CN110616886A - Lifting platform for house building construction - Google Patents

Lifting platform for house building construction Download PDF

Info

Publication number
CN110616886A
CN110616886A CN201910796152.XA CN201910796152A CN110616886A CN 110616886 A CN110616886 A CN 110616886A CN 201910796152 A CN201910796152 A CN 201910796152A CN 110616886 A CN110616886 A CN 110616886A
Authority
CN
China
Prior art keywords
fixedly connected
support
cavity
rod
block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910796152.XA
Other languages
Chinese (zh)
Inventor
黄秋筠
付梦求
林顺添
黄芷敏
廖伟东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Provincial Architectural Engineering Machinery Construction Co Ltd
Original Assignee
Guangdong Provincial Architectural Engineering Machinery Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Provincial Architectural Engineering Machinery Construction Co Ltd filed Critical Guangdong Provincial Architectural Engineering Machinery Construction Co Ltd
Priority to CN201910796152.XA priority Critical patent/CN110616886A/en
Publication of CN110616886A publication Critical patent/CN110616886A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/18Scaffolds primarily resting on the ground adjustable in height
    • E04G1/20Scaffolds comprising upright members and provision for supporting cross-members or platforms at different positions therealong
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/24Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground
    • E04G1/24Scaffolds primarily resting on the ground comprising essentially special base constructions; comprising essentially special ground-engaging parts, e.g. inclined struts, wheels
    • E04G2001/242Scaffolds movable on wheels or tracks

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Movable Scaffolding (AREA)

Abstract

本发明公开了一种用于房屋建筑施工的升降平台,包括基座,所述基座的底部固定连接有两对安装块,两对所述安装块上均转动连接有滚轮,所述滚轮的一侧设有安装板,所述安装板上设有安装腔,所述安装腔内设有第一螺纹杆,所述第一螺纹杆的一端与安装腔的内壁转动连接,所述第一螺纹杆的另一端贯穿安装腔的内壁并固定连接有转块,所述第一螺纹杆位于安装腔内的侧壁上螺纹套接有移动板,所述移动板的一端贯穿安装腔的内壁并向下延伸。本发明便于对装置进行移动固定,在施工人员作业时稳定性更高,提高安全性能,降低风险,且操作简单。

The invention discloses a lifting platform for building construction, which comprises a base, two pairs of installation blocks are fixedly connected to the bottom of the base, and rollers are connected to the two pairs of installation blocks in rotation, and the rollers of the rollers are One side is provided with a mounting plate, the mounting plate is provided with a mounting cavity, the mounting cavity is provided with a first threaded rod, one end of the first threaded rod is rotatably connected with the inner wall of the mounting cavity, and the first threaded rod The other end of the rod runs through the inner wall of the installation cavity and is fixedly connected with a turning block. The first threaded rod is located on the side wall of the installation cavity and is threaded with a moving plate. One end of the moving plate penetrates the inner wall of the installation cavity and Extend down. The invention is convenient to move and fix the device, has higher stability when construction personnel work, improves safety performance, reduces risks, and is easy to operate.

Description

一种用于房屋建筑施工的升降平台Lifting platform for building construction

技术领域technical field

本发明涉及建筑施工设备技术领域,尤其涉及一种用于房屋建筑施工的升降平台。The invention relates to the technical field of building construction equipment, in particular to a lifting platform used for building construction.

背景技术Background technique

建筑施工是指工程建设实施阶段的生产活动,是各类建筑物的建造过程,也可以说是把设计图纸上的各种线条,在指定的地点,变成实物的过程。它包括基础工程施工、主体结构施工、屋面工程施工、装饰工程施工等。施工作业的场所称为“建筑施工现场”或叫“施工现场”,也叫工地,建筑施工在对进行天花板施工以及高墙施工工作时,需要借助辅助设施来完成 登高作业。Building construction refers to the production activities in the implementation stage of engineering construction. It is the construction process of various buildings. It can also be said to be the process of turning various lines on the design drawings into real objects at designated locations. It includes basic engineering construction, main structure construction, roofing engineering construction, decoration engineering construction, etc. The place of construction work is called "building construction site" or "construction site", also called construction site. When building construction is doing ceiling construction and high wall construction work, it is necessary to use auxiliary facilities to complete the climbing operation.

但是现有的在对天花板进行施工以及高墙施工工作时,需要借助脚手架设施来完成登高作业,但是脚手架需要一定的时间进行组装,效率较低,且牢固性较差,降低了施工安全性。However, in the existing construction of ceilings and high walls, it is necessary to use scaffolding facilities to complete the climbing operation, but the scaffolding needs a certain amount of time to assemble, the efficiency is low, and the firmness is poor, which reduces the construction safety.

发明内容Contents of the invention

1.要解决的技术问题1. Technical problems to be solved

本发明的目的是为了解决现有技术中对天花板进行施工以及高墙施工工作时,需要借助脚手架设施来完成登高作业,但是脚手架需要一定的时间进行组装,效率较低,且牢固性较差,降低了施工安全性的问题,而提出的一种用于房屋建筑施工的升降平台。The purpose of the present invention is to solve the need to use scaffolding facilities to complete the climbing operation when the ceiling and high wall construction work in the prior art, but the scaffolding needs a certain amount of time to assemble, the efficiency is low, and the firmness is relatively poor. The problem of construction safety is reduced, and a lifting platform for building construction is proposed.

2.技术方案2. Technical solution

为了实现上述目的,本发明采用了如下技术方案:In order to achieve the above object, the present invention adopts the following technical solutions:

一种用于房屋建筑施工的升降平台,包括基座,所述基座的底部固定连接有两对安装块,两对所述安装块上均转动连接有滚轮,所述滚轮的一侧设有安装板,所述安装板上设有安装腔,所述安装腔内设有第一螺纹杆,所述第一螺纹杆的一端与安装腔的内壁转动连接,所述第一螺纹杆的另一端贯穿安装腔的内壁并固定连接有转块,所述第一螺纹杆位于安装腔内的侧壁上螺纹套接有移动板,所述移动板的一端贯穿安装腔的内壁并向下延伸,所述安装板上设有与移动板对应的滑口,所述移动板延伸的一侧固定连接有连接块,所述连接块远离移动板的一端上固定连接有弧形卡块,所述基座上设有安装槽,所述安装槽内固定连接有电机,所述电机的输出端固定连接有第一齿轮,所述第一齿轮的两侧均设有相啮合的第二齿轮,所述第二齿轮上固定插设有第二螺纹杆,所述第二螺纹杆的一端与安装槽的内壁转动连接,所述第二螺纹杆的另一端贯穿安装槽的内壁并向上延伸,所述基座的顶部设有支撑台,所述支撑台的底部固定连接有L型支板,所述L型支板远离支撑台的一端螺纹套接在第二螺纹杆上,所述支撑台的顶部固定连接有围栏,所述第二螺纹杆远离第二齿轮的一端贯穿安装槽的内壁并与支撑台转动连接,所述基座上设有空腔,所述空腔内滑动连接有支撑杆,所述支撑杆的一端贯穿空腔的内壁并与支撑台固定连接,所述基座的顶部固定连接有支撑块,所述支撑块上滑动插设有卡杆,所述支撑杆上设有与卡杆对应的多个卡槽,所述卡杆靠近支撑杆的一端固定套接有固定套。A lifting platform for building construction, comprising a base, two pairs of mounting blocks are fixedly connected to the bottom of the base, and rollers are rotatably connected to the two pairs of mounting blocks, and one side of the rollers is provided with The installation plate is provided with an installation cavity, and a first threaded rod is arranged in the installation cavity, and one end of the first threaded rod is rotatably connected with the inner wall of the installation cavity, and the other end of the first threaded rod Through the inner wall of the installation cavity and fixedly connected with a turning block, the first threaded rod is located on the side wall of the installation cavity and is threaded with a moving plate, one end of the moving plate penetrates the inner wall of the installation cavity and extends downwards, so The mounting plate is provided with a sliding opening corresponding to the moving plate, and a connecting block is fixedly connected to the extended side of the moving plate, and an arc-shaped locking block is fixedly connected to the end of the connecting block away from the moving plate, and the base There is a mounting groove on the top, and a motor is fixedly connected to the mounting groove, and a first gear is fixedly connected to the output end of the motor. Both sides of the first gear are provided with meshing second gears. A second threaded rod is fixedly inserted on the second gear, one end of the second threaded rod is rotatably connected to the inner wall of the installation groove, the other end of the second threaded rod penetrates the inner wall of the installation groove and extends upward, and the base The top of the support platform is provided with a support platform, the bottom of the support platform is fixedly connected with an L-shaped support plate, and the end of the L-shaped support plate away from the support platform is threaded on the second threaded rod, and the top of the support platform is fixedly connected There is a fence, the end of the second threaded rod away from the second gear runs through the inner wall of the installation groove and is connected to the support platform in rotation, the base is provided with a cavity, and a support rod is slidably connected to the cavity, and the One end of the support rod penetrates the inner wall of the cavity and is fixedly connected with the support platform, the top of the base is fixedly connected with a support block, and a clamping rod is slidably inserted on the support block, and a clamping rod is provided on the support rod. Corresponding to the plurality of slots, the end of the clamping rod close to the support rod is fixedly sleeved with a fixed sleeve.

优选地,所述基座的一侧固定连接有连接板,所述连接板的一侧固定连接有多个牵引块,多个所述牵引块上均设有安装口。Preferably, a connection plate is fixedly connected to one side of the base, a plurality of traction blocks are fixedly connected to one side of the connection plate, and installation openings are provided on each of the plurality of traction blocks.

优选地,所述支撑杆位于空腔内的一端上固定连接有防脱块。Preferably, an anti-off block is fixedly connected to one end of the support rod located in the cavity.

优选地,所述支撑杆上套设有第一弹簧,所述第一弹簧的两端分别与防脱块和空腔内壁固定连接。Preferably, a first spring is sheathed on the support rod, and both ends of the first spring are respectively fixedly connected with the anti-falling block and the inner wall of the cavity.

优选地,所述卡杆上套设有第二弹簧,所述第二弹簧的两端分别与固定套和支撑块固定连接。Preferably, a second spring is sheathed on the locking rod, and two ends of the second spring are respectively fixedly connected to the fixing sleeve and the support block.

优选地,所述弧形卡块远离连接块的一侧固定连接有橡胶垫。Preferably, a rubber pad is fixedly connected to the side of the arc-shaped block away from the connecting block.

优选地,所述转块上设有多道防滑齿纹。Preferably, the rotary block is provided with multiple anti-slip tooth lines.

优选地,所述支撑台的顶部固定连接有防滑板。Preferably, an anti-skid plate is fixedly connected to the top of the support platform.

3.有益效果3. Beneficial effect

相比于现有技术,本发明的优点在于:Compared with the prior art, the present invention has the advantages of:

(1)本发明中,使用者在使用时首先通过连接板上的牵引块与牵引机构进行连接,再根据实际施工区域利用滚轮进行移动,在位置移动到指定区域后转动转块带动第一螺纹杆进行转动,此时安装在第一螺纹杆上的移动板进行移动从而推动弧形卡块相抵住滚轮,对基座的位置进行固定。(1) In the present invention, the user first connects the traction mechanism with the traction block on the connecting plate, and then uses the rollers to move according to the actual construction area. After the position moves to the designated area, the user turns the block to drive the first thread When the rod rotates, the moving plate mounted on the first threaded rod moves so as to push the arc-shaped block against the roller to fix the position of the base.

(2)然后打开电机带动第一齿轮转动,此时第一齿轮将啮合两侧的第二齿轮转动,安装在第二齿轮上的两个第二螺纹杆发生转动带动L型支板在第二螺纹杆上移动从而推动支撑台移动,在移动到指定高度后在下方的工作人员可将卡杆插入至支撑杆上的卡槽内实现支撑杆的固定。本发明便于对装置进行移动固定,在施工人员作业时稳定性更高,提高安全性能,降低风险,且操作简单。(2) Then turn on the motor to drive the first gear to rotate. At this time, the first gear will mesh with the second gear on both sides to rotate, and the two second threaded rods installed on the second gear rotate to drive the L-shaped support plate on the second The threaded rod moves up to push the support table to move. After moving to a specified height, the staff below can insert the clamp rod into the slot on the support rod to fix the support rod. The invention is convenient to move and fix the device, has higher stability when construction personnel work, improves safety performance, reduces risks, and is easy to operate.

附图说明Description of drawings

图1为本发明提出的一种用于房屋建筑施工的升降平台的结构示意图;Fig. 1 is the structural representation of a kind of lifting platform that is used for building construction that the present invention proposes;

图2为图1的A处结构示意图;Fig. 2 is a structural schematic diagram of A place in Fig. 1;

图3为图1的支撑台顶部结构示意图。FIG. 3 is a schematic diagram of the top structure of the supporting platform in FIG. 1 .

图中:1基座 、2安装块、3滚轮、4安装板、5第一螺纹杆、6转块、7移动板、8连接块、9弧形卡块、10电机、11第一齿轮、12第二齿轮、13第二螺纹杆、14支撑台、15围栏、16支撑杆、17支撑块、18卡杆、19固定套、20连接板、21牵引块、22防脱块、23第一弹簧、24第二弹簧、25防滑板、26橡胶垫、27L型支板。In the figure: 1 base, 2 mounting block, 3 roller, 4 mounting plate, 5 first threaded rod, 6 turning block, 7 moving plate, 8 connecting block, 9 arc-shaped block, 10 motor, 11 first gear, 12 second gear, 13 second threaded rod, 14 support platform, 15 fence, 16 support rod, 17 support block, 18 card rod, 19 fixed sleeve, 20 connecting plate, 21 traction block, 22 anti-off block, 23 first Spring, 24 second springs, 25 anti-skid plates, 26 rubber pads, 27L type support plates.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention.

在本发明的描述中,需要理解的是,术语“上”、“下”、“前”、“后”、“左”、“右”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In describing the present invention, it should be understood that the terms "upper", "lower", "front", "rear", "left", "right", "top", "bottom", "inner", " The orientation or positional relationship indicated by "outside", etc. is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, so as to Specific orientation configurations and operations, therefore, are not to be construed as limitations on the invention.

实施例1:Example 1:

参照图1-3,一种用于房屋建筑施工的升降平台,包括基座1,基座1的底部固定连接有两对安装块2,用于安装滚轮3,两对安装块2上均转动连接有滚轮3,用于移动基座1,滚轮3的一侧设有安装板4,安装板4上设有安装腔,安装腔内设有第一螺纹杆5,用于带动移动板7移动,第一螺纹杆5的一端与安装腔的内壁转动连接,第一螺纹杆5的另一端贯穿安装腔的内壁并固定连接有转块6,用于转动第一螺纹杆5,第一螺纹杆5位于安装腔内的侧壁上螺纹套接有移动板7,用于推动弧形卡块9,移动板7的一端贯穿安装腔的内壁并向下延伸,安装板4上设有与移动板7对应的滑口,移动板7延伸的一侧固定连接有连接块8,连接块8远离移动板7的一端上固定连接有弧形卡块9,用于相抵固定滚轮3,基座1上设有安装槽,安装槽内固定连接有电机10,用于带动第一齿轮11转动,电机10的输出端固定连接有第一齿轮11,用于啮合第二齿轮12转动,第一齿轮11的两侧均设有相啮合的第二齿轮12,用于带动第二螺纹杆13转动,第二齿轮12上固定插设有第二螺纹杆13,用于带动L型支板27移动,第二螺纹杆13的一端与安装槽的内壁转动连接,第二螺纹杆13的另一端贯穿安装槽的内壁并向上延伸,基座1的顶部设有支撑台14,用于支撑施工人员,支撑台14的底部固定连接有L型支板27,用于推动支撑台14移动,L型支板27远离支撑台14的一端螺纹套接在第二螺纹杆13上,支撑台14的顶部固定连接有围栏15,用于对施工人员进行防护,第二螺纹杆13远离第二齿轮12的一端贯穿安装槽的内壁并与支撑台14转动连接,基座1上设有空腔,空腔内滑动连接有支撑杆16,用于支撑支撑台14移动,支撑杆16的一端贯穿空腔的内壁并与支撑台14固定连接,基座1的顶部固定连接有支撑块17,用于支撑卡杆18,支撑块17上滑动插设有卡杆18,用于限定支撑杆16,支撑杆16上设有与卡杆18对应的多个卡槽,卡杆18靠近支撑杆16的一端固定套接有固定套19,用于防止卡杆18脱落。Referring to Figures 1-3, a lifting platform for building construction includes a base 1, and two pairs of mounting blocks 2 are fixedly connected to the bottom of the base 1 for mounting rollers 3, and both pairs of mounting blocks 2 are rotated A roller 3 is connected to move the base 1. One side of the roller 3 is provided with a mounting plate 4. The mounting plate 4 is provided with a mounting cavity. The mounting cavity is provided with a first threaded rod 5 for driving the moving plate 7 to move. , one end of the first threaded rod 5 is rotatably connected to the inner wall of the installation cavity, the other end of the first threaded rod 5 penetrates the inner wall of the installation cavity and is fixedly connected with a turning block 6 for rotating the first threaded rod 5, the first threaded rod 5. A moving plate 7 is screwed on the side wall of the installation cavity to push the arc block 9. One end of the moving plate 7 penetrates the inner wall of the installation cavity and extends downward. The installation plate 4 is provided with a moving plate 7 corresponding to the sliding port, the side of the moving plate 7 extended is fixedly connected with a connecting block 8, and the end of the connecting block 8 away from the moving plate 7 is fixedly connected with an arc-shaped clamping block 9, which is used to offset the fixed roller 3, on the base 1 A mounting groove is provided, and a motor 10 is fixedly connected in the mounting groove to drive the first gear 11 to rotate, and the output end of the motor 10 is fixedly connected to the first gear 11 for engaging the second gear 12 to rotate, and the first gear 11 Both sides are provided with the second gear 12 that is meshed, for driving the second threaded rod 13 to rotate, the second gear 12 is fixedly inserted with the second threaded rod 13, for driving the L-shaped support plate 27 to move, the second One end of the threaded rod 13 is rotatably connected with the inner wall of the installation groove, and the other end of the second threaded rod 13 penetrates the inner wall of the installation groove and extends upwards. The top of the base 1 is provided with a support platform 14 for supporting construction personnel. The support platform 14 The bottom of the bottom is fixedly connected with an L-shaped support plate 27, which is used to push the support platform 14 to move. The end of the L-shaped support plate 27 away from the support platform 14 is threaded on the second threaded rod 13, and the top of the support platform 14 is fixedly connected with a fence. 15. It is used to protect construction personnel. The end of the second threaded rod 13 away from the second gear 12 penetrates the inner wall of the installation groove and is connected to the support platform 14 in rotation. A cavity is provided on the base 1, and a cavity is slidingly connected in the cavity. Support rod 16 is used to support the movement of support table 14. One end of support rod 16 runs through the inner wall of the cavity and is fixedly connected with support table 14. The top of base 1 is fixedly connected with support block 17 for supporting clamping rod 18. Block 17 is slidably inserted with clamping rod 18 for limiting support rod 16. Support rod 16 is provided with a plurality of draw-in slots corresponding to clamp rod 18. One end of clamp rod 18 near support rod 16 is fixedly sleeved with a fixed sleeve. 19, used to prevent the clamping rod 18 from falling off.

本发明中,基座1的一侧固定连接有连接板20,连接板20的一侧固定连接有多个牵引块21,多个牵引块21上均设有安装口,用于与牵引机构进行连接,支撑杆16位于空腔内的一端上固定连接有防脱块22,防止支撑杆16脱落,支撑杆16上套设有第一弹簧23,第一弹簧23的两端分别与防脱块22和空腔内壁固定连接,增加支撑杆16移动时的缓冲力,卡杆18上套设有第二弹簧24,第二弹簧24的两端分别与固定套19和支撑块17固定连接,方便卡杆18回弹至卡槽内,弧形卡块9远离连接块8的一侧固定连接有橡胶垫26,转块6上设有多道防滑齿纹,增加摩擦力方便转动,支撑台14的顶部固定连接有防滑板25,增加摩擦力,防止施工人员滑倒。In the present invention, one side of the base 1 is fixedly connected with a connection plate 20, and one side of the connection plate 20 is fixedly connected with a plurality of traction blocks 21, and a plurality of traction blocks 21 are provided with mounting ports for carrying out with the traction mechanism. Connect, the support rod 16 is fixedly connected with the anti-off block 22 on one end in the cavity, prevents the support rod 16 from falling off, the support rod 16 is set with the first spring 23, and the two ends of the first spring 23 are connected with the anti-off block respectively. 22 is fixedly connected with the inner wall of the cavity to increase the buffer force when the support rod 16 moves, and the clamp rod 18 is provided with a second spring 24, and the two ends of the second spring 24 are fixedly connected with the fixed sleeve 19 and the support block 17 respectively, which is convenient The clamping rod 18 rebounds into the draw-in groove, and the side of the arc-shaped clamping block 9 away from the connecting block 8 is fixedly connected with a rubber pad 26, and the rotating block 6 is provided with multiple anti-slip tooth lines, which increases friction to facilitate rotation, and the supporting platform 14 The top of the top is fixedly connected with anti-skid plate 25, which increases frictional force and prevents construction workers from slipping.

本发明中,使用者在使用时首先通过连接板20上的牵引块21与牵引机构进行连接,再根据实际施工区域利用滚轮3进行移动,在位置移动到指定区域后转动转块6带动第一螺纹杆5进行转动,此时安装在第一螺纹杆5上的移动板7进行移动从而推动弧形卡块9相抵住滚轮3,对基座1的位置进行固定,然后打开电机10带动第一齿轮11转动,此时第一齿轮11将啮合两侧的第二齿轮12转动,安装在第二齿轮12上的两个第二螺纹杆13发生转动带动L型支板27在第二螺纹杆13上移动从而推动支撑台14移动,在支撑台14移动的同时支撑杆16在基座内滑动,增加支撑台14移动时的稳定性,在移动到指定高度后在下方的工作人员可将卡杆18插入至支撑杆16上的卡槽内实现支撑杆16的固定。In the present invention, the user first connects with the traction mechanism through the traction block 21 on the connecting plate 20, and then uses the roller 3 to move according to the actual construction area, and turns the rotary block 6 to drive the first The threaded rod 5 rotates, and the moving plate 7 installed on the first threaded rod 5 moves to push the arc-shaped block 9 against the roller 3, and the position of the base 1 is fixed, and then the motor 10 is turned on to drive the first When the gear 11 rotates, the first gear 11 will mesh with the second gear 12 on both sides to rotate, and the two second threaded rods 13 installed on the second gear 12 will rotate to drive the L-shaped support plate 27 on the second threaded rod 13. Move up to push the support platform 14 to move, while the support platform 14 moves, the support rod 16 slides in the base, increasing the stability of the support platform 14 when moving, after moving to the specified height, the staff at the bottom can move the clamp bar 18 is inserted into the slot on the support rod 16 to fix the support rod 16.

以上所述,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,根据本发明的技术方案及其发明构思加以等同替换或改变,都应涵盖在本发明的保护范围之内。The above is only a preferred embodiment of the present invention, but the scope of protection of the present invention is not limited thereto, any person familiar with the technical field within the technical scope disclosed in the present invention, according to the technical solution of the present invention Any equivalent replacement or change of the inventive concepts thereof shall fall within the protection scope of the present invention.

Claims (8)

1.一种用于房屋建筑施工的升降平台,包括基座(1),其特征在于,所述基座(1)的底部固定连接有两对安装块(2),两对所述安装块(2)上均转动连接有滚轮(3),所述滚轮(3)的一侧设有安装板(4),所述安装板(4)上设有安装腔,所述安装腔内设有第一螺纹杆(5),所述第一螺纹杆(5)的一端与安装腔的内壁转动连接,所述第一螺纹杆(5)的另一端贯穿安装腔的内壁并固定连接有转块(6),所述第一螺纹杆(5)位于安装腔内的侧壁上螺纹套接有移动板(7),所述移动板(7)的一端贯穿安装腔的内壁并向下延伸,所述安装板(4)上设有与移动板(7)对应的滑口,所述移动板(7)延伸的一侧固定连接有连接块(8),所述连接块(8)远离移动板(7)的一端上固定连接有弧形卡块(9),所述基座(1)上设有安装槽,所述安装槽内固定连接有电机(10),所述电机(10)的输出端固定连接有第一齿轮(11),所述第一齿轮(11)的两侧均设有相啮合的第二齿轮(12),所述第二齿轮(12)上固定插设有第二螺纹杆(13),所述第二螺纹杆(13)的一端与安装槽的内壁转动连接,所述第二螺纹杆(13)的另一端贯穿安装槽的内壁并向上延伸,所述基座(1)的顶部设有支撑台(14),所述支撑台(14)的底部固定连接有L型支板(27),所述L型支板(27)远离支撑台(14)的一端螺纹套接在第二螺纹杆(13)上,所述支撑台(14)的顶部固定连接有围栏(15),所述基座(1)上设有空腔,所述空腔内滑动连接有支撑杆(16),所述支撑杆(16)的一端贯穿空腔的内壁并与支撑台(14)固定连接,所述基座(1)的顶部固定连接有支撑块(17),所述支撑块(17)上滑动插设有卡杆(18),所述支撑杆(16)上设有与卡杆(18)对应的多个卡槽,所述卡杆(18)靠近支撑杆(16)的一端固定套接有固定套(19)。1. A lifting platform for building construction, comprising a base (1), characterized in that two pairs of mounting blocks (2) are fixedly connected to the bottom of the base (1), and two pairs of mounting blocks (2) are rotatably connected with rollers (3), one side of the rollers (3) is provided with a mounting plate (4), the mounting plate (4) is provided with a mounting cavity, and the mounting cavity is provided with A first threaded rod (5), one end of the first threaded rod (5) is rotatably connected to the inner wall of the installation cavity, and the other end of the first threaded rod (5) penetrates the inner wall of the installation cavity and is fixedly connected with a turning block (6), the first threaded rod (5) is located on the side wall of the installation cavity and is threaded with a moving plate (7), one end of the moving plate (7) penetrates the inner wall of the installation cavity and extends downwards, The mounting plate (4) is provided with a sliding opening corresponding to the moving plate (7), and the extended side of the moving plate (7) is fixedly connected with a connecting block (8), and the connecting block (8) is far away from the moving One end of the plate (7) is fixedly connected with an arc-shaped block (9), and the base (1) is provided with a mounting groove, and a motor (10) is fixedly connected in the mounting groove, and the motor (10) The output end of the output end is fixedly connected with a first gear (11), and both sides of the first gear (11) are provided with meshing second gears (12), and the second gear (12) is fixedly inserted with The second threaded rod (13), one end of the second threaded rod (13) is rotatably connected with the inner wall of the installation groove, the other end of the second threaded rod (13) penetrates the inner wall of the installation groove and extends upward, the The top of the base (1) is provided with a support platform (14), and the bottom of the support platform (14) is fixedly connected with an L-shaped support plate (27), and the L-shaped support plate (27) is far away from the support platform (14) One end threaded on the second threaded rod (13), the top of the support table (14) is fixedly connected with a fence (15), the base (1) is provided with a cavity, the cavity A support rod (16) is slidingly connected, one end of the support rod (16) penetrates the inner wall of the cavity and is fixedly connected with the support table (14), and the top of the base (1) is fixedly connected with a support block (17) , the support block (17) is slidably inserted with a clamping rod (18), the support rod (16) is provided with a plurality of clamping slots corresponding to the clamping rod (18), and the clamping rod (18) is close to One end of the support rod (16) is fixedly sleeved with a fixed sleeve (19). 2.根据权利要求1所述的一种用于房屋建筑施工的升降平台,其特征在于,所述基座(1)的一侧固定连接有连接板(20),所述连接板(20)的一侧固定连接有多个牵引块(21),多个所述牵引块(21)上均设有安装口。2. A lifting platform for building construction according to claim 1, characterized in that, one side of the base (1) is fixedly connected with a connecting plate (20), and the connecting plate (20) One side of one side is fixedly connected with a plurality of traction blocks (21), and the plurality of traction blocks (21) are all provided with installation openings. 3.根据权利要求1所述的一种用于房屋建筑施工的升降平台,其特征在于,所述支撑杆(16)位于空腔内的一端上固定连接有防脱块(22)。3 . The lifting platform for building construction according to claim 1 , characterized in that, one end of the support rod ( 16 ) located in the cavity is fixedly connected with an anti-off block ( 22 ). 4 . 4.根据权利要求3所述的一种用于房屋建筑施工的升降平台,其特征在于,所述支撑杆(16)上套设有第一弹簧(23),所述第一弹簧(23)的两端分别与防脱块(22)和空腔内壁固定连接。4. A lifting platform for building construction according to claim 3, characterized in that, the support rod (16) is sheathed with a first spring (23), and the first spring (23) The two ends are respectively fixedly connected with the anti-off block (22) and the inner wall of the cavity. 5.根据权利要求1所述的一种用于房屋建筑施工的升降平台,其特征在于,所述卡杆(18)上套设有第二弹簧(24),所述第二弹簧(24)的两端分别与固定套(19)和支撑块(17)固定连接。5. A lifting platform for building construction according to claim 1, characterized in that, a second spring (24) is sheathed on the clamping rod (18), and the second spring (24) The two ends are respectively fixedly connected with the fixed sleeve (19) and the support block (17). 6.根据权利要求1所述的一种用于房屋建筑施工的升降平台,其特征在于,所述弧形卡块(9)远离连接块(8)的一侧固定连接有橡胶垫(26)。6. A lifting platform for building construction according to claim 1, characterized in that a rubber pad (26) is fixedly connected to the side of the arc-shaped block (9) away from the connecting block (8) . 7.根据权利要求1所述的一种用于房屋建筑施工的升降平台,其特征在于,所述转块(6)上设有多道防滑齿纹。7. The lifting platform for building construction according to claim 1, characterized in that, the turning block (6) is provided with multiple anti-slip tooth lines. 8.根据权利要求1所述的一种用于房屋建筑施工的升降平台,其特征在于,所述支撑台(14)的顶部固定连接有防滑板(25)。8 . The lifting platform used for building construction according to claim 1 , characterized in that, the top of the support platform ( 14 ) is fixedly connected with an anti-skid plate ( 25 ).
CN201910796152.XA 2019-08-27 2019-08-27 Lifting platform for house building construction Pending CN110616886A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910796152.XA CN110616886A (en) 2019-08-27 2019-08-27 Lifting platform for house building construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910796152.XA CN110616886A (en) 2019-08-27 2019-08-27 Lifting platform for house building construction

Publications (1)

Publication Number Publication Date
CN110616886A true CN110616886A (en) 2019-12-27

Family

ID=68922068

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910796152.XA Pending CN110616886A (en) 2019-08-27 2019-08-27 Lifting platform for house building construction

Country Status (1)

Country Link
CN (1) CN110616886A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112360131A (en) * 2020-11-04 2021-02-12 江苏晟德机械设备有限公司 Detachable integral lifting steel platform system for super high-rise variable-plane construction and construction method
CN112853979A (en) * 2021-01-04 2021-05-28 安徽理工大学 Pouring support device for building
CN114232973A (en) * 2022-01-26 2022-03-25 遂昌县匠锐机械设计有限公司 High-altitude operation platform for construction of steel structure engineering

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207332275U (en) * 2017-09-24 2018-05-08 胡现勇 A kind of temporary construction hoistable platform
CN108545104A (en) * 2018-04-10 2018-09-18 丁路勇 A kind of power equipment transport vehicle convenient for handling
CN109989567A (en) * 2019-05-10 2019-07-09 诸暨天雅科技有限公司 A kind of small-sized lift work platform of assembled architecture construction
CN211080948U (en) * 2019-08-27 2020-07-24 广东省建筑工程机械施工有限公司 Lifting platform for house building construction

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN207332275U (en) * 2017-09-24 2018-05-08 胡现勇 A kind of temporary construction hoistable platform
CN108545104A (en) * 2018-04-10 2018-09-18 丁路勇 A kind of power equipment transport vehicle convenient for handling
CN109989567A (en) * 2019-05-10 2019-07-09 诸暨天雅科技有限公司 A kind of small-sized lift work platform of assembled architecture construction
CN211080948U (en) * 2019-08-27 2020-07-24 广东省建筑工程机械施工有限公司 Lifting platform for house building construction

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112360131A (en) * 2020-11-04 2021-02-12 江苏晟德机械设备有限公司 Detachable integral lifting steel platform system for super high-rise variable-plane construction and construction method
CN112853979A (en) * 2021-01-04 2021-05-28 安徽理工大学 Pouring support device for building
CN114232973A (en) * 2022-01-26 2022-03-25 遂昌县匠锐机械设计有限公司 High-altitude operation platform for construction of steel structure engineering

Similar Documents

Publication Publication Date Title
CN110616886A (en) Lifting platform for house building construction
CN105366495A (en) Folding residential escalator
CN110571707B (en) Auxiliary tool for mounting overhead line power insulator
CN211499909U (en) Support bracket for constructional engineering
CN108386126A (en) Elevator pit climbing ladder apparatus
CN216512341U (en) Lifting device for mounting glass curtain wall plate
CN108277970A (en) Elevator civil construction mobile platform
CN221118889U (en) Quick detach formula photovoltaic curtain
CN211080948U (en) Lifting platform for house building construction
CN217802394U (en) Labor-saving portable prefabricated wall body reinforcing bar binding device
CN207538432U (en) A kind of movable building scaffold
CN211473310U (en) An adjustable scaffolding for construction sites
CN117720040A (en) Handling device for outdoor power cabinet installation
CN210366828U (en) Ceiling lamp lifting device is used in indoor decoration
CN210067410U (en) Support device for climbing scaffold
CN211499735U (en) Wall-attached support for automatic climbing frame
CN110080511B (en) Moving platform for light steel structure building installation
CN221742126U (en) Support arrangement for building consolidates
CN220395116U (en) Lifting type building construction platform
CN114701966A (en) Hand jack of portable
CN114412157A (en) A hydraulic sliding frame climbing frame with high stability
CN208546881U (en) A kind of decorative engineering lighting device
CN223165185U (en) Electromechanical pipeline laying equipment for building
CN219898689U (en) Auxiliary paint spraying device
CN117052196B (en) Supporting structure for building construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191227