CN110617072A - Tunnel excavation construction method for obliquely passing existing operation tunnel at minimum clear distance - Google Patents

Tunnel excavation construction method for obliquely passing existing operation tunnel at minimum clear distance Download PDF

Info

Publication number
CN110617072A
CN110617072A CN201911040059.2A CN201911040059A CN110617072A CN 110617072 A CN110617072 A CN 110617072A CN 201911040059 A CN201911040059 A CN 201911040059A CN 110617072 A CN110617072 A CN 110617072A
Authority
CN
China
Prior art keywords
tunnel
existing operating
excavation
area
excavated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911040059.2A
Other languages
Chinese (zh)
Other versions
CN110617072B (en
Inventor
邓成宏
吴志勐
胡云飞
张青
俞然刚
赵耀
冯慧君
王子利
张连震
高子明
陈健
于雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kunming Railway Construction Co Ltd Of Zhong Tiebaju Group
China University of Petroleum East China
Original Assignee
Kunming Railway Construction Co Ltd Of Zhong Tiebaju Group
China University of Petroleum East China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kunming Railway Construction Co Ltd Of Zhong Tiebaju Group, China University of Petroleum East China filed Critical Kunming Railway Construction Co Ltd Of Zhong Tiebaju Group
Priority to CN201911040059.2A priority Critical patent/CN110617072B/en
Publication of CN110617072A publication Critical patent/CN110617072A/en
Application granted granted Critical
Publication of CN110617072B publication Critical patent/CN110617072B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明涉及一种极小净距斜下穿既有运营隧道的隧道开挖施工方法,包括以下步骤:步骤1:获取待开挖隧道掌子面前方岩层分布与围岩物理力学参数;步骤2:对掌子面前方的围岩进行非对称注浆加固;步骤3:预留核心土,采用切削研磨的方式开挖开挖槽,步骤4:在开挖槽中安装支护结构;步骤5:采用切削研磨的方式对预留的核心土进行开挖;步骤3和步骤5中对既有运营隧道的支护应力状态和位移进行监测,步骤6:获得既有运营隧道的差异沉降情况;步骤7:对既有运营隧道差异沉降值大于设定值的区域下方的围岩进行注浆;步骤8:采用步骤1‑7的方法,依次进行多个步距的注浆和开挖工作,本发明的施工方法能够有效保持既有运营隧道的稳定性。

The invention relates to a tunnel excavation construction method for obliquely penetrating an existing operating tunnel with a minimum clear distance, comprising the following steps: Step 1: obtaining the distribution of rock layers in front of the tunnel face to be excavated and physical and mechanical parameters of surrounding rocks; Step 2 : Carry out asymmetric grouting reinforcement to the surrounding rock in front of the face; Step 3: Reserve core soil and excavate the excavation groove by cutting and grinding; Step 4: Install the supporting structure in the excavation groove; Step 5 : Excavate the reserved core soil by cutting and grinding; monitor the support stress state and displacement of the existing operating tunnels in steps 3 and 5, and step 6: obtain the differential settlement of the existing operating tunnels; Step 7: Grouting the surrounding rock below the area where the differential settlement value of the existing operating tunnel is greater than the set value; Step 8: Using the method of Steps 1-7, grouting and excavation in multiple steps are performed in sequence. The construction method of the invention can effectively maintain the stability of the existing operating tunnel.

Description

一种极小净距斜下穿既有运营隧道的隧道开挖施工方法A tunnel excavation construction method for obliquely passing through an existing operating tunnel with a minimal clear distance

技术领域technical field

本发明涉及隧道及地下工程技术领域,具体涉及一种极小净距斜下穿既有运营隧道的隧道开挖施工方法。The invention relates to the technical field of tunnels and underground engineering, in particular to a tunnel excavation construction method for obliquely penetrating an existing operating tunnel with a minimum clear distance.

背景技术Background technique

城市地铁运营隧道线路一般呈网络状分布,不可避免存在线路相互交叉的情况,在新地铁线路建设过程中,大量存在拟建隧道下穿既有运营隧道的情况。下穿隧道开挖施工对既有运营隧道具有显著的扰动影响,常导致既有运营隧道沉降、衬砌结构变形开裂、道床脱空等问题,尤其当拟建隧道以极小净距斜下穿既有运营隧道时,会造成既有运营隧道明显的扭转效应,在垂直运营隧道轴线断面上发生不均匀变形,既有运营隧道靠近拟建隧道一侧沉降变形较大,而另一侧沉降变形较小,隧道结构有可能发生扭转破坏。The urban subway operating tunnel lines are generally distributed in a network, and it is inevitable that the lines will cross each other. During the construction of new subway lines, there are a lot of cases where the proposed tunnels pass through the existing operating tunnels. The excavation of the underpassing tunnel has a significant disturbance impact on the existing operating tunnels, which often lead to problems such as settlement of the existing operating tunnels, deformation and cracking of the lining structure, and voiding of the track bed, especially when the proposed tunnel obliquely underpasses the existing operating tunnel with a very small clear distance. When there are operating tunnels, it will cause obvious torsion effect of the existing operating tunnels, and uneven deformation will occur on the axis section of the vertical operating tunnels. Small, the tunnel structure may suffer torsional failure.

针对极小净距斜下穿既有运营隧道的工况,钻爆法是常用的施工方法,该方法主要采用钻孔爆破的方式破除掌子面前方岩体,从而实现开挖掘进。发明人发现,上述方法存在以下不足:①从短期施工来看,钻爆法施工过程中的爆破冲击力会对拟建隧道掌子面上方岩体造成强烈扰动,围岩强度被降低,当拟建隧道与上方既有运营隧道间距较小时,有可能造成既有运营隧道失稳;②从长期运营来看,由于钻爆施工造成既有运营隧道下方岩体力学性能降低,其抵抗运营列车长期动荷载的能力下降,既有运营隧道地基可能会发生疲劳破坏,无法保证运营隧道的长期稳定性。Drilling and blasting method is a commonly used construction method for the working condition of obliquely penetrating existing operating tunnels with extremely small clear distance. The inventor found that the above method has the following shortcomings: 1. From the perspective of short-term construction, the blasting impact force during the drilling and blasting construction process will cause strong disturbance to the rock mass above the face of the proposed tunnel, and the surrounding rock strength is reduced. When the distance between the construction tunnel and the existing operating tunnel above is small, the existing operating tunnel may become unstable; ② From the perspective of long-term operation, the mechanical properties of the rock mass below the existing operating tunnel are reduced due to drilling and blasting construction, which resists long-term operating trains. The capacity of the dynamic load decreases, and the foundation of the existing operating tunnel may suffer fatigue damage, which cannot guarantee the long-term stability of the operating tunnel.

发明内容SUMMARY OF THE INVENTION

本发明的目的是为克服现有技术的不足,提供一种极小净距斜下穿既有运营隧道的隧道开挖施工方法,能够有效降低对既有运营隧道的扭转效应和扰动,保证了既有运营隧道的稳定性。The purpose of the present invention is to overcome the deficiencies of the prior art, and provide a tunnel excavation construction method for obliquely passing through the existing operating tunnels with a minimum clear distance, which can effectively reduce the torsional effect and disturbance on the existing operating tunnels, and ensure that the Stability of existing operating tunnels.

为实现上述目的,本发明采用下述技术方案:To achieve the above object, the present invention adopts the following technical solutions:

一种极小净距斜下穿既有运营隧道的隧道开挖施工方法,包括以下步骤:A tunnel excavation construction method for obliquely passing through an existing operating tunnel with a minimum clear distance, comprising the following steps:

步骤1:综合地质勘查资料及超前探孔取芯测试结果,获取待开挖隧道掌子面前方隧道开挖影响范围内岩层分布与围岩物理力学参数。Step 1: Based on the geological exploration data and the test results of advanced drilling and coring, obtain the distribution of rock formations and the physical and mechanical parameters of the surrounding rock within the influence area of the tunnel excavation in front of the tunnel face to be excavated.

步骤2:在沿待开挖隧道轴线方向一个步距范围内,对待开挖隧道掌子面前方的围岩进行非对称注浆加固,用于提高待开挖隧道与既有运营隧道重叠区域围岩的力学性能。Step 2: Within a step range along the axis of the tunnel to be excavated, perform asymmetric grouting reinforcement on the surrounding rock in front of the face of the tunnel to be excavated to improve the surrounding area of the overlapping area between the tunnel to be excavated and the existing operating tunnel. mechanical properties of rock.

步骤3:预留核心土,采用切削研磨的方式对掌子面前方岩体开挖出沿待开挖隧道边缘轮廓线设置的深度等于步距的开挖槽,开挖过程中监测既有运营隧道的支护应力状态与位移。Step 3: Reserve core soil, excavate the rock mass in front of the face by cutting and grinding, and excavate trenches with a depth equal to the step distance set along the contour line of the tunnel edge to be excavated, and monitor existing operations during the excavation process. Tunnel support stress state and displacement.

步骤4:在开挖槽中安装支护结构。Step 4: Install the support structure in the excavation trench.

步骤5:采用切削研磨的方式对预留的核心土进行开挖,开挖过程中监测既有运营隧道的支护应力状态与位移。Step 5: The reserved core soil is excavated by cutting and grinding, and the support stress state and displacement of the existing operating tunnels are monitored during the excavation process.

步骤6:根据步骤3和步骤5得到的运营隧道的支护应力状态和位移状态,获得既有运营隧道同一断面上不同位置的差异沉降情况。Step 6: According to the support stress state and displacement state of the operating tunnel obtained in steps 3 and 5, the differential settlement of different positions on the same section of the existing operating tunnel is obtained.

步骤7:通过待开挖隧道掌子面对既有运营隧道差异沉降值大于设定值的区域下方的围岩进行注浆,使既有运营隧道差异沉降值大于设定值的区域的差异沉降值小于设定值。Step 7: grouting the surrounding rock below the area where the differential settlement value of the existing operating tunnel is greater than the set value through the face of the tunnel to be excavated, so as to make the differential settlement of the area where the differential settlement value of the existing operating tunnel is greater than the set value. The value is less than the set value.

步骤8:采用步骤1-步骤7的方法,依次进行沿待开挖隧道轴线方向多个步距的注浆和开挖工作,直至完成所有注浆与开挖工作。Step 8: Using the methods from Step 1 to Step 7, perform grouting and excavation work in multiple steps along the axis direction of the tunnel to be excavated in sequence until all grouting and excavation work is completed.

进一步的,所述步骤2中,非对称注浆加固的围岩的水平范围内区域为待开挖隧道和既有运营隧道在水平面内投影重叠的区域,竖向范围内区域为待开挖隧道轮廓线与既有运营隧道轮廓线之间的区域。Further, in the step 2, the area within the horizontal range of the surrounding rock reinforced by asymmetric grouting is the area where the tunnel to be excavated and the existing operating tunnel are projected and overlapped in the horizontal plane, and the area within the vertical range is the tunnel to be excavated. The area between the contour line and the existing operating tunnel contour line.

进一步的,所述步骤2中,注浆材料采用水泥单液浆,水泥浆液的水灰比范围为0.8-1,水泥浆液水灰比范围要求不能过高或过低,过高的水灰比会导致注浆加固范围内自由水过多,注浆加固效果不满足要求,过低的水灰比会导致浆液的可注性较差,围岩裂隙充填率过低,进而注浆加固效果不满足要求。Further, in the step 2, the grouting material adopts cement single liquid slurry, the water-cement ratio of the cement slurry is in the range of 0.8-1, and the water-cement ratio range of the cement slurry cannot be too high or too low, and an excessively high water-cement ratio It will lead to too much free water in the grouting reinforcement range, and the grouting reinforcement effect does not meet the requirements. Too low water-cement ratio will lead to poor grouting ability of the slurry, and the filling rate of the surrounding rock cracks will be too low, and the grouting reinforcement effect will not be good. fulfil requirements.

进一步的,所述步骤3中,开挖槽的开挖方法为:首先在隧道一侧边墙沿轮廓线切削研磨出第一开挖槽部,然后在另一侧边缘沿轮廓线切削研磨出第二开挖槽部,最后沿隧道拱顶边缘轮廓线切削研磨出第三开挖槽部,第一开挖槽部、第二开挖槽部及第三开挖槽部构成开挖槽。Further, in the step 3, the excavation method of the excavation groove is as follows: firstly, the first excavation groove portion is cut and ground along the contour line on one side wall of the tunnel, and then the other side edge is cut and ground along the contour line. The second excavation groove portion is finally cut and ground along the edge contour of the tunnel vault to form the third excavation groove portion.

进一步的,所述步骤5中,对预留的核心土的切削研磨运动轨迹为自下而上的S型轨迹,核心土的开挖深度与步距相等。Further, in the step 5, the cutting and grinding motion trajectory of the reserved core soil is a bottom-up S-shaped trajectory, and the excavation depth of the core soil is equal to the step distance.

进一步的,所述步骤3和步骤5进行之前,在既有运营隧道内设置多个监测点,用于对支护的应力状态和位移进行监测,所述监测点设置在既有运营隧道设定区域内的多个监测截面上,每个监测截面设置多个监测点,所述设定区域的确定方法为:确定待开挖隧道掌子面在既有运营隧道中所对应的区域,以该区域为中心,沿既有运营隧道轴线前后方向设定距离处为设定区域的边界,两个边界之间为设定区域。Further, before the steps 3 and 5 are carried out, a plurality of monitoring points are set in the existing operating tunnels to monitor the stress state and displacement of the support, and the monitoring points are set in the existing operating tunnels. On a plurality of monitoring sections in the area, each monitoring section is set with a plurality of monitoring points, and the method for determining the set area is: determine the area corresponding to the face of the tunnel to be excavated in the existing operating tunnel, and use the The area is the center, the set distance along the front and rear directions of the existing operating tunnel axis is the boundary of the set area, and the area between the two boundaries is the set area.

进一步的,所述设定距离为待开挖隧道直径的1.5倍,相邻监测截面的距离与步距相等。Further, the set distance is 1.5 times the diameter of the tunnel to be excavated, and the distance between adjacent monitoring sections is equal to the step distance.

进一步的,同一个监测截面中,既有运营隧道的拱顶位置、拱底位置和两个拱腰位置各设置一个监测点,拱顶和两个拱腰的监测点之间分别等间距插入一个监测点,拱底和两个拱腰的监测点之间分别等间距插入一个监测点。Further, in the same monitoring section, one monitoring point is set at the vault position, the vault bottom position and the two vault waist positions of the existing operating tunnel, and one monitoring point is inserted at equal intervals between the monitoring points of the vault and the two vault waists. A monitoring point is inserted at an equal distance between the monitoring points of the arch bottom and the two arch waists respectively.

进一步的,所述步骤7中,注浆材料采用水泥单液浆,水泥浆液的水灰比范围为0.8-1,水泥浆液水灰比范围要求不能过高或过低,过高的水灰比会导致注浆范围内自由水过多,注浆加固效果及抬升效果不满足要求,过低的水灰比会导致浆液的可注性较差,围岩裂隙充填率过低,进而注浆加固效果及抬升效果不满足要求。Further, in the step 7, the grouting material adopts cement single-liquid slurry, the water-cement ratio of the cement slurry is in the range of 0.8-1, and the water-cement ratio range of the cement slurry should not be too high or too low, and an excessively high water-cement ratio It will lead to too much free water in the grouting range, and the grouting reinforcement effect and lifting effect will not meet the requirements. Too low water-cement ratio will lead to poor grouting of the slurry, and the filling rate of surrounding rock fissures will be too low, which will lead to grouting reinforcement. The effect and lifting effect do not meet the requirements.

进一步的,所述步骤7中,所述设定值为0.3cm,不超过能保证既有运营隧道的列车运行安全与衬砌结构安全的差异沉降限值。Further, in the step 7, the set value is 0.3 cm, which does not exceed the differential settlement limit that can ensure the safety of train operation in the existing operating tunnel and the safety of the lining structure.

本发明的有益效果:Beneficial effects of the present invention:

1.本发明的施工方法,掌子面开挖前,对既有运营隧道和待开挖隧道重叠部分的围岩区域进行注浆加固,可有效减少待开挖隧道施工时既有运营隧道的空间扭转效应,减少既有运营隧道的不均匀沉降和不均匀受力。1. In the construction method of the present invention, before excavation of the face, grouting reinforcement is performed on the surrounding rock area of the overlapping part of the existing operating tunnel and the tunnel to be excavated, which can effectively reduce the amount of damage to the existing operating tunnel during the construction of the tunnel to be excavated. Spatial torsion effect reduces uneven settlement and uneven stress of existing operating tunnels.

2.本发明的施工方法,采用切削研磨的方式开挖开挖槽,之后直接进行安装支护结构,此种方式极大降低了对围岩的扰动,进而保证了既有运营隧道下方的围岩力学性能的稳定性,保证了围岩对既有运营隧道的承载能力。2. In the construction method of the present invention, the excavation groove is excavated by cutting and grinding, and then the supporting structure is directly installed. This method greatly reduces the disturbance to the surrounding rock, thereby ensuring the surrounding area under the existing operating tunnel. The stability of rock mechanical properties ensures the bearing capacity of surrounding rock for existing operating tunnels.

3.本发明的施工方法,开挖开挖槽后直接进行安装支护结构,缩短了从开挖至进行支护作业的时间,更有利于工程的安全。3. The construction method of the present invention directly installs the support structure after excavating the trench, shortens the time from excavation to the support operation, and is more conducive to the safety of the project.

4.本发明的施工方法,开挖开挖槽时预留了核心土,有利于保证开挖及支护作业过程中掌子面的稳定性。4. In the construction method of the present invention, core soil is reserved when excavating the excavation groove, which is beneficial to ensure the stability of the face during the excavation and support operations.

5.本发明的施工方法,能够对既有运营隧道的支护应力状态和位移状态进行监测,进而获取既有运营隧道沉降过大的区域,对该区域下方进行注浆使该区域既有运营隧道抬升,保证了运营隧道的沉降值在允许限值内。5. The construction method of the present invention can monitor the support stress state and displacement state of the existing operating tunnel, and then obtain the area with excessive settlement of the existing operating tunnel, and perform grouting under the area to make the existing operation in the area. The lifting of the tunnel ensures that the settlement value of the operating tunnel is within the allowable limit.

附图说明Description of drawings

构成本申请的一部分的说明书附图用来提供对本申请的进一步理解,本申请的示意性实施例及其说明用于解释本申请,并不构成对本申请的限定。The accompanying drawings that constitute a part of the present application are used to provide further understanding of the present application, and the schematic embodiments and descriptions of the present application are used to explain the present application and do not constitute a limitation to the present application.

图1为本发明实施例1既有运营隧道和待开挖隧道交叉部分两个端部的一个步距内注浆加固围岩区域示意图;Fig. 1 is the schematic diagram of the grouting reinforcement surrounding rock area within one step of the two ends of the intersection of the existing operating tunnel and the tunnel to be excavated according to Embodiment 1 of the present invention;

图2为本发明图1中的A向截面示意图;Fig. 2 is the A-direction cross-sectional schematic diagram in Fig. 1 of the present invention;

图3为本发明图1中的B向截面示意图;Fig. 3 is the B-direction cross-sectional schematic diagram in Fig. 1 of the present invention;

图4为本发明实施例1开挖槽和核心土开挖横向截面示意图;4 is a schematic diagram of a transverse cross-section of excavation trenches and core soil excavation in Example 1 of the present invention;

图5为本发明实施例1开挖槽和核心土开挖纵向截面示意图;Fig. 5 is the longitudinal section schematic diagram of excavation trench and core soil excavation in Example 1 of the present invention;

图6为本发明实施例1监测点在既有运营隧道监测截面的布置示意图;6 is a schematic diagram of the arrangement of monitoring points in the monitoring section of an existing operating tunnel according to Embodiment 1 of the present invention;

其中,1.既有运营隧道,2.待开挖隧道,3.交叉部分,4.掌子面,4-1.上部工作面,4-2.下部工作面,5.注浆加固的围岩区域,6.步距,7.注浆孔,8.开挖槽,8-1.第一开挖槽部,8-2.第二开挖槽部,8-3.第三开挖槽部,9.左侧隧道边墙,10.右侧隧道边墙,11.拱顶隧道边墙,12.支护结构,13.监测点,14.核心土。Among them, 1. Existing operating tunnel, 2. Tunnel to be excavated, 3. Intersection, 4. Face, 4-1. Upper working face, 4-2. Lower working face, 5. Grouting reinforcement enclosure Rock area, 6. Step distance, 7. Grouting hole, 8. Excavation groove, 8-1. First excavation groove part, 8-2. Second excavation groove part, 8-3. Third excavation Groove, 9. Left side tunnel wall, 10. Right side tunnel side wall, 11. Vaulted tunnel side wall, 12. Support structure, 13. Monitoring point, 14. Core soil.

具体实施方式Detailed ways

应该指出,以下详细说明都是例示性的,旨在对本申请提供进一步的说明。除非另有指明,本文使用的所有技术和科学术语具有与本申请所属技术领域的普通技术人员通常理解的相同含义。It should be noted that the following detailed description is exemplary and intended to provide further explanation of the application. Unless otherwise defined, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs.

需要注意的是,这里所使用的术语仅是为了描述具体实施方式,而非意图限制根据本申请的示例性实施方式。如在这里所使用的,除非上下文另外明确指出,否则单数形式也意图包括复数形式,此外,还应当理解的是,当在本说明书中使用术语“包含”和/或“包括”时,其指明存在特征、步骤、操作、器件、组件和/或它们的组合。It should be noted that the terminology used herein is for the purpose of describing specific embodiments only, and is not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly dictates otherwise, the singular is intended to include the plural as well, furthermore, it is to be understood that when the terms "comprising" and/or "including" are used in this specification, it indicates that There are features, steps, operations, devices, components, and/or combinations thereof.

为了方便叙述,本发明中如果出现“上”、“下”、“左”“右”字样,仅表示与附图本身的上、下、左、右方向一致,并不对结构起限定作用,仅仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的设备或元件必须具有特定的方位,以特定的方位构造和操作,因此不能理解为对本发明的限制。For the convenience of description, if the words "up", "down", "left" and "right" appear in the present invention, it only means that the directions of up, down, left and right are consistent with the drawings themselves, and do not limit the structure. It is for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operate in a specific orientation, and therefore should not be construed as a limitation of the present invention.

正如背景技术所介绍的,目前对于位于既有运营隧道下方、与既有运营隧道交叉设置且与既有运营隧道净距较小的隧道进行施工时,既有运营隧道的稳定性能不保证,针对上述问题,本申请提出了一种极小净距斜下穿既有运营隧道的隧道开挖施工方法。As described in the background art, at present, when constructing a tunnel that is located under the existing operating tunnel, crosses the existing operating tunnel, and has a small clear distance from the existing operating tunnel, the stability of the existing operating tunnel is not guaranteed. In view of the above problems, the present application proposes a tunnel excavation construction method that obliquely penetrates an existing operating tunnel with a very small clear distance.

本申请的一种典型实施方式实施例1中,如图1-5所示,既有运营隧道拱顶埋深5.1-13.5m,主要位于中风化花岗岩地层中,覆岩厚度0.4-11.5m,隧道结构为马蹄形断面,隧道采用矿山法施工,支护形式为初支+二衬复合式衬砌,隧道支护设计尺寸宽×高为6.3m×6.6m。下部待开挖隧道拱顶埋深18.3m-20.8m,隧道洞身主要位于强风化、中风化及微风化花岗岩中,设计采用矿山法上、下台阶施工,开挖步距为0.5m,马蹄形断面,支护形式为初支+二衬复合式衬砌,隧道支护设计尺寸宽×高为7m×7.4m。下部待开挖隧道以小净距斜下穿既有运营隧道,下部隧道轴线与既有运营隧道轴线所呈角度为25°,下穿段施工范围内最近距上部既有运营隧道仅1.7米,属于一级重大风险源。In Example 1 of a typical implementation of the present application, as shown in Figures 1-5, the vaults of the existing operating tunnels are buried at a depth of 5.1-13.5m, mainly located in moderately weathered granite strata, and the thickness of the overlying rock is 0.4-11.5m. The tunnel structure is a horseshoe-shaped section, the tunnel is constructed by the mining method, the support form is the primary support + secondary lining composite lining, and the design dimension of the tunnel support is 6.3m × 6.6m in width and height. The lower part of the tunnel to be excavated has a vault depth of 18.3m-20.8m. The tunnel body is mainly located in strongly weathered, moderately weathered and slightly weathered granite. The mining method is designed to be constructed by ascending and descending steps. The excavation step distance is 0.5m. Section, the support form is primary support + secondary lining composite lining, and the design dimension of tunnel support is 7m × 7.4m in width and height. The lower tunnel to be excavated obliquely penetrates the existing operating tunnel with a small clear distance, and the angle between the axis of the lower tunnel and the existing operating tunnel is 25°. It belongs to the first-level major risk source.

本实施例中,待开挖隧道2未穿过既有运营隧道1的部分采用台阶法进行施工,待开挖隧道施工至斜下穿既有运营隧道的部分3时,掌子面4被台阶分为上部工作面4-1和下部工作面4-2。In this embodiment, the part of the tunnel 2 to be excavated that does not pass through the existing operating tunnel 1 is constructed by using the step method. When the tunnel to be excavated is constructed to obliquely descends through the part 3 of the existing operating tunnel, the face 4 is covered by the steps. It is divided into upper working face 4-1 and lower working face 4-2.

其具体施工包括以下步骤:Its specific construction includes the following steps:

步骤1:综合地质勘查资料及超前探孔取芯测试结果,获取掌子面前方隧道开挖影响范围内岩层分布与围岩物理力学参数,所述步骤1采用现有隧道施工的常用方法,其具体步骤在此不进行详细叙述。Step 1: Comprehensive geological exploration data and advanced drilling core test results to obtain the distribution of rock formations and physical and mechanical parameters of surrounding rock within the influence area of tunnel excavation in front of the tunnel. The step 1 adopts the common method of existing tunnel construction. The specific steps are not described in detail here.

步骤2:如图1-3所示,对待开挖隧道掌子面的上部工作面前方的围岩进行非对称注浆加固,具体的,沿待开挖隧道轴线方向一个步距6的距离范围内,对待开挖隧道上部轮廓线与既有运营隧道下部轮廓线之间的围岩进行注浆加固,注浆加固的围岩区域5为待开挖隧道和既有运营隧道在竖直方向上重叠部分之间的围岩区域,即在待开挖隧道轴线方向一个步距范围内,非对称注浆加固的围岩的水平范围内区域为待开挖隧道和既有运营隧道在水平面内投影重叠的区域,竖向范围内区域为待开挖隧道轮廓线与既有运营隧道轮廓线之间的区域。Step 2: As shown in Figure 1-3, perform asymmetric grouting reinforcement on the surrounding rock in front of the upper working face of the tunnel face to be excavated. Specifically, a distance range of 6 steps along the axis of the tunnel to be excavated Inside, the surrounding rock between the upper contour line of the tunnel to be excavated and the lower contour line of the existing operating tunnel is grouted for reinforcement, and the surrounding rock area 5 for grouting reinforcement is the vertical direction of the tunnel to be excavated and the existing operating tunnel. The surrounding rock area between the overlapping parts, that is, within a step range in the axial direction of the tunnel to be excavated, the area within the horizontal range of the surrounding rock reinforced by asymmetric grouting is the projection of the tunnel to be excavated and the existing operating tunnel in the horizontal plane The overlapping area, the area within the vertical range is the area between the outline of the tunnel to be excavated and the outline of the existing operating tunnel.

所述注浆加固采用小导管注浆方式进行,将多个超前导管通过掌子面的上部工作面设置的注浆孔7钻入掌子面前方的岩体中,利用超前导管向上部工作面前方的围岩进行注浆,所述超前导管的插入深度和角度应满足需要注浆加固的围岩区域的要求,所述注浆材料采用水泥单液浆,水泥浆液水灰比范围要求不能过高或过低,过高的水灰比会导致注浆加固范围内自由水过多,注浆加固效果不满足要求,过低的水灰比会导致浆液的可注性较差,围岩裂隙充填率过低,进而注浆加固效果不满足要求,最终水泥单液浆的水灰比控制在0.8-1的范围内。注浆过程中,当注浆压力达到1MPa且单孔注浆量达到设定标准值时,停止该注浆孔的注浆作业。The grouting reinforcement is carried out by grouting with small conduits, and a plurality of advanced conduits are drilled into the rock mass in front of the face through the grouting holes 7 provided on the upper working face of the face, and the leading conduit is used to move to the upper working face. For grouting with square surrounding rock, the insertion depth and angle of the advanced conduit should meet the requirements of the surrounding rock area that needs grouting reinforcement. Too high or too low, too high water-cement ratio will lead to too much free water in the grouting reinforcement range, and the grouting reinforcement effect will not meet the requirements, too low water-cement ratio will lead to poor injectability of the grout and cracks in the surrounding rock. The filling rate is too low, and the grouting reinforcement effect does not meet the requirements, and the final water-cement ratio of the cement single slurry is controlled within the range of 0.8-1. During the grouting process, when the grouting pressure reaches 1MPa and the grouting volume of a single hole reaches the set standard value, the grouting operation of the grouting hole is stopped.

步骤3:如图4-5所示,拆除超前导管,采用悬臂式掘进机利用切削研磨的方式在掌子面的上部工作面上开挖开挖槽8,具体的,预留核心土14,首先,在上部工作面一侧沿左侧隧道边墙9轮廓线开挖第一开挖槽部8-1,然后在上部工作面另一侧沿右侧隧道边墙10轮廓线开挖第二开挖槽部8-2,最后沿隧道的拱顶隧道边墙11轮廓线位置开挖第三开挖槽部8-3,第一开挖槽部、第二开挖槽部和第三开挖槽部共同构成开挖槽,所述开挖槽的深度等于一个步距的长度。Step 3: As shown in Figure 4-5, remove the leading conduit, and use the cantilever roadheader to excavate the excavation groove 8 on the upper working surface of the face by cutting and grinding. Specifically, reserve the core soil 14, First, the first excavation groove portion 8-1 is excavated along the contour line of the left tunnel side wall 9 on one side of the upper working face, and then the second excavation groove portion 8-1 is excavated along the contour line of the right tunnel side wall 10 on the other side of the upper working face. The groove portion 8-2 is excavated, and finally the third excavation groove portion 8-3, the first excavation groove portion, the second excavation groove portion and the third excavation groove portion are excavated along the contour line position of the side wall 11 of the vaulted tunnel of the tunnel. The trough portions together form a trough, the depth of which is equal to the length of one step.

开挖槽开挖过程中,实时监测既有运营隧道的支护应力状态和位移,支护应力状态包括衬砌的应力与应变状态,位移状态包括支护的竖向位移和水平位移。During the excavation of the trench, the support stress state and displacement of the existing operating tunnels are monitored in real time. The support stress state includes the stress and strain state of the lining, and the displacement state includes the vertical and horizontal displacement of the support.

悬臂式掘进机工作过程中,掘进头的侧面对土体起到切削作用,掘进头的前端面对土体起到研磨作用,相对于传统的钻爆法施工方式,能够大幅度的减少开挖施工对围岩的扰动,开挖开挖槽时,预留核心土,可以有效保持掌子面的稳定性。During the working process of the cantilever roadheader, the side of the roadhead plays a cutting role on the soil, and the front end of the roadhead faces the soil and grinds the soil. Compared with the traditional drilling and blasting method, the excavation can be greatly reduced. When the construction disturbs the surrounding rock, the core soil is reserved when excavating the excavation groove, which can effectively maintain the stability of the face.

步骤4:开挖槽施工完成后,直接在开挖槽内部安装初期支护结构12,具体的在开挖槽中搭设格栅拱架,格栅拱架搭设完成后,喷射速凝混凝土,使格栅拱架埋入混凝土,形成初期支护结构。Step 4: After the construction of the excavation groove is completed, the initial support structure 12 is directly installed inside the excavation groove. Specifically, the grid arch frame is erected in the excavation groove. After the grid arch frame is erected, the quick-setting concrete is injected to make the The grid arch is embedded in concrete to form the initial support structure.

步骤:5:初期的支护结构施工完成后,利用悬臂式掘进机采用切削研磨的方式开挖预留的核心土,开挖核心土时,悬臂式掘进机的掘进头运动轨迹自下至上,左右依次循环呈S型轨迹,直至开挖完成,核心土的开挖深度等于一个步距的距离。Step: 5: After the construction of the initial support structure is completed, use the cantilever roadheader to excavate the reserved core soil by cutting and grinding. The left and right are circulated in an S-shaped trajectory until the excavation is completed, and the excavation depth of the core soil is equal to the distance of one step.

核心土开挖过程中,实时监测既有运营隧道的支护应力状态和位移,支护应力状态包括衬砌的应力与应变状态,位移状态包括支护的竖向位移和水平位移。During the excavation of the core soil, the support stress state and displacement of the existing operating tunnels are monitored in real time. The support stress state includes the stress and strain state of the lining, and the displacement state includes the vertical and horizontal displacement of the support.

所述步骤5进行过程中,同时对掌子面的下部工作面开挖,开挖深度等于一个步距的距离,并同时搭设支护结构,其方法可采用现有的台阶法施工方法,在此不进行详细叙述。During the process of step 5, the lower working face of the tunnel face is excavated at the same time, the excavation depth is equal to the distance of one step, and the supporting structure is erected at the same time, and the method can adopt the existing step method construction method. This will not be described in detail.

步骤6:根据步骤3和步骤5得到的运营隧道的支护应力状态和位移状态,获得既有运营隧道同一断面上不同位置的差异沉降情况。Step 6: According to the support stress state and displacement state of the operating tunnel obtained in steps 3 and 5, the differential settlement of different positions on the same section of the existing operating tunnel is obtained.

步骤7:通过待开挖隧道掌子面对既有运营隧道差异沉降值大于设定值的区域下方的围岩进行注浆,使既有运营隧道差异沉降值大于设定值的区域的差异沉降值小于设定值,本实施例中,所述设定值不超过能保证既有运营隧道的列车运行安全与衬砌结构安全的差异沉降限值,本实施例中所述设定值采用0.3cm,当既有运营隧道同一断面上的不同位置差异沉降差达到0.3cm时,便认为差异沉降值过大,对既有运营隧道差异沉降值过大的部分下方的围岩区域进行注浆,通过注浆,将既有运营隧道差异沉降值过大的部分进行抬升,使其差异沉降值满足要求,所述注浆加固采用小导管注浆方式,注浆材料采用水泥单液浆,水泥浆液水灰比范围要求不能过高或过低,过高的水灰比会导致注浆加固范围内自由水过多,注浆加固效果不满足要求,过低的水灰比会导致浆液的可注性较差,围岩裂隙充填率过低,进而注浆加固效果不满足要求,最终水泥单液浆的水灰比控制在0.8-1之间。Step 7: grouting the surrounding rock below the area where the differential settlement value of the existing operating tunnel is greater than the set value through the face of the tunnel to be excavated, so as to make the differential settlement of the area where the differential settlement value of the existing operating tunnel is greater than the set value. The value is less than the set value. In this embodiment, the set value does not exceed the differential settlement limit that can ensure the safety of the train operation and the safety of the lining structure of the existing operating tunnel. The set value in this embodiment adopts 0.3cm , when the differential settlement difference between different positions on the same section of the existing operating tunnel reaches 0.3 cm, the differential settlement value is considered to be too large, and the surrounding rock area under the part where the differential settlement value of the existing operating tunnel is too large is grouted. Grouting is to lift the part of the existing operating tunnel whose differential settlement value is too large to meet the requirements. The range of cement ratio should not be too high or too low. Too high water-cement ratio will lead to too much free water in the grouting reinforcement range, and the effect of grouting reinforcement does not meet the requirements. Too low water-cement ratio will lead to the injectability of the grout. Poor, the filling rate of the surrounding rock cracks is too low, and the grouting reinforcement effect does not meet the requirements, and the final water-cement ratio of the cement single slurry is controlled between 0.8-1.

步骤8:采用步骤1-步骤7的方法,沿待开挖隧道轴线方向,依次进行多个步距范围内的注浆和开挖工作,直至待开挖隧道斜下穿既有运营隧道的部分开挖完成。Step 8: Using the method from Step 1 to Step 7, along the axis of the tunnel to be excavated, perform grouting and excavation work in multiple steps in sequence until the tunnel to be excavated obliquely penetrates the part of the existing operating tunnel. Excavation completed.

所述步骤3进行之前,在既有运营隧道内设置多个监测点,用于对既有隧道的支护应力状态和位移进行监测,如图6所示,在既有运营隧道内的设定区域设置多个监测截面,每个监测截面的距离为0.5m,每个监测截面上设置八个监测点13,拱顶位置设置一个、拱底位置设置一个,两侧拱腰位置设置一个,在上述相邻监测点之间等距插入一个监测点,共八个监测点,所述监测点处安装相应的监测仪器,对支护的应力状态和位移状态进行监测,所述监测仪器采用现有设备即可,在此不进行详细叙述。Before the step 3 is carried out, multiple monitoring points are set in the existing operating tunnel to monitor the support stress state and displacement of the existing tunnel. As shown in Figure 6, the setting in the existing operating tunnel Multiple monitoring sections are set up in the area, the distance between each monitoring section is 0.5m, and eight monitoring points 13 are set on each monitoring section, one at the top of the arch, one at the bottom of the arch, and one at the waist of the arch. A monitoring point is inserted equidistantly between the above-mentioned adjacent monitoring points, with a total of eight monitoring points. Corresponding monitoring instruments are installed at the monitoring points to monitor the stress state and displacement state of the support. The equipment is sufficient, and detailed description is not given here.

既有运营隧道上设定区域的确定方法为,步骤2进行前,确定掌子面上部工作面在既有运营隧道中的对应区域,将该对应区域沿既有运营隧道轴线方向前后扩展设定距离得到设定区域的两个边界,两个边界之间的区域为设定区域,所述设定距离要求不小于待开挖隧道的开挖影响范围,待开挖隧道的开挖影响范围取待开挖隧道直径的1.5倍,相邻监测截面的距离与步距相等,本实施例中,所述设定距离为10m。The method for determining the set area on the existing operating tunnel is: before step 2, determine the corresponding area of the upper working face of the face in the existing operating tunnel, and extend the corresponding area forward and backward along the axis direction of the existing operating tunnel. The distance is obtained from the two boundaries of the set area, and the area between the two boundaries is the set area, and the set distance requirement is not less than the excavation influence range of the tunnel to be excavated. 1.5 times the diameter of the tunnel to be excavated, the distance between adjacent monitoring sections is equal to the step distance. In this embodiment, the set distance is 10m.

待开挖隧道的每个步距的步骤3工作前,均需要在既有运营隧道上布置监测点和监测仪器。Before step 3 of each step of the tunnel to be excavated, monitoring points and monitoring instruments need to be arranged on the existing operating tunnel.

本实施例的施工方法,通过步骤2的非对称注浆加固,可有效抵消待开挖隧道施工时对既有运营隧道产生的空间扭转效应,减少了既有运营隧道的不均匀沉降和不均匀受力,同时对开挖槽和核心土进行开挖时,采用了切削研磨的开挖方式,相比于传统的钻爆法施工,可以大幅度减少开挖施工对围岩的扰动,有效保证围岩力学性能满足既有运营隧道对围岩承载力的要求。The construction method of this embodiment, through the asymmetric grouting reinforcement in step 2, can effectively offset the spatial torsion effect on the existing operating tunnel during the construction of the tunnel to be excavated, and reduce the uneven settlement and uneven settlement of the existing operating tunnel. When the excavation groove and core soil are excavated at the same time, the cutting and grinding excavation method is adopted. Compared with the traditional drilling and blasting method, the disturbance of the surrounding rock during the excavation construction can be greatly reduced, effectively guaranteeing The mechanical properties of the surrounding rock meet the requirements of the existing operating tunnels for the bearing capacity of the surrounding rock.

上述虽然结合附图对本发明的具体实施方式进行了描述,但并非对本发明保护范围的限制,所属领域技术人员应该明白,在本发明的技术方案的基础上,本领域技术人员不需要付出创造性劳动即可做出的各种修改或变形仍在本发明的保护范围以内。Although the specific embodiments of the present invention have been described above in conjunction with the accompanying drawings, they do not limit the scope of protection of the present invention. Those skilled in the art should understand that on the basis of the technical solutions of the present invention, those skilled in the art do not need to pay creative work. Various modifications or deformations that can be made are still within the protection scope of the present invention.

Claims (9)

1.一种极小净距斜下穿既有运营隧道的隧道开挖施工方法,其特征在于,包括以下步骤:1. a tunnel excavation construction method of obliquely passing through an existing operating tunnel with a minimum clear distance, is characterized in that, comprises the following steps: 步骤1:综合地质勘查资料及超前探孔取芯测试结果,获取待开挖隧道掌子面前方隧道开挖影响范围内岩层分布与围岩物理力学参数;Step 1: Obtain the distribution of rock formations and the physical and mechanical parameters of surrounding rock within the influence area of the tunnel excavation in front of the tunnel face to be excavated by synthesizing the geological exploration data and the test results of advanced drilling and coring; 步骤2:在沿待开挖隧道轴线方向一个步距范围内,对待开挖隧道掌子面前方的围岩进行非对称注浆加固,用于提高待开挖隧道与既有运营隧道重叠区域围岩的力学性能;Step 2: Within a step range along the axis of the tunnel to be excavated, perform asymmetric grouting reinforcement on the surrounding rock in front of the face of the tunnel to be excavated to improve the surrounding area of the overlapping area between the tunnel to be excavated and the existing operating tunnel. mechanical properties of rock; 步骤3:预留核心土,采用切削研磨的方式对掌子面前方岩体开挖出沿待开挖隧道边缘轮廓线设置的深度等于步距的开挖槽,开挖过程中监测既有运营隧道的支护应力状态与位移;Step 3: Reserve core soil, excavate the rock mass in front of the face by cutting and grinding, and excavate trenches with a depth equal to the step distance set along the contour line of the tunnel edge to be excavated, and monitor existing operations during the excavation process. Tunnel support stress state and displacement; 步骤4:在开挖槽中安装支护结构;Step 4: Install the support structure in the excavation groove; 步骤5:采用切削研磨的方式对预留的核心土进行开挖,开挖过程中监测既有运营隧道的支护应力状态与位移;Step 5: Excavate the reserved core soil by cutting and grinding, and monitor the support stress state and displacement of the existing operating tunnel during the excavation process; 步骤6:根据步骤3和步骤5得到的运营隧道的支护应力状态和位移,获得既有运营隧道同一断面上不同位置的差异沉降情况;Step 6: According to the support stress state and displacement of the operating tunnel obtained in Step 3 and Step 5, the differential settlement of different positions on the same section of the existing operating tunnel is obtained; 步骤7:对既有运营隧道差异沉降值大于设定值的区域下方的围岩进行注浆,使既有运营隧道差异沉降值大于设定值的区域的差异沉降值小于设定值;Step 7: grouting the surrounding rock below the area where the differential settlement value of the existing operating tunnel is greater than the set value, so that the differential settlement value of the area where the differential settlement value of the existing operating tunnel is greater than the set value is less than the set value; 步骤8:采用步骤1-步骤7的方法,依次进行沿待开挖隧道轴线方向多个步距的注浆和开挖工作,直至完成所有注浆与开挖工作。Step 8: Using the methods from Step 1 to Step 7, perform grouting and excavation work in multiple steps along the axis direction of the tunnel to be excavated in sequence until all grouting and excavation work is completed. 2.如权利要求1所述的一种极小净距斜下穿既有运营隧道的隧道开挖施工方法,其特征在于,所述步骤2中,非对称注浆加固的围岩的水平范围内区域为待开挖隧道和既有运营隧道在水平面内投影重叠的区域,竖向范围内区域为待开挖隧道轮廓线与既有运营隧道轮廓线之间的区域。2. A kind of tunnel excavation construction method for obliquely passing through an existing operating tunnel with a minimal clear distance as claimed in claim 1, wherein in the step 2, the horizontal range of the surrounding rock reinforced by asymmetric grouting The inner area is the area where the projections of the tunnel to be excavated and the existing operating tunnel overlap in the horizontal plane, and the area within the vertical range is the area between the outline of the tunnel to be excavated and the outline of the existing operating tunnel. 3.如权利要求1所述的一种极小净距斜下穿既有运营隧道的隧道开挖施工方法,其特征在于,所述步骤2中,注浆材料采用水泥单液浆,水泥浆液的水灰比范围为0.8-1。3. A kind of tunnel excavation construction method for obliquely passing through an existing operating tunnel with a minimal clear distance as claimed in claim 1, characterized in that, in the step 2, the grouting material adopts cement single slurry, and the cement slurry The water-cement ratio ranges from 0.8 to 1. 4.如权利要求1所述的一种极小净距斜下穿既有运营隧道的隧道开挖施工方法,其特征在于,所述步骤3中,开挖槽的开挖方法为:首先在隧道一侧边墙沿轮廓线切削研磨出第一开挖槽部,然后在另一侧边缘沿轮廓线切削研磨出第二开挖槽部,最后沿隧道拱顶边缘轮廓线切削研磨出第三开挖槽部,第一开挖槽部、第二开挖槽部及第三开挖槽部构成开挖槽。4. a kind of tunnel excavation construction method for obliquely passing through existing operating tunnels under a very small clear distance as claimed in claim 1, it is characterized in that, in described step 3, the excavation method of excavation groove is: first in the The side wall of one side of the tunnel is cut and ground along the contour line to form the first excavation groove, then the second excavation groove is cut and ground along the contour line on the other side edge, and finally the third groove is cut and ground along the contour line of the tunnel vault. The excavation groove part, the first excavation groove part, the second excavation groove part and the third excavation groove part constitute the excavation groove part. 5.如权利要求1所述的一种极小净距斜下穿既有运营隧道的隧道开挖施工方法,其特征在于,所述步骤5中,对预留的核心土的切削研磨运动轨迹为自下而上的S型轨迹,核心土的开挖深度与步距相等。5. A kind of tunnel excavation construction method for obliquely passing through an existing operating tunnel with a minimal clear distance as claimed in claim 1, wherein in the step 5, the cutting and grinding motion trajectory of the reserved core soil is carried out. For the bottom-up S-shaped trajectory, the excavation depth of the core soil is equal to the step distance. 6.如权利要求1所述的一种极小净距斜下穿既有运营隧道的隧道开挖施工方法,其特征在于,所述步骤3进行之前,在既有运营隧道内设置多个监测点,用于对支护的应力状态和位移进行监测,所述监测点设置在既有运营隧道设定区域内的多个监测截面上,每个监测截面设置多个监测点,所述设定区域的确定方法为:确定待开挖隧道掌子面在既有运营隧道中所对应的区域,以该区域为中心,沿既有运营隧道轴线前后方向设定距离处为设定区域的边界,两个边界之间为设定区域。6. A kind of tunnel excavation construction method for obliquely passing through an existing operating tunnel with a very small clear distance as claimed in claim 1, characterized in that, before the step 3 is carried out, a plurality of monitoring devices are set in the existing operating tunnel The monitoring points are used to monitor the stress state and displacement of the support. The monitoring points are set on multiple monitoring sections in the set area of the existing operating tunnel, and each monitoring section is set with multiple monitoring points. The determination method of the area is as follows: determine the area corresponding to the face of the tunnel to be excavated in the existing operating tunnel, take this area as the center, and set the distance along the axis of the existing operating tunnel as the boundary of the set area. Between the two boundaries is the setting area. 7.如权利要求6所述的一种极小净距斜下穿既有运营隧道的隧道开挖施工方法,其特征在于,所述设定距离为待开挖隧道直径的1.5倍,相邻监测截面的距离与步距相等。7. The tunnel excavation construction method for obliquely penetrating an existing operating tunnel with a minimal clear distance as claimed in claim 6, wherein the set distance is 1.5 times the diameter of the tunnel to be excavated, and the adjacent The distance of the monitoring section is equal to the step distance. 8.如权利要求6所述的一种极小净距斜下穿既有运营隧道的隧道开挖施工方法,其特征在于,同一个监测截面中,既有运营隧道的拱顶位置、拱底位置和两个拱腰位置各设置一个监测点,拱顶和两个拱腰的监测点之间分别等间距插入一个监测点,拱底和两个拱腰的监测点之间分别等间距插入一个监测点。8. A kind of tunnel excavation construction method for obliquely passing through an existing operating tunnel with a minimal clear distance as claimed in claim 6, characterized in that, in the same monitoring section, the vault position and the vault bottom of the existing operating tunnel One monitoring point is set at the position and the two arch waist positions, one monitoring point is inserted at equal intervals between the monitoring points of the vault and the two arch waists, and one monitoring point is inserted at equal intervals between the monitoring points of the arch bottom and the two arch waists. Monitoring points. 9.如权利要求1所述的一种极小净距斜下穿既有运营隧道的隧道开挖施工方法,其特征在于,所述步骤7中,注浆材料采用水泥单液浆,水泥浆液的水灰比范围为0.8-1。9. A kind of tunnel excavation construction method for obliquely passing through an existing operating tunnel with a minimal clear distance as claimed in claim 1, wherein in the step 7, the grouting material adopts cement single slurry, and the cement slurry The water-cement ratio ranges from 0.8 to 1.
CN201911040059.2A 2019-10-29 2019-10-29 A tunnel excavation construction method for obliquely passing through an existing operating tunnel with a minimal clear distance Expired - Fee Related CN110617072B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911040059.2A CN110617072B (en) 2019-10-29 2019-10-29 A tunnel excavation construction method for obliquely passing through an existing operating tunnel with a minimal clear distance

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911040059.2A CN110617072B (en) 2019-10-29 2019-10-29 A tunnel excavation construction method for obliquely passing through an existing operating tunnel with a minimal clear distance

Publications (2)

Publication Number Publication Date
CN110617072A true CN110617072A (en) 2019-12-27
CN110617072B CN110617072B (en) 2021-03-02

Family

ID=68927110

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911040059.2A Expired - Fee Related CN110617072B (en) 2019-10-29 2019-10-29 A tunnel excavation construction method for obliquely passing through an existing operating tunnel with a minimal clear distance

Country Status (1)

Country Link
CN (1) CN110617072B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112196544A (en) * 2020-10-15 2021-01-08 中铁二局第二工程有限公司 Construction method for crossing existing tunnel on contact discharge flue of high-ground-stress soft rock stratum
CN112377198A (en) * 2020-11-02 2021-02-19 中铁十九局集团广州工程有限公司 Construction method of up-down cross tunnel
CN112761675A (en) * 2021-01-26 2021-05-07 中铁八局集团昆明铁路建设有限公司 Construction method of composite support system for extremely-small-clear-distance obliquely downward-penetrating existing subway tunnel
CN112781656A (en) * 2021-01-18 2021-05-11 中铁八局集团有限公司 Method for monitoring safety of intersected existing tunnel during construction of underpass high-speed railway tunnel
CN113389190A (en) * 2021-06-23 2021-09-14 武钢集团昆明钢铁股份有限公司 Rapid treatment method for plate bottom void of narrow area of red viscous soil factory
CN113586079A (en) * 2021-08-24 2021-11-02 中国电建集团中南勘测设计研究院有限公司 Tunnel crossroad structure and construction method thereof
CN114000885A (en) * 2021-10-29 2022-02-01 四川省交通勘察设计研究院有限公司 A kind of construction method of tunnel excavation in surrounding rock

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004257109A (en) * 2003-02-26 2004-09-16 Ando Corp Widening method of existing tunnel
CN102287195A (en) * 2011-05-13 2011-12-21 中铁四局集团第二工程有限公司 Construction method of large-span tunnel passing through rapid transit railway with shallow tunneling process
CN203097896U (en) * 2013-01-31 2013-07-31 中铁十四局集团有限公司 Separated type large-section multi-cavern underpass existing building sedimentation controlling structure
CN105350973A (en) * 2015-10-08 2016-02-24 同济大学 Construction method for large-span section loess tunnel under-crossing highway
CN105781573A (en) * 2016-03-18 2016-07-20 中铁九局集团第六工程有限公司 Railway down-traversing highway tunnel double-layer casing pipe reinforcement double-pipe shed follow-pipe drilling construction method
CN106246193A (en) * 2016-09-06 2016-12-21 中铁二十四局集团南昌铁路工程有限公司 Strong karst high rich water urban shallow tunnel cantilever excavator construction
CN109184743A (en) * 2018-09-25 2019-01-11 中铁十二局集团有限公司 Existing tunnel construction method is worn under circle boulder clay rock compound stratum slurry shield short distance

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2004257109A (en) * 2003-02-26 2004-09-16 Ando Corp Widening method of existing tunnel
CN102287195A (en) * 2011-05-13 2011-12-21 中铁四局集团第二工程有限公司 Construction method of large-span tunnel passing through rapid transit railway with shallow tunneling process
CN203097896U (en) * 2013-01-31 2013-07-31 中铁十四局集团有限公司 Separated type large-section multi-cavern underpass existing building sedimentation controlling structure
CN105350973A (en) * 2015-10-08 2016-02-24 同济大学 Construction method for large-span section loess tunnel under-crossing highway
CN105781573A (en) * 2016-03-18 2016-07-20 中铁九局集团第六工程有限公司 Railway down-traversing highway tunnel double-layer casing pipe reinforcement double-pipe shed follow-pipe drilling construction method
CN106246193A (en) * 2016-09-06 2016-12-21 中铁二十四局集团南昌铁路工程有限公司 Strong karst high rich water urban shallow tunnel cantilever excavator construction
CN109184743A (en) * 2018-09-25 2019-01-11 中铁十二局集团有限公司 Existing tunnel construction method is worn under circle boulder clay rock compound stratum slurry shield short distance

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
曲建生: "承压富水砂土地铁下穿既有桥梁施工技术研究", 《科技创新与生产力》 *
曹海林: "新建隧道下穿既有公路隧道施工技术", 《铁道建筑技术》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112196544A (en) * 2020-10-15 2021-01-08 中铁二局第二工程有限公司 Construction method for crossing existing tunnel on contact discharge flue of high-ground-stress soft rock stratum
CN112196544B (en) * 2020-10-15 2022-10-18 中铁二局第二工程有限公司 Construction method for crossing existing tunnel on contact discharge flue of high-ground-stress soft rock stratum
CN112377198A (en) * 2020-11-02 2021-02-19 中铁十九局集团广州工程有限公司 Construction method of up-down cross tunnel
CN112781656A (en) * 2021-01-18 2021-05-11 中铁八局集团有限公司 Method for monitoring safety of intersected existing tunnel during construction of underpass high-speed railway tunnel
CN112761675A (en) * 2021-01-26 2021-05-07 中铁八局集团昆明铁路建设有限公司 Construction method of composite support system for extremely-small-clear-distance obliquely downward-penetrating existing subway tunnel
CN113389190A (en) * 2021-06-23 2021-09-14 武钢集团昆明钢铁股份有限公司 Rapid treatment method for plate bottom void of narrow area of red viscous soil factory
CN113586079A (en) * 2021-08-24 2021-11-02 中国电建集团中南勘测设计研究院有限公司 Tunnel crossroad structure and construction method thereof
CN113586079B (en) * 2021-08-24 2024-02-13 中国电建集团中南勘测设计研究院有限公司 Tunnel cross intersection structure and construction method thereof
CN114000885A (en) * 2021-10-29 2022-02-01 四川省交通勘察设计研究院有限公司 A kind of construction method of tunnel excavation in surrounding rock

Also Published As

Publication number Publication date
CN110617072B (en) 2021-03-02

Similar Documents

Publication Publication Date Title
CN110617072A (en) Tunnel excavation construction method for obliquely passing existing operation tunnel at minimum clear distance
CN102134998B (en) Construction method for wind-blown sand tunnel
CN110374633B (en) Tunnel opening section construction method for tunnel to pass through loose body
CN104389610B (en) A kind of ultrashort step construction method of traversing operation freeway tunnel
CN103628894B (en) Method is repaiied in a kind of rich water fault belt based on angle umbrella pre-grouting lane, tunnel of collapsing
CN110878696B (en) Method for reinforcing surrounding rock of tunnel section at junction of upper soft and lower hard stratum shield method and mine method
CN105781573A (en) Railway down-traversing highway tunnel double-layer casing pipe reinforcement double-pipe shed follow-pipe drilling construction method
CN100513705C (en) Underground Beam-Pile Frame Structure for Slope Reinforcement
CN209510334U (en) A kind of soft lower hard large cross-section tunnel bilateral hole core local method constructing structure
CN104912562A (en) Construction method for deformation control over existing operation tunnel crossing under shield
CN110617067A (en) Low-risk construction method for full-section boundary advanced pipe shed of extremely-soft surrounding rock tunnel
CN110159298A (en) A kind of first branch button arch construction method of Underground Subway Station
CN110284885A (en) Shield inspection-pit construction method
CN114352292A (en) Shallow-buried bias-pressure multi-arch tunnel construction method for weathering phyllite stratum
CN111810184A (en) A kind of variable section tunnel construction method
CN108180018A (en) A kind of shallow embedding collapsible loess tunnel Core Soil and glass bolt anchorage construction method
CN201771514U (en) Concealed tunneling structure with pile foundation
CN108374674B (en) Six pilot tunnels, 12 step Underground Space Excavation method for protecting support
CN110439011A (en) A kind of side slope antiskid supporting construction and its construction method
CN107829748B (en) A complementary circulating excavation method suitable for large-section tunnels in boulder formations
CN211115996U (en) Reinforced structure in tunnel section at junction of upper soft and lower hard stratum shield method and mine method
CN105178355B (en) The stratum pre-reinforcement processing method of underground space construction
CN107165658A (en) Pass through the inter-laminar dislocation band impermeable management structure and construction method of underground chamber
CN108843339B (en) The auxiliary slip casting platform and construction method of large-scale solution cavity are passed through when existing tunnel digs
CN207297039U (en) Pass through the inter-laminar dislocation band impermeable management structure of underground chamber

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20210302

Termination date: 20211029

CF01 Termination of patent right due to non-payment of annual fee