352017A (en) * | 2022-02-17 | 2022-04-15 | 合肥建工集团有限公司 | Full cast-in-place outer wall construction method |
| CN114525924A (en) * | 2020-12-18 | 2022-05-24 | 新疆苏中建设工程有限公司 | Bealock cast-in-situ wall structure and construction method |
| CN114635503A (en) * | 2022-03-22 | 2022-06-17 | 北京华清安地建筑设计有限公司 | Fair-faced concrete wall flexibly connected with concrete frame column and construction method |
| CN115095052A (en) * | 2022-08-02 | 2022-09-23 | 江苏扬建集团有限公司 | Cast-in-place weight-reducing filler wall and construction method thereof |
| CN115897850A (en) * | 2023-01-10 | 2023-04-04 | 苏州良浦住宅工业有限公司 | A wall panel side flexible connection structure and construction technology |
| CN117947970A (en) * | 2024-02-18 | 2024-04-30 | 罗学贵 | Treatment method of cold joints at the interface between new and old concrete in concrete shear wall replacement and wall |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103556749A (en) * | 2013-10-10 | 2014-02-05 | 南京工业大学 | Suspension type flexible connection for precast concrete infilled wall |
| KR101477464B1 (en) * | 2014-09-16 | 2015-01-06 | 충남대학교산학협력단 | Forecasting method of seismic performance of infill wall having slits composed of rc structure |
| CN107503450A (en) * | 2017-08-22 | 2017-12-22 | 中建四局第六建筑工程有限公司 | A kind of cast-in-place hollow armored concrete filling wall and its construction technology |
| CN108412094A (en) * | 2018-05-08 | 2018-08-17 | 中建四局第四建筑工程有限公司 | The construction method and device of the hollow concrete wall of masonry between a kind of replacement shear wall |
| CN211499326U (en) * | 2019-11-12 | 2020-09-15 | 中国新兴建筑工程有限责任公司 | A synchronous construction structure of concrete infill wall and cast-in-place structure |
-
2019
- 2019-11-12 CN CN201911100129.9A patent/CN110777983A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103556749A (en) * | 2013-10-10 | 2014-02-05 | 南京工业大学 | Suspension type flexible connection for precast concrete infilled wall |
| KR101477464B1 (en) * | 2014-09-16 | 2015-01-06 | 충남대학교산학협력단 | Forecasting method of seismic performance of infill wall having slits composed of rc structure |
| CN107503450A (en) * | 2017-08-22 | 2017-12-22 | 中建四局第六建筑工程有限公司 | A kind of cast-in-place hollow armored concrete filling wall and its construction technology |
| CN108412094A (en) * | 2018-05-08 | 2018-08-17 | 中建四局第四建筑工程有限公司 | The construction method and device of the hollow concrete wall of masonry between a kind of replacement shear wall |
| CN211499326U (en) * | 2019-11-12 | 2020-09-15 | 中国新兴建筑工程有限责任公司 | A synchronous construction structure of concrete infill wall and cast-in-place structure |
Non-Patent Citations (1)
| Title |
|---|
| 邓志峰、王炎伟: "全现浇混凝土填充墙结构拉缝施工技术", 安徽建筑, no. 5, 5 September 2017 (2017-09-05), pages 162 - 165 * |
Cited By (17)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN107503450A (en) * | 2017-08-22 | 2017-12-22 | 中建四局第六建筑工程有限公司 | A kind of cast-in-place hollow armored concrete filling wall and its construction technology |
| CN111335490A (en) * | 2020-03-13 | 2020-06-26 | 山西四建集团有限公司 | Crack-resistant structure at joint of filler wall and shear wall under full-concrete outer wall window and construction method of crack-resistant structure |
| CN111441499A (en) * | 2020-04-17 | 2020-07-24 | 中建一局集团第一建筑有限公司 | Joint structure and method for common concrete and iron ore sand concrete super-thick wall |
| CN112411816A (en) * | 2020-12-02 | 2021-02-26 | 安徽格构材料科技有限公司 | Assembled wallboard and connecting method |
| CN112575923A (en) * | 2020-12-09 | 2021-03-30 | 中机国际工程设计研究院有限责任公司 | Full-concrete outer wall structure rigidity reduction method and full-concrete outer wall with reduced structure rigidity |
| CN112575923B (en) * | 2020-12-09 | 2022-06-03 | 中机国际工程设计研究院有限责任公司 | Full-concrete outer wall structure rigidity reduction method and full-concrete outer wall with reduced structure rigidity |
| CN114525924A (en) * | 2020-12-18 | 2022-05-24 | 新疆苏中建设工程有限公司 | Bealock cast-in-situ wall structure and construction method |
| CN112709358A (en) * | 2020-12-25 | 2021-04-27 | 浙江东设建筑设计有限公司 | Shear force wall and integrative connection structure of pouring of infilled wall and template structure thereof |
| CN113006321A (en) * | 2021-03-12 | 2021-06-22 | 昆山市建设工程质量检测中心 | Construction method for connecting joints between combined precast concrete wall bodies |
| CN113006321B (en) * | 2021-03-12 | 2021-09-28 | 昆山市建设工程质量检测中心 | Construction method for connecting joints between combined precast concrete wall bodies |
| CN113863541A (en) * | 2021-09-29 | 2021-12-31 | 中国建筑第八工程局有限公司 | Construction method of ultra-long thin-wall clear water concrete wall |
| CN114352017A (en) * | 2022-02-17 | 2022-04-15 | 合肥建工集团有限公司 | Full cast-in-place outer wall construction method |
| CN114352017B (en) * | 2022-02-17 | 2024-02-09 | 合肥建工集团有限公司 | Full cast-in-situ exterior wall construction method |
| CN114635503A (en) * | 2022-03-22 | 2022-06-17 | 北京华清安地建筑设计有限公司 | Fair-faced concrete wall flexibly connected with concrete frame column and construction method |
| CN115095052A (en) * | 2022-08-02 | 2022-09-23 | 江苏扬建集团有限公司 | Cast-in-place weight-reducing filler wall and construction method thereof |
| CN115897850A (en) * | 2023-01-10 | 2023-04-04 | 苏州良浦住宅工业有限公司 | A wall panel side flexible connection structure and construction technology |
| CN117947970A (en) * | 2024-02-18 | 2024-04-30 | 罗学贵 | Treatment method of cold joints at the interface between new and old concrete in concrete shear wall replacement and wall |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110777983A (en) | Synchronous construction structure and method for concrete filled wall and cast-in-place structure | |
| CN103410317A (en) | Construction method for site assembly and casting integral wall body by adopting wall body prefabricated part | |
| CN108824220A (en) | A kind of cast-in-place support and construction method of the rigid structure of cantilever T-type | |
| CN103590602B (en) | The construction method of cast-in-place concrete hollow building roof | |
| CN103953114B (en) | Steel frame-reinforced masonry shear wall combinative structure and construction method thereof | |
| CN111734018A (en) | Formwork structure, disassembly-free mold and concrete wall construction method | |
| CN211499326U (en) | A synchronous construction structure of concrete infill wall and cast-in-place structure | |
| CN112726878A (en) | Formwork-erecting-free construction method for masonry filler wall constructional column, prefabricated module and mould | |
| CN105134009A (en) | Sill coping concrete structure of frame structure infilled wall and construction method | |
| CN111042569B (en) | Construction method for additionally building linear accelerator machine room in limited space of hospital basement | |
| CN104295003A (en) | Structural column construction method | |
| CN212053307U (en) | Steel wire net frame cement light composite heat insulation wall | |
| CN103696437A (en) | Construction method for cutting latticed column | |
| CN115584808A (en) | Steel pipe constructional column built by filling wall, horizontal tie beam and lintel construction method | |
| CN112900854B (en) | Template system for slope bottom plate construction and construction method | |
| CN105926657B (en) | A construction method for prefabricated concrete foundation slabs | |
| CN116220244B (en) | Construction method of thermal insulation exterior wall structure with window sill opening | |
| CN210597742U (en) | Shear wall | |
| CN204418691U (en) | A kind of for cast-in-place vertical member and horizontal member junction concrete blocking apparatus | |
| CN209195425U (en) | Existing tunnel lining reinforcement structure | |
| CN115370176B (en) | A construction method for in-situ reinforcement during reconstruction of old protected buildings | |
| CN207277679U (en) | Air-entrained concrete building block and armored concrete outline border integral wall | |
| CN117403799A (en) | A kind of foam concrete wall construction method | |
| CN214615420U (en) | Manufacturing device for formwork splicing section | |
| CN117107962A (en) | A construction method of ultra-high ALC wall panel nodes |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200211 |
|
| RJ01 | Rejection of invention patent application after publication |
