CN110629782A - Foundation bolt offline assembling device and adjusting method thereof - Google Patents
Foundation bolt offline assembling device and adjusting method thereof Download PDFInfo
- Publication number
- CN110629782A CN110629782A CN201910845778.5A CN201910845778A CN110629782A CN 110629782 A CN110629782 A CN 110629782A CN 201910845778 A CN201910845778 A CN 201910845778A CN 110629782 A CN110629782 A CN 110629782A
- Authority
- CN
- China
- Prior art keywords
- positioning
- adjustable
- foundation bolt
- holes
- foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 19
- 229910000831 Steel Inorganic materials 0.000 claims description 20
- 239000010959 steel Substances 0.000 claims description 20
- 229910001294 Reinforcing steel Inorganic materials 0.000 abstract description 7
- 239000002699 waste material Substances 0.000 abstract description 5
- 239000004568 cement Substances 0.000 abstract 1
- 238000009434 installation Methods 0.000 description 12
- 238000010276 construction Methods 0.000 description 9
- 230000002787 reinforcement Effects 0.000 description 6
- 239000000463 material Substances 0.000 description 5
- 238000003466 welding Methods 0.000 description 5
- 238000010586 diagram Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 230000003014 reinforcing effect Effects 0.000 description 2
- 230000006978 adaptation Effects 0.000 description 1
- 238000004873 anchoring Methods 0.000 description 1
- 238000012790 confirmation Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 238000006073 displacement reaction Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000008092 positive effect Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000012797 qualification Methods 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/32—Foundations for special purposes
- E02D27/42—Foundations for poles, masts or chimneys
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/18—Adjusting tools; Templates
- E04G21/1841—Means for positioning building parts or elements
- E04G21/185—Means for positioning building parts or elements for anchoring elements or elements to be incorporated in the structure
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Foundations (AREA)
Abstract
The invention provides an offline assembling device for foundation bolts, which comprises a fixed part, a positioning part and an adjustable part, wherein the positioning part is embedded in the fixed part and is arranged above the adjustable part; the adjustable part is perpendicular to the longitudinal axis direction of the fixed part and detachably connected with the fixed part, and the adjustable part horizontally penetrates through the fixed part and the adjustable part in sequence. The invention further provides an adjusting method of the offline assembling device for the foundation bolt. The device designed by the invention has a simple structure, is assembled off-line before bolts are installed, fixes all foundation bolts and binds reinforcing steel bars after the bolts are installed, thereby avoiding rework, reducing labor input and reinforcing steel bar waste, and reducing the offset caused by the impact of cement on the foundation bolts in the pouring process to the maximum extent.
Description
Technical Field
The invention belongs to the technical field of construction steel structure installation auxiliary devices, and particularly relates to a foundation bolt offline assembling device and an adjusting method thereof.
Background
The prior art method is mostly used for installing bolts in a foundation after steel bars are bound, because the steel bars are bound, the bound steel bars need to be cut during bolt installation, the bolts need to be recovered and reinforced after the bolt installation, the construction efficiency is low, materials are wasted, the cost is high, and the popularization of the bolt installation technology is not facilitated.
Disadvantages of the prior art
1. After the steel bars are bound, the bolts are installed to damage the original steel bar cage;
2. after the bolts are installed, the original reinforcement cage needs to be restored and reinforced, so that the construction efficiency is reduced, and the cost is increased;
3. rag bolt fixes on the steel reinforcement cage, and concrete placement in-process impact force can lead to the steel reinforcement cage to produce the displacement to lead to rag bolt skew, the accuracy can't be guaranteed.
Disclosure of Invention
The invention aims to solve the problem of providing an offline assembling device for foundation bolts and an adjusting method thereof. The bolt fixing is an independent system and is not connected with an original steel bar cage, so that the offset generated by impact force in the pouring process is ensured to have no influence on the bolt fixing system.
In order to solve the technical problems, the invention adopts the technical scheme that:
an offline assembling device for foundation bolts comprises a fixed part, a positioning part and an adjustable part, wherein the positioning part is embedded in the fixed part and is arranged above the adjustable part, a plurality of groups of first through holes are formed in the positioning part, the foundation bolts penetrate through the first through holes to be vertically arranged, and the positioning part is perpendicular to the fixed part and is arranged in parallel with the adjustable part; the adjustable part is perpendicular to the direction of the longitudinal axis of the fixed part, the adjustable part is detachably connected with the fixed part, and the adjustable part horizontally penetrates through the fixed part and the adjustable part in sequence.
Furthermore, the fixing part comprises a plurality of first supports and second supports which are arranged in parallel, the first supports and the second supports are arranged perpendicularly, and the first supports and the positioning parts are arranged in parallel.
Furthermore, the first support is arranged at two ends of the second support, and the first support is connected in a tail-ending manner to form a square structure.
Furthermore, the second support is the angle steel of right angle shape structure, and adjacent setting the side that the second support counterpoint set up all is equipped with the second through-hole of one row of vertical setting, the second through-hole evenly sets up on the second support, just the adjustable portion level runs through the second through-hole setting.
Furthermore, location portion includes the locating plate that a plurality of groups set up side by side, the locating plate cross section is the recess type structure, the opening of locating plate is close to adjustable portion one side sets up.
Furthermore, the first through holes are uniformly formed in the upper end plane of the positioning plate, and the first through holes are arranged in two rows and in longitudinal rows.
Furthermore, a plurality of third through holes are symmetrically arranged on the side surface of the positioning plate, and the third through holes are matched with the adjustable part.
Furthermore, a side plate is arranged on one side, close to the adjustable part, of the positioning plate.
Furthermore, the adjustable part comprises a plurality of supporting pieces, and each positioning plate is provided with four supporting pieces.
An adjusting method of an offline assembling device for a foundation bolt, which adopts the device as any one of the above, comprises the following steps:
s1: assembling the fixing part, and placing the fixing part at a position where the foundation bolt is arranged;
s2: determining the height of the positioning part according to the position of the foundation bolt, and enabling the adjustable part to sequentially penetrate through the fixing part and the positioning part so as to fix the positioning part on the fixing part;
s3: arranging the foundation bolt through the first through hole in the positioning part, adjusting the position of the foundation bolt, ensuring that the foundation bolt is horizontally placed on the upper end surface of the positioning part and is perpendicular to the positioning part;
s4: and after the foundation bolt is fixed, the adjustable part, the positioning part and the fixing part are sequentially detached.
Compared with the prior art, the off-line assembling device can not only ensure the accuracy of the relative position and the verticality of the foundation bolt group, but also ensure the consistent elevation of the foundation bolt group; the device is simple to manufacture, the materials are convenient to obtain on the spot, the occupied space is small, the fixing materials of the foundation bolt group are saved, the forming is firm, the foundation bolt group is not easy to deform, and the assembled foundation bolt group can be transported to a construction site at any time for installation.
Drawings
FIG. 1 is a schematic structural diagram of an offline assembly apparatus for a rag bolt according to an embodiment of the present invention;
FIG. 2 is a cross-sectional view A-A of one embodiment of the present invention;
FIG. 3 is a schematic structural diagram of a fixing portion according to an embodiment of the present invention;
FIG. 4 is a top view of a positioning portion of an embodiment of the present invention;
FIG. 5 is a front view of a positioning portion according to an embodiment of the present invention;
fig. 6 is a plan view of a positioning portion according to another embodiment of the present invention.
In the figure:
10. fixed part 11, first support plate 12, second support plate
13. Second through hole 20, positioning part 21 and positioning plate
22. First through hole 23, third through hole 30, adjustable portion
40. Foundation bolt
Detailed Description
The invention is further illustrated by the following examples and figures:
an off-line assembling device for foundation bolts according to an embodiment of the present invention, as shown in fig. 1-2, includes a fixing portion 10, a positioning portion 20 and an adjustable portion 30, wherein the positioning portion 20 is embedded in the fixing portion 10 and is disposed above the adjustable portion 30, a plurality of sets of first through holes 22 are disposed inside the positioning portion 10, the foundation bolts 40 are vertically disposed through the first through holes 22, and the positioning portion 20 is disposed perpendicular to the fixing portion 10 and parallel to the adjustable portion 30. The adjustable part 30 is perpendicular to the vertical axis direction of the fixing part 10, the adjustable part 30 is detachably connected with the fixing part 10, and the adjustable part 30 horizontally penetrates through the fixing part 10 and the adjustable part 20 in sequence to be fixedly arranged.
Specifically, as shown in fig. 2-3, the fixing portion 10 includes a plurality of first brackets 11 and second brackets 12 arranged in parallel, the first brackets 11 are arranged perpendicular to the second brackets 12, and the first brackets 11 are arranged parallel to the positioning portion 20, that is, the first brackets 11 and the positioning portion 20 are both arranged horizontally and horizontally. First support 11 fixed welding is in the both ends department of second support 12, and first support 11 connects the welding in the end and encloses into a rectangle or square structure, and the inner structure of fixed part 10 and the outer wall structure looks adaptation of location portion 20. Second support 12 is the angle steel of right angle shape structure, all is equipped with the second through-hole 13 of a row of vertical setting at the side that the counterpoint of the second support 12 of adjacent setting set up, and second through-hole 13 evenly sets up on second support 12, and adjustable portion 30 level runs through the setting of second through-hole 13. Specifically, as shown in fig. 2, the positioning portion 30 is fitted to the second through hole 13.
Further, as shown in fig. 4-6, the positioning portion 20 includes a plurality of sets of positioning plates 21 arranged in parallel, the cross section of the positioning plate 21 is a groove-shaped structure, and an opening of the positioning plate 21 is disposed near one side of the adjustable portion 30, that is, the opening is disposed downward. The first through holes 22 are uniformly formed in the upper end plane of the positioning plate 21, the first through holes 22 penetrate through the positioning plate 21, and the first through holes 22 are formed in two rows of longitudinal rows and are used for being matched with the foundation bolts 40. Specifically, on the positioning plate 21, two first through holes 22 are provided per column, as shown in fig. 5; on the positioning plate 21, three first through holes 22 are provided in each column, as shown in fig. 6; the arrangement of the first through holes 22 on the positioning plate 21 is consistent with the number and the positions of the foundation bolts 40; the columns and the rows of the first through holes 22 can be changed at any time, which can be determined according to the actual working conditions, but the positions of the first through holes 22 which must be arranged up and down correspond to each other, and in this embodiment, three positioning plates 21 are provided. A side plate is arranged on one side of the positioning plate 21 close to the adjustable part 30, a plurality of third through holes 23 are symmetrically arranged on one side of the side plate surface, and the third through holes 23 are matched with the adjustable part 30 and are the same in number.
The adjustable portion 30 includes a plurality of supporting members, four supporting members are disposed around each positioning plate 21, preferably, the supporting members are bolts, and the bolts penetrate through the second through holes 13 and the third through holes 23 to fix the positioning plate 21 on the frame of the fixing portion 10, so that the stability of the whole device can be ensured.
An adjusting method of an offline assembling device for a foundation bolt, which adopts the device as any one of the above, comprises the following steps:
s1: the fixing part 10 is assembled, and the fixing part 10 is placed at the position of the set anchor bolt 40.
S2: the height of the fixing part 20 is determined according to the position of the anchor bolt 40, and the adjustable part 30 is sequentially disposed through the fixing part 10 and the fixing part 20 such that the fixing part 20 is fixed to the fixing part 10.
S3: the anchor bolts 40 are arranged to penetrate through the first through holes 22 in the positioning portion 20, the positions of the anchor bolts 40 are adjusted, and it is ensured that the anchor bolts 40 are horizontally placed on the horizontal surface of the positioning portion 20 in a consistent manner, fixed on the upper end surface of the positioning portion 20, and arranged perpendicular to the positioning portion 20.
S4: after the anchor bolt 40 is fixed, the adjustable portion 30, the positioning portion 20 and the fixing portion 10 are removed in sequence, and the removal work is completed.
This technique adopts fixed part 10, location portion 20 and adjustable portion 30 to make into assembly device, and fixed part 10 uses first support 11 and second support 12 all to adopt the angle steel, assembles the welding jointly into a cuboid, guarantees "violently flat vertical" among the welding process. One side of the position, which is adjacent to the central axis of the near side surface in the vertical direction of the first support 11, is provided with a row of uniformly distributed second through holes 13, the positioning part 20 is fixed on the fixing part 10 through a support part of the adjustable part 30, and the plurality of second through holes 13 are uniformly arranged in the vertical direction of the first support 11, so that the position of the positioning plate 21 can be quickly fixed, and the positioning plate 21 can be stably installed on the fixing part 10. At least two sets of quick supporting pieces are manufactured according to the adjustable part 30, the positioning plates 21 are fixed, the relative positions of the supporting pieces ensure accurate positioning, different supporting pieces can be correspondingly adjusted, and the positioning plate 21 positioned at the lowermost end avoids the phenomenon of different heights and influences the installation of upper structures/equipment in order to ensure the consistency of the whole elevation of the foundation bolt 40.
A level may be used to ensure that the anchoring portion 10 is level and upright. The positioning part 30 comprises at least two groups of positioning plates 21 which are horizontally arranged, the positioning plate 21 at the lower end can be matched with the adjustable part 30 and can be adjusted according to the length of the adjustable part 30, and the fixed part 10 is formed by welding reinforcing steel bar waste or angle steel waste after position confirmation. The adjustable part 30 can realize the accurate location of location portion 20 on fixed part 10, place rag bolt 40 on the up end of the locating plate 21 of lowermost end back again, run through the locating plate 21 of upper end again to adjust the relative position and the straightness that hangs down of rag bolt 40 through this locating plate 21. Can use the reinforcing bar to be in the same place rag bolt 40 interconnect after the installation is accomplished, ensure rag bolt 40 firm connection, demolish adjustable portion 30, location portion 20 and fixed part 10 in proper order again, accomplish the dismantlement work, and then demolish back rag bolt 40 and can not warp. The next process is carried out after the fixing of the foundation bolt 40 is completed, the foundation bolt 40 which is processed is arranged in the bearing platform, the installation precision of the foundation bolt 40 can be guaranteed only by rechecking the axis and the elevation, the time and the operation are saved, and the processing efficiency can be effectively improved. According to the invention, offline assembly is carried out before the foundation bolts 40 are installed, and reinforcement is bound after all the foundation bolts 40 are fixed and installed, so that rework is avoided, and labor input and reinforcement waste are reduced.
In a new energy engineering project of Dongri-Nissan Tang province, two identical plants are provided, the foundation anchor bolts 40 are M56, wherein a 1# roasting furnace workshop adopts a traditional process, namely, steel bars are firstly bound, then the anchor bolts 40 are installed, and a 2# roasting furnace workshop adopts the technology of the invention, namely, the anchor bolts 40 are firstly installed off line, and then the steel bars are bound. The method comprises the following steps of pouring a foundation cushion of a workshop of the No. 1 roasting furnace for 1 day, maintaining and positioning the cushion for 1 day, binding steel bars for 5 days, positioning and cutting the steel bars influencing bolt installation, wherein the construction period is 1 day, the bolt installation adjustment time is 3 days, the steel bar recovery and reinforcement time is 1 day, a template is reinforced for 3 days, concrete pouring is 1 day, and the total construction period is 16 days. A2 # roasting furnace workshop foundation cushion layer is 1 day, positioning and paying off are carried out for 1 day, bolt offline assembly and cushion layer pouring are carried out synchronously, the time is 2 days, the bolt installation time is 1 day, reinforcing steel bars are bound for 5 days, a template is reinforced for 3 days, concrete pouring is carried out for 1 day, and the total construction period is 12 days. The total construction period is saved by 4 days, the qualification rate of foundation bolts in a workshop of the 2# roasting furnace is 100%, a small amount of foundation bolts in the workshop of the 1# roasting furnace need to be adjusted, and each basic reinforcing rib consumes 12.64kg after the reinforcing steel bars are cut.
The invention has the advantages and positive effects that:
compared with the prior art, the off-line assembling device can not only ensure the accuracy of the relative position and the verticality of the foundation bolt group, but also ensure the consistent elevation of the foundation bolt group; the device is simple to manufacture, the materials are convenient to obtain on the spot, the occupied space is small, the fixing materials of the foundation bolt group are saved, the forming is firm, the foundation bolt group is not easy to deform, and the assembled foundation bolt group can be transported to a construction site at any time for installation. Off-line assembly is carried out before the bolts are installed, all foundation bolts are fixed and are then bound with reinforcing steel bars after being installed, rework is avoided, and labor input and reinforcing steel bar waste are reduced. The bolt fixing is an independent system and is not connected with an original steel bar cage, so that the offset generated by impact force in the pouring process is ensured to have no influence on the bolt fixing system.
The embodiments of the present invention have been described in detail, and the description is only for the preferred embodiments of the present invention and should not be construed as limiting the scope of the present invention. All equivalent changes and modifications made within the scope of the present invention shall fall within the scope of the present invention.
Claims (10)
1. The device for assembling the foundation bolt off line is characterized by comprising a fixed part, a positioning part and an adjustable part, wherein the positioning part is embedded in the fixed part and is arranged above the adjustable part, a plurality of groups of first through holes are formed in the positioning part, the foundation bolt penetrates through the first through holes to be vertically arranged, and the positioning part is perpendicular to the fixed part and is arranged in parallel with the adjustable part; the adjustable part is perpendicular to the direction of the longitudinal axis of the fixed part, the adjustable part is detachably connected with the fixed part, and the adjustable part horizontally penetrates through the fixed part and the adjustable part in sequence.
2. The offline assembly device for the foundation bolt according to claim 1, wherein the fixing portion comprises a plurality of first brackets and second brackets which are arranged in parallel, the first brackets and the second brackets are arranged vertically, and the first brackets and the positioning portions are arranged in parallel.
3. The offline assembly device for the foundation bolt as claimed in claim 2, wherein the first bracket is disposed at two ends of the second bracket, and the first bracket is connected in a closed end to form a square structure.
4. The offline assembly device for the foundation bolts as claimed in claim 3, wherein the second brackets are angle steels with right-angle structures, a row of second through holes which are vertically arranged are respectively arranged on the side edges of the adjacently arranged second brackets which are aligned, the second through holes are uniformly arranged on the second brackets, and the adjustable portions horizontally penetrate through the second through holes.
5. The offline assembly device for the foundation bolt according to any one of claims 1 to 4, wherein the positioning portion comprises a plurality of groups of positioning plates arranged side by side, the cross section of each positioning plate is of a groove-shaped structure, and an opening of each positioning plate is arranged close to one side of the adjustable portion.
6. The offline assembly device for the foundation bolt as claimed in claim 5, wherein the first through holes are uniformly arranged on the upper end plane of the positioning plate, and the first through holes are arranged in two rows and in longitudinal columns.
7. The offline assembly device for the floor bolt as recited in claim 6, wherein a plurality of third through holes are symmetrically formed on the side surface of the positioning plate, and the third through holes are matched with the adjustable part.
8. The offline assembly device for the foundation bolt as claimed in claim 7, wherein a side plate is disposed on one side of the positioning plate close to the adjustable portion.
9. The offline assembly device for an anchor bolt as recited in claim 8, wherein said adjustable portion comprises a plurality of supporting members, and each of said positioning plates is provided with four of said supporting members.
10. A method for adjusting an offline assembling device of a foundation bolt, which is characterized in that the device according to any one of claims 1-9 is adopted, and the method comprises the following steps:
s1: assembling the fixing part, and placing the fixing part at a position where the foundation bolt is arranged;
s2: determining the height of the positioning part according to the position of the foundation bolt, and enabling the adjustable part to sequentially penetrate through the fixing part and the positioning part so as to fix the positioning part on the fixing part;
s3: arranging the foundation bolt through the first through hole in the positioning part, adjusting the position of the foundation bolt, ensuring that the foundation bolt is horizontally placed on the upper end surface of the positioning part and is perpendicular to the positioning part;
s4: and after the foundation bolt is fixed, the adjustable part, the positioning part and the fixing part are sequentially detached.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910845778.5A CN110629782B (en) | 2019-09-02 | 2019-09-02 | Adjusting method of anchor bolt offline assembly device |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910845778.5A CN110629782B (en) | 2019-09-02 | 2019-09-02 | Adjusting method of anchor bolt offline assembly device |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN110629782A true CN110629782A (en) | 2019-12-31 |
| CN110629782B CN110629782B (en) | 2024-03-26 |
Family
ID=68971986
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201910845778.5A Active CN110629782B (en) | 2019-09-02 | 2019-09-02 | Adjusting method of anchor bolt offline assembly device |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN110629782B (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111254968A (en) * | 2020-01-19 | 2020-06-09 | 中国十七冶集团有限公司 | Installation device and installation method for large-diameter embedded bolt of large-scale equipment foundation |
| CN113202133A (en) * | 2021-04-12 | 2021-08-03 | 北京首钢建设集团有限公司 | Method for mounting large equipment foundation high and large bolt sleeve |
Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101338566A (en) * | 2008-08-29 | 2009-01-07 | 河北省第四建筑工程公司 | Integral built-in process for groups of anchor bolts |
| CN202611258U (en) * | 2012-05-22 | 2012-12-19 | 天津二十冶建设有限公司 | Large-diameter foundation bolt assembly bracket |
| CN204040056U (en) * | 2014-06-26 | 2014-12-24 | 中国建筑第八工程局有限公司 | A kind of location and installation support of pre-embedded anchoring bolts |
| CN204059395U (en) * | 2014-07-14 | 2014-12-31 | 中国建筑第八工程局有限公司 | The pre-buried location structure of stone bolt |
| CN108222056A (en) * | 2018-03-06 | 2018-06-29 | 防城港中重工有限公司 | Apparatus foundation bolt group's installation method |
| CN109914462A (en) * | 2019-04-03 | 2019-06-21 | 江铃汽车集团江西工程建设有限公司 | A kind of locating support and construction method of steel column embedding anchor bolts |
| CN110080273A (en) * | 2019-04-30 | 2019-08-02 | 中国化学工程第六建设有限公司 | The method for carrying out the installation of steel construction foundation bolt using flitch |
| CN209324004U (en) * | 2018-10-23 | 2019-08-30 | 中建八局第二建设有限公司 | A kind of overhead section of contact net foundation bolt offsetting adjustment device of subway |
| CN211395731U (en) * | 2019-09-02 | 2020-09-01 | 中冶天工集团有限公司 | Foundation bolt off-line assembly device |
-
2019
- 2019-09-02 CN CN201910845778.5A patent/CN110629782B/en active Active
Patent Citations (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101338566A (en) * | 2008-08-29 | 2009-01-07 | 河北省第四建筑工程公司 | Integral built-in process for groups of anchor bolts |
| CN202611258U (en) * | 2012-05-22 | 2012-12-19 | 天津二十冶建设有限公司 | Large-diameter foundation bolt assembly bracket |
| CN204040056U (en) * | 2014-06-26 | 2014-12-24 | 中国建筑第八工程局有限公司 | A kind of location and installation support of pre-embedded anchoring bolts |
| CN204059395U (en) * | 2014-07-14 | 2014-12-31 | 中国建筑第八工程局有限公司 | The pre-buried location structure of stone bolt |
| CN108222056A (en) * | 2018-03-06 | 2018-06-29 | 防城港中重工有限公司 | Apparatus foundation bolt group's installation method |
| CN209324004U (en) * | 2018-10-23 | 2019-08-30 | 中建八局第二建设有限公司 | A kind of overhead section of contact net foundation bolt offsetting adjustment device of subway |
| CN109914462A (en) * | 2019-04-03 | 2019-06-21 | 江铃汽车集团江西工程建设有限公司 | A kind of locating support and construction method of steel column embedding anchor bolts |
| CN110080273A (en) * | 2019-04-30 | 2019-08-02 | 中国化学工程第六建设有限公司 | The method for carrying out the installation of steel construction foundation bolt using flitch |
| CN211395731U (en) * | 2019-09-02 | 2020-09-01 | 中冶天工集团有限公司 | Foundation bolt off-line assembly device |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111254968A (en) * | 2020-01-19 | 2020-06-09 | 中国十七冶集团有限公司 | Installation device and installation method for large-diameter embedded bolt of large-scale equipment foundation |
| CN113202133A (en) * | 2021-04-12 | 2021-08-03 | 北京首钢建设集团有限公司 | Method for mounting large equipment foundation high and large bolt sleeve |
Also Published As
| Publication number | Publication date |
|---|---|
| CN110629782B (en) | 2024-03-26 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN104695557A (en) | Steel structure building construction method for one-step pre-burying of foundation bolts | |
| CN102619235B (en) | Concrete foundation embedded bolt bracket and embedding method for concrete foundation embedded bolts | |
| CN108222056B (en) | Equipment foundation bolt group installation method | |
| CN202194244U (en) | Positioning support for embedding of ultra-high steel-work pedestals | |
| CN113512940B (en) | Low tower cable-stayed bridge cable beam anchoring block construction process based on adjustable brackets | |
| CN106884541B (en) | Positioning assembly, positioning device and positioning method for reserved dowel bars in shear wall | |
| CN110629782A (en) | Foundation bolt offline assembling device and adjusting method thereof | |
| CN106193330A (en) | A kind of steel building construction land tenure foot bolt pre-embedded construction method | |
| JP5183606B2 (en) | Unit structure of anchor bolt used for foundation construction of equipment and foundation construction method of equipment using it | |
| CN113846607B (en) | Precise positioning and fixing device for embedded bars in cast-in-situ bottom plate of assembled trench side wall and construction method | |
| CN112620353B (en) | Vertical rolling mill frame foundation embedded part installation device and installation adjustment method | |
| CN211395731U (en) | Foundation bolt off-line assembly device | |
| CN111927106B (en) | Auxiliary device for controlling installation interval of reinforcing steel bars | |
| CN203879041U (en) | Embedded plate positioning support frame | |
| CN206034428U (en) | SMW worker method stake shaped steel positioning die | |
| JP3673108B2 (en) | Hollow slab void member installation method | |
| CN217268831U (en) | Descending plate hanging mould supporting construction structure | |
| CN216664746U (en) | Adjustable shear force wall reinforcing bar locating rack | |
| CN215561870U (en) | Sea vase pier steel reinforcement framework limiting device | |
| CN110565675B (en) | Large anchor bolt group mounting bracket of high-strength anchor bolts and construction method thereof | |
| CN218801694U (en) | Reinforced concrete structure tool positioning device and processing platform thereof | |
| CN219509179U (en) | Beam bottom surface formwork appurtenance | |
| CN109252536B (en) | A precise positioning system and positioning method of long thin steel tie rod group | |
| CN113914614A (en) | Construction process for pouring large-volume reinforced concrete beam at one time | |
| CN217924443U (en) | Floor reinforcing bar installation positioner |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |