CN110512609A - A kind of novel jackstone systematic conduit frame and its building technology - Google Patents

A kind of novel jackstone systematic conduit frame and its building technology Download PDF

Info

Publication number
CN110512609A
CN110512609A CN201910759098.1A CN201910759098A CN110512609A CN 110512609 A CN110512609 A CN 110512609A CN 201910759098 A CN201910759098 A CN 201910759098A CN 110512609 A CN110512609 A CN 110512609A
Authority
CN
China
Prior art keywords
box
jacket
frame
error
bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910759098.1A
Other languages
Chinese (zh)
Other versions
CN110512609B (en
Inventor
方龙
吴正峰
季秋兵
沈鹏鹏
施浩杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nantong Zhenhua Heavy Equipment Manufacturing Co Ltd
Original Assignee
Nantong Zhenhua Heavy Equipment Manufacturing Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nantong Zhenhua Heavy Equipment Manufacturing Co Ltd filed Critical Nantong Zhenhua Heavy Equipment Manufacturing Co Ltd
Priority to CN201910759098.1A priority Critical patent/CN110512609B/en
Publication of CN110512609A publication Critical patent/CN110512609A/en
Application granted granted Critical
Publication of CN110512609B publication Critical patent/CN110512609B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/10Placing gravel or light material under water inasmuch as not provided for elsewhere

Abstract

The present invention relates to a kind of novel jackstone systematic conduit frame and its building technology, it is characterised in that: including jacket frame, box girder construction and bracket structure;The box girder construction is embedded on jacket frame, in the overall structure that jacket frame is arranged in the bracket structure and box girder construction is formed;Specific construction step includes S1: jacket frame construction;S2: box beam structure building;S3: bracket structure is built;S4: integral assembling;Each stage in jackstone systematic conduit frame building course is considered to place welding allowance for shrinkage and reversible deformation, prefabricated in strict accordance with component progress, reinforces the control of assembly critical size;The sequence of welding equipment is positioned in strict accordance with the sequence progress installed step by step from lower to upper, by interior principle outward;The technique facilitates welding, closes up precision height, can be improved welding quality and working efficiency.

Description

A kind of novel jackstone systematic conduit frame and its building technology
Technical field
The present invention relates to ocean engineering and shipbuilding technical field more particularly to a kind of novel jackstone systematic conduit frame and Its building technology.
Background technique
Port Zhuhai and Macao bridge is the Super Engineering that the world attractes attention, and wherein seabed tunnel engineering technology difficulty highest, creates crowd More the first in the world.Port Zhuhai and Macao bridge seabed tunnel rubble bedding is laid with using first laid process technique, compared to same using first laid process Two immersed tube tunnel engineerings in Denmark Oresund and Busan, Korea of technique, rubble leveling amount of work is big, and rubble is laid with total Measure 36.3 ten thousand m3;Rubble base bed flattening slope change is big, amounts to 29 kinds of gradients;Water depth ratio is big, 8~45m of the bedding depth of water;Immersed tube The levelling process on basis and leveling required precision are very high, and underwater absolute altitude control difficulty is big.
Jack up broken stone leveling ship is design-and-build exclusively for the project implementation, it includes main hull, 4 from Lift-type spud leg (containing hydraulic system), mobile trolley used, moving trolley, trailing type belt feeder, fixed belt feeder, feed hopper, throwing Madreporic canal, rubble leveling head etc..
As one of jack up broken stone leveling ship critical component, there are many difficult points for the construction of jackstone systematic conduit frame:
1, jackstone systematic conduit frame structure is mostly row frame structure, and structure is intensive, and assembly precision requires height, to guarantee final installation essence Degree, the size welding of procedure calls at different levels, assembly precision are especially high.
2, box girder construction welding space is small in jackstone systematic conduit frame, and welding capacity is big, be easy to produce biggish stress and Deformation, need it is stringent require to be welded according to welding sequence and corresponding WPS, select appropriate Current Voltage, control Speed of welding.
3, the control of welding deformation: making full use of tooling and moulding bed, put back deformation in advance, place welding allowance for shrinkage, and Reasonable welding sequence is formulated to connect.
Therefore, it is badly in need of researching and developing that a kind of construction environment is good, facilitates that welding, production precision is high, can be improved welding quality and work The jack up broken stone leveling ship jackstone systematic conduit frame building technology for making efficiency is imperative.Through examining related document, do not find With the same or similar technical solution of the present invention.
Summary of the invention
That the technical problem to be solved in the present invention is to provide a kind of construction environments is good, facilitate welding, closes up that precision is high, Neng Gouti The jack up broken stone leveling ship jackstone systematic conduit frame and its building technology of high welding quality and working efficiency.
In order to solve the above technical problems, the technical solution of the present invention is as follows: a kind of novel jackstone systematic conduit frame, innovative point It is: including jacket frame, box girder construction and bracket structure;The box girder construction is embedded on jacket frame, institute It states in the overall structure that jacket frame is arranged in bracket structure and box girder construction is formed;
The jacket frame includes ship stern trimming flag piece, port and starboard plate and end grillage;The port and starboard plate is vertically set on The two sides of ship stern trimming flag piece form U-shaped structure;The both ends of U-shaped structure are arranged in the end panel frame;
The box girder construction includes larboard box-structure, starboard box-structure, bottom box-structure and loose mail structure;The left side Side of a ship box-structure is disposed in parallel relation to one another with starboard box-structure, and the bottom box structure setting is vertically set on larboard box knot Larboard box-structure is connected by structure with the bottom end of starboard box-structure with starboard box-structure;Loose mail structure tool there are four and It is connected on larboard box-structure both ends and starboard box-structure both ends;
The bracket structure includes top bracket and lower part bracket;The lower part bracket is mounted on jacket frame and case in a ring On the integrally-built circumferential outer profile that type girder construction is formed.
A kind of novel jackstone systematic conduit frame building technology, innovative point are: specific construction step is as follows: including S1: Jacket frame construction;S2: box beam structure building;S3: bracket structure is built;S4: integral assembling;
S1: jacket frame construction:
S1.1: jacket frame is divided into ship stern trimming flag piece, port and starboard plate and end grillage;To jacket frame in straight tooling Frame carries out the prefabricated of above-mentioned sheet body component;
S1.2: it in middle group of tooling, using ship stern trimming flag piece as benchmark plate, carries out organizing assembly in frame, after middle group of assembly Before welding, firm welding will be carried out between ship stern trimming flag piece and middle group of tooling with card Ma, to prevent plate in welding process from turning round It is bent;
S2: box beam structure building:
S2.1: jacket box girder construction is divided into larboard box-structure, starboard box-structure, bottom box-structure and loose mail Structure;It is prefabricated that above-mentioned component is carried out to the box girder construction of jacket on moulding bed;
S2.2: on assembled station, larboard box-structure, starboard box-structure are positioned according to drawing requirement, and uses Card Ma is fixed;Then positioning lifting bottom box girder construction, finally installs loose mail structure;
S3: bracket structure is built:
S3.1: being divided into top bracket and lower part bracket for bracket structure, and it is standby that top bracket with lower part bracket presets to component respectively With;
S4: integral assembling:
S4.1: on the basis of the jacket frame made, the assembly of jacket structure is carried out;Jacket box girder construction is turned over Body is lifted to positioning on jacket frame, and is welded and fixed using Auxiliary support, is welded referring to welding requirements;
S4.2: after the process for completing S4.1, location and installation lower part bracket, top bracket tack welding when jackstone system general assembly It connects.
Further, the production of jacket frame plate requires in the S1.1: integral smoothness error≤2mm, diagonal line Error≤2mm.
Further, in the S1.2 jacket frame need to meet at middle group it is claimed below: stern plate flatness error ≤ 2mm, the left and right side of a ship plate error of perpendicularity≤2mm;It needs to meet after the completion of middle group: error in length ± 4mm, width error ± 1mm, Space Oblique diagonal error ± 2mm.
Further, in the S2.1 jacket box girder construction need to meet in component prefabrication process it is claimed below: institute There is the reserved 40mm machining allowance of pin hole;It is 4mm that plane machining, which reserves machining allowance,;The error of perpendicularity ± 1mm;It is left and right Side of a ship box-structure error in length ± 3mm;Bottom box-structure otic placode center allowable error ± 1mm.
Further, larboard box-structure in the S2, starboard box-structure center are away from control in ± 2mm;Bottom box Structure vertical degree error ± 1mm, lug plate holes centre distance horizontal plane error under ±2 mm.
Further, in the S2.1 loose mail structure by wearing plate clipping room away from control in ± 3mm;The error of perpendicularity ± 1mm。
Further, in the S2.2 on box girder construction middle pulley earhole center and jacket between trolley center away from From relative level error ± 1mm and the vertical state error of perpendicularity between error under ±2 mm, with jacket.
Further, range error ± 1mm between trolley center on plane and jacket on the bracket of the middle and lower part S4.2, Surrounding bracket integral planar degree error ± 1mm.
The present invention has the advantages that
1) construction of jackstone systematic conduit frame is divided into step progress: frame manufacture in the present invention, and box beam makes, bracket production, finally It is whole to carry out total group, then whole machining;Each stage in jackstone systematic conduit frame building course is considered to place welding Allowance for shrinkage and reversible deformation carry out prefabricated, the control of reinforcement assembly critical size in strict accordance with component;The sequence for positioning welding equipment is tight Lattice according to: the sequence installed step by step from lower to upper, by interior principle outward carries out;The technique facilitates welding, closes up precision Height can be improved welding quality and working efficiency.
Detailed description of the invention
The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.
Fig. 1 is a kind of novel jackstone systematic conduit frame circuit theory schematic diagram of the invention.
Fig. 2 is a kind of side of a ship sheet structure figure of novel jackstone systematic conduit frame frame structure of the invention.
Fig. 3 is a kind of ship stern trimming flag chip architecture figure of novel jackstone systematic conduit frame of the invention.
Fig. 4 is a kind of box beam structural perspective of novel jackstone systematic conduit frame of the invention.
Fig. 5 is that ship stern trimming flag positions upper moulding bed schematic diagram.
Fig. 6 is strake location and installation schematic diagram.
Fig. 7 is moulding bed schematic diagram on port and starboard box structure.
Fig. 8 is that moulding bed positions schematic diagram on the box-structure of bottom.
Fig. 9 is loose mail scheme of installation.
Figure 10 is moulding bed installation diagram on jacket.
Figure 11 is that box girder construction and jacket are coupled figure.
Figure 12 is lower part bracket location and installation.
Specific embodiment
The following examples can make professional and technical personnel that the present invention be more fully understood, but therefore not send out this It is bright to be limited among the embodiment described range.
A kind of novel jackstone systematic conduit frame as shown in Figures 1 to 4, including jacket frame 1,2 and of box girder construction Bracket structure;The box girder construction 2 is embedded on jacket frame 1, and the bracket structure is arranged in jacket frame 1 and case In the overall structure that type girder construction 2 is formed.
Jacket frame 1 includes ship stern trimming flag piece 11, port and starboard plate 12 and end grillage;The port and starboard plate 12 is vertical The two sides that ship stern trimming flag piece 11 is arranged in form U-shaped structure;The both ends of U-shaped structure are arranged in the end panel frame.
Box girder construction 2 includes larboard box-structure 21, starboard box-structure 22, bottom box-structure 23 and loose mail structure 24;The larboard box-structure 21 is disposed in parallel relation to one another with 22 structure of starboard box, and the bottom box-structure 23 is arranged vertically The bottom end of larboard box-structure 21 and starboard box-structure 22 is set by 22 phase of larboard box-structure 21 and starboard box-structure Even;There are four the tools of loose mail structure 24 and is connected to 21 both ends of larboard box-structure and 22 both ends of starboard box-structure On.
Bracket structure 3 includes top bracket and lower part bracket 31;The lower part bracket 31 is mounted on jacket frame in a ring On the integrally-built circumferential outer profile that frame 1 and box girder construction 2 are formed.
A kind of novel jackstone systematic conduit frame building technology, specific construction step as shown in Fig. 5 to Figure 12 are as follows: including S1: jacket frame construction;S2: box beam structure building;S3: bracket structure is built;S4: integral assembling;
S1: jacket frame construction:
S1.1: jacket frame is divided into ship stern trimming flag piece, port and starboard plate and end grillage;To jacket frame in straight tooling Frame carries out the prefabricated of above-mentioned sheet body component;The production of jacket frame plate requires: integral smoothness error≤2mm, diagonal line miss Difference≤2mm.
S1.2: it in middle group of tooling, using ship stern trimming flag piece as benchmark plate, carries out organizing assembly in frame, in middle group of assembly knot Before welding after beam, firm welding will be carried out between ship stern trimming flag piece and middle group of tooling with card Ma, to prevent plate in welding process from sending out Raw distortion;Jacket frame need to meet claimed below at middle group: stern plate flatness error≤2mm, left and right side of a ship plate are vertical Spend error≤2mm;It needs to meet after the completion of middle group: error in length ± 4mm, width error ± 1mm, Space Oblique diagonal error ± 2mm。
S2: box beam structure building:
S2.1: jacket box girder construction is divided into larboard box-structure, starboard box-structure, bottom box-structure and loose mail Structure;It is prefabricated that above-mentioned component is carried out to the box girder construction of jacket on moulding bed;Jacket box girder construction is prefabricated in component It needs to meet in the process claimed below: the reserved 40mm machining allowance of all pin holes;Plane machining reserves machining allowance 4mm;The error of perpendicularity ± 1mm;Left and right side of a ship box-structure error in length ± 3mm;Bottom box-structure otic placode center allowable error ±1mm;Loose mail structure is by wearing plate clipping room away from control in ± 3mm;The error of perpendicularity ± 1mm.
S2.2: on assembled station, larboard box-structure, starboard box-structure being positioned according to drawing requirement, and It is fixed using card Ma;Then positioning lifting bottom box girder construction, finally installs loose mail structure;Larboard box-structure, the right side Side of a ship box-structure center is away from control in ± 2mm;Bottom box structure vertical degree error ± 1mm, the horizontal base of lug plate holes centre distance Quasi- surface error ± 2mm;The distance between trolley center error under ±2 mm on box girder construction middle pulley earhole center and jacket, Relative level error ± 1mm and the vertical state error of perpendicularity between jacket.
S3: bracket structure is built:
S3.1: being divided into top bracket and lower part bracket for bracket structure, and it is standby that top bracket with lower part bracket presets to component respectively With;Range error ± 1mm between trolley center on plane and jacket on the bracket of lower part, surrounding bracket integral planar degree error ± 1mm。
S4: integral assembling:
S4.1: on the basis of the jacket frame made, the assembly of jacket structure is carried out;Jacket box girder construction is turned over Body is lifted to positioning on jacket frame, and is welded and fixed using Auxiliary support, is welded referring to welding requirements.
S4.2: after the process for completing S4.1, location and installation lower part bracket, positioning when jackstone system general assembly of top bracket Welding.
It should be understood by those skilled in the art that the present invention is not limited to the above embodiments, above-described embodiment and explanation It is merely illustrated the principles of the invention described in book, without departing from the spirit and scope of the present invention, the present invention also has Various changes and modifications, these changes and improvements all fall within the protetion scope of the claimed invention.The claimed scope of the invention It is defined by the appending claims and its equivalent thereof.

Claims (9)

1. a kind of novel jackstone systematic conduit frame, it is characterised in that: including jacket frame, box girder construction and bracket structure; The box girder construction is embedded on jacket frame, and the bracket structure setting is formed in jacket frame and box girder construction Overall structure on;
The jacket frame includes ship stern trimming flag piece, port and starboard plate and end grillage;The port and starboard plate is vertically set on The two sides of ship stern trimming flag piece form U-shaped structure;The both ends of U-shaped structure are arranged in the end panel frame;
The box girder construction includes larboard box-structure, starboard box-structure, bottom box-structure and loose mail structure;The left side Side of a ship box-structure is disposed in parallel relation to one another with starboard box-structure, and the bottom box structure setting is vertically set on larboard box knot Larboard box-structure is connected by structure with the bottom end of starboard box-structure with starboard box-structure;Loose mail structure tool there are four and It is connected on larboard box-structure both ends and starboard box-structure both ends;
The bracket structure includes top bracket and lower part bracket;The lower part bracket is mounted on jacket frame and case in a ring On the integrally-built circumferential outer profile that type girder construction is formed.
2. a kind of novel jackstone systematic conduit frame building technology described in claim 1, it is characterised in that: specific construction step is such as Under: including S1: jacket frame construction;S2: box beam structure building;S3: bracket structure is built;S4: integral assembling;
S1: jacket frame construction:
S1.1: jacket frame is divided into ship stern trimming flag piece, port and starboard plate and end grillage;To jacket frame in straight tooling Frame carries out the prefabricated of above-mentioned sheet body component;
S1.2: it in middle group of tooling, using ship stern trimming flag piece as benchmark plate, carries out organizing assembly in frame, after middle group of assembly Before welding, firm welding will be carried out between ship stern trimming flag piece and middle group of tooling with card Ma, to prevent plate in welding process from turning round It is bent;
S2: box beam structure building:
S2.1: jacket box girder construction is divided into larboard box-structure, starboard box-structure, bottom box-structure and loose mail Structure;It is prefabricated that above-mentioned component is carried out to the box girder construction of jacket on moulding bed;
S2.2: on assembled station, larboard box-structure, starboard box-structure are positioned according to drawing requirement, and uses Card Ma is fixed;Then positioning lifting bottom box girder construction, finally installs loose mail structure;
S3: bracket structure is built:
S3.1: being divided into top bracket and lower part bracket for bracket structure, and it is standby that top bracket with lower part bracket presets to component respectively With;
S4: integral assembling:
S4.1: on the basis of the jacket frame made, the assembly of jacket structure is carried out;Jacket box girder construction is turned over Body is lifted to positioning on jacket frame, and is welded and fixed using Auxiliary support, is welded referring to welding requirements;
S4.2: after the process for completing S4.1, location and installation lower part bracket, top bracket tack welding when jackstone system general assembly It connects.
3. a kind of novel jackstone systematic conduit frame building technology according to claim 2, it is characterised in that: in the S1.1 The production of jacket frame plate requires: integral smoothness error≤2mm, diagonal error≤2mm.
4. a kind of novel jackstone systematic conduit frame building technology according to claim 2, it is characterised in that: in the S1.2 Jacket frame need to meet claimed below at middle group: stern plate flatness error≤2mm, the left and right side of a ship plate error of perpendicularity ≤2mm;It needs to meet after the completion of middle group: error in length ± 4mm, width error ± 1mm, Space Oblique diagonal error ± 2mm.
5. a kind of novel jackstone systematic conduit frame building technology according to claim 2, it is characterised in that: in the S2.1 Jacket box girder construction needs to meet claimed below in component prefabrication process: the reserved 40mm machining allowance of all pin holes; It is 4mm that plane machining, which reserves machining allowance,;The error of perpendicularity ± 1mm;Left and right side of a ship box-structure error in length ± 3mm;Bottom Box-structure otic placode center allowable error ± 1mm.
6. a kind of novel jackstone systematic conduit frame building technology according to claim 2, it is characterised in that: left in the S2 Side of a ship box-structure, starboard box-structure center are away from control in ± 2mm;Bottom box structure vertical degree error ± 1mm, in lug plate holes The heart is apart from horizontal plane error under ±2 mm.
7. a kind of novel jackstone systematic conduit frame building technology according to claim 2, it is characterised in that: in the S2.1 Loose mail structure is by wearing plate clipping room away from control in ± 3mm;The error of perpendicularity ± 1mm.
8. a kind of novel jackstone systematic conduit frame building technology according to claim 2, it is characterised in that: in the S2.2 The distance between box girder construction middle pulley earhole center and trolley center on jacket phase between error under ±2 mm, with jacket To horizontal error ± 1mm and the vertical state error of perpendicularity.
9. a kind of novel jackstone systematic conduit frame building technology according to claim 2, it is characterised in that: in the S4.2 Range error ± 1mm between trolley center on plane and jacket on the bracket of lower part, surrounding bracket integral planar degree error ± 1mm。
CN201910759098.1A 2019-08-16 2019-08-16 Riprap system jacket and construction process thereof Active CN110512609B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910759098.1A CN110512609B (en) 2019-08-16 2019-08-16 Riprap system jacket and construction process thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910759098.1A CN110512609B (en) 2019-08-16 2019-08-16 Riprap system jacket and construction process thereof

Publications (2)

Publication Number Publication Date
CN110512609A true CN110512609A (en) 2019-11-29
CN110512609B CN110512609B (en) 2021-05-28

Family

ID=68625505

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910759098.1A Active CN110512609B (en) 2019-08-16 2019-08-16 Riprap system jacket and construction process thereof

Country Status (1)

Country Link
CN (1) CN110512609B (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204056240U (en) * 2014-05-21 2014-12-31 中铁第五勘察设计院集团有限公司 Buoyancy tank pile foundation support table
CN204370469U (en) * 2014-12-24 2015-06-03 广州华申建设工程管理有限公司 A kind of drilled pile long leg jacket offshore wind turbine foundation
CN204370466U (en) * 2014-12-23 2015-06-03 广州华申建设工程管理有限公司 A kind of jacket offshore wind turbine foundation with bracket
WO2016124263A1 (en) * 2015-02-06 2016-08-11 Maritime Offshore Group Gmbh Offshore foundation structure with gangway and improved boat landing
JP2018178662A (en) * 2017-04-21 2018-11-15 東京電力ホールディングス株式会社 Construction method for replacement of steel tower
CN209025085U (en) * 2018-09-14 2019-06-25 江苏华西村海洋工程服务有限公司 Jacket pile pipe pitching pile combined console

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204056240U (en) * 2014-05-21 2014-12-31 中铁第五勘察设计院集团有限公司 Buoyancy tank pile foundation support table
CN204370466U (en) * 2014-12-23 2015-06-03 广州华申建设工程管理有限公司 A kind of jacket offshore wind turbine foundation with bracket
CN204370469U (en) * 2014-12-24 2015-06-03 广州华申建设工程管理有限公司 A kind of drilled pile long leg jacket offshore wind turbine foundation
WO2016124263A1 (en) * 2015-02-06 2016-08-11 Maritime Offshore Group Gmbh Offshore foundation structure with gangway and improved boat landing
JP2018178662A (en) * 2017-04-21 2018-11-15 東京電力ホールディングス株式会社 Construction method for replacement of steel tower
CN209025085U (en) * 2018-09-14 2019-06-25 江苏华西村海洋工程服务有限公司 Jacket pile pipe pitching pile combined console

Also Published As

Publication number Publication date
CN110512609B (en) 2021-05-28

Similar Documents

Publication Publication Date Title
CN101439754B (en) Hull section non-allowance healing accuracy control process
CN102357783A (en) Manufacturing process of pile shoe of wind power installation vessel
CN201891081U (en) Steel hanging box concrete bottom plate used in boxed cofferdam construction
CN110512609A (en) A kind of novel jackstone systematic conduit frame and its building technology
CN202175179U (en) Hatch coaming
CN101817393A (en) Shipbuilding method by utilizing floating dock
CN107399412B (en) The method of construction of MOPU
CN218148238U (en) Combined water drilling platform system
CN111139808B (en) Method for carrying cantilever beam of self-elevating drilling platform
CN110153599A (en) Crane mounting process
CN215053167U (en) Prefabricated formula steel construction cushion cap basis
CN109720502A (en) A kind of method of construction of mono-point mooring buoy turntable
CN211006742U (en) Bearing platform beam type pile-free tower crane foundation
CN204920244U (en) Supporting structure of large -span steel construction segmentation hoist and mount
CN210395121U (en) Steel platform combines portable thick liquid board decking construction frock of ending of broach board formula
CN109778883B (en) Novel steel cofferdam structure and installation method
CN217759259U (en) Prefabricated balcony slab that stability is strong
CN105040991B (en) The supporting construction and method for supporting of large-span steel segmental hoisting
CN103406732A (en) Sectional manufacturing process for pile leg flat pallet
CN217680517U (en) Self-locking type cylindrical template
CN215104725U (en) Box type unit correcting platform device for steel truss arch bridge
CN219886576U (en) Curved surface abnormal type inner concrete outer steel main tower decoration structure
CN219053291U (en) Super-large-section double-wall reinforced concrete beam with ribs
CN204711375U (en) A kind of welding connection structure of self-elevating drilling platform leg chord assembly
CN210134424U (en) Existing-service bridge underwater pile head defect repairing and reinforcing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant