CN110499789A - A kind of floor structure pressure release construction method - Google Patents

A kind of floor structure pressure release construction method Download PDF

Info

Publication number
CN110499789A
CN110499789A CN201910807876.XA CN201910807876A CN110499789A CN 110499789 A CN110499789 A CN 110499789A CN 201910807876 A CN201910807876 A CN 201910807876A CN 110499789 A CN110499789 A CN 110499789A
Authority
CN
China
Prior art keywords
pressure release
bottom plate
construction method
floor structure
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910807876.XA
Other languages
Chinese (zh)
Inventor
王立军
任远敏
岳巍
苏伟
刘辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Bureau First Construction Engineering Co Ltd
Original Assignee
China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Bureau First Construction Engineering Co Ltd filed Critical China Construction Fourth Bureau First Construction Engineering Co Ltd
Priority to CN201910807876.XA priority Critical patent/CN110499789A/en
Publication of CN110499789A publication Critical patent/CN110499789A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/10Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure
    • E02D31/12Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against soil pressure or hydraulic pressure against upward hydraulic pressure

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a kind of floor structure pressure release construction method, the present invention is so that the buoyancy of underground water is slightly larger than the self weight of basement always by discharging bottom plate lower part underground water, to ensure the safety built;Specifically implement by following process: determining tapping point → aperture → installation pressure release dispensing equipment → seal clearance → discharge water pressure release according to the pressure gauge of pressure release dispensing equipment interruption.Present invention can ensure that basement bottom board waterproof construction will not damage.Prevent bottom plate rear pouring tape or waterproof construction weak part from phenomena such as arch camber, crack, irregular leakage occur.

Description

A kind of floor structure pressure release construction method
Technical field
The technology of the present invention is related to a kind of floor structure pressure release construction method, belongs to technical field of building construction.
Background technique
Swimming pool is had in some buildings, also some buildings go sightseeing to require to meet, or even have river out of building Pass through, has the building of water storage requirement for above-mentioned indoor large span, water-proofing treatment is always technical problem.Due to floor structure pad Red clay under layer will become stream modeling shape soil after being impregnated for a long time by underground water, after the change of surrounding geological conditions as After lower room water level climbs, stream modeling shape soil will become fluid, move under bottom plate.It over time can be to bed course and waterproof Structure damages.Bottom plate rear pouring tape or waterproof construction weak part will appear arch camber, and crack is irregular to leak.Conventional construction Method can not handle this kind of leakages.
Summary of the invention
The object of the present invention is to provide a kind of floor structure pressure release construction methods, by discharging bottom plate lower part underground water The buoyancy of underground water is set to be slightly larger than the self weight of basement always, to ensure the safety built;To overcome the prior art not Foot.
To achieve the above object, the present invention adopts the following technical scheme:
A kind of floor structure pressure release construction method of the invention, this method are to make underground water by discharging bottom plate lower part underground water Buoyancy is slightly larger than the self weight of basement always, to ensure the safety built;Specifically by following process implement: determine tapping point → Aperture → installation pressure release dispensing equipment → seal clearance → discharged water pressure release according to the pressure gauge of pressure release dispensing equipment interruption.
In preceding method, the determining tapping point process is to play arch area according to bottom plate to be determined tapping point;If bottom Sump is then being found around bottom plate arch camber, tapping point is sump relative to basement regional center in plate arch camber position Side wall;If bottom plate spring is then tapping point is arranged along shear wall by gutter side along shear wall fringe region.
In preceding method, the aperture process is to bore aperture using electric hammer or water mill in selected tapping point;Tapping point is When sump side wall, the top edge in hole should be lower than bottom plate lower edge;When tapping point is arranged along shear wall by gutter side, Kong Ying Through bottom plate, the density in hole is determined according to sump section.
In preceding method, the installation pressure release dispensing equipment process is that the water free from admixture in hole overflows, and water quality is limpid Installation pressure release dispensing equipment is carried out after bright.
In preceding method, the pressure release dispensing equipment includes chimney filter, and chimney filter is connect with valve, the junction of valve and chimney filter Equipped with pressure gauge.
In preceding method, the seal clearance process is using leak stopping king after pressure release dispensing equipment insert structure to structure Gap between equipment is blocked.
In preceding method, the pressure gauge according to pressure release dispensing equipment carries out being interrupted the pressure release that discharges water;To ensure underground water Buoyancy be slightly larger than the self weight of basement always, to ensure the safety built.
By adopting the above-described technical solution, compared with prior art, the present invention the prior art can not be handled because of bottom plate knot Red clay under structure bed course will become stream modeling shape soil after being impregnated for a long time by underground water, cause bottom plate rear pouring tape or waterproof Structural weak position will appear arch camber, crack, the problem irregularly leaked.The present invention makes ground by discharging bottom plate lower part underground water The buoyancy being lauched is slightly larger than the self weight of basement always, it can be ensured that building structure will not because subsurface pressure it is excessive caused by arch camber, The problem of crack, irregular leakage.
Detailed description of the invention
Fig. 1 is to carry out the construction schematic diagram of pressure release in sump side;
Fig. 2 is the construction schematic diagram that shear wall carries out pressure release.
Specific embodiment
The present invention is described in further detail with reference to the accompanying drawings and examples.
A kind of floor structure pressure release construction method of the invention, this method are to make underground by discharging bottom plate lower part underground water The buoyancy of water is slightly larger than the self weight of basement always, to ensure the safety built;Specifically implement by following process: determining aperture Point → aperture → installation pressure release dispensing equipment → seal clearance → discharged water pressure release according to the pressure gauge of pressure release dispensing equipment interruption.
In preceding method, the determining tapping point process is to play arch area according to bottom plate to be determined tapping point;Such as 1 institute Show, if sump is being found, tapping point is relative to basement regional center in bottom plate arch camber position around bottom plate arch camber Sump side wall;As shown in Fig. 2, tapping point is along shear wall by gutter one if being along shear wall fringe region if bottom plate spring Side arrangement.The aperture process is to bore aperture using electric hammer or water mill in selected tapping point;When tapping point is sump side wall, The top edge in hole should be lower than bottom plate lower edge;When tapping point is arranged along shear wall by gutter side, hole should run through bottom plate, hole Density is determined according to sump section.The installation pressure release dispensing equipment process is that the water free from admixture in hole overflows, water quality It is limpid it is bright after carry out installation pressure release dispensing equipment.The pressure release dispensing equipment includes chimney filter, and chimney filter is connect with valve, valve with The junction of chimney filter is equipped with pressure gauge.The seal clearance process is that leak stopping king couple is used after pressure release dispensing equipment insert structure Gap between structure and equipment is blocked.It is carried out being interrupted the pressure release that discharges water according to the pressure gauge of pressure release dispensing equipment;To ensure The buoyancy of underground water is slightly larger than the self weight of basement always, to ensure building safety.
Embodiment
Construction Principle of the invention:
With groundwater pressure for 56KN/ ㎡, for dead load is 50KN/ ㎡.The following conditions should be met:
(dead load ÷ water buoyancy) >=1.05
Learn that water buoyancy should maintain 47.7KN/ ㎡ or so by above formula.
It is known as 56KN/ ㎡, therefore should be controlled between the pressure area that can sluice: 56-47.7=8.3KN/ ㎡.To 100 ㎡'s Basement carry out pressure release can pressure release power answer are as follows: 8.3 × 100=0.83mpa.
It constructs by following process: determining tapping point → aperture → installation pressure release dispensing equipment → seal clearance → according to pressure release The pressure gauge of dispensing equipment is interrupted the pressure release that discharges water.
It should be carried out by following rule when Specific construction:
1, when determining tapping point: if bottom plate arch camber position is when basement is close to intermediate region, tapping point is located at catch pit side Wall;If bottom plate spring position, when close to shear wall fringe region, tapping point is arranged along shear wall edge.
2, after tapping point determines, aperture is bored using electric hammer or water mill;In boiled water flat hole on catch pit side wall, should consult The top edge of drawing upper plate thickness, lateral aperture should be lower than bottom plate lower edge;Tapping point is opened vertical when being located at shear wall edge Straight hole, vertical hole should run through bottom plate, if gushing out after aperture without bright water, in addition find position of opening;Aperture density is every 100 Two holes are opened within the scope of square meter.It can need to open up 3 to 4 holes according to scene.
3, after hole is held successfully, Kong Zhongying has underground water to gush out, and starting the water gushed out is slime water, to the water free from admixture in hole It overflows, by pressure release dispensing equipment that pre-production is good when water quality is limpid bright: inserting in the hole.Pressure release dispensing equipment includes chimney filter, Chimney filter insert in the hole part tube wall on be evenly equipped with aperture, the exposed one end of chimney filter is connect with valve, the connection of valve and chimney filter Place is equipped with pressure gauge, and the survey pressure range of pressure gauge is 0~10MP;It is sealed in gap between chimney filter and hole with leak stopping king It is stifled.Guarantee to seal between equipment and floor structure.When pressure release dispensing equipment is inserted into vertical hole, dewatering outlet should be towards sump side To avoiding water from flinging shear wall.
4, after pressure release dispensing equipment installs, the pressure release that discharges water can be carried out, gage pressure value is observed before discharging water.Pressure The numerical value of table is that 47.7~56 KN/ ㎡ are normal value, when the numerical value of pressure gauge is equal to or more than 56 KN/ ㎡, opens valve It discharges water;When the numerical value of pressure gauge is equal to or less than 47.7 KN/ ㎡, closes valve stopping and discharge water;Repeating operation makes Groundwater pressure remains between 47.7~56 KN/ ㎡.It uninterruptedly discharges water: appropriate in the frequency that discharges water of high-incidence time in rainy season Increase.
When basement bottom board many places waterproof construction destroys, can also be let out simultaneously using horizontal drainage pressure release and vertical drainage Press two ways.To ensure building safety.It can ensure that basement bottom board waterproof construction will not damage by above method.It is anti- Only there is phenomena such as arch camber, crack, irregular leakage in bottom plate rear pouring tape or waterproof construction weak part.

Claims (7)

1. a kind of floor structure pressure release construction method, it is characterised in that: this method is to make ground by discharging bottom plate lower part underground water The buoyancy being lauched is slightly larger than the self weight of basement always, to ensure the safety built;Specifically implement by following process: determination is opened Hole point → aperture → installation pressure release dispensing equipment → seal clearance → discharged water pressure release according to the pressure gauge of pressure release dispensing equipment interruption.
2. floor structure pressure release construction method according to claim 1, it is characterised in that: the determining tapping point process is root Arch area, which is played, according to bottom plate is determined tapping point;If bottom plate arch camber position is relative to basement regional center, then the bottom of at Sump is found around plate arch camber, tapping point is sump side wall;If bottom plate spring is then to open along shear wall fringe region Hole point is arranged along shear wall by gutter side.
3. floor structure pressure release construction method according to claim 2, it is characterised in that: the aperture process is selected Tapping point bores aperture using electric hammer or water mill;When tapping point is sump side wall, the top edge in hole should be lower than bottom plate lower edge;It opens When hole point is arranged along shear wall by gutter side, hole should run through bottom plate, and the density in hole is determined according to sump section.
4. floor structure pressure release construction method according to claim 3, it is characterised in that: the installation pressure release dispensing equipment work Sequence is that water free from admixture in hole overflows, water quality it is limpid it is bright after carry out installation pressure release dispensing equipment.
5. floor structure pressure release construction method according to claim 4, it is characterised in that: the pressure release dispensing equipment includes filter Pipe, chimney filter are connect with valve, and the junction of valve and chimney filter is equipped with pressure gauge.
6. floor structure pressure release construction method according to claim 5, it is characterised in that: the seal clearance process is to let out The gap between structure and equipment is blocked using leak stopping king after pressing wetting system insert structure.
7. floor structure pressure release construction method according to claim 5, it is characterised in that: described according to pressure release dispensing equipment Pressure gauge carries out being interrupted the pressure release that discharges water;To ensure that the buoyancy of underground water is slightly larger than the self weight of basement always, to ensure to build Safety.
CN201910807876.XA 2019-08-29 2019-08-29 A kind of floor structure pressure release construction method Pending CN110499789A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910807876.XA CN110499789A (en) 2019-08-29 2019-08-29 A kind of floor structure pressure release construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910807876.XA CN110499789A (en) 2019-08-29 2019-08-29 A kind of floor structure pressure release construction method

Publications (1)

Publication Number Publication Date
CN110499789A true CN110499789A (en) 2019-11-26

Family

ID=68590393

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910807876.XA Pending CN110499789A (en) 2019-08-29 2019-08-29 A kind of floor structure pressure release construction method

Country Status (1)

Country Link
CN (1) CN110499789A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112376594A (en) * 2020-11-13 2021-02-19 深圳市天健(集团)股份有限公司 Intelligent water pressure monitoring equipment for anti-floating early warning
CN112523271A (en) * 2020-11-13 2021-03-19 中国建筑西南勘察设计研究院有限公司 Pressure-controlled intelligent drainage pressure relief device and drainage pressure relief method thereof
PL445717A1 (en) * 2023-07-31 2025-02-03 Wojskowa Akademia Techniczna Im. Jarosława Dąbrowskiego Device for measuring piezometric pressure and method of performing such measurement

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205530386U (en) * 2016-03-21 2016-08-31 上海长凯岩土工程有限公司 Water pressure control system for underground works with outlet pipe
CN107386338A (en) * 2017-07-25 2017-11-24 刘保材 A kind of building construction substrate drainage pressure-reducing design

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN205530386U (en) * 2016-03-21 2016-08-31 上海长凯岩土工程有限公司 Water pressure control system for underground works with outlet pipe
CN107386338A (en) * 2017-07-25 2017-11-24 刘保材 A kind of building construction substrate drainage pressure-reducing design

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112376594A (en) * 2020-11-13 2021-02-19 深圳市天健(集团)股份有限公司 Intelligent water pressure monitoring equipment for anti-floating early warning
CN112523271A (en) * 2020-11-13 2021-03-19 中国建筑西南勘察设计研究院有限公司 Pressure-controlled intelligent drainage pressure relief device and drainage pressure relief method thereof
PL445717A1 (en) * 2023-07-31 2025-02-03 Wojskowa Akademia Techniczna Im. Jarosława Dąbrowskiego Device for measuring piezometric pressure and method of performing such measurement
PL247270B1 (en) * 2023-07-31 2025-06-09 Wojskowa Akademia Techniczna Im Jaroslawa Dabrowskiego Device for measuring piezometric pressure and method of performing such measurement

Similar Documents

Publication Publication Date Title
CN111691467B (en) Construction method for basement water prevention and drainage combination
CN206386134U (en) A kind of Underground Subway Station guarded drainage construction
CN204572015U (en) A kind of tunnel shunting combined type waterproof and water drainage system
CN107059903A (en) Bottom plate plugging dewatering well construction method is worn in foundation ditch
CN110499789A (en) A kind of floor structure pressure release construction method
CN105544622B (en) A kind of anti-floating system and its checking device of underground structure
CN104806272A (en) Tunnel diversion composite type waterproof and drainage system as well as construction method and use method thereof
CN106320353B (en) A kind of construction method of basement construction Yield rainfall relation device
CN102519860A (en) Impermeability test method for asphalt concrete with impermeable function
CN109339215B (en) Device and method for replacing water inlet and outlet gates without water interruption
CN201254732Y (en) Prevention and training combined water proofing system for basement
CN108166517A (en) For the shut-in well method and well-sealing device of superelevation floor height hydraulic pressure dewatering well of deep well
CN205894121U (en) Emergent anti structure of floating of basement
CN205530388U (en) Forced induction water pressure control system for underground works
CN209129624U (en) A high water pressure tunnel drainage and pressure reduction type embedded maintenance grouting device
CN209082651U (en) A kind of toilet with drainage system three times
CN214402966U (en) Shock insulation building
CN106480979B (en) A kind of active antiseepage basement shear wall and its construction technology
CN110004990A (en) A kind of construction method and device for pressure relief construction of basement in rich water and dark river area
CN208293627U (en) A kind of basement bottom board waterproof/drainage structure
CN207331931U (en) A kind of water seepage prevention floor drain
CN208072433U (en) A kind of interim precipitation steel sleeve being used for basic posthole and catch pit
CN216130157U (en) A deep foundation pit spring water gushing drainage structure
CN207987984U (en) A kind of basement waterproofing structure
CN1804234B (en) Drainage Method and Drainage Device of Red Mud Stockyard in Karst Area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191126

RJ01 Rejection of invention patent application after publication