CN110593080B - 一种与内支撑体系结合的撑间栈桥系统及施工方法 - Google Patents
一种与内支撑体系结合的撑间栈桥系统及施工方法 Download PDFInfo
- Publication number
- CN110593080B CN110593080B CN201910917157.3A CN201910917157A CN110593080B CN 110593080 B CN110593080 B CN 110593080B CN 201910917157 A CN201910917157 A CN 201910917157A CN 110593080 B CN110593080 B CN 110593080B
- Authority
- CN
- China
- Prior art keywords
- inter
- trestle
- support
- template
- strut
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D15/00—Movable or portable bridges; Floating bridges
- E01D15/12—Portable or sectional bridges
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02A—TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
- Y02A30/00—Adapting or protecting infrastructure or their operation
- Y02A30/60—Planning or developing urban green infrastructure
Landscapes
- Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Road Paving Structures (AREA)
Abstract
Description
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910917157.3A CN110593080B (zh) | 2019-09-26 | 2019-09-26 | 一种与内支撑体系结合的撑间栈桥系统及施工方法 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910917157.3A CN110593080B (zh) | 2019-09-26 | 2019-09-26 | 一种与内支撑体系结合的撑间栈桥系统及施工方法 |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN110593080A CN110593080A (zh) | 2019-12-20 |
| CN110593080B true CN110593080B (zh) | 2024-11-05 |
Family
ID=68863716
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201910917157.3A Active CN110593080B (zh) | 2019-09-26 | 2019-09-26 | 一种与内支撑体系结合的撑间栈桥系统及施工方法 |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN110593080B (zh) |
Families Citing this family (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111851509A (zh) * | 2020-07-22 | 2020-10-30 | 深圳市工勘岩土集团有限公司 | 基于深基坑内支撑结构的临时通道施工方法 |
| CN113914330A (zh) * | 2021-11-26 | 2022-01-11 | 广东省工程勘察院 | 一种基于深基坑支撑体系的空间取土栈桥 |
| CN114961342A (zh) * | 2022-06-14 | 2022-08-30 | 浙江大学建筑设计研究院有限公司 | 一种利用基坑内已有对撑的出土通道结构 |
Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110004936A (zh) * | 2019-05-20 | 2019-07-12 | 中建四局土木工程有限公司 | 一种基于深基坑支护结构的出土坡道及施工方法 |
| CN211340370U (zh) * | 2019-09-26 | 2020-08-25 | 中建钢构有限公司 | 一种与内支撑体系结合的撑间栈桥系统 |
Family Cites Families (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| ITTO20030243A1 (it) * | 2003-03-28 | 2004-09-29 | Carlo Chiaves | Procedimento per realizzare un segmento di un'opera |
| CN204690573U (zh) * | 2015-06-01 | 2015-10-07 | 中建八局第三建设有限公司 | 一种便捷式土方运输斜栈桥 |
| CN207109824U (zh) * | 2017-04-13 | 2018-03-16 | 北京市第三建筑工程有限公司 | 混凝土栈桥与基坑连接结点构造 |
-
2019
- 2019-09-26 CN CN201910917157.3A patent/CN110593080B/zh active Active
Patent Citations (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110004936A (zh) * | 2019-05-20 | 2019-07-12 | 中建四局土木工程有限公司 | 一种基于深基坑支护结构的出土坡道及施工方法 |
| CN211340370U (zh) * | 2019-09-26 | 2020-08-25 | 中建钢构有限公司 | 一种与内支撑体系结合的撑间栈桥系统 |
Also Published As
| Publication number | Publication date |
|---|---|
| CN110593080A (zh) | 2019-12-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| KR100951097B1 (ko) | 지하구조물의 슬래브 및 합벽 구조물과 시공 방법, 그리고 받침브라켓 | |
| CN104018518B (zh) | 预制式地下连续墙以及施工地下室外墙和楼板的方法 | |
| CN106968256A (zh) | 基坑装配式钢栈桥施工方法 | |
| CN102995659B (zh) | 超大型地下工程的先中心区结合周边的施工方法 | |
| CN110593080B (zh) | 一种与内支撑体系结合的撑间栈桥系统及施工方法 | |
| US20230279632A1 (en) | Poor foundation reinforcement system and reinforcement method based on underground concealed arch structures | |
| CN206495233U (zh) | 门形装配式钢筋混凝土箱型涵洞 | |
| KR101011805B1 (ko) | 파일기초부를 횡단하는 지중구조물 시공 방법 및 그를 이용하여 축조된 지중구조물 | |
| CN112049011B (zh) | 一种大跨度预应力现浇桥梁逆作法施工方法 | |
| CN207597418U (zh) | 一种用于t梁预制施工的型钢台座 | |
| KR101058892B1 (ko) | 콘크리트 침목을 이용하여 축조된 옹벽 및 옹벽 축조방법 | |
| CN111705576A (zh) | 一种采用高密度eps填料的陡坡高填路基结构 | |
| CN220927477U (zh) | 一种装配式下穿桥小箱梁兼作支护桩对撑施工结构 | |
| CN112627035A (zh) | 一种大跨径贝雷钢栈桥的设计建造方法 | |
| CN111074916A (zh) | 抗滑桩兼结构桩的支挡结构及施工方法 | |
| KR101761477B1 (ko) | 적층형 토목섬유 보강토지반벽체와 스프레드 토대판을 사용한 무조인트교량 시공방법 | |
| CN114991027A (zh) | 一种盾构切割跨河桥梁桩基托换方法及桩基托换结构 | |
| CN100441782C (zh) | 新型预应力脚手架系统 | |
| KR101149362B1 (ko) | 콘크리트 침목을 이용하여 축조된 옹벽, 계단형 옹벽 및 옹벽 축조방법 | |
| CN206800434U (zh) | 一种桥梁桩基复合加固结构 | |
| CN111042214A (zh) | 一种浅覆土地下结构的抗浮结构及其施工方法 | |
| CN117513082A (zh) | 一种混凝土重载道路路面防变形施工方法 | |
| CN206110151U (zh) | 提高挡土墙背后场地标高的混凝土结构 | |
| CN117418558A (zh) | 一种高桩承台钢筋砼薄板底模施工方法 | |
| CN212247826U (zh) | 地上堆建的超大跨度通道结构 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| CB02 | Change of applicant information | ||
| CB02 | Change of applicant information |
Country or region after: China Address after: 3801, 38 / F, China Construction Science and engineering building, No. 3331, Weilan Coast Community Central Road, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province Applicant after: China Construction Science And Industry Co.,Ltd. Address before: Room 2701, 27th floor, Zhongjian Steel Building, 3331 Yuehai Street Center Road, Nanshan District, Shenzhen City, Guangdong Province, 518000 Applicant before: China Construction Steel Structure Corp.,Ltd. Country or region before: China |
|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| EE01 | Entry into force of recordation of patent licensing contract | ||
| EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20191220 Contract record no.: X2025980047396 Denomination of invention: A bridge system between supports combined with an internal support system and construction method Granted publication date: 20241105 License type: Common License Record date: 20251225 Application publication date: 20191220 Contract record no.: X2025980047414 Denomination of invention: A bridge system between supports combined with an internal support system and construction method Granted publication date: 20241105 License type: Common License Record date: 20251225 |