CN110541417A - Anchor cable for continuous basalt fiber composite reinforcement - Google Patents
Anchor cable for continuous basalt fiber composite reinforcement Download PDFInfo
- Publication number
- CN110541417A CN110541417A CN201910947990.2A CN201910947990A CN110541417A CN 110541417 A CN110541417 A CN 110541417A CN 201910947990 A CN201910947990 A CN 201910947990A CN 110541417 A CN110541417 A CN 110541417A
- Authority
- CN
- China
- Prior art keywords
- fiber composite
- basalt fiber
- continuous basalt
- anchor
- flange
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
一种连续玄武岩纤维复合筋材的锚索,包括注浆管(1)、钢铰线(6)、施加预应力的锚具、连续玄武岩纤维复合筋束(2)、法兰连接结构和PVC管(12)。所述锚索通过法兰连接结构和施加预应力的锚具将连续玄武岩纤维复合筋束和钢铰线连接在一起;所述连续玄武岩纤维复合筋束通过均匀分布的多个定位对中器(3)安装在PVC管中;所述注浆管内嵌一截注锚固浆管,锚固浆从此管进入法兰内部把连续玄武岩纤维复合筋束和钢绞线紧密连接在一起。本发明提供的连续玄武岩纤维复合筋材锚索,能代替钢绞线、高强钢丝等成为主要抗拉筋材;在满足抗拉强度的同时,又拥有较低的抗剪强度,从而在后期周边工程施工时能较轻松的切割土层中残留的锚索钢材。
An anchor cable for continuous basalt fiber composite reinforcement, including grouting pipe (1), steel hinge wire (6), prestressed anchorage, continuous basalt fiber composite tendon (2), flange connection structure and PVC tube (12). The anchor cable connects the continuous basalt fiber composite tendon and the steel hinge wire through the flange connection structure and the prestressed anchor; the continuous basalt fiber composite tendon passes through a plurality of evenly distributed positioning centering devices 3) Installed in a PVC pipe; the grouting pipe is embedded with a cut anchor grout pipe, and the anchor grout enters the flange from this pipe to tightly connect the continuous basalt fiber composite tendons and steel strands together. The continuous basalt fiber composite reinforcement anchor cable provided by the invention can replace steel strands, high-strength steel wires, etc. During engineering construction, it is easier to cut the remaining anchor cable steel in the soil layer.
Description
技术领域technical field
本发明涉及一种连续玄武岩纤维复合筋材的锚索,属土木工程技术领域。The invention relates to an anchor cable of continuous basalt fiber composite reinforcement, which belongs to the technical field of civil engineering.
背景技术Background technique
随着时代的发展,人们对地下空间的需求越来越大,从而加大了对地下工程的建设。基坑支护工程是地下工程的重要组成部分,通常可以使用锚索对基坑周围土体进行加固,目前使用的锚索多为钢筋和钢绞线材质。钢材的锚索的耐腐蚀性比较差,往往需要增加额外的防腐工序,施工较为复杂;而且锚索不易回收,一般都留在土层里,对于后期周边工程来说,施工时遇到此类障碍,切割钢绞线十分不便,给施工带来了困难。With the development of the times, people's demand for underground space is increasing, thus increasing the construction of underground projects. Foundation pit support engineering is an important part of underground engineering. Usually, anchor cables can be used to reinforce the soil around the foundation pit. At present, most of the anchor cables used are steel bars and steel strands. The corrosion resistance of steel anchor cables is relatively poor, and additional anti-corrosion procedures are often required, and the construction is more complicated; moreover, the anchor cables are not easy to recycle, and are generally left in the soil layer. For the surrounding projects in the later stage, such obstacles are encountered during construction. , It is very inconvenient to cut steel strands, which brings difficulties to the construction.
玄武岩纤维是一种无机非金属纤维,具有强度高、耐久性好、耐腐蚀(耐酸耐碱)等综合性能,而且性价比适中,是一种经济、绿色环保、高性能的材料。玄武岩纤维复合筋是一种由高强度玄武岩纤维加乙烯基树脂(环氧树脂),并通过生产线拉挤、缠绕、表面涂覆、复合成型、连续生产的新型建筑材料。玄武岩纤维复合筋的膨胀系数与混凝土相近,两者之间不会产生较大的温度应力;它的抗拉强度为钢筋的3倍左右,而密度只有钢筋的1/3左右。尤其是一种连续玄武岩纤维(CBF),它的抗剪能力较弱,容易切割,便于后期周边工程的施工。Basalt fiber is an inorganic non-metallic fiber with comprehensive properties such as high strength, good durability, corrosion resistance (acid and alkali resistance), and moderate cost performance. It is an economical, green and high-performance material. Basalt fiber composite reinforcement is a new type of building material that is made of high-strength basalt fiber plus vinyl resin (epoxy resin), and is pultruded, wound, surface coated, composite formed, and continuously produced through a production line. The expansion coefficient of basalt fiber composite bars is similar to that of concrete, and there will be no large temperature stress between the two; its tensile strength is about 3 times that of steel bars, and its density is only about 1/3 of that of steel bars. Especially a kind of continuous basalt fiber (CBF), which has weak shear resistance and is easy to cut, which is convenient for the construction of surrounding projects in the later stage.
发明内容Contents of the invention
本发明的目的是,为了解决后期周边工程施工过程中遇到的锚索钢绞线难以清除等问题,本发明提出一种连续玄武岩纤维复合筋材的锚索。The purpose of the present invention is to solve the problems that the steel strands of the anchor cables are difficult to remove and the like encountered in the construction process of the surrounding projects in the later period. The present invention proposes an anchor cable of continuous basalt fiber composite reinforcement.
本发明实现的技术方案如下,一种连续玄武岩纤维复合筋材的锚索,包括注浆管、钢铰线和施加预应力的锚具;还包括连续玄武岩纤维复合筋束、法兰连接结构和PVC管。所述锚索通过述法兰连接结构和施加预应力的锚具将连续玄武岩纤维复合筋束和钢铰线连接在一起;所述连续玄武岩纤维复合筋束通过均匀分布的多个定位对中器安装在PVC管中;所述注浆管内嵌一截注锚固浆管,锚固浆从此管进入法兰内部把连续玄武岩纤维复合筋束和钢绞线紧密连接在一起。The technical scheme that the present invention realizes is as follows, a kind of anchor cable of continuous basalt fiber composite reinforcement, comprises grouting pipe, steel hinge wire and the anchorage that applies prestress; Also comprises continuous basalt fiber composite tendon, flange connection structure and PVC pipe. The anchor cable connects the continuous basalt fiber composite tendon and the steel hinge wire through the flange connection structure and the prestressed anchor; the continuous basalt fiber composite tendon passes through a plurality of evenly distributed positioning centering devices Installed in a PVC pipe; the grouting pipe is embedded with a cut anchor grout pipe, and the anchor grout enters the flange from this pipe to tightly connect the continuous basalt fiber composite tendons and steel strands together.
所述法兰连接结构由一对相同的法兰和两个相同的锚具组成,两个锚具分别安装在两个法兰内;一个锚具连接连续玄武岩纤维复合筋束和注浆管;另一个锚具连接钢绞线。The flange connection structure is composed of a pair of identical flanges and two identical anchorages, and the two anchorages are respectively installed in the two flanges; one anchorage is connected to the continuous basalt fiber composite tendon and the grouting pipe; Another anchor connects the strands.
所述法兰由一对法兰盘、一对钢套筒、一对扩口和一个橡胶垫圈构成;由四个螺栓固定;扩口嵌入并固定在法兰盘中心台阶圆孔内,钢套筒嵌入扩口中心孔中,锚具放置于法兰的扩口内,构成法兰的左边连接结构;相同的扩口、法兰盘、钢套筒、锚具构成法兰的右边连接结构;法兰的左边连接结构和法兰的右边连接结构相对合拢,中间垫入橡胶垫圈,并对准两个法兰盘的安装孔,通过螺栓和螺母将法兰的左右连接结构连成整体。The flange is composed of a pair of flanges, a pair of steel sleeves, a pair of flares and a rubber gasket; it is fixed by four bolts; the flares are embedded and fixed in the circular hole in the center of the flange, and the steel sleeve The cylinder is embedded in the center hole of the flare, and the anchor is placed in the flare of the flange to form the left connection structure of the flange; the same flare, flange plate, steel sleeve, and anchor constitute the right connection structure of the flange; The left connection structure of the flange and the right connection structure of the flange are relatively closed, and a rubber gasket is placed in the middle, and aligned with the mounting holes of the two flanges, and the left and right connection structures of the flange are connected into a whole by bolts and nuts.
所述锚具放置于法兰的扩口内,当使用法兰时,预先将法兰内两个锚具分别连接连续玄武岩纤维复合筋束、注浆管和钢绞线;使其内部充满环氧树脂型锚固胶从而使连续玄武岩纤维复合筋束、注浆管和钢绞线与锚具连接的更紧密。The anchors are placed in the flaring of the flange. When the flange is used, the two anchors in the flange are connected to the continuous basalt fiber composite tendons, grouting pipes and steel strands in advance; the interior is filled with epoxy The resin-type anchoring glue makes the continuous basalt fiber composite tendons, grouting pipes and steel strands more closely connected with the anchorage.
所述连续玄武岩纤维复合筋束和钢绞线从锚具穿出后的固定,采用夹片结构,即将两个夹片夹持连续玄武岩纤维复合筋束或钢绞线后,夹片的小直径端直接嵌入锚具孔中。The fixing of the continuous basalt fiber composite tendons and steel strands passing through the anchorage adopts a clip structure, that is, after the two clips clamp the continuous basalt fiber composite tendons or steel strands, the small diameter of the clips The end is directly embedded in the anchor hole.
所述定位对中器形状为圆柱形,在定位对中器的轴线方向内含有多个通孔,中心有注浆管孔,四周均匀分布多个连续玄武岩纤维复合筋束孔。The positioning centering device is cylindrical in shape, and contains a plurality of through holes in the axial direction of the positioning centering device. There is a grouting pipe hole in the center, and a plurality of continuous basalt fiber composite tendon holes are evenly distributed around.
所述施加预应力的锚具由垫板、锚环和夹片组成;锚环和夹片内部做粗糙化处理;所述夹片由带轴向内孔的圆台从中轴线方向一剖为二而成;两个夹片将钢绞线夹住后,嵌入锚环,使钢绞线安装固定在锚具中,锚具的另一端安装在垫板上。The prestressed anchor is composed of a backing plate, an anchor ring and a clip; the interior of the anchor ring and the clip is roughened; the clip is divided into two from the central axis by a round table with an axial inner hole After the two clips clamp the steel strand, they are embedded in the anchor ring, so that the steel strand is installed and fixed in the anchor, and the other end of the anchor is installed on the backing plate.
所述注浆管锚固段均匀分布梅花形出浆孔;注浆管头部至法兰部分内嵌小直径的注锚固浆管。The anchoring section of the grouting pipe is evenly distributed with quincunx-shaped grouting holes; the grouting pipe head to the flange part is embedded with a small-diameter anchoring grouting pipe.
所述连续玄武岩纤维复合筋束分散布置于注浆管四周,使用定位对中器连接固定。The continuous basalt fiber composite tendons are scattered and arranged around the grouting pipe, and connected and fixed by a positioning centering device.
一种连续玄武岩纤维复合筋材的锚索,其制备方法步骤如下:A kind of anchor cable of continuous basalt fiber composite reinforcement, its preparation method steps are as follows:
(1)备料。包括连续玄武岩纤维复合筋束、注浆管、钢铰线、施加预应力的锚具配件、法兰连接结构配件、定位对中器和PVC管。(1) Prepare materials. Including continuous basalt fiber composite tendons, grouting pipes, steel hinge wires, prestressed anchor fittings, flange connection structural fittings, positioning centering devices and PVC pipes.
确定连续玄武岩纤维复合筋束的根数,选择相应的锚具和定位对中器。Determine the number of continuous basalt fiber composite tendons, and select the corresponding anchorage and positioning centering device.
(2)确定一定长度的连续玄武岩纤维复合筋束和注浆管,将连续玄武岩纤维复合筋束和注浆管依次插入多个定位对中器相应的孔中;注浆管插入中心孔,连续玄武岩纤维复合筋束均匀分布于中心孔外圆周区域内的孔中;定位对中器把分散在注浆管周围的连续玄武岩纤维复合筋束和注浆管连接成一个整体;(2) Determine a certain length of continuous basalt fiber composite tendons and grouting pipes, insert the continuous basalt fiber composite tendons and grouting pipes into the corresponding holes of multiple positioning centering devices in sequence; insert the grouting pipes into the center hole, and continuously The basalt fiber composite tendons are evenly distributed in the hole in the outer circumference area of the central hole; the positioning centering device connects the continuous basalt fiber composite tendons scattered around the grouting pipe and the grouting pipe into a whole;
(3)将安装在多个定位对中器的连续玄武岩纤维复合筋束和注浆管插入PVC管中;多个定位对中器均匀分布在连续玄武岩纤维复合筋束和注浆管的长度方向上;注浆管伸出PVC管的一端,注浆管头部至法兰部分内嵌小直径的注锚固浆管;(3) Insert the continuous basalt fiber composite tendon and grouting pipe installed in multiple positioning centering devices into the PVC pipe; multiple positioning centering devices are evenly distributed in the length direction of the continuous basalt fiber composite tendon and grouting pipe Above; the grouting pipe protrudes from one end of the PVC pipe, and a small-diameter anchoring grouting pipe is embedded from the head of the grouting pipe to the flange;
(4)在PVC管另一端,伸出的连续玄武岩纤维复合筋束和注浆管的一端嵌入由钢套筒、扩口和法兰盘后,穿出锚具相应的孔,每一根连续玄武岩纤维复合筋由一对夹片夹持后,回嵌入锚具孔中,将连续玄武岩纤维复合筋一端固定在锚具中,构成半个法兰连接结构;(4) At the other end of the PVC pipe, the protruding continuous basalt fiber composite tendons and one end of the grouting pipe are embedded with steel sleeves, flares and flanges, and pass through the corresponding holes of the anchorage. Each continuous After the basalt fiber composite reinforcement is clamped by a pair of clips, it is embedded back into the anchorage hole, and one end of the continuous basalt fiber composite reinforcement is fixed in the anchorage to form a half-flange connection structure;
(5)将钢铰线的一端嵌入由钢套筒、扩口和法兰盘后;穿出锚具相应的孔,由一对夹片夹持后,回插嵌入锚具孔中,将钢铰线一端固定在锚具中,构成另半个法兰连接结构;(5) Embed one end of the steel hinge line into the steel sleeve, flaring and flange; pass through the corresponding hole of the anchorage, clamped by a pair of clips, insert it back into the hole of the anchorage, and insert the steel One end of the hinge line is fixed in the anchor to form the other half of the flange connection structure;
(6)钢铰线的另一端,穿过垫板,由一对夹片夹持后,嵌入锚环中,将钢铰线一端固定在施加预应力的锚具中;(6) The other end of the steel hinge wire passes through the backing plate, is clamped by a pair of clips, embedded in the anchor ring, and one end of the steel hinge wire is fixed in the prestressed anchor;
(7)将安装有连续玄武岩纤维复合筋束的半个法兰连接结构与安装有钢铰线的半个法兰连接结构合拢,中间插入橡胶垫圈,用螺栓将法兰连接结构合为一体;(7) Close the half flange connection structure installed with continuous basalt fiber composite tendons and the half flange connection structure installed with steel hinge lines, insert rubber gaskets in the middle, and integrate the flange connection structure with bolts;
(8)注浆管内嵌一截注锚固浆管,锚固浆从此管进入法兰内部把连续玄武岩纤维复合筋束和钢绞线紧密连接在一起。(8) An anchoring grout pipe is embedded in the grouting pipe, and the anchoring grout enters the flange from this pipe to tightly connect the continuous basalt fiber composite tendons and steel strands together.
本发明的有益效果是,本发明提供的连续玄武岩纤维复合筋材锚索,能代替钢绞线、高强钢丝等成为主要抗拉筋材;在满足工程所需的抗拉强度的同时,又拥有较低的抗剪强度,从而在后期周边工程施工时能较轻松的切割土层中残留的锚索钢材。在施加预应力的锚具处采用钢绞线代替连续玄武岩纤维复合筋束,可以避免连续玄武岩纤维复合筋束在施加预应力时受到剪切破坏。除此以外,本发明还具有重量轻强度高,便于运输和耐腐蚀,耐久性好的优点。The beneficial effect of the present invention is that the continuous basalt fiber composite reinforcement anchor cable provided by the present invention can replace steel strands, high-strength steel wires, etc. as the main tensile reinforcement; while meeting the tensile strength required by the project, it also has The lower shear strength makes it easier to cut the remaining anchor cable steel in the soil layer during the later surrounding engineering construction. The use of steel strands instead of continuous basalt fiber composite tendons at prestressed anchorages can prevent continuous basalt fiber composite tendons from being sheared when prestressed. In addition, the invention also has the advantages of light weight, high strength, convenient transportation, corrosion resistance and good durability.
附图说明Description of drawings
图1为本发明连续玄武岩纤维复合筋锚索的结构示意图;Fig. 1 is the structural representation of continuous basalt fiber composite bar anchor cable of the present invention;
图2为本发明注浆管结构部分示意图;图3为注浆管结构示意图;Fig. 2 is a schematic view of the structure of the grouting pipe of the present invention; Fig. 3 is a schematic view of the structure of the grouting pipe;
图4为锚具结构示意图;图5为夹块结构示意图;Fig. 4 is a schematic diagram of the anchorage structure; Fig. 5 is a schematic diagram of the clamp block structure;
图6为锚环结构示意图;图7为垫板结构示意图;Fig. 6 is a schematic diagram of the structure of the anchor ring; Fig. 7 is a schematic diagram of the structure of the backing plate;
图8为定位对中器结构示意图;图9为法兰结构示意图;Fig. 8 is a structural schematic diagram of a positioning centering device; Fig. 9 is a schematic structural diagram of a flange;
图9(a)为法兰盘与扩口安装结构示意图;Figure 9 (a) is a schematic diagram of the installation structure of the flange and the flare;
图9(b)为钢套筒结构示意图;Figure 9(b) is a schematic diagram of the structure of the steel sleeve;
图9(c)为扩口结构示意图;Figure 9(c) is a schematic diagram of the flaring structure;
图9(d)为橡胶垫圈结构示意图;Figure 9(d) is a schematic diagram of the structure of the rubber gasket;
图中,1为注浆管;2为连续玄武岩纤维复合筋束;3为定位对中器,3-1为连续玄武岩纤维复合筋束孔,3-2为注浆管孔;4为锚具;5为法兰;5-1为法兰盘,5-2为钢套筒,5-3为扩口,5-4为橡胶垫圈,5-5为螺栓和螺母;5-6为法兰盘安装孔;6为钢绞线;7为螺旋加强筋;8为垫板;9为锚环;10为夹片;11为钢套筒;12为PVC管;13为注锚固浆管;14为出浆孔。In the figure, 1 is the grouting pipe; 2 is the continuous basalt fiber composite tendon; 3 is the positioning centering device, 3-1 is the continuous basalt fiber composite tendon hole, 3-2 is the grouting pipe hole; 4 is the anchor ;5 is flange; 5-1 is flange, 5-2 is steel sleeve, 5-3 is flaring, 5-4 is rubber gasket, 5-5 is bolt and nut; 5-6 is flange Plate installation hole; 6 is steel strand; 7 is spiral reinforcement; 8 is backing plate; 9 is anchor ring; 10 is clip; 11 is steel sleeve; 12 is PVC pipe; 13 is grout injection pipe; 14 For the pulp hole.
具体实施方式Detailed ways
本实施例一种连续玄武岩纤维复合筋材的锚索如图1所示,本实施例提供的一种连续玄武岩纤维复合筋材的锚索,由多根连续玄武岩纤维复合筋束2和多个定位对中器3组成。定位对中器3把分散在注浆管1周围的连续玄武岩纤维复合筋束2和注浆管1连接成一个整体。The anchor cable of a kind of continuous basalt fiber composite reinforcement of the present embodiment is shown in Figure 1, and the anchor cable of a kind of continuous basalt fiber composite reinforcement provided by the present embodiment is composed of multiple continuous basalt fiber composite tendons 2 and a plurality of The positioning centering device consists of 3 components. The positioning centering device 3 connects the continuous basalt fiber composite tendons 2 scattered around the grouting pipe 1 and the grouting pipe 1 into a whole.
如图2和图3所示,本实施例锚索的注浆管1在锚固段管身上均匀分布梅花形出浆孔1-1,注浆管1头部至法兰5部分内嵌小直径的注锚固浆管13,锚固浆从此管进入法兰5内部把连续玄武岩纤维复合筋束2和钢绞线6紧密连接在一起。锚固浆可采用环氧树脂型锚固胶。As shown in Fig. 2 and Fig. 3, the grouting pipe 1 of the anchor cable in this embodiment is evenly distributed on the pipe body of the anchor section with plum blossom-shaped grouting holes 1-1, and the part from the head of the grouting pipe 1 to the flange 5 is embedded with a small diameter Anchor slurry injection pipe 13, from which the anchor slurry enters the inside of flange 5 to tightly connect continuous basalt fiber composite tendon 2 and steel strand 6 together. The anchoring slurry can use epoxy resin anchoring glue.
如图4~图7所示,本实施例锚索施加预应力处的锚具由垫板8、锚环9和夹片10组成。锚环9和夹片10内部做粗糙化处理。As shown in FIGS. 4 to 7 , the anchorage at the place where the anchor cable is prestressed in this embodiment consists of a backing plate 8 , an anchor ring 9 and a clip 10 . The interior of the anchor ring 9 and the clip 10 is roughened.
如图8所示,本实施例使用的定位对中器3中心为注浆管孔3-2,注浆管孔3-2四周均匀分布连续玄武岩纤维复合筋束孔3-1。其中,连续玄武岩纤维复合筋束孔3-2的个数根据实际工程情况确定。As shown in Fig. 8, the center of the positioning centering device 3 used in this embodiment is the grouting pipe hole 3-2, and the continuous basalt fiber composite tendon holes 3-1 are evenly distributed around the grouting pipe hole 3-2. Wherein, the number of continuous basalt fiber composite tendon holes 3-2 is determined according to actual engineering conditions.
如图9所示,本实施例使用的法兰由一对法兰盘9-1、一对钢套筒9-2、一对扩口9-3和一个橡胶垫圈9-4构成,设有四个螺栓9-5固定。As shown in Figure 9, the flange used in this embodiment consists of a pair of flanges 9-1, a pair of steel sleeves 9-2, a pair of flared openings 9-3 and a rubber gasket 9-4. Four bolts 9-5 are fixed.
本实施例一种连续玄武岩纤维复合筋材的锚索,其制备方法步骤如下:The anchor cable of a kind of continuous basalt fiber composite reinforcement of the present embodiment, its preparation method steps are as follows:
(1)备料。包括连续玄武岩纤维复合筋束2、注浆管1、钢铰线6、施加预应力的锚具配件、法兰连接结构配件、定位对中器和PVC管12。(1) Prepare materials. It includes continuous basalt fiber composite tendon 2, grouting pipe 1, steel hinge wire 6, prestressed anchor fittings, flange connection structural fittings, positioning centering device and PVC pipe 12.
确定连续玄武岩纤维复合筋束2的根数,选择相应的锚具4和定位对中器3。Determine the number of continuous basalt fiber composite tendons 2, and select the corresponding anchorage 4 and positioning centering device 3.
(2)确定一定长度的连续玄武岩纤维复合筋束和注浆管,将连续玄武岩纤维复合筋束2和注浆管1依次插入多个定位对中器3相应的孔中;注浆管1插入中心孔,连续玄武岩纤维复合筋束2均匀分布于中心孔外圆周区域内的孔中;定位对中器3把分散在注浆管1周围的连续玄武岩纤维复合筋束2和注浆管1连接成一个整体。(2) Determine a certain length of continuous basalt fiber composite tendon and grouting pipe, insert the continuous basalt fiber composite tendon 2 and grouting pipe 1 into the corresponding holes of multiple positioning centering devices 3 in sequence; insert grouting pipe 1 into In the center hole, the continuous basalt fiber composite tendons 2 are evenly distributed in the hole in the outer circumference area of the center hole; the positioning centering device 3 connects the continuous basalt fiber composite tendons 2 scattered around the grouting pipe 1 to the grouting pipe 1 into a whole.
(3)将安装在多个定位对中器3的连续玄武岩纤维复合筋束2和注浆管1插入PVC管12中;多个定位对中器3均匀分布在连续玄武岩纤维复合筋束2和注浆管1的长度方向上;注浆管1伸出PVC管12的一端,注浆管1头部至法兰5部分内嵌小直径的注锚固浆管13。(3) Insert the continuous basalt fiber composite tendon 2 and the grouting pipe 1 installed on multiple positioning centering devices 3 into the PVC pipe 12; multiple positioning centering devices 3 are evenly distributed between the continuous basalt fiber composite tendon 2 and the In the length direction of the grouting pipe 1 ; the grouting pipe 1 protrudes from one end of the PVC pipe 12 , and the small-diameter anchoring grouting pipe 13 is embedded in the part from the head of the grouting pipe 1 to the flange 5 .
(4)在PVC管12另一端,伸出的连续玄武岩纤维复合筋束2和注浆管1的一端嵌入由钢套筒5-2、扩口5-3和法兰盘5-1后,穿出锚具4相应的孔,每一根连续玄武岩纤维复合筋2由一对夹片10夹持后,回插嵌入锚具孔中,将连续玄武岩纤维复合筋2一端固定在锚具4中,构成半个法兰连接结构。(4) At the other end of the PVC pipe 12, the protruding continuous basalt fiber composite tendon 2 and one end of the grouting pipe 1 are embedded with the steel sleeve 5-2, flared mouth 5-3 and flange 5-1, Pass through the corresponding hole of the anchorage 4, and after each continuous basalt fiber composite bar 2 is clamped by a pair of clips 10, insert it back into the anchorage hole, and fix one end of the continuous basalt fiber composite bar 2 in the anchorage 4 , forming a half-flange connection structure.
(5)将钢铰线的一端插入由钢套筒5-2、扩口5-3和法兰盘5-1后;穿出锚具4相应的孔,由一对夹片10夹持后,回插嵌入锚具孔中,将钢铰线一端固定在锚具4中,构成另半个法兰连接结构。(5) Insert one end of the steel hinge wire into the steel sleeve 5-2, flare 5-3 and flange 5-1; pass through the corresponding hole of the anchorage 4, and clamp it by a pair of clips 10 , inserted back into the anchorage hole, and one end of the steel hinge wire is fixed in the anchorage 4 to form the other half of the flange connection structure.
(6)钢铰线6的另一端,穿过垫板8,由一对夹片10夹持后,嵌入锚环9中,将钢铰线6一端固定在施加预应力的锚具中。(6) The other end of the steel hinge 6 passes through the backing plate 8 and is clamped by a pair of clips 10, then embedded in the anchor ring 9, and one end of the steel hinge 6 is fixed in the prestressed anchor.
(7)将安装有连续玄武岩纤维复合筋束2的半个法兰连接结构与安装有钢铰线6的半个法兰连接结构合拢,中间插入橡胶垫圈5-4,用螺栓5-5将法兰5连接结构合为一体。(7) Close the half flange connection structure installed with continuous basalt fiber composite tendon 2 and the half flange connection structure installed with steel hinge line 6, insert rubber gasket 5-4 in the middle, and use bolt 5-5 to secure The connection structure of the flange 5 is integrated.
(8)注浆管1内嵌一截注锚固浆管13,锚固浆从此管进入法兰5内部把连续玄武岩纤维复合筋束2和钢绞线6紧密连接在一起。(8) An anchoring grout pipe 13 is embedded in the grouting pipe 1, and the anchoring grout enters the flange 5 from this pipe to tightly connect the continuous basalt fiber composite tendon 2 and the steel strand 6 together.
综上所述,本实施例提供的锚索采用连续玄武岩纤维复合筋束作为主要抗拉材料,使用定位对中器进行连接、定位。在施加预应力处采用钢绞线代替连续玄武岩纤维复合筋束,从而避免产生剪切破坏或达不到预应力设计值。本实施例提供的锚索具有高抗拉强度、低质量、低抗剪强度,易于切割的优点,可以较好地解决作为遗留在土层中的锚索给其他工程施工带来的阻碍问题。To sum up, the anchor cable provided in this example uses continuous basalt fiber composite tendons as the main tensile material, and is connected and positioned using a positioning centering device. Steel strands are used instead of continuous basalt fiber composite tendons at the place where the prestress is applied, so as to avoid shear failure or fail to reach the prestress design value. The anchor cable provided by this embodiment has the advantages of high tensile strength, low quality, low shear strength, and easy cutting, and can better solve the obstacle problem caused by the anchor cable left in the soil layer to other engineering constructions.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910947990.2A CN110541417A (en) | 2019-10-08 | 2019-10-08 | Anchor cable for continuous basalt fiber composite reinforcement |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910947990.2A CN110541417A (en) | 2019-10-08 | 2019-10-08 | Anchor cable for continuous basalt fiber composite reinforcement |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN110541417A true CN110541417A (en) | 2019-12-06 |
Family
ID=68715257
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201910947990.2A Pending CN110541417A (en) | 2019-10-08 | 2019-10-08 | Anchor cable for continuous basalt fiber composite reinforcement |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN110541417A (en) |
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111424700A (en) * | 2020-04-21 | 2020-07-17 | 中铁西北科学研究院有限公司 | BFRP-spiral sleeve valve type composite anchoring system for high-intensity seismic area and construction method thereof |
| CN113231256A (en) * | 2021-05-25 | 2021-08-10 | 中国地质调查局武汉地质调查中心 | Glue injection device and glue injection method for composite-structure anchor cable steel connector |
| CN113622420A (en) * | 2021-07-26 | 2021-11-09 | 中国地质调查局武汉地质调查中心 | Bank side slope basalt fiber rib integrated anchoring structure and monitoring system thereof |
| CN113756301A (en) * | 2021-09-24 | 2021-12-07 | 中国地质调查局武汉地质调查中心 | A kind of basalt fiber precise segmented grouting anchoring system and its installation method |
| CN114150664A (en) * | 2021-11-15 | 2022-03-08 | 中国地质调查局武汉地质调查中心 | Rapid construction device and method for prestressed basalt fiber anchor rod |
| CN115538339A (en) * | 2022-11-10 | 2022-12-30 | 成都建工第三建筑工程有限公司 | Bridge beam body reinforcing apparatus based on basalt fiber mesh |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2002213048A (en) * | 2001-01-18 | 2002-07-31 | Ps Corp | Composite strand, composite cable, and its using method |
| JP2002227198A (en) * | 2001-02-02 | 2002-08-14 | Ps Corp | Anticorrosive ground anchor |
| CN207277332U (en) * | 2017-09-06 | 2018-04-27 | 瑞腾基础工程技术(北京)股份有限公司 | A kind of more steel strand wires flange coupling connectors |
| CN210917347U (en) * | 2019-10-08 | 2020-07-03 | 华东交通大学 | Anchor cable of continuous basalt fiber composite bar |
-
2019
- 2019-10-08 CN CN201910947990.2A patent/CN110541417A/en active Pending
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2002213048A (en) * | 2001-01-18 | 2002-07-31 | Ps Corp | Composite strand, composite cable, and its using method |
| JP2002227198A (en) * | 2001-02-02 | 2002-08-14 | Ps Corp | Anticorrosive ground anchor |
| CN207277332U (en) * | 2017-09-06 | 2018-04-27 | 瑞腾基础工程技术(北京)股份有限公司 | A kind of more steel strand wires flange coupling connectors |
| CN210917347U (en) * | 2019-10-08 | 2020-07-03 | 华东交通大学 | Anchor cable of continuous basalt fiber composite bar |
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN111424700A (en) * | 2020-04-21 | 2020-07-17 | 中铁西北科学研究院有限公司 | BFRP-spiral sleeve valve type composite anchoring system for high-intensity seismic area and construction method thereof |
| CN111424700B (en) * | 2020-04-21 | 2024-04-23 | 中铁西北科学研究院有限公司 | BFRP-spiral sleeve valve type composite anchoring system for high-intensity earthquake region and construction method thereof |
| CN113231256A (en) * | 2021-05-25 | 2021-08-10 | 中国地质调查局武汉地质调查中心 | Glue injection device and glue injection method for composite-structure anchor cable steel connector |
| CN113622420A (en) * | 2021-07-26 | 2021-11-09 | 中国地质调查局武汉地质调查中心 | Bank side slope basalt fiber rib integrated anchoring structure and monitoring system thereof |
| CN113756301A (en) * | 2021-09-24 | 2021-12-07 | 中国地质调查局武汉地质调查中心 | A kind of basalt fiber precise segmented grouting anchoring system and its installation method |
| CN114150664A (en) * | 2021-11-15 | 2022-03-08 | 中国地质调查局武汉地质调查中心 | Rapid construction device and method for prestressed basalt fiber anchor rod |
| CN114150664B (en) * | 2021-11-15 | 2023-04-07 | 中国地质调查局武汉地质调查中心 | Rapid construction device and method for prestressed basalt fiber anchor rod |
| CN115538339A (en) * | 2022-11-10 | 2022-12-30 | 成都建工第三建筑工程有限公司 | Bridge beam body reinforcing apparatus based on basalt fiber mesh |
| CN115538339B (en) * | 2022-11-10 | 2023-09-05 | 成都建工第三建筑工程有限公司 | Bridge beam body reinforcing device based on basalt fiber grids |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN110541417A (en) | Anchor cable for continuous basalt fiber composite reinforcement | |
| CN100570067C (en) | Method and device for replaceable prestressed anchorage of suspension bridge | |
| CN107366389A (en) | A kind of steel pipe sleeve for being used for precast shear wall, post and preparation method thereof | |
| CN206512925U (en) | Full grout sleeve, sleeve connection structure, concrete component and concrete component attachment structure | |
| CN107882051B (en) | A kind of conical pipe anchor bar connecting structure for precast assembly structure | |
| CN105064625A (en) | Grout sleeve for reinforcement connection and reinforcement connecting method | |
| CN107304545A (en) | A kind of combination set for anchoring and connecting for FRP muscle | |
| CN207079491U (en) | A kind of anti-bend reinforced device of bridge prestress high-strength steel cord | |
| CN107435293A (en) | Pre-stress FRP bar stretching and anchoring device and its construction method for precast assembly bridge pier | |
| CN210917347U (en) | Anchor cable of continuous basalt fiber composite bar | |
| CN107514097B (en) | Prestressed corrugated pipe assembly and installation and construction method thereof | |
| EP2417310B1 (en) | Reinforcement element for structural concrete construction | |
| CN217105824U (en) | Prefabricated UHPC-steel-UHPC pipe concrete composite column | |
| CN214401766U (en) | Anchor rod anchoring end structure and glass fiber rib | |
| CN107165059B (en) | Construction method of a bridge prestressed high-strength steel wire rope anti-bending reinforcement device | |
| CN212452621U (en) | A quick-assembled tension-compression composite anchor | |
| CN212743146U (en) | Large-diameter prestressed carbon fiber reinforced plastic cable anchorage | |
| CN205529907U (en) | P -type anchorage device at fixed end | |
| CN107165060A (en) | A kind of anti-bend reinforced device of bridge prestress high-strength steel cord | |
| CN115977083B (en) | Pressure type carbon fiber anchor cable device and anchoring method | |
| CN105114412B (en) | Using the composite material tube jointing and its application method of prestressed cable | |
| CN212641447U (en) | A prestressed tension-compression composite anti-floating anchor | |
| CN204112601U (en) | The threaded bond type anchorage of new-type FRP rebar | |
| CN111945925A (en) | Additional rib FRP (fiber reinforced plastic) longitudinal rib bundling connection vertical prefabricated part | |
| CN109518885B (en) | Prestressed anchoring device, anchoring system applying prestressed anchoring device and construction method |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191206 |
|
| RJ01 | Rejection of invention patent application after publication |