CN110489840A - A kind of structure final settlement quantity algorithm considering immersed tube tunnel special process - Google Patents

A kind of structure final settlement quantity algorithm considering immersed tube tunnel special process Download PDF

Info

Publication number
CN110489840A
CN110489840A CN201910732127.5A CN201910732127A CN110489840A CN 110489840 A CN110489840 A CN 110489840A CN 201910732127 A CN201910732127 A CN 201910732127A CN 110489840 A CN110489840 A CN 110489840A
Authority
CN
China
Prior art keywords
immersed tube
tube tunnel
special process
final settlement
considering
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910732127.5A
Other languages
Chinese (zh)
Other versions
CN110489840B (en
Inventor
贺维国
范国刚
周华贵
吕洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Liuyuan Group Co Ltd
CRTG Survey and Design Institute Co Ltd
Original Assignee
China Railway Liuyuan Group Co Ltd
China Railway Tianjin Tunnel Engineering Survey and Design Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Liuyuan Group Co Ltd, China Railway Tianjin Tunnel Engineering Survey and Design Co Ltd filed Critical China Railway Liuyuan Group Co Ltd
Priority to CN201910732127.5A priority Critical patent/CN110489840B/en
Publication of CN110489840A publication Critical patent/CN110489840A/en
Application granted granted Critical
Publication of CN110489840B publication Critical patent/CN110489840B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/063Tunnels submerged into, or built in, open water
    • E02D29/073Tunnels or shuttering therefor assembled from sections individually sunk onto, or laid on, the water-bed, e.g. in a preformed trench

Abstract

The invention discloses a kind of structure final settlement quantity algorithms for considering immersed tube tunnel special process, and the algorithm is the following steps are included: one: determining that base form influences COEFFICIENT K1;Two: determine the rigidity of structure and connector (containing with secretly bury a section connector) influence COEFFICIENT K2;Three: calculating the sand bedding course settling amount S for the influences that consider backbreak, back-silt etc.1;Four: calculating and consider to excavate the original settlement of foundation S for loosening and springing back under sand bedding course2;Five: calculating final precipitation capacity S=K1K2(S1+S2).This algorithm considers immersed tube tunnel process and structure feature, including backbreaks under water, excavates a variety of key factors influential on final settlement such as loosening is influenced, back-silted, the rigidity of structure, connector, ground are sprung back, so that the calculated result of final settlement is more accurate.

Description

A kind of structure final settlement quantity algorithm considering immersed tube tunnel special process
Technical field
The present invention relates in immersed tube tunnel final settlement algorithmic technique field more particularly to a kind of consideration immersed tube tunnel The structure final settlement quantity algorithm of special process.
Background technique
Immersed tube tunnel is that the processes such as tube coupling prefabricated in depressed place, towage transportation by driving, sinking docking, based process, backfill covering are built At submerged tunnel.Top earthing is shallow, length of tunnel is short, is connected more flexible with waters two sides road for it, can greatly save center Urban land resource is one of the main method that inland river submerged tunnel is built in city.80% or more immersed tube tunnel is all in pipe Pass through the harmful gap for filling sand bedding course elimination tube coupling bottom surface and foundation trench bottom after saving sinking.Tunnel inner concrete backfills ballast and tunnel Outer rubble backfill protective layer gravity causes to fill sand bedding course and the compression of original ground, so as to cause structure sediment.
Immersed tube tunnel structure final quantity settlement calculation method does not consider the influence of immersed tube special process at present, calculated value with Measured data there are relatively large deviation, cannot effectively design take corresponding settlement Control measure, respectively managed so as to cause tunnel Differential settlement is saved, leads to connector leak between tube coupling, influences tunnel operation security.
Summary of the invention
The purpose of the invention is to propose a kind of structure final settlement quantity algorithm for considering immersed tube tunnel special process, solution Certainly current immersed tube tunnel structure final quantity settlement calculation method does not consider the influence of immersed tube special process, calculated value and actual measurement number According to the shortcomings that there are relatively large deviations.
To achieve the goals above, present invention employs following technical solutions:
A kind of structure final settlement quantity algorithm considering immersed tube tunnel special process, comprising the following steps:
Step 1: determine that base form influences COEFFICIENT K1
Step 2: determine the rigidity of structure and connector (containing with secretly bury a section connector) influence COEFFICIENT K2
Step 3: the sand bedding course settling amount S for the influences that consider backbreak, back-silt etc. is calculated1
Step 4: it calculates and considers to excavate the original settlement of foundation S for loosening and springing back under sand bedding course2
Step 5: final precipitation capacity is calculated:
S=k1k2(S1+S2)。
Preferably, base form influences COEFFICIENT K in the step 11General desirable 0.85.
Preferably, COEFFICIENT K is influenced in the step 22Value between 0.8~1.2, to tunnel profile intermediate tube Pipeline section can take large values at section and slope paddy, for secretly bury structure and connect pipeline section and get the small value in tunnel profile top of a hill pipeline section. Preferably, sand bedding course settling amount S in the step 31Calculation method:
P0For additional stress at the top of sand bedding course, tunnel buoyancy is subtracted for the sum of tunnel structure self weight and top earthing pressure, Unit kN/m2
H1For bedding design thickness, unit m;
A is thickness of backbreaking, horizontal according to equipment situation and construction technology, can use 0.5m~1m, equipment is superior, construction technology Height can get the small value, otherwise can take large values;
K3Coefficient is influenced to back-silt, sand bedding course is comprehensively considered, excavates foundation trench geologic(al) factor and the comprehensive determination of hydrologic condition, one As value 0.6~1.0;
EΨFor the sand bedding course deformation modulus for considering construction technology, filling sand pressure, the influence factors such as inland river water flow, units MPa, It can use 10MPa when primary Calculation, the later period can adjust according to test data;
Preferably, original settlement of foundation S in the step 42Calculation method:
H2For foundation calculation thickness, can be determined according to " Code for design of building (GB5007) ";
ESFor original ground weighted comprehensive deformation modulus, units MPa, calculation method is each soil layer deformation modulus of original ground It multiplied by its thickness, then sums, then divided by the sum of each soil layer overall thickness;
P ' is to calculate additional stress, unit kN/m2, calculation method:
D is tunnel pipeline section cross section width;
α is stress spread angle, can be determined according to " Code for design of building (GB5007) ";
H ' be consider tunnel foundation trench macroscopic destruction springback influence original ground corrected Calculation thickness, calculation method:
Beneficial effects of the present invention:
Consider immersed tube tunnel process and structure feature, including backbreak under water, excavate loosening influence, back-silt, the rigidity of structure, A variety of key factors influential on final settlement such as connector, ground rebound, so that the calculated result of final settlement is more smart Really.
Specific embodiment
Embodiment one
A kind of structure final settlement quantity algorithm considering immersed tube tunnel special process, comprising the following steps:
(1) determine that base form influences coefficient k1, generally desirable 0.85;
(2) determine the rigidity of structure and connector (containing with secretly bury a section connector) influence coefficient k2, it is connect calculating and secretly burying structure Pipeline section and be in tunnel profile top of a hill pipeline section when, k2Value be 0.8;
(3) the sand bedding course settling amount S for the influences that consider backbreak, back-silt etc. is calculated1, S1Calculation method:
P0For additional stress at the top of sand bedding course, tunnel buoyancy is subtracted for the sum of tunnel structure self weight and top earthing pressure, Unit kN/m2
H1For bedding design thickness, unit m;
A is thickness of backbreaking, and horizontal according to equipment situation and construction technology, equipment is superior, and when construction technology is high, a value is taken 0.5m;
K3Coefficient is influenced to back-silt, sand bedding course is comprehensively considered, excavates foundation trench geologic(al) factor and the comprehensive determination of hydrologic condition, one As value 0.6~1.0;
EΨFor the sand bedding course deformation modulus for considering construction technology, filling sand pressure, the influence factors such as inland river water flow, units MPa, It can use 10MPa when primary Calculation, the later period can adjust according to test data;
(4) it calculates and considers to excavate the original settlement of foundation S for loosening and springing back under sand bedding course2, S2Calculation method:
H2For foundation calculation thickness, can be determined according to " Code for design of building (GB5007) ";
ESFor original ground weighted comprehensive deformation modulus, units MPa, calculation method is each soil layer deformation modulus of original ground It multiplied by its thickness, then sums, then divided by the sum of each soil layer overall thickness;
P ' is to calculate additional stress, unit kN/m2, calculation method:
D is tunnel pipeline section cross section width;
α is stress spread angle, can be determined according to " Code for design of building (GB5007) ";
H ' be consider tunnel foundation trench macroscopic destruction springback influence original ground corrected Calculation thickness, calculation method:
(5) final precipitation capacity is calculated:
S=k1k2(S1+S2)
Embodiment two
A kind of structure final settlement quantity algorithm considering immersed tube tunnel special process, comprising the following steps:
(1) determine that base form influences coefficient k1, generally desirable 0.85;
(2) determine the rigidity of structure and connector (containing with secretly bury a section connector) influence coefficient k2, calculating among tunnel profile At pipeline section and slope paddy when pipeline section, k2Value be 1.2;
(3) the sand bedding course settling amount S for the influences that consider backbreak, back-silt etc. is calculated1, S1Calculation method:
P0For additional stress at the top of sand bedding course, tunnel buoyancy is subtracted for the sum of tunnel structure self weight and top earthing pressure, Unit kN/m2
H1For bedding design thickness, unit m;
A is thickness of backbreaking, and horizontal according to equipment situation and construction technology, equipment is general, and when construction technology is low, a value takes 1m;
K3Coefficient is influenced to back-silt, sand bedding course is comprehensively considered, excavates foundation trench geologic(al) factor and the comprehensive determination of hydrologic condition, one As value 0.6~1.0;
EΨFor the sand bedding course deformation modulus for considering construction technology, filling sand pressure, the influence factors such as inland river water flow, units MPa, It can use 10MPa when primary Calculation, the later period can adjust according to test data;
(6) it calculates and considers to excavate the original settlement of foundation S for loosening and springing back under sand bedding course2, S2Calculation method:
H2For foundation calculation thickness, can be determined according to " Code for design of building (GB5007) ";
ESFor original ground weighted comprehensive deformation modulus, units MPa, calculation method is each soil layer deformation modulus of original ground It multiplied by its thickness, then sums, then divided by the sum of each soil layer overall thickness;
P ' is to calculate additional stress, unit kN/m2, calculation method:
D is tunnel pipeline section cross section width;
α is stress spread angle, can be determined according to " Code for design of building (GB5007) ";
H ' be consider tunnel foundation trench macroscopic destruction springback influence original ground corrected Calculation thickness, calculation method:
(7) final precipitation capacity is calculated:
S=k1k2(S1+S2)。
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.

Claims (5)

1. it is a kind of consider immersed tube tunnel special process structure final settlement quantity algorithm, which is characterized in that the algorithm include with Lower step:
Step 1: determine that base form influences COEFFICIENT K1
Step 2: determine the rigidity of structure and connector (containing with secretly bury a section connector) influence COEFFICIENT K2
Step 3: the sand bedding course settling amount S for the influences that consider backbreak, back-silt etc. is calculated1
Step 4: it calculates and considers to excavate the original settlement of foundation S for loosening and springing back under sand bedding course2
Step 5: final precipitation capacity is calculated:
S=k1k2(S1+S2)。
2. a kind of structure final settlement quantity algorithm for considering immersed tube tunnel special process according to claim 1, feature It is, base form influences COEFFICIENT K in the step 11General desirable 0.85.
3. a kind of structure final settlement quantity algorithm for considering immersed tube tunnel special process according to claim 1, feature It is, influences COEFFICIENT K in the step 22Value between 0.8~1.2.
4. a kind of structure final settlement quantity algorithm for considering immersed tube tunnel special process according to claim 1, feature It is, sand bedding course settling amount S in the step 31Calculation method:
5. a kind of structure final settlement quantity algorithm for considering immersed tube tunnel special process according to claim 1, feature It is, original settlement of foundation S in the step 42Calculation method:
CN201910732127.5A 2019-08-09 2019-08-09 Structure final settlement method considering immersed tube tunnel special process Active CN110489840B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910732127.5A CN110489840B (en) 2019-08-09 2019-08-09 Structure final settlement method considering immersed tube tunnel special process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910732127.5A CN110489840B (en) 2019-08-09 2019-08-09 Structure final settlement method considering immersed tube tunnel special process

Publications (2)

Publication Number Publication Date
CN110489840A true CN110489840A (en) 2019-11-22
CN110489840B CN110489840B (en) 2020-05-22

Family

ID=68550244

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910732127.5A Active CN110489840B (en) 2019-08-09 2019-08-09 Structure final settlement method considering immersed tube tunnel special process

Country Status (1)

Country Link
CN (1) CN110489840B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111581696A (en) * 2020-04-23 2020-08-25 中铁(天津)隧道工程勘察设计有限公司 Method for calculating safety coefficient of extra-large cross-chamber supporting structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07197481A (en) * 1993-12-28 1995-08-01 Sumitomo Rubber Ind Ltd Cut-off structure of immersed tunnel and secondary cut-off rubber for immersed tunnel using the cut-off structure
CN104567710A (en) * 2015-01-23 2015-04-29 浙江大学城市学院 Immersed tube tunnel deformation monitoring and stress analyzing system and application method and functions of immersed tube tunnel deformation monitoring and stress analyzing system
CN106649931A (en) * 2016-09-26 2017-05-10 浙江大学城市学院 Calculation method for post-construction ground surface settlement of rectangular jacking pipe tunnel construction
CN107784193A (en) * 2017-10-20 2018-03-09 西安市地下铁道有限责任公司 The computational methods of existing line stratum settlement amount are worn under single bore tunnel work progress
CN108694286A (en) * 2018-05-25 2018-10-23 中铁第四勘察设计院集团有限公司 A kind of soft soil roadbed settlement after construction computational methods

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07197481A (en) * 1993-12-28 1995-08-01 Sumitomo Rubber Ind Ltd Cut-off structure of immersed tunnel and secondary cut-off rubber for immersed tunnel using the cut-off structure
CN104567710A (en) * 2015-01-23 2015-04-29 浙江大学城市学院 Immersed tube tunnel deformation monitoring and stress analyzing system and application method and functions of immersed tube tunnel deformation monitoring and stress analyzing system
CN106649931A (en) * 2016-09-26 2017-05-10 浙江大学城市学院 Calculation method for post-construction ground surface settlement of rectangular jacking pipe tunnel construction
CN107784193A (en) * 2017-10-20 2018-03-09 西安市地下铁道有限责任公司 The computational methods of existing line stratum settlement amount are worn under single bore tunnel work progress
CN108694286A (en) * 2018-05-25 2018-10-23 中铁第四勘察设计院集团有限公司 A kind of soft soil roadbed settlement after construction computational methods

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
WEI, G 等: "Analysis of Settlement Control Measures in Immersed Tunnel", 《APPLIED MECHANICS AND MATERIALS》 *
岳夏冰: "外海大回淤沉管隧道软基沉降特征与控制计算研究", 《中国博士学位论文全文数据库 工程科技Ⅱ辑》 *
邵俊江 等: "潮汐荷载引起沉管隧道沉降计算方法", 《同济大学学报(自然科学版)》 *
魏纲 等: "沉管隧道竖向不均匀沉降的计算方法及分布研究", 《现代隧道技术》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111581696A (en) * 2020-04-23 2020-08-25 中铁(天津)隧道工程勘察设计有限公司 Method for calculating safety coefficient of extra-large cross-chamber supporting structure
CN111581696B (en) * 2020-04-23 2022-11-22 中铁(天津)隧道工程勘察设计有限公司 Method for calculating safety coefficient of extra-large cross-chamber supporting structure

Also Published As

Publication number Publication date
CN110489840B (en) 2020-05-22

Similar Documents

Publication Publication Date Title
CN110174506B (en) Method for estimating organic carbon in soil in karst region
CN103122635B (en) Foundation pit confined water resistant system and uprush stability judging method thereof
WO2021164432A1 (en) Method for improving anti-sliding and anti-overturning safety of existing balanced-weight retaining wall
JP2014101661A (en) Groundwater level raising system, and groundwater level raising method
Yasuda et al. New project to prevent liquefaction-induced damage in a wide existing residential area by lowering the ground water table
CN207143981U (en) 3rd is rich water half diagenesis Sandstone Section Metro station excavation discharge structure
CN113742826B (en) Active anti-floating design method based on anti-floating variable water level
CN110489840A (en) A kind of structure final settlement quantity algorithm considering immersed tube tunnel special process
CN112417550A (en) Simplified calculation method for vertical bearing capacity of gravel pile
CN107326919A (en) A kind of open caisson end heavy stage deviation-rectifying system and its application method
CN102322078A (en) Method for calculating and processing inrushing destruction of excavation and depressurization coupling effect of foundation pit with confined water
CN111274638B (en) Method for improving anti-overturning safety of existing balance weight retaining wall
CN114809125B (en) Method for predicting anti-tilting stability of steel cylinder
CN116796396A (en) Analysis method for deformation of underlying tunnel caused by foundation pit excavation and precipitation
CN113221233B (en) Composite soil layer shield tunnel cross section design method and shield tunnel
CN113240274B (en) Plain area groundwater exploitation amount evaluation method based on reasonable ecological water level
CN113609547B (en) Building indoor terrace elevation calculation method based on planning and design points
CN109024711A (en) Underground structure anti-floating system and its construction method
CN108049418A (en) Underground parking controls construction method with the Resistant heave of ultra-deep open caisson
CN106760722B (en) Without pile foundation single layer underground garage anti-floating construction method
CN107038291B (en) Method for calculating pressure of vertical soil on top of high-fill culvert
CN108133108B (en) Method for predicting influence of confined water precipitation on building settlement
CN105917777A (en) Optimal filling thickness control method for coal gangue
CN111636454A (en) Complete well water surface design method for controlling underground structure settlement through confined water stratum
CN117493754B (en) Comprehensive determination method for anti-floating fortification water level

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 36 Zhonghuan West Road, pilot free trade zone (Airport Economic Zone), Binhai New Area, Tianjin

Patentee after: CHINA RAILWAY LIUYUAN GROUP Co.,Ltd.

Patentee after: CHINA RAILWAY TUNNEL SURVEY & DESIGN INSTITUTE Co.,Ltd.

Address before: 36 Zhonghuan West Road, pilot free trade zone (Airport Economic Zone), Binhai New Area, Tianjin

Patentee before: CHINA RAILWAY LIUYUAN GROUP Co.,Ltd.

Patentee before: CHINA RAILWAY (TIANJIN) TUNNEL ENGINEERING SURVEY & DESIGN Co.,Ltd.