CN110644761B - A construction protection platform - Google Patents

A construction protection platform Download PDF

Info

Publication number
CN110644761B
CN110644761B CN201910996903.2A CN201910996903A CN110644761B CN 110644761 B CN110644761 B CN 110644761B CN 201910996903 A CN201910996903 A CN 201910996903A CN 110644761 B CN110644761 B CN 110644761B
Authority
CN
China
Prior art keywords
mounting plate
limiting
lower mounting
wall
elevator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201910996903.2A
Other languages
Chinese (zh)
Other versions
CN110644761A (en
Inventor
张争取
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Zhongrongyu Construction Engineering Co ltd
Original Assignee
Shenzhen Zhongrongyu Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Zhongrongyu Construction Engineering Co ltd filed Critical Shenzhen Zhongrongyu Construction Engineering Co ltd
Priority to CN201910996903.2A priority Critical patent/CN110644761B/en
Publication of CN110644761A publication Critical patent/CN110644761A/en
Application granted granted Critical
Publication of CN110644761B publication Critical patent/CN110644761B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G2003/286Mobile scaffolds; Scaffolds with mobile platforms mobile vertically

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Types And Forms Of Lifts (AREA)

Abstract

本发明公开了一种建筑施工防护平台,其技术方案要点是:包括下安装板,下安装板下端设置有限定下安装板位置的限位机构,限位机构包括呈倾斜设置的若干限位杆和将限位杆与下安装板连接的若干连接杆,限位杆的一端与电梯井道内壁抵接,限位杆的另一端与楼层板上端抵接,与楼层板上端抵接的限位杆的一端向下倾斜,连接杆的一端均固定于下安装板下端,连接杆的另一端与限位杆连接,下安装板侧壁与电梯井道内壁连接。在完成一个楼层的电梯井道的施工之后,将下安装板和限位机构拆卸并安装于位于上方的楼层的电梯井道内,此时不再需要在电梯井道内一层层搭设脚手架,减少了搭设和拆卸脚手架所需要的时间,增加了工作的效率。

Figure 201910996903

The invention discloses a building construction protection platform, the technical solution of which is as follows: comprising a lower mounting plate, the lower end of the lower mounting plate is provided with a limiting mechanism for limiting the position of the lower mounting plate, and the limiting mechanism includes a plurality of limiting rods arranged obliquely and several connecting rods connecting the limit rod with the lower mounting plate, one end of the limit rod is in contact with the inner wall of the elevator shaft, the other end of the limit rod is in contact with the upper end of the floor board, and the limit rod is in contact with the upper end of the floor board One end of the connecting rod is inclined downward, one end of the connecting rod is fixed on the lower end of the lower mounting plate, the other end of the connecting rod is connected with the limit rod, and the side wall of the lower mounting plate is connected with the inner wall of the elevator shaft. After completing the construction of the elevator shaft on one floor, the lower mounting plate and the limiting mechanism are disassembled and installed in the elevator shaft on the upper floor. At this time, it is no longer necessary to set up scaffolding layer by layer in the elevator shaft, which reduces the need for erection. And the time required to disassemble the scaffolding increases the efficiency of the work.

Figure 201910996903

Description

Building construction protection platform
Technical Field
The invention belongs to the technical field of building engineering, and particularly relates to a building construction protection platform.
Background
Along with the rapid development of economy in China, the population is increased, a large number of rural population is flooded into cities to cause that urban land resources are more and more scarce, and in order to meet the demand of urban development, more and more commercial or civil engineering adopts small high-rise, high-rise and even super high-rise. The increase of floor makes the elevator more and more become the indispensable part in the building engineering, and the increase of floor also makes the difficulty of buildding of elevator well construction platform more and more big simultaneously.
In the past construction, the steel pipe is used for building a full hall frame or the whole full hall frame is welded by adopting section steel or the two ends of the steel pipe are built on a shear wall of an elevator shaft and used as a cross beam for building upper scaffold. No matter which kind all need build the scaffold, at the in-process of setting up, because elevator well space is narrow and small, speed of setting up is slow, at the dismantlement in-process in later stage, need dismantle the limit and transport the steel pipe out of elevator well, need spend a large amount of time, reduce the efficiency of construction.
Therefore, a new technical solution is needed to solve the above problems.
Disclosure of Invention
Aiming at the defects in the prior art, the invention aims to provide a building construction protection platform, which does not need to set up scaffolds layer by layer any more, reduces the time required for setting up and dismounting the scaffolds and increases the construction efficiency.
In order to realize the purpose, the invention provides the following technical scheme: the utility model provides a construction protection platform, includes lower mounting panel, the mounting panel lower extreme is provided with the stop gear of installation plate position under the limited, stop gear is including being a plurality of gag lever posts that the slope set up and a plurality of connecting rods of being connected the gag lever post with lower mounting panel, the one end and the elevator well inner wall butt of gag lever post, the other end and the floor board upper end butt of gag lever post, with floor board upper end butt the one end downward sloping of gag lever post, the one end of connecting rod all is fixed in mounting panel lower extreme down, the other end and the gag lever post of connecting rod are connected, mounting panel lateral wall and elevator well inner wall connection down.
Through adopting above-mentioned technical scheme, after the construction of the elevator well of accomplishing a floor, will descend mounting panel and stop gear to dismantle and install in the elevator well of the floor that is located the top, no longer need set up the scaffold frame layer upon layer in the elevator well this moment, reduced set up and dismantled the required time of scaffold frame, increased the efficiency of work.
The invention is further configured to: a set of stop gear's gag lever post is connected with the butt piece jointly, the inner wall butt in elevator door opening is seted up with the elevator well to the butt piece.
Through adopting above-mentioned technical scheme, utilize the butt joint piece to inject the position of gag lever post, make the gag lever post can not take place to keep away from the removal of elevator well to make stop gear's use more stable.
The invention is further configured to: the upper end of the lower mounting plate is connected with an upper mounting plate, the lower end of the upper mounting plate is also connected with a limiting mechanism, the upper end of a connecting rod of the limiting mechanism connected with the upper mounting plate is fixedly connected with the lower end face of the upper mounting plate, a driving mechanism enabling the upper mounting plate and the lower mounting plate to alternatively climb is arranged between the upper mounting plate and the lower mounting plate, the driving mechanism comprises a lead screw and a motor driving the lead screw to rotate, the lower end of the lead screw penetrates through the lower mounting plate and is in threaded connection with the lower mounting plate, the upper end of the lead screw penetrates through the upper mounting plate and is coaxially fixed with a worm wheel, an output shaft of the motor is coaxially fixed with a worm, and the worm wheel is meshed with the worm.
Through adopting above-mentioned technical scheme, go up the mounting panel and can upwards remove in turn with lower mounting panel under actuating mechanism's drive, no longer need at this moment remove the construction material of placing on last mounting panel and the lower mounting panel again to the process that makes the construction is more convenient.
The invention is further configured to: the gag lever post all is articulated with the connecting rod lower extreme, and the gag lever post is the level setting with the articulated axis of connecting rod.
Through adopting above-mentioned technical scheme, when last mounting panel and lower mounting panel rebound, thereby the gag lever post can take place to rotate and can not produce the hindrance to stop gear's removal, no longer need dismantle stop gear and reinstall this moment to it is more convenient to make the use of protection platform.
The invention is further configured to: the equal fixedly connected with spring in gag lever post lateral wall upper end, the upper end and the last mounting panel of spring or mounting panel fixed connection down, the spring is located the connecting rod and keeps away from one side of elevator door opening.
Through adopting above-mentioned technical scheme, utilize the spring to apply decurrent elasticity to the one end of gag lever post tilt up, make the one end of gag lever post tilt up rotate downwards, no longer need the manual work to rotate the gag lever post this moment and make it pass the elevator door opening to it is more convenient to make guiding mechanism's use.
The invention is further configured to: the supporting and connecting structure is characterized in that positioning blocks are fixedly connected to two ends of the supporting and connecting block, and the sum of the lengths of the supporting and connecting block and the positioning blocks is larger than the width of the elevator door opening.
Through adopting above-mentioned technical scheme, utilize the locating piece to make the butt piece can't pass through elevator door opening to make guiding mechanism's use can not receive the influence.
The invention is further configured to: go up the up end of mounting panel and the up end of mounting panel down and all be connected with a plurality of guiding mechanism, guiding mechanism include with the guide block of elevator well inner wall butt and two guide bolt of injecing the guide block position, the guide block upper end all runs through has waist type groove, two guide bolt passes waist type groove and last mounting panel or mounting panel threaded connection down.
Through adopting above-mentioned technical scheme, utilize the guide block to prescribe a limit to the position of going up mounting panel and lower mounting panel, make the mounting panel can not take place along the rotation of the articulated axis of connecting rod and gag lever post with lower mounting panel to the use that makes go up mounting panel and lower mounting panel is difficult for receiving the influence.
The invention is further configured to: the guide block is far away from the terminal surface of lead screw and all rotates and is connected with the gyro wheel, the axis of gyro wheel is the level setting, the lateral wall and the elevator well inner wall butt of gyro wheel.
Through adopting above-mentioned technical scheme, utilize the gyro wheel to change the sliding friction of guide block and elevator well inner wall into rolling friction to reduce the frictional force between guide block and the elevator well inner wall, made the difficult production of elevator well inner wall damage.
In conclusion, the invention has the following beneficial effects:
1. the upper mounting plate and the lower mounting plate are alternately moved upwards through the driving mechanism, and the scaffolds do not need to be erected and disassembled layer by layer when the inner wall of the elevator shaft is constructed, so that the time consumed is reduced, and the construction efficiency is improved;
2. the limiting rods in the same limiting mechanism are simultaneously connected with the abutting blocks, and the positions of the limiting rods are limited by the abutting blocks, so that the limiting rods cannot move when supporting the upper mounting plate or the lower mounting plate, and the using process of the protective platform is more stable;
3. utilize the position piece to restrict the removal family of butt joint piece, make the butt joint piece can not pass from the elevator door opening to make stop gear's use be difficult for receiving the influence.
Drawings
FIG. 1 is a perspective view of the present embodiment;
FIG. 2 is a schematic view illustrating the connection between the driving mechanism and the upper mounting plate according to the present embodiment;
fig. 3 is an enlarged view of a portion a of fig. 2.
Description of the drawings: 1. an upper mounting plate; 2. a lower mounting plate; 3. a limiting mechanism; 31. a limiting rod; 32. a connecting rod; 33. a butting block; 34. a spring; 35. positioning blocks; 4. a drive mechanism; 41. a lead screw; 42. a motor; 43. a limiting ring; 44. a worm gear; 45. a worm; 5. a guide mechanism; 51. a guide block; 511. a waist-shaped groove; 52. a guide bolt; 53. and a roller.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
The utility model provides a construction protection platform, as shown in figure 1, including being lower mounting panel 2 and the last mounting panel 1 of rectangle, go up mounting panel 1 lower extreme and 2 lower extremes of lower mounting panel and all be provided with a set of stop gear 3 of injecing both positions, stop gear 3 is including being four gag lever posts 31 that the slope set up and four connecting rods 32 of being connected gag lever post 31 and last mounting panel 1 or lower mounting panel 2. The lower end of the connecting rod 32 is hinged to one limiting rod 31, the hinge axis of the connecting rod and the limiting rod is horizontally arranged, and the upper end of the connecting rod 32 is fixedly connected with the lower end face of the lower mounting plate 2 or the lower end face of the upper mounting plate 1 through bolts. One end of the limiting rod 31 is abutted against the inner wall of the elevator shaft, the other end of the limiting rod is abutted against the upper end of the floor plate, one end of the limiting rod 31 abutted against the floor plate is inclined downwards, and the upper end face of the lower mounting plate 2 or the upper end face of the upper mounting plate 1 is respectively positioned on the same plane as the upper end face of the upper floor plate of the floor plate connected with the limiting rod 31. At the moment, the lower mounting plate 2 and the upper mounting plate 1 are limited in the elevator shaft through the limiting rod 31, so that the positions of the upper mounting plate 1 and the lower mounting plate 2 in the elevator shaft are fixed, the lower mounting plate 2 or the upper mounting plate 1 positioned below is detached and reinstalled in the elevator shaft of a floor needing to be constructed after the construction of the elevator shaft of one floor is completed, and scaffolds do not need to be erected in the elevator shaft layer by layer at the moment, so that the working efficiency is increased, and the cost is reduced.
As shown in fig. 1, since the limiting rod 31 only depends on the friction between the limiting rod 31 and the inner wall of the elevator shaft, the friction between the limiting rod 31 and the upper end surface of the floor plate limits the movement of the limiting rod 31, and when the downward pressure applied by the upper mounting plate 1 or the lower mounting plate 2 received by the limiting rod 31 is greater than the force received by the limiting rod 31 to obstruct the movement of the limiting rod 31, the limiting rod 31 cannot be stably supported. Therefore, the limiting rods 31 of the group of limiting mechanisms 3 are connected with a butt joint block 33 through bolts, and the butt joint block 33 is abutted against the inner wall of the elevator shaft where the elevator door opening is formed. The position of the limiting rod 31 is limited by the abutting block 33, so that the limiting rod 31 cannot move away from the elevator shaft, and the using process of the limiting mechanism 3 is more stable.
As shown in fig. 1, when the inner wall of the elevator shaft on the upper floor is machined, the limiting mechanism 3 connected to the upper mounting plate 1 or the lower mounting plate 2 needs to be detached, and then the upper mounting plate 1 and the limiting mechanism 3 connected thereto or the lower mounting plate 2 and the limiting mechanism 3 connected thereto are moved to the upper floor for installation again, which is still troublesome. Therefore, a driving mechanism 4 for driving the upper mounting plate 1 and the lower mounting plate 2 to alternately ascend and descend is connected between the two mounting plates, and the driving mechanism 4 comprises a lead screw 41 rotatably connected to the lower end of the mounting plates and a motor 42 for driving the lead screw 41 to rotate. The lower end of the screw rod 41 penetrates through the lower mounting plate 2 and is in threaded connection with the lower mounting plate 2, two limiting rings 43 (shown in figure 2) are coaxially welded at the upper end of the screw rod 41, and the upper mounting plate 1 is clamped by the two limiting rings 43. The upper end of the screw rod 41 penetrates through the upper mounting plate 1 and is coaxially connected with a worm wheel 44 by using a flat key, the motor 42 is fixed on the upper end surface of the upper mounting plate 1 by using bolts, the output shaft of the motor is coaxially connected with a worm 45 by using a flat key, and the worm 45 is meshed with the worm wheel 44. After the construction of the elevator well of accomplishing a floor, stop gear 3 that will be located the below is dismantled, utilize actuating mechanism 4 to drive the last mounting panel 1 that is located the below or mounting panel 2 rebound to the last floor that makes progress down, install stop gear 3, later dismantle stop gear 3 that will be located the top, utilize actuating mechanism 4 to make the last mounting panel 1 that is located the top or mounting panel 2 rebound to last floor down, the rebound of last mounting panel 1 and lower mounting panel 2 has been accomplished this moment, can continue the elevator well inner wall construction to last floor, and need not shift the material that is used for the construction of placing on last mounting panel 1 and lower mounting panel 2, the process that makes the construction is more convenient.
As shown in fig. 2, the upper mounting plate 1 and the lower mounting plate 2 still need to be manually removed during the process of moving upwards, which is still troublesome. Therefore, the limiting rods 31 are hinged with the lower ends of the connecting rods 32, and the hinge axes of the limiting rods and the connecting rods are horizontally arranged. At this moment, when last mounting panel 1 and lower mounting panel 2 rebound, the one end of gag lever post 31 near butt piece 33 rotates downwards, gag lever post 31 can not produce the hindrance to the rebound of guiding mechanism 5 this moment, when gag lever post 31 removed to the elevator door opening that is located the top in, the manual work is upwards rotated the one end that is close to butt piece 33 gag lever post 31, make gag lever post 31 pass the elevator door opening, guiding mechanism 5 rebound makes the both ends of gag lever post 31 fixed this moment, the ascending lifting of last mounting panel 1 and lower mounting panel 2 has been accomplished this moment, no longer need dismantle guiding mechanism 5 this moment, thereby make protection platform's use more convenient.
As shown in fig. 2, in order to make the use process of the guide mechanism 5 more convenient, springs 34 are welded to the upper ends of the side walls of the limiting rods 31, the upper ends of the springs 34 are welded to the upper mounting plate 1 or the lower mounting plate 2, and the springs 34 are located on one side, away from the elevator door opening, of the connecting rod 32. The spring 34 is used for applying downward elastic force to the end, inclined upwards, of the limiting rod 31, so that the end, inclined upwards, of the limiting rod 31 rotates downwards, the limiting rod 31 does not need to be rotated manually to penetrate through an elevator door opening, and therefore the guide mechanism 5 is more convenient to use.
As shown in fig. 2, when the guide mechanism 5 moves into the elevator door opening located above, the position of the stopper rod 31 is not limited, and the abutting block 33 easily passes through the elevator door opening and is separated from the elevator shaft, and at this time, the abutting block 33 cannot limit the position of the stopper rod 31. Therefore, the two ends of the abutting block 33 are welded with the positioning blocks 35 for limiting the position of the abutting block 33, the sum of the lengths of the two positioning blocks 35 and the abutting block 33 is larger than the width of the elevator door opening, and the abutting block 33 cannot pass through the elevator door opening at the moment, so that the use of the guide mechanism 5 cannot be influenced.
As shown in fig. 3, since the sizes of the different elevator shafts are different, if the upper mounting plate 1 and the lower mounting plate 2 cannot contact the inner wall of the elevator shaft, the upper end surface of the upper mounting plate 1 and the upper end surface of the lower mounting plate 2 are inclined, which may affect the use. Therefore, the upper end surface of the upper mounting plate 1 and the upper end surface of the lower mounting plate 2 are both connected with a plurality of groups of guide mechanisms 5 for limiting the positions of the guide mechanisms 5, the guide mechanisms 5 are respectively connected with four inner walls in the vertical direction of the elevator shaft, and each guide mechanism 5 comprises a guide block 51 abutted against the inner wall of the elevator shaft and two guide bolts 52 for limiting the position of the guide block 51. The upper ends of the guide blocks 51 are all provided with a waist-shaped groove 511 in a penetrating manner, and the two guide bolts 52 are all connected with the upper mounting plate 1 or the lower mounting plate 2 in a threaded manner after penetrating through the waist-shaped groove 511. The positions of the upper mounting plate 1 and the lower mounting plate 2 are limited by the guide blocks 51, so that the upper mounting plate 1 and the lower mounting plate 2 do not rotate along the hinge axis of the connecting rod 32 and the limiting rod 31, and the use of the upper mounting plate 1 and the lower mounting plate 2 is not easily affected.
As shown in fig. 3, the guide blocks 51 may continuously rub against the inner wall of the elevator shaft during the upward movement of the upper mounting plate 1 and the lower mounting plate 2, which may easily damage the inner wall of the elevator shaft. Therefore, the end surfaces of the guide blocks 51 far away from the screw rod 41 are all rotatably connected with rollers 53, the axes of the rollers 53 are horizontally arranged, and the side walls of the rollers are abutted against the inner wall of the elevator shaft. Sliding friction between the guide block 51 and the inner wall of the elevator shaft is changed into rolling friction by the roller 53, so that friction between the guide block 51 and the inner wall of the elevator shaft is reduced, and the inner wall of the elevator shaft is not easy to damage.
The working principle is as follows:
when in use, the limiting mechanism 3 connected with the lower mounting plate 2 is placed in an elevator shaft, then the lower mounting plate 2 is in threaded connection with the connecting rod 32, and then the position of the guide block 51 is adjusted to enable the roller 53 to be abutted against the inner wall of the elevator shaft, so that the upper end surface of the lower mounting plate 2 is kept horizontal. Then, the limiting mechanism 3 connected with the upper mounting plate 1 is arranged in the elevator shaft and positioned at the upper end of the lower mounting plate 2, the upper mounting plate 1 is connected with the limiting mechanism 3, the position of a guide block 51 connected with the limiting mechanism is adjusted, then the screw rod 41 is connected with the lower mounting plate 2, the motor 42 is mounted, and construction can be carried out at the moment. After the construction of one floor is completed, the motor 42 drives the screw 41 to rotate, so as to drive the lower mounting plate 2 to move upwards to the floor above and enable the lower end of the limiting rod 31 to pass through the elevator door opening, and then the motor 42 rotates reversely to enable the lower mounting plate 2 to move downwards so as to enable the upper end of the limiting rod 31 to be abutted against the inner wall of the elevator shaft and enable the abutting block 33 to be abutted against the inner wall of the elevator shaft. Then the motor 42 continues to rotate to move the upper mounting plate 1 upwards, so that the upper mounting plate 1 moves to be fixed at the upper floor.
The embodiments of the present invention are all preferred embodiments of the present invention, and the scope of the present invention is not limited thereby, so: all equivalent changes made according to the structure, shape and principle of the invention are covered by the protection scope of the invention.

Claims (4)

1. The utility model provides a construction protection platform which characterized in that: comprises a lower mounting plate (2), the lower end of the lower mounting plate (2) is provided with a limiting mechanism (3) for limiting the position of the lower mounting plate (2), the limiting mechanism (3) comprises a plurality of limiting rods (31) which are obliquely arranged and a plurality of connecting rods (32) for connecting the limiting rods (31) with the lower mounting plate (2), one end of each limiting rod (31) is abutted against the inner wall of an elevator shaft, the other end of each limiting rod (31) is abutted against the upper end of a floor plate, one end of each limiting rod (31) which is abutted against the upper end of the floor plate is inclined downwards, one end of each connecting rod (32) is fixed at the lower end of the lower mounting plate (2), the other end of each connecting rod (32) is connected with the corresponding limiting rod (31), the side wall of the lower mounting plate (2) is connected with the inner wall of the elevator shaft, the limiting rods are hinged with the lower ends of the connecting rods, and the limiting rods and the hinged axes of the connecting rods are horizontally arranged, the limiting rods of the limiting mechanisms are connected with a butting block together, the butting block is butted with the inner wall, provided with an elevator door opening, of an elevator shaft, springs are welded at the upper ends of the side walls of the limiting rods, the upper ends of the springs are welded with the lower mounting plate, and the springs are located on one side, away from the elevator door opening, of the connecting rods;
The upper end of the lower mounting plate (2) is connected with an upper mounting plate (1), the lower end of the upper mounting plate (1) is connected with a limiting mechanism (3) for limiting the position of the upper mounting plate, the upper end of a connecting rod (32) of the limiting mechanism (3) connected with the upper mounting plate (1) is fixedly connected with the lower end face of the upper mounting plate (1), a driving mechanism (4) for enabling the upper mounting plate (1) and the lower mounting plate (2) to alternately climb is arranged between the upper mounting plate (1) and the lower mounting plate (2), the driving mechanism (4) comprises a lead screw (41) which is rotatably connected with the upper mounting plate (1) and a motor (42) which drives the lead screw (41) to rotate, the lower end of the lead screw (41) penetrates through the lower mounting plate (2) and is in threaded connection with the lower mounting plate (2), the upper end of the lead screw (41) penetrates through the upper mounting plate (1) and is coaxially fixed with a worm wheel (44), and an output shaft of the motor (42) is coaxially fixed with a worm (45), the worm wheel (44) is meshed with the worm (45).
2. The building construction protection platform of claim 1, characterized in that: the elevator door opening is characterized in that positioning blocks (35) are fixedly connected to two ends of the abutting block (33), and the sum of the lengths of the abutting block (33) and the positioning blocks (35) is larger than the width of the elevator door opening.
3. The building construction protection platform of claim 1, characterized in that: go up the up end of mounting panel (1) and the up end of lower mounting panel (2) and all be connected with a plurality of guiding mechanism (5), guiding mechanism (5) include with guide block (51) of elevator well inner wall butt and two guide bolt (52) of injecing guide block (51) position, guide block (51) upper end has all run through waist type groove (511), two guide bolt (52) pass waist type groove (511) and last mounting panel (1) or mounting panel (2) threaded connection down.
4. The building construction protection platform of claim 3, characterized in that: the terminal surface that lead screw (41) were kept away from in guide block (51) all rotates and is connected with gyro wheel (53), the axis of gyro wheel (53) is the level setting, the lateral wall and the elevator well inner wall butt of gyro wheel (53).
CN201910996903.2A 2019-10-19 2019-10-19 A construction protection platform Expired - Fee Related CN110644761B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910996903.2A CN110644761B (en) 2019-10-19 2019-10-19 A construction protection platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910996903.2A CN110644761B (en) 2019-10-19 2019-10-19 A construction protection platform

Publications (2)

Publication Number Publication Date
CN110644761A CN110644761A (en) 2020-01-03
CN110644761B true CN110644761B (en) 2022-06-28

Family

ID=69013122

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910996903.2A Expired - Fee Related CN110644761B (en) 2019-10-19 2019-10-19 A construction protection platform

Country Status (1)

Country Link
CN (1) CN110644761B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113775164B (en) * 2021-10-12 2022-09-30 福建省建融工程建设有限公司 Construction platform for building elevator shaft
CN116427686B (en) * 2023-04-11 2026-02-13 北京国际建设集团有限公司 A self-climbing elevator shaft operating platform

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2641018A1 (en) * 1988-12-22 1990-06-29 Otis Elevator Co Building-site scaffolding to be climbed in particular in elevator hoppers
CN204435922U (en) * 2015-02-10 2015-07-01 中冶建工集团有限公司 Protection device of elevator shaft
CN205654103U (en) * 2016-05-06 2016-10-19 浙江欣捷建设有限公司 Loading and unloading formula operation platform
CN107975233B (en) * 2018-01-11 2023-07-14 山东方正建筑新型材料有限公司 Elevator shaft inner formwork balance system

Also Published As

Publication number Publication date
CN110644761A (en) 2020-01-03

Similar Documents

Publication Publication Date Title
CN109356632B (en) Temporary supporting equipment for tunnel bridge construction
CN114961306B (en) Winding device for curing film of concrete column
CN116181113B (en) Support system for mounting assembly type building and construction method
CN114382296B (en) Adjustable tooling for truss installation and construction method thereof
CN110644761B (en) A construction protection platform
CN115162199A (en) Steel box girder segment field installation accurate positioning device and construction method
CN114655837A (en) A prefabricated wall auxiliary installation device
CN111573262A (en) Stacking device with staggered stacking structure for H steel production
KR100475544B1 (en) Wall form climbing system for constructing concrete wall of high-rise buldings
CN114673370A (en) Be used for quick location erection equipment of prefabricated building
CN218265127U (en) Reinforcing device for a steel structure workshop
CN217172933U (en) Balanced girder steel of hoist and mount of assembled stair hoist and mount usefulness
CN218292712U (en) But height-adjusting's scaffold frame for house construction
CN218508973U (en) Early-dismantling support frame for house civil engineering
CN211161302U (en) Multifunctional straightening equipment for H-beam processing
CN214456322U (en) Road and bridge component hoisting structure
CN117263017B (en) Novel steel construction house AAC board hoist and mount are supplementary device
CN111764567B (en) Roof keel installation construction method
CN108755384A (en) A kind of belt track free cantilever erection steel girder bridge and its construction method
CN210480655U (en) An assembled lighting roof glass hoisting machine
CN205893923U (en) A fast dismantle device that steel construction was demolishd in was used for narrow space
CN117552612B (en) A prefabricated building construction platform and its construction method
CN217618695U (en) Jig frame for assembling pipe truss
CN216587861U (en) Building structure reinforcing apparatus
CN224077921U (en) Concrete pavement elevation control device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20220628