CN110593115A - Cast-in-place box girder support system and its construction method - Google Patents

Cast-in-place box girder support system and its construction method Download PDF

Info

Publication number
CN110593115A
CN110593115A CN201910925909.0A CN201910925909A CN110593115A CN 110593115 A CN110593115 A CN 110593115A CN 201910925909 A CN201910925909 A CN 201910925909A CN 110593115 A CN110593115 A CN 110593115A
Authority
CN
China
Prior art keywords
support
cast
hoop
bailey
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910925909.0A
Other languages
Chinese (zh)
Inventor
齐昌广
忻见敏
王梁志
张智超
姜苏珂
单艳玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo University
Original Assignee
Ningbo University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo University filed Critical Ningbo University
Priority to CN201910925909.0A priority Critical patent/CN110593115A/en
Publication of CN110593115A publication Critical patent/CN110593115A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及现浇箱梁支架体系,包括立柱支撑、抱箍支撑、电动液压千斤顶、横梁、贝雷梁和底模梁;所述的立柱支撑主要是由两个钢立柱和基础组成的,钢立柱上设置电动液压千斤顶,两个钢立柱之间设置立柱系梁,基础设置在陡峭地形的高位区尖端处;陡峭地形的低位区设置高墩;所述的抱箍支撑主要是由贯穿孔、L型抱箍板、加劲肋和对拉螺栓组成的,贯穿孔预留在高墩中,L型抱箍板设有螺栓预留孔和加劲肋,对拉螺栓设置在贯穿孔与螺栓预留孔中。本发明的有益效果是:本发明利用既有高墩形成抱箍支撑体系,减少了传统技术中在高墩附近架设钢立柱的工艺,增加了施工速度,降低了工程造价。

The invention relates to a cast-in-place box girder support system, including column supports, hoop supports, electro-hydraulic jacks, beams, Bailey beams and bottom formwork beams; the column supports are mainly composed of two steel columns and a foundation, and the steel An electro-hydraulic jack is set on the column, a column tie beam is set between two steel columns, the foundation is set at the tip of the high-level area of the steep terrain; a high pier is set in the low-level area of the steep terrain; the hoop support is mainly composed of through holes, Composed of L-shaped hoop plates, stiffeners and tension bolts, the through holes are reserved in the high pier. in the hole. The beneficial effects of the invention are: the invention utilizes the existing high piers to form a hoop support system, which reduces the process of erecting steel columns near the high piers in the traditional technology, increases the construction speed, and reduces the construction cost.

Description

现浇箱梁支架体系及其施工方法Cast-in-place box girder support system and its construction method

技术领域technical field

本发明涉及支架体系,特别涉及一种现浇箱梁支架体系及其施工方法。The invention relates to a support system, in particular to a cast-in-place box girder support system and a construction method thereof.

背景技术Background technique

目前,在进行现浇梁施工时,一般的施工方法是先对地基进行加固处理,然后搭设满堂支架放置好模板、钢筋后进行混凝土浇筑施工。而高墩现浇箱梁施工中常用的一种支架形式是贝雷梁钢管柱组合支架(也就是贝雷梁+钢管柱作为支架),尤其在重荷载、高墩柱、跨度大的情况时,则是较为经济安全的一种支架型式。相关专利有:桥梁高墩现浇箱施工支撑体系(ZL 201520713361.0)、一种桥梁少支架施工方法以及桥梁(ZL201610423219.1)、结合抱箍与贝雷梁现浇箱梁的无落地支架的施工方法(实质审查中,申请号CN201810746490.8)、贝雷梁索鞍吊装支架(ZL 201820129079.1)、一种基于贝雷梁支架的简支桥梁支撑结构(ZL 201620340399.2)、跨河桥梁底部贝雷梁临时支架顶升浮运拆除方法(ZL 201711227627.0)、一种贝雷梁支架拆除装置(ZL 201821049367.2)。然而对于地势陡峭,且墩身高达40m及以上的高墩现浇箱梁而言,采用满堂支架施工不仅存在钢管柱及其基础无法架设打设或架设打设困难、大跨度贝雷梁过长导致中间部位挠度大、支架体系预压施工大等问题,而且安全性低,材料、人员投入也较大。因此,为了克服这些问题,亟需寻找一种适用于陡峭地形的现浇箱梁支架体系及其施工方法。At present, during the construction of cast-in-place beams, the general construction method is to first reinforce the foundation, and then set up a full support to place the formwork and steel bars and then carry out concrete pouring construction. A commonly used support form in the construction of cast-in-place box girders with high piers is the combined support of Bailey beams and steel pipe columns (that is, Bailey beams + steel pipe columns as supports), especially in the case of heavy loads, high pier columns, and large spans. , which is a more economical and safer bracket type. Related patents include: construction support system of cast-in-place box for high bridge piers (ZL 201520713361.0), a construction method for bridges with few supports, and bridges (ZL201610423219.1), construction of cast-in-place box girders combining hoops and Bailey beams without floor supports Method (under substantive examination, application number CN201810746490.8), Bailey beam cable saddle lifting bracket (ZL 201820129079.1), a simply supported bridge support structure based on Bailey beam bracket (ZL 201620340399.2), Bailey beam at the bottom of a bridge crossing a river A temporary support lifting and floating removal method (ZL 201711227627.0), a Bailey beam support removal device (ZL 201821049367.2). However, for the cast-in-place box girder with high pier with a steep terrain and a pier body height of 40m or more, the use of full-wall support not only has the disadvantages that the steel pipe column and its foundation cannot be erected or erected, and the long-span Bailey beam is too long to cause the middle There are problems such as large deflection of parts and large preloading construction of the support system, and the safety is low, and the investment in materials and personnel is also large. Therefore, in order to overcome these problems, it is urgent to find a cast-in-place box girder support system and its construction method suitable for steep terrain.

发明内容Contents of the invention

本发明的目的是克服现有技术中的不足,提供一种现浇箱梁支架体系及其施工方法。The purpose of the present invention is to overcome the deficiencies in the prior art and provide a cast-in-place box girder support system and a construction method thereof.

这种现浇箱梁支架体系,包括立柱支撑、抱箍支撑、电动液压千斤顶、横梁、贝雷梁和底模梁;所述的立柱支撑主要是由两个钢立柱和基础组成的,钢立柱上设置电动液压千斤顶,两个钢立柱之间设置立柱系梁,基础设置在陡峭地形的高位区尖端处;陡峭地形的低位区设置高墩;所述的抱箍支撑主要是由贯穿孔、L型抱箍板、加劲肋和对拉螺栓组成的,贯穿孔预留在高墩中,L型抱箍板设有螺栓预留孔和加劲肋,对拉螺栓设置在贯穿孔与螺栓预留孔中;钢立柱顶部的电动液压千斤顶和抱箍支撑顶部的电动液压千斤顶上均设有横梁,横梁上方设置贝雷梁,贝雷梁顶部设置底模梁,高墩顶部设置支座,底模梁和支座上方设置现浇箱梁模板。This cast-in-place box girder support system includes column supports, hoop supports, electro-hydraulic jacks, beams, Bailey beams and bottom formwork beams; the column supports are mainly composed of two steel columns and foundations, and the steel columns An electro-hydraulic jack is set on the top, a column beam is set between two steel columns, the foundation is set at the tip of the high-level area of the steep terrain; a high pier is set in the low-level area of the steep terrain; the hoop support is mainly composed of through holes, L The L-type hoop plate is composed of a stiffening rib and a tension bolt, and the through hole is reserved in the high pier. Middle; the electro-hydraulic jack on the top of the steel column and the electro-hydraulic jack on the top of the hoop support are equipped with beams, the Bailey beam is set above the beam, the bottom form beam is set on the top of the Bailey beam, the support is set on the top of the high pier, and the bottom form beam Set the cast-in-place box girder formwork above the support.

作为优选:若横梁的跨度过大,则采用预应力贝雷梁,预应力贝雷梁是在贝雷梁的两端设置端板,端板下部设置筋孔、预应力筋和锚具,预应力筋穿过筋孔和锚具。As a preference: if the span of the beam is too large, use a prestressed Bailey beam. The prestressed Bailey beam is provided with end plates at both ends of the Bailey beam. Stress tendons pass through tendon holes and anchors.

作为优选:电动液压千斤顶设有栓接用的底座,并栓接在立柱支撑和抱箍支撑上。As an optimization: the electro-hydraulic jack is provided with a base for bolting, and is bolted to the column support and the hoop support.

作为优选:横梁底部设有凹槽,并与电动液压千斤顶的柱塞对接。As an optimization: the bottom of the beam is provided with a groove, and is docked with the plunger of the electro-hydraulic jack.

作为优选:底模梁顶部与高墩上的支座顶部齐平。As a preference: the top of the bottom form beam is flush with the top of the support on the high pier.

作为优选:钢立柱截面是圆角矩形。Preferably: the section of the steel column is a rounded rectangle.

这种现浇箱梁支架体系的施工方法,包括以下步骤:The construction method of this cast-in-place box girder support system comprises the following steps:

1)、在高墩施工时,在其上部适宜位置处预留贯穿孔,然后在贯穿孔两侧设置L型抱箍板,L型抱箍板中设有加劲肋和螺栓预留孔,通过贯穿孔与螺栓预留孔设置对拉螺栓,构成抱箍支撑;1) When constructing a high pier, reserve a through hole at a suitable position on the upper part, and then set an L-shaped hoop plate on both sides of the through hole. The L-shaped hoop plate is provided with stiffening ribs and reserved holes for bolts. The through hole and the bolt reserved hole are provided with pull bolts to form a hoop support;

2)、在高墩墩柱两跨之间的陡峭地形中,寻找适合钢立柱及其基础施工的区域,进行基础施工,之后架设好两个钢管柱,安装钢立柱时利用钢管柱来固定,并在钢立柱之间设置立柱系梁;2) In the steep terrain between the two spans of high pier columns, find an area suitable for steel columns and their foundation construction, carry out foundation construction, and then erect two steel pipe columns, and use steel pipe columns to fix the steel columns when installing them. And set the column tie beam between the steel columns;

3)、在抱箍支撑和钢立柱上分别安装电动液压千斤顶;3) Install electro-hydraulic jacks on the hoop supports and steel columns respectively;

4)、在抱箍支撑和钢立柱的电动液压千斤顶上分别放置横梁,横梁底部设有凹槽,并与电动液压千斤顶的柱塞对接;4) Place beams respectively on the hoop support and the electro-hydraulic jack of the steel column, the bottom of the beam is provided with a groove, and docked with the plunger of the electro-hydraulic jack;

5)、在抱箍支撑的横梁上吊放贝雷梁,同时在高墩顶部放置支座,同时在立柱支撑的横梁上也吊放贝雷梁;若横梁的跨度过大,采用预应力贝雷梁;预应力贝雷梁是在贝雷梁的两端设置端板,通过端板下部的筋孔、预应力筋和锚具进行预应力施加;5) Hang the Bailey beam on the beam supported by the hoop, and place the support on the top of the high pier at the same time, and hang the Bailey beam on the beam supported by the column at the same time; if the span of the beam is too large, use prestressed Bailey Beams; prestressed Bailey beams are provided with end plates at both ends of Bailey beams, and prestressing is applied through the tendon holes, prestressed tendons and anchors in the lower part of the end plates;

6)、在贝雷梁上按照一定的间距设置底模梁,然后在底模梁上逐步布设现浇箱梁模板、钢筋以及预应力体系;6) On the Bailey beam, set the bottom form beam according to a certain interval, and then gradually lay out the cast-in-place box girder formwork, steel bars and prestressed system on the bottom form beam;

7)、浇筑混凝土,同时启动电动液压千斤顶进行高度自动补偿,随着混凝土浇筑越多,补偿越多,待混凝土浇筑完毕并达到一定强度后施加预应力;7) Concrete is poured, and the electro-hydraulic jack is started at the same time for automatic height compensation. As more concrete is poured, more compensation will be made. After the concrete is poured and reaches a certain strength, prestress is applied;

8)、待高墩现浇箱梁强度满足要求后,依次拆除掉现浇箱梁模板、底模梁、贝雷梁、横梁、电动液压千斤顶、抱箍支撑和立柱支撑,并将高墩上的贯穿孔回填混凝土充实。8) After the strength of the cast-in-place box girder of the high pier meets the requirements, remove the formwork of the cast-in-place box girder, bottom form beam, Bailey beam, beam, electro-hydraulic jack, hoop support and column support in sequence, and place the The through holes are backfilled with concrete.

本发明的有益效果是:The beneficial effects of the present invention are:

(1)、本发明利用既有高墩形成抱箍支撑体系,减少了传统技术中在高墩附近架设钢立柱的工艺,增加了施工速度,降低了工程造价。(1), the present invention utilizes the existing high pier to form the hoop support system, which reduces the process of erecting steel columns near the high pier in the traditional technology, increases the construction speed, and reduces the engineering cost.

(2)、本发明的钢立柱设置在相邻两高墩之间的高位尖端处,采用两个圆角矩形状立柱与立柱系梁组合形成钢立柱,增强立柱的侧向刚度的同时,又可减小钢立柱的高度,从而降低造价,具有明显的经济效益。(2), the steel column of the present invention is arranged at the tip of the high position between two adjacent high piers, and two rounded rectangular columns and column tie beams are used to form a steel column, which enhances the lateral rigidity of the column and also The height of the steel column can be reduced, thereby reducing the cost and having obvious economic benefits.

(3)、本发明的电动液压千斤顶具有高度自动补偿功能,使得整个支架不需要进行预压,具有明显的技术与经济效益。(3) The electrohydraulic jack of the present invention has the function of automatic height compensation, so that the whole support does not need to be preloaded, and has obvious technical and economic benefits.

(4)、对于大跨度的贝雷梁,可采用预应力贝雷梁,有利于减小贝雷梁的中间挠度,再加上电动液压千斤顶的自动补偿,可进一步地有利于确保模板位置的准确性,进而保证了现浇箱梁的施工精度。(4) For large-span Bailey beams, prestressed Bailey beams can be used, which is beneficial to reduce the middle deflection of Bailey beams, and the automatic compensation of electro-hydraulic jacks can further help ensure the accuracy of the formwork position Accuracy, thereby ensuring the construction accuracy of the cast-in-place box girder.

(5)、本发明的预应力贝雷梁是在传统贝雷梁的两侧设置端板,然后通过端板下部的筋孔、预应力筋和锚具进行预应力施加而成的,构造简单,便于现场操作。(5), the prestressed Bailey beam of the present invention is that end plates are arranged on both sides of the traditional Bailey beam, and then prestressing is applied through the reinforcement holes, prestressed tendons and anchors at the bottom of the end plate, and the structure is simple , easy to operate on site.

(6)本发明在传统贝雷梁钢管柱组合支架基础上,通过改进贝雷梁的支撑体系,形成了复合式支架体系,为类似工程施工提供了一定的参考价值。(6) On the basis of the traditional Bailey beam steel tube column composite support, the present invention forms a composite support system by improving the support system of the Bailey beam, which provides a certain reference value for similar engineering construction.

附图说明Description of drawings

图1是抱箍支撑示意图;Fig. 1 is a schematic diagram of hoop support;

图2是钢立柱立面图;Fig. 2 is the elevation view of steel column;

图3是钢立柱俯视图;Fig. 3 is a top view of a steel column;

图4是抱箍支撑安装千斤顶示意图;Fig. 4 is a schematic diagram of hoop support installation jack;

图5是钢立柱顶面安装千斤顶示意图;Fig. 5 is a schematic diagram of a jack installed on the top surface of a steel column;

图6是横梁底部细节图;Figure 6 is a detailed view of the bottom of the beam;

图7是抱箍支撑上设置横梁示意图;Fig. 7 is a schematic diagram of setting a crossbeam on the hoop support;

图8是钢立柱上设置横梁示意图;Fig. 8 is a schematic diagram of crossbeams arranged on steel columns;

图9是抱箍支撑上吊放贝雷梁及高墩上安装支座示意图;Fig. 9 is a schematic diagram of hoisting a Bailey beam on a hoop support and installing a support on a high pier;

图10是钢立柱上吊放贝雷梁示意图;Fig. 10 is a schematic diagram of hanging a Bailey beam on a steel column;

图11是预应力贝雷梁示意图;Figure 11 is a schematic diagram of a prestressed Bailey beam;

图12是模板体系安装示意图;Figure 12 is a schematic diagram of the installation of the formwork system;

附图标记说明:1-电动液压千斤顶;2-横梁;3-贝雷梁;4-底模梁;5-钢立柱;6-基础;7-立柱系梁;8-陡峭地形;9-贯穿孔;10-L型抱箍板;11-加劲肋;12-对拉螺栓;13-高墩;14-端板;15-筋孔;16-预应力筋;17-锚具;18-底座;19-凹槽;20-支座;21-柱塞;22-现浇箱梁模板。Explanation of reference signs: 1-electro-hydraulic jack; 2-beam; 3-Berry beam; 4-bottom form beam; 5-steel column; 6-foundation; 7-column tie beam; 8-steep terrain; 9-through Hole; 10-L-type hoop plate; 11-stiffener; 12-pull bolt; 13-high pier; 14-end plate; 15-reinforcement hole; 16-prestressed tendon; 17-anchor; 18-base ; 19-groove; 20-support; 21-plunger; 22-cast-in-place box girder template.

具体实施方式Detailed ways

下面结合实施例对本发明做进一步描述。下述实施例的说明只是用于帮助理解本发明。应当指出,对于本技术领域的普通技术人员来说,在不脱离本发明原理的前提下,还可以对本发明进行若干改进和修饰,这些改进和修饰也落入本发明权利要求的保护范围内。The present invention will be further described below in conjunction with the examples. The description of the following examples is provided only to aid the understanding of the present invention. It should be pointed out that for those skilled in the art, without departing from the principles of the present invention, some improvements and modifications can be made to the present invention, and these improvements and modifications also fall within the protection scope of the claims of the present invention.

如图1所示,在柱形的高墩13施工时,在其上部适宜位置处预留两排贯穿孔9,然后在贯穿孔9两侧各设置一个L型抱箍板10,L型抱箍板10中设有加劲肋11和两个螺栓预留孔,通过两排贯穿孔9与两个螺栓预留孔,设置两个对拉螺栓12,构成抱箍支撑。As shown in Figure 1, during the construction of a columnar high pier 13, two rows of through holes 9 are reserved at suitable positions on the upper part, and then an L-shaped hoop plate 10 is arranged on both sides of the through hole 9. The hoop plate 10 is provided with a stiffener 11 and two bolt reserved holes, through two rows of through holes 9 and the two bolt reserved holes, two pull bolts 12 are set to form a hoop support.

如图2、3所示,在高墩13墩柱两跨之间的陡峭地形8中,寻找有利于减小钢立柱5的长度,进而节约造价的高位区的尖端区,作为钢立柱5及其基础6施工的区域,进行基础6施工,之后在基础6上架设好两个钢管柱,安装钢立柱5时利用钢管柱来固定,钢立柱5的顶部要与高墩13处L型抱箍板10的顶部保持持平,待钢立柱5布设成型后,拆除钢管柱,并在两个钢立柱5之间设置立柱系梁7,钢立柱5截面为圆角矩形。As shown in Figures 2 and 3, in the steep terrain 8 between the two spans of the high pier 13 pier columns, find the tip area of the high-position area that is conducive to reducing the length of the steel column 5, and then save the cost, as the steel column 5 and In the area where the foundation 6 is constructed, the foundation 6 is constructed, and then two steel pipe columns are erected on the foundation 6. When installing the steel column 5, the steel column is used to fix it. The top of the steel column 5 must be connected with 13 L-shaped hoops on the high pier The top of the plate 10 is kept flat. After the steel columns 5 are laid and formed, the steel tube columns are removed, and a column tie beam 7 is set between the two steel columns 5. The section of the steel columns 5 is a rounded rectangle.

如图4、5所示,通过电动液压千斤顶1底部栓接用的底座18,将其分别栓接在抱箍支撑和钢立柱5上,同时电动液压千斤顶1带有自动补偿效应。As shown in Figures 4 and 5, the base 18 for bolting the bottom of the electro-hydraulic jack 1 is bolted to the hoop support and the steel column 5 respectively, and the electro-hydraulic jack 1 has an automatic compensation effect.

如图6、7、8所示,在每个抱箍支撑和钢立柱5上分别放置一个柱形的横梁2,横梁2底部设有四个圆形的凹槽19,并与电动液压千斤顶1的柱塞21对接,凹槽19的直径要大于柱塞21的外直径2~3mm。As shown in Figures 6, 7, and 8, a columnar beam 2 is respectively placed on each hoop support and steel column 5, and the bottom of the beam 2 is provided with four circular grooves 19, which are connected with the electrohydraulic jack 1 The plunger 21 is docked, and the diameter of the groove 19 is 2 to 3 mm larger than the outer diameter of the plunger 21.

如图9、10所示,在抱箍支撑的横梁2上吊放贝雷梁3,同时在高墩13顶部放置支座20,同时在立柱支撑的横梁2上也吊放贝雷梁3;若横梁2的跨度过大,可采用预应力贝雷梁,便于减小贝雷梁3的挠度。As shown in Figures 9 and 10, the Bailey beam 3 is suspended on the beam 2 supported by the hoop, and the support 20 is placed on the top of the high pier 13 at the same time, and the Bailey beam 3 is also suspended on the beam 2 supported by the column; if If the span of the crossbeam 2 is too large, a prestressed Bailey beam can be used to reduce the deflection of the Bailey beam 3 .

如图11所示,预应力贝雷梁是在贝雷梁3的两端设置端板14,端板14为棱台状,通过端板14下部预设的筋孔15、预应力筋16和锚具17进行预应力施加。As shown in Figure 11, the prestressed Bailey beam is that end plates 14 are arranged at the two ends of the Bailey beam 3, and the end plates 14 are truss-shaped, and the rib holes 15, prestressed tendons 16 and The anchor 17 is prestressed.

如图12所示,在贝雷梁3上按照一定的间距设置底模梁4,底模梁4顶部要与高墩13上的支座20顶部保持齐平,形成模板体系;然后在底模梁4上逐步布设现浇箱梁模板22、钢筋以及预应力体系。As shown in Figure 12, base form beams 4 are arranged at certain intervals on the Bailey beams 3, and the tops of the base form beams 4 are kept flush with the tops of the supports 20 on the high pier 13 to form a formwork system; On the beam 4, the cast-in-place box girder formwork 22, steel bars and prestressing system are gradually laid out.

浇筑混凝土,同时启动电动液压千斤顶1进行高度自动补偿,随着混凝土浇筑越多,补偿越多,待混凝土浇筑完毕并达到一定强度后施加预应力。Concrete is poured, and the electro-hydraulic jack 1 is started at the same time for automatic height compensation. As more concrete is poured, more compensation will be made. After the concrete is poured and reaches a certain strength, prestress is applied.

待高墩现浇箱梁强度满足要求后,依次拆除掉现浇箱梁模板22、底模梁4、贝雷梁3、横梁2、电动液压千斤顶1、抱箍支撑和立柱支撑,并将高墩13上的贯穿孔9回填。After the strength of the cast-in-place box girder of the high pier meets the requirements, the cast-in-place box girder template 22, bottom form beam 4, Bailey beam 3, beam 2, electro-hydraulic jack 1, hoop support and column support are removed in sequence, and the high The through hole 9 on the pier 13 is backfilled.

Claims (7)

1. Cast-in-place box girder support system, its characterized in that: comprises an upright post support, a hoop support, an electric hydraulic jack (1), a cross beam (2), a Bailey beam (3) and a bottom mould beam (4); the upright post support mainly comprises two steel upright posts (5) and a foundation (6), wherein the steel upright posts (5) are provided with electric hydraulic jacks (1), an upright post tie beam (7) is arranged between the two steel upright posts (5), and the foundation (6) is arranged at the tip of a high-level area of a steep terrain (8); a high pier (13) is arranged in a low-level area of the steep terrain (8); the hoop support mainly comprises a through hole (9), an L-shaped hoop plate (10), a stiffening rib (11) and a split bolt (12), the through hole (9) is reserved in a high pier (13), the L-shaped hoop plate (10) is provided with a bolt reserved hole and the stiffening rib (11), and the split bolt (12) is arranged in the through hole (9) and the bolt reserved hole; all be equipped with crossbeam (2) on electro-hydraulic jack (1) at steel stand (5) top and the staple bolt support electro-hydraulic jack (1) at top, crossbeam (2) top sets up bailey roof beam (3), and bailey roof beam (3) top sets up end mould roof beam (4), and high mound (13) top sets up support (20), and end mould roof beam (4) and support (20) top set up cast-in-place case beam mold board (22).
2. The cast-in-place box beam support system of claim 1, wherein: if the span of the cross beam (2) is too large, a prestressed Bailey beam is adopted, end plates (14) are arranged at two ends of the Bailey beam (3), rib holes (15), prestressed ribs (16) and an anchorage device (17) are arranged at the lower parts of the end plates (14), and the prestressed ribs (16) penetrate through the rib holes (15) and the anchorage device (17).
3. The cast-in-place box beam support system of claim 1, wherein: the electro-hydraulic jack (1) is provided with a base (18) for bolting and is bolted on the upright post support and the hoop support.
4. The cast-in-place box beam support system of claim 1, wherein: the bottom of the cross beam (2) is provided with a groove (19) and is butted with a plunger (21) of the electric hydraulic jack (1).
5. The cast-in-place box beam support system of claim 1, wherein: the top of the bottom mould beam (4) is flush with the top of the support (20) on the high pier (13).
6. The cast-in-place box beam support system of claim 1, wherein: the section of the steel upright post (5) is a round corner rectangle.
7. A construction method of a cast-in-place box girder support system based on the steel plate frame as claimed in claim 1 is characterized in that: the method comprises the following steps:
1) when the high pier (13) is constructed, a through hole (9) is reserved at a proper position at the upper part of the high pier, then L-shaped hoop plates (10) are arranged on two sides of the through hole (9), stiffening ribs (11) and bolt reserved holes are arranged in the L-shaped hoop plates (10), and split bolts (12) are arranged through the through hole (9) and the bolt reserved holes to form a hoop support;
2) in a steep terrain (8) between two spans of a pier column of a high pier (13), searching an area suitable for construction of a steel upright column (5) and a foundation (6) thereof, constructing the foundation (6), erecting two steel pipe columns, fixing the steel upright columns (5) by using the steel pipe columns, and arranging upright column tie beams (7) between the steel upright columns (5);
3) the hoop supports and the steel upright posts (5) are respectively provided with an electric hydraulic jack (1);
4) respectively placing a cross beam (2) on the hoop support and the electric hydraulic jack (1) of the steel upright post (5), wherein the bottom of the cross beam (2) is provided with a groove (19) and is butted with a plunger (21) of the electric hydraulic jack (1);
5) the Bailey beam (3) is hung on the cross beam (2) supported by the hoop, the support (20) is placed at the top of the high pier (13), and the Bailey beam (3) is also hung on the cross beam (2) supported by the upright post; if the span of the cross beam (2) is too large, a prestressed Bailey beam is adopted; the prestressed Bailey beam is characterized in that end plates (14) are arranged at two ends of a Bailey beam (3), and prestress is applied through reinforcement holes (15) at the lower part of the end plates (14), prestressed reinforcements (16) and an anchorage device (17);
6) arranging bottom mould beams (4) on the Bailey beam (3) according to a certain interval, and then gradually arranging a cast-in-situ box beam template (22), a reinforcing steel bar and a prestress system on the bottom mould beams (4);
7) the method comprises the following steps of pouring concrete, starting the electric hydraulic jack (1) to perform automatic height compensation, and applying prestress after the concrete is poured and reaches a certain strength, wherein the compensation is increased along with the increase of the poured concrete;
8) and after the strength of the high-pier cast-in-place box girder meets the requirement, sequentially removing the cast-in-place box girder template (22), the bottom formwork girder (4), the Bailey girder (3), the cross beam (2), the electric hydraulic jack (1), the hoop support and the upright post support, and backfilling the through holes (9) in the high piers (13) with concrete.
CN201910925909.0A 2019-09-27 2019-09-27 Cast-in-place box girder support system and its construction method Pending CN110593115A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910925909.0A CN110593115A (en) 2019-09-27 2019-09-27 Cast-in-place box girder support system and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910925909.0A CN110593115A (en) 2019-09-27 2019-09-27 Cast-in-place box girder support system and its construction method

Publications (1)

Publication Number Publication Date
CN110593115A true CN110593115A (en) 2019-12-20

Family

ID=68864265

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910925909.0A Pending CN110593115A (en) 2019-09-27 2019-09-27 Cast-in-place box girder support system and its construction method

Country Status (1)

Country Link
CN (1) CN110593115A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112659598A (en) * 2020-12-03 2021-04-16 杭州瑞声海洋仪器有限公司 Large-scale vulcanization tool in air guide sleeve and operation method
CN113152248A (en) * 2021-01-06 2021-07-23 中铁大桥局集团有限公司 High pier support structure and aqueduct construction method
CN113622309A (en) * 2021-07-29 2021-11-09 中交二公局第三工程有限公司 Prefabricated section beam side span less support assembling structure and construction method
CN115467465A (en) * 2022-09-13 2022-12-13 中铁上海工程局集团有限公司 Subway station steel support assembly type tie beam and construction process thereof
CN116397536A (en) * 2023-03-30 2023-07-07 广东国哲自动化设备有限公司 Hoop type combined beam

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200240457Y1 (en) * 2001-04-25 2001-10-12 코벡주식회사 Frame for substitu ting steel girder of a railway bridge for concrete slab
CN206941412U (en) * 2017-06-29 2018-01-30 中铁十七局集团第六工程有限公司 The high pier cast-in-situ beam anchor ear rod iron sectional shelf-unit of highway
CN108999085A (en) * 2018-07-20 2018-12-14 浙江交工宏途交通建设有限公司 Sea area construction of cast-in-situ box-beam bracket and sea area construction of cast-in-situ box-beam method
CN109356040A (en) * 2018-09-29 2019-02-19 中铁二局集团有限公司 A kind of high pier group of mean people radius curve Cast-in-situ Beam Bailey beam rack construction system
CN109972531A (en) * 2019-05-13 2019-07-05 中铁二十四局集团安徽工程有限公司 It is a kind of for improving the external prestressing device of Bailey beam falsework span
CN209194354U (en) * 2018-11-22 2019-08-02 中交路桥建设有限公司 High-altitude long-span binder base-supporting shellfish thunder support construction
CN209228054U (en) * 2018-10-08 2019-08-09 恒德建设有限公司 Large cantilever combined type anchors Bailey beam operation platform
CN211036710U (en) * 2019-09-27 2020-07-17 宁波大学 Cast-in-place box girder support system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR200240457Y1 (en) * 2001-04-25 2001-10-12 코벡주식회사 Frame for substitu ting steel girder of a railway bridge for concrete slab
CN206941412U (en) * 2017-06-29 2018-01-30 中铁十七局集团第六工程有限公司 The high pier cast-in-situ beam anchor ear rod iron sectional shelf-unit of highway
CN108999085A (en) * 2018-07-20 2018-12-14 浙江交工宏途交通建设有限公司 Sea area construction of cast-in-situ box-beam bracket and sea area construction of cast-in-situ box-beam method
CN109356040A (en) * 2018-09-29 2019-02-19 中铁二局集团有限公司 A kind of high pier group of mean people radius curve Cast-in-situ Beam Bailey beam rack construction system
CN209228054U (en) * 2018-10-08 2019-08-09 恒德建设有限公司 Large cantilever combined type anchors Bailey beam operation platform
CN209194354U (en) * 2018-11-22 2019-08-02 中交路桥建设有限公司 High-altitude long-span binder base-supporting shellfish thunder support construction
CN109972531A (en) * 2019-05-13 2019-07-05 中铁二十四局集团安徽工程有限公司 It is a kind of for improving the external prestressing device of Bailey beam falsework span
CN211036710U (en) * 2019-09-27 2020-07-17 宁波大学 Cast-in-place box girder support system

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112659598A (en) * 2020-12-03 2021-04-16 杭州瑞声海洋仪器有限公司 Large-scale vulcanization tool in air guide sleeve and operation method
CN113152248A (en) * 2021-01-06 2021-07-23 中铁大桥局集团有限公司 High pier support structure and aqueduct construction method
CN113622309A (en) * 2021-07-29 2021-11-09 中交二公局第三工程有限公司 Prefabricated section beam side span less support assembling structure and construction method
CN115467465A (en) * 2022-09-13 2022-12-13 中铁上海工程局集团有限公司 Subway station steel support assembly type tie beam and construction process thereof
CN116397536A (en) * 2023-03-30 2023-07-07 广东国哲自动化设备有限公司 Hoop type combined beam

Similar Documents

Publication Publication Date Title
CN110593115A (en) Cast-in-place box girder support system and its construction method
CN110387822B (en) Cast-in-situ bent cap assembly type steel pipe support and construction method thereof
CN108660903A (en) CFST Arch Bridge and construction method
CN106677070A (en) Construction support and method for overhead large-span heavy-duty cross beam
CN105672134A (en) Through concrete-filled steel tube tied-arch bridge erection construction method
CN211947993U (en) Support for large-span cast-in-situ bridge construction
CN112554077B (en) Construction system and method of steel tube concrete assembled truss composite beam
CN113756209B (en) Cable-stayed pushing construction method for large-span steel beam
CN103410102A (en) H-shaped double column pier wide-bridge-surface cantilever temporary consolidation structure and construction method thereof
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN106223183A (en) Assembled concrete-filled rectangular steel tube combination truss bridge and construction method
CN115387234A (en) Template system of lower beam of ultrahigh rhombic tower pier and construction method
CN109778700B (en) Cast-in-place trough beam three-point sliding pushing construction method for crossing existing road
CN213233105U (en) Small-span concrete cast-in-place box girder support system
CN116084293B (en) Triangular steel arch formwork system and construction method for cast-in-place concrete main arch ring
CN210049103U (en) High-grade high-speed highway bracket spanned by large-span cast-in-place box girder
CN112726411A (en) Integral dragging construction method for single-hole large cantilever steel truss girder
CN210684429U (en) A kind of long-span tied arch bridge approach bridge jacking system
CN211036710U (en) Cast-in-place box girder support system
CN115928608A (en) A reverse construction method of continuous steel truss web-plate truss double-layer combined swivel bridge
CN110424246A (en) A long-span tied arch bridge approach jacking system and jacking construction method
CN214168790U (en) Concrete-filled steel tube assembled truss composite beam construction system
CN114561865A (en) Prestressed concrete cover beam based on prefabricated prestressed UHPC shell and its construction technology
CN222990595U (en) Multifunctional portal for suspension bridge construction
CN209816632U (en) Arch foot structure for special-shaped space arch bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191220