CN110700443A - Integral concrete structure of steel frame shear wall structure and construction method thereof - Google Patents

Integral concrete structure of steel frame shear wall structure and construction method thereof Download PDF

Info

Publication number
CN110700443A
CN110700443A CN201910972778.1A CN201910972778A CN110700443A CN 110700443 A CN110700443 A CN 110700443A CN 201910972778 A CN201910972778 A CN 201910972778A CN 110700443 A CN110700443 A CN 110700443A
Authority
CN
China
Prior art keywords
steel
shear wall
frame shear
vertical
horizontal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910972778.1A
Other languages
Chinese (zh)
Inventor
刘京城
王恒
申利成
钟涛
钟鑫
张羽
李振波
卢海丰
李哲
赵健成
李文忠
葛占祥
吴杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Urban Construction Group Co Ltd
Original Assignee
Beijing Urban Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Urban Construction Group Co Ltd filed Critical Beijing Urban Construction Group Co Ltd
Priority to CN201910972778.1A priority Critical patent/CN110700443A/en
Publication of CN110700443A publication Critical patent/CN110700443A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/58Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of metal

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

The invention provides an integral concrete structure of a steel frame shear wall structure, which comprises a vertical structure, L-shaped angle steel and a horizontal structure connected with the vertical structure through the L-shaped angle steel, wherein the vertical structure comprises a plurality of steel stiffened columns and a steel column core tube wall body connected between the steel stiffened columns, the horizontal structure comprises a steel bar truss plate and a steel beam erected between the steel column core tube wall bodies, the steel bar truss plate is placed on the L-shaped angle steel and bound on the steel beam, and then concrete with the horizontal structure is poured. The invention also provides a construction method of the integral concrete structure of the steel frame shear wall structure. Compared with the related art, the invention has the following advantages: the construction period can be saved, the construction progress is accelerated, and the construction quality and safety can be ensured.

Description

一种钢框架剪力墙结构整体混凝土结构及其施工方法Integral concrete structure of steel frame shear wall structure and construction method thereof

【技术领域】【Technical field】

本发明涉及建筑施工技术领域,尤其涉及一种钢框架剪力墙结构整体混凝土结构及其施工方法。The invention relates to the technical field of building construction, in particular to an integral concrete structure of a steel frame shear wall structure and a construction method thereof.

【背景技术】【Background technique】

通常钢框架剪力墙结构中包括钢框架结构,而钢框架结构需要使用连接结构进行连接稳固,然而采用现有的钢框架结构采用连接板加螺栓的方式需装配的构件较多,并且使用的螺栓会突出于梁或柱的表面,使得梁或柱的表面不平整,在进行墙板和钢框架结构的连接时连接处难以处理,而涉及焊接的连接方式需要使用大量的设备和人力,因此在采用现有技术装配钢框架剪力墙结构的过程中,存在现场施工复杂,施工效率较为低下,施工质量难以保证的问题。Usually, the steel frame shear wall structure includes the steel frame structure, and the steel frame structure needs to use the connection structure for connection and stability. However, the existing steel frame structure uses the connection plate and bolts to assemble more components, and the use of The bolts will protrude from the surface of the beam or column, making the surface of the beam or column uneven, and it is difficult to handle the connection when connecting the wall panel and the steel frame structure, and the connection method involving welding requires a lot of equipment and manpower, so In the process of assembling the steel frame shear wall structure using the prior art, there are problems of complicated on-site construction, low construction efficiency, and difficulty in guaranteeing construction quality.

【发明内容】[Content of the invention]

本发明的目的在于提供一种钢框架剪力墙结构整体混凝土结构及其施工方法,其可以解决背景技术涉及的技术问题。The purpose of the present invention is to provide an integral concrete structure of a steel frame shear wall structure and a construction method thereof, which can solve the technical problems involved in the background technology.

本发明的技术方案如下:The technical scheme of the present invention is as follows:

一种钢框架剪力墙结构整体混凝土结构,包括竖向结构、L型角钢以及通过所述L型角钢与所述竖向结构连接的水平结构,所述竖向结构包括多根型钢劲性柱和连接于所述型钢劲性柱之间的钢骨柱核心筒墙体,所述水平结构包括钢筋桁架板和架设于所述钢骨柱核心筒墙体之间的型钢梁,所述钢筋桁架板放置于所述L型角钢上并绑扎于所述型钢梁上,之后浇筑水平结构混泥土。An integral concrete structure of a steel frame shear wall structure includes a vertical structure, an L-shaped angle steel, and a horizontal structure connected with the vertical structure through the L-shaped angle steel, and the vertical structure includes a plurality of steel-shaped rigid columns and the steel frame core tube wall connected between the steel frame rigid columns, the horizontal structure includes a steel truss plate and a steel frame beam erected between the steel frame column core tube walls, the steel bars The truss plate is placed on the L-shaped angle steel and bound to the shaped steel beam, and then the horizontal structural concrete is poured.

作为本发明的一种改进,在钢筋桁架板受力边与所述钢骨柱核心筒墙体部位设置后增钢梁。As an improvement of the present invention, steel beams are added after the reinforcement of the reinforced truss plate and the wall of the core tube of the steel column.

作为本发明的一种改进,水平构件和竖向结构采用栓焊连接。As an improvement of the present invention, the horizontal member and the vertical structure are connected by bolt welding.

作为本发明的一种改进,所述型钢梁选自于C16a、C20a、HM294x200x8x12、HW300x300x10x15。As an improvement of the present invention, the profiled steel beam is selected from C16a, C20a, HM294x200x8x12, and HW300x300x10x15.

作为本发明的一种改进,所述钢筋桁架板铺设进入所述钢骨核心筒墙体1.5cm。As an improvement of the present invention, the reinforced truss plate is laid 1.5 cm into the wall of the steel core tube.

作为本发明的一种改进,所述钢骨核心筒墙体采用15mm厚多层板,次龙骨为50*50*3mm钢包木,主龙骨为48mm直径钢管。As an improvement of the present invention, the steel skeleton core tube wall adopts 15mm thick multi-layer board, the secondary keel is 50*50*3mm ladle wood, and the main keel is 48mm diameter steel pipe.

作为本发明的一种改进,所述型钢梁边缘放置位置距离核心筒墙体结构400mm。As an improvement of the present invention, the edge of the profiled steel beam is placed at a distance of 400 mm from the core tube wall structure.

本发明还提供了一种钢框架剪力墙结构整体混凝土结构施工方法,依序包括如下步骤:采用塔吊吊装竖向构件,绑扎竖向结构钢筋,竖向结构模板支设,吊装水平构件,水平构件与竖向结构连接,铺设钢筋桁架板,绑扎水平结构钢筋,整体浇筑竖向及水平结构混凝土。The invention also provides a construction method for an integral concrete structure of a steel frame shear wall structure. The components are connected with the vertical structure, the steel truss plates are laid, the horizontal structural steel bars are bound, and the vertical and horizontal structural concrete is poured as a whole.

与相关技术相比,本发明具有如下优点:可节约工期,加快施工进度,同时可确保施工质量和安全。Compared with the related art, the invention has the following advantages: the construction period can be saved, the construction progress can be accelerated, and the construction quality and safety can be ensured at the same time.

【附图说明】【Description of drawings】

为了更清楚地说明本发明实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其它的附图,其中:In order to illustrate the technical solutions in the embodiments of the present invention more clearly, the following briefly introduces the accompanying drawings used in the description of the embodiments. Obviously, the accompanying drawings in the following description are only some embodiments of the present invention. For those of ordinary skill in the art, under the premise of no creative work, other drawings can also be obtained from these drawings, wherein:

图1为本发明一种钢框架剪力墙结构整体混凝土结构示意图。FIG. 1 is a schematic diagram of the overall concrete structure of a steel frame shear wall structure of the present invention.

【具体实施方式】【Detailed ways】

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅是本发明的一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其它实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

请参阅图1所示,本发明提供了一种钢框架剪力墙结构整体混凝土结构,包括竖向结构、L型角钢以及通过所述L型角钢与所述竖向结构连接的水平结构,所述竖向结构包括多根型钢劲性柱1和连接于所述型钢劲性柱1之间的钢骨柱核心筒墙体2,所述水平结构包括钢筋桁架板3和架设于所述钢骨柱核心筒墙体2之间的型钢梁4,所述钢筋桁架板3放置于所述L型角钢上并绑扎于所述型钢梁4上,之后浇筑水平结构混泥土。Referring to FIG. 1, the present invention provides an integral concrete structure of a steel frame shear wall structure, including a vertical structure, an L-shaped angle steel, and a horizontal structure connected to the vertical structure through the L-shaped angle steel. The vertical structure includes a plurality of shaped steel stiffening columns 1 and a steel column core tube wall 2 connected between the shaped steel stiffening columns 1, and the horizontal structure includes a steel truss plate 3 and a steel frame erected on the steel frame. The profiled steel beams 4 between the column core tube walls 2, the reinforced truss plates 3 are placed on the L-shaped angle steel and bound on the profiled steel beams 4, and then the horizontal structural concrete is poured.

需要进一步说明的是,所述水平构件和竖向结构采用栓焊连接,在铺设所述钢筋桁架板3前,经计算,在所述钢筋桁架板3受力边与所述钢骨柱核心筒墙体2部位设置后增钢梁5,用来解决所述钢筋桁架板3悬挑段过长造成变形问题。It should be further explained that the horizontal member and the vertical structure are connected by bolt welding. Before laying the reinforced truss plate 3, after calculation, the stress side of the reinforced truss plate 3 is connected to the core tube of the steel column. A steel beam 5 is added after the wall body 2 is set to solve the problem of deformation caused by the overlong cantilever section of the reinforced truss plate 3 .

所述钢筋桁架板3铺设进入所述钢骨柱核心筒墙体1.5cm,然后绑扎水平结构钢筋,整体浇筑竖向及水平结构混凝土。The reinforced truss plate 3 is laid 1.5 cm into the core wall of the steel column, and then the horizontal structural steel bars are bound, and vertical and horizontal structural concrete is poured as a whole.

所述钢骨柱核心筒墙体2采用15mm厚多层板,次龙骨为50*50*3mm钢包木,主龙骨为48mm直径钢管,周边为保证所述钢筋桁架板3支撑,分别增加后增钢梁5,所述后增钢梁5可以为槽钢、工字型钢。所述后增钢梁5边缘放置位置,距离所述钢骨柱核心筒墙体400mm,便于给墙体模板支设时留出操作空间。The steel column core tube wall 2 is made of 15mm thick multi-layer board, the secondary keel is 50*50*3mm ladle wood, the main keel is a 48mm diameter steel pipe, and the surrounding area is to ensure the support of the steel truss plate 3. Steel beam 5, the post-added steel beam 5 can be channel steel or I-shaped steel. The edge placement position of the post-added steel beam 5 is 400 mm away from the core tube wall of the steel column, which is convenient for leaving room for operation when the wall formwork is supported.

所述型钢梁选自于C16a、C20a、HM294x200x8x12、HW300x300x10x15,确保水平结构与竖向结构能一次性浇筑完成。The profiled steel beams are selected from C16a, C20a, HM294x200x8x12, HW300x300x10x15, to ensure that the horizontal structure and the vertical structure can be poured at one time.

增加后增钢梁5应同时满足①变形量

Figure BDA0002232646440000031
应小于
Figure BDA0002232646440000032
②应力(
Figure BDA0002232646440000033
其中
Figure BDA0002232646440000034
)小于300Mpa,即可符合要求,其中,q=单位面积均布荷载(计算范围详附图1中的A区域),L=后增钢梁的长度,E=2.05*105,h=后增钢梁的高度,t=后增钢梁腹板的厚度, The added steel beam 5 should satisfy ① the deformation amount at the same time
Figure BDA0002232646440000031
should be less than
Figure BDA0002232646440000032
② Stress (
Figure BDA0002232646440000033
in
Figure BDA0002232646440000034
) is less than 300Mpa, it can meet the requirements, wherein, q = uniform load per unit area (the calculation range is detailed in area A in Figure 1), L = the length of the rear steel beam, E = 2.05*10 5 , h = rear The height of the steel beam, t = the thickness of the web of the rear steel beam,

本发明还提供了一种钢框架剪力墙结构整体混凝土结构施工方法,依序包括如下步骤:采用塔吊吊装竖向构件,绑扎竖向结构钢筋,竖向结构模板支设,吊装水平构件,水平构件与竖向结构连接,铺设钢筋桁架板,绑扎水平结构钢筋,整体浇筑竖向及水平结构混凝土。采用该施工方法,可节约工期,加快施工进度,同时可确保施工质量和安全。The invention also provides a construction method for an integral concrete structure of a steel frame shear wall structure. The components are connected with the vertical structure, the steel truss plates are laid, the horizontal structural steel bars are bound, and the vertical and horizontal structural concrete is poured as a whole. By adopting the construction method, the construction period can be saved, the construction progress can be accelerated, and the construction quality and safety can be ensured at the same time.

尽管本发明的实施方案已公开如上,但并不仅仅限于说明书和实施方案中所列运用,它完全可以被适用于各种适合本发明的领域,对于熟悉本领域的人员而言,可容易地实现另外的修改,因此在不背离权利要求及等同范围所限定的一般概念下,本发明并不限于特定的细节和这里所示出与描述的图例。Although the embodiment of the present invention has been disclosed as above, it is not limited to the application listed in the description and the embodiment, and it can be applied to various fields suitable for the present invention. For those skilled in the art, it can be easily Additional modifications are implemented, therefore, the invention is not limited to the specific details and illustrations shown and described herein without departing from the general concept defined by the appended claims and the scope of equivalents.

Claims (8)

1.一种钢框架剪力墙结构整体混凝土结构,其特征在于,包括竖向结构、L型角钢以及通过所述L型角钢与所述竖向结构连接的水平结构,所述竖向结构包括多根型钢劲性柱和连接于所述型钢劲性柱之间的钢骨柱核心筒墙体,所述水平结构包括钢筋桁架板和架设于所述钢骨柱核心筒墙体之间的型钢梁,所述钢筋桁架板放置于所述L型角钢上并绑扎于所述型钢梁上,之后浇筑水平结构混泥土。1. a steel frame shear wall structure integral concrete structure, is characterized in that, comprises vertical structure, L-shaped angle steel and the horizontal structure that is connected with described vertical structure by described L-shaped angle steel, and described vertical structure comprises A plurality of shaped steel stiffening columns and a steel skeleton column core tube wall connected between the shaped steel stiffening columns, and the horizontal structure includes a reinforced truss plate and a shaped steel column core tube wall erected between the steel skeleton column core wall bodies Steel beam, the reinforced truss plate is placed on the L-shaped angle steel and bound on the shaped steel beam, and then the horizontal structural concrete is poured. 2.根据权利要求1所述的一种钢框架剪力墙结构整体混凝土结构,其特征在于,在钢筋桁架板受力边与所述钢骨柱核心筒墙体部位设置后增钢梁。2 . The integral concrete structure of a steel frame shear wall structure according to claim 1 , wherein a post-reinforced beam is arranged on the stressed side of the reinforced truss plate and the wall of the core tube of the steel column. 3 . 3.根据权利要求1所述的一种钢框架剪力墙结构整体混凝土结构,其特征在于,水平构件和竖向结构采用栓焊连接。3 . The integral concrete structure of a steel frame shear wall structure according to claim 1 , wherein the horizontal member and the vertical structure are connected by bolt welding. 4 . 4.根据权利要求1所述的一种钢框架剪力墙结构整体混凝土结构,其特征在于,所述型钢梁选自于C16a、C20a、HM294x200x8x12、HW300x300x10x15。4 . The integral concrete structure of a steel frame shear wall structure according to claim 1 , wherein the profiled steel beams are selected from C16a, C20a, HM294x200x8x12, and HW300x300x10x15. 5 . 5.根据权利要求1所述的一种钢框架剪力墙结构整体混凝土结构,其特征在于,所述钢筋桁架板铺设进入所述钢骨核心筒墙体1.5cm。5 . The steel frame shear wall structure integral concrete structure according to claim 1 , wherein the reinforced truss plates are laid 1.5 cm into the steel core tube wall. 6 . 6.根据权利要求1或2所述的一种钢框架剪力墙结构整体混凝土结构,其特征在于,所述钢骨核心筒墙体采用15mm厚多层板,次龙骨为50*50*3mm钢包木,主龙骨为48mm直径钢管。6. The overall concrete structure of a steel frame shear wall structure according to claim 1 or 2, characterized in that, the steel skeleton core tube wall adopts 15mm thick multi-layer board, and the secondary keel is 50*50*3mm Ladle wood, the main keel is 48mm diameter steel pipe. 7.根据权利要求1所述的一种钢框架剪力墙结构整体混凝土结构,其特征在于,所述型钢梁边缘放置位置距离核心筒墙体结构400mm。7 . The integral concrete structure of a steel frame shear wall structure according to claim 1 , wherein the edge of the profiled steel beam is placed at a distance of 400 mm from the core tube wall structure. 8 . 8.一种钢框架剪力墙结构整体混凝土结构施工方法,其特征在于,依序包括如下步骤:采用塔吊吊装竖向构件,绑扎竖向结构钢筋,竖向结构模板支设,吊装水平构件,水平构件与竖向结构连接,铺设钢筋桁架板,绑扎水平结构钢筋,整体浇筑竖向及水平结构混凝土。8. A construction method for an integral concrete structure of a steel frame shear wall structure, characterized in that it comprises the following steps in sequence: hoisting vertical members by a tower crane, binding vertical structural steel bars, supporting vertical structural formwork, and hoisting horizontal members, The horizontal members are connected with the vertical structure, the steel truss plates are laid, the horizontal structural steel bars are bound, and the vertical and horizontal structural concrete is poured as a whole.
CN201910972778.1A 2019-10-14 2019-10-14 Integral concrete structure of steel frame shear wall structure and construction method thereof Pending CN110700443A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910972778.1A CN110700443A (en) 2019-10-14 2019-10-14 Integral concrete structure of steel frame shear wall structure and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910972778.1A CN110700443A (en) 2019-10-14 2019-10-14 Integral concrete structure of steel frame shear wall structure and construction method thereof

Publications (1)

Publication Number Publication Date
CN110700443A true CN110700443A (en) 2020-01-17

Family

ID=69199764

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910972778.1A Pending CN110700443A (en) 2019-10-14 2019-10-14 Integral concrete structure of steel frame shear wall structure and construction method thereof

Country Status (1)

Country Link
CN (1) CN110700443A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116220384A (en) * 2023-03-30 2023-06-06 浙江省一建建设集团有限公司 Synchronous construction method for steel structure frame and reinforced concrete core tube
CN119062122A (en) * 2024-10-18 2024-12-03 北京市住宅产业化集团股份有限公司 A collaborative construction method for an internal steel frame and an external precast concrete shear wall structure

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004211288A (en) * 2002-12-26 2004-07-29 Shimizu Corp Building structure
CN106049679A (en) * 2016-07-07 2016-10-26 中建二局第三建筑工程有限公司 Super high-rise steel reinforced concrete framework core barrel structural system and construction method
CN107795005A (en) * 2017-11-27 2018-03-13 江苏沪宁钢机股份有限公司 A kind of steel core concrete column and reinforced concrete column concrete core cylinder mixed structure and installation method
CN108755940A (en) * 2018-07-12 2018-11-06 华南理工大学 A kind of steel core concrete column framed bent-Reinforced Concrete Core Walls Structure structural system
CN208122027U (en) * 2018-03-23 2018-11-20 青岛腾远设计事务所有限公司 A kind of prefabricated PC frame core wall structure
CN109162358A (en) * 2018-09-06 2019-01-08 广东省建筑设计研究院 A kind of full Baogang's frame-core tube-Special-Shaped Column architectural structure system of assembled
CN211472958U (en) * 2019-10-14 2020-09-11 北京城建集团有限责任公司 Integral concrete structure of steel frame shear wall structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004211288A (en) * 2002-12-26 2004-07-29 Shimizu Corp Building structure
CN106049679A (en) * 2016-07-07 2016-10-26 中建二局第三建筑工程有限公司 Super high-rise steel reinforced concrete framework core barrel structural system and construction method
CN107795005A (en) * 2017-11-27 2018-03-13 江苏沪宁钢机股份有限公司 A kind of steel core concrete column and reinforced concrete column concrete core cylinder mixed structure and installation method
CN208122027U (en) * 2018-03-23 2018-11-20 青岛腾远设计事务所有限公司 A kind of prefabricated PC frame core wall structure
CN108755940A (en) * 2018-07-12 2018-11-06 华南理工大学 A kind of steel core concrete column framed bent-Reinforced Concrete Core Walls Structure structural system
CN109162358A (en) * 2018-09-06 2019-01-08 广东省建筑设计研究院 A kind of full Baogang's frame-core tube-Special-Shaped Column architectural structure system of assembled
CN211472958U (en) * 2019-10-14 2020-09-11 北京城建集团有限责任公司 Integral concrete structure of steel frame shear wall structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116220384A (en) * 2023-03-30 2023-06-06 浙江省一建建设集团有限公司 Synchronous construction method for steel structure frame and reinforced concrete core tube
CN119062122A (en) * 2024-10-18 2024-12-03 北京市住宅产业化集团股份有限公司 A collaborative construction method for an internal steel frame and an external precast concrete shear wall structure

Similar Documents

Publication Publication Date Title
CN103352563B (en) The board-like bar frame gang form of self-supporting and construction method thereof
CN106193589B (en) Concrete superelevation heavy type beam and overlapping board combining structure method for supporting
CN201649623U (en) Large basement shear wall truss type steel pipe single-side support formwork structure
CN111962860A (en) Design and Construction Method of Shear Key Assembled Formwork for Empty Sandwich Panel
CN110409624A (en) A large-scale equipment installation and main structure reverse calculation and construction method
CN103572707B (en) Case girder steel outer template and construction method
CN101694127B (en) Formwork support system for steel frame structure cast-in-place concrete floorslabs
CN110700443A (en) Integral concrete structure of steel frame shear wall structure and construction method thereof
CN115387233A (en) Construction method for large-span and large-volume bent cap of transition pier of composite beam cable-stayed bridge
CN207700680U (en) A kind of roof boarding hangs mould
CN214834809U (en) A formwork-free jig
CN220828037U (en) Truss floor carrier plate supporting structure
CN101701493B (en) Template support system of box type girder cast-in-place concrete floor plate of steel frame construction
CN113047609A (en) Construction method for constructing super-thick concrete top plate by utilizing simple latticed column laminated slab system
CN211472958U (en) Integral concrete structure of steel frame shear wall structure
CN207987777U (en) A kind of high pier girder steel pushing tow support device
CN219118366U (en) A large-span assembled steel support
CN217353589U (en) Template supporting structure with adjustable length
CN218205143U (en) A permanent prefabricated composite formwork system
CN215858982U (en) Follow-on corner support of encorbelmenting
CN206487012U (en) A kind of steel plate shear wall structure
CN216475804U (en) A steel truss floor deck
CN117927011A (en) Construction process of frame structure under aluminum alloy building template system
CN204531180U (en) Control the stiff skeleton of large-scale component reinforcing bar binding precision
CN203403668U (en) Self-supporting plate type steel bar mesh frame combination formwork

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200117