CN110485421A - A kind of pile crown quickly abolishes construction technology - Google Patents
A kind of pile crown quickly abolishes construction technology Download PDFInfo
- Publication number
- CN110485421A CN110485421A CN201910906403.5A CN201910906403A CN110485421A CN 110485421 A CN110485421 A CN 110485421A CN 201910906403 A CN201910906403 A CN 201910906403A CN 110485421 A CN110485421 A CN 110485421A
- Authority
- CN
- China
- Prior art keywords
- pile crown
- pile
- steel reinforcement
- reinforcement cage
- construction technology
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D9/00—Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
Abstract
The present invention relates to technical field of building construction, more particularly to a kind of pile crown quickly abolishes construction technology, by when steel reinforcement cage is bound, cancel the tie hoop at steel reinforcement cage pile crown position, and reinforcing rib is set in the top at steel reinforcement cage pile body position, and pearl cotton casing is arranged in each main reinforcement at steel reinforcement cage pile crown position, and the suitable for reading of casing and lower mouth are blocked so that concrete and pile crown main reinforcement is isolated, so that soap-free emulsion polymeization intensity between concrete and pile crown reinforcing bar, the construction period is abolished to substantially reduce pile crown, and a large amount of labour cost is omitted, both the construction speed of pile foundation engineering had been accelerated, also save the cost that pile crown abolishes construction, with very strong practicability.
Description
Technical field
The present invention relates to technical field of building construction more particularly to a kind of pile crown quickly to abolish construction technology.
Background technique
At present in pile foundation engineering construction, because it is contemplated that the bottom scarfing cinder of drilling construction space-time can not be thorough during pile foundation construction
Bottom, therefore squeezed out bottom residues, mud using concrete pressure difference using when concrete pouring construction, therefore pile crown 1m range coagulation
Native intensity is on the weak side, is unable to satisfy design requirement, needs to abolish pile crown after the completion of pile foundation construction.Pile crown is abolished in tradition and is applied
Work frequently with manually abolish entirely with ring cutting abolish construction two kinds of techniques, but no matter use the equal labor intensive amount of which kind of construction technology
Greatly, construction speed is slow, and to pile crown reinforcing bar well damage, these are all that those skilled in the art do not expect to see.
Summary of the invention
In view of the above problems, the invention discloses a kind of pile crowns quickly to abolish construction technology, wherein including as follows
Step:
Step S1, banding steel cage are cancelled the tie hoop at steel reinforcement cage pile crown position, and are carried out to steel reinforcement cage pile crown position
Processing;
Wherein, the step of handling steel reinforcement cage pile crown position includes: that the top setting in steel reinforcement cage pile body position adds
Strengthening tendons, and pearl cotton casing is arranged in each main reinforcement at steel reinforcement cage pile crown position, and by the suitable for reading of pearl cotton casing and
Lower mouth is blocked;
Step S2 installs steel reinforcement cage after the examination of pile foundation pore-forming in Yu Suoshu pile foundation pore-forming;
Step S3 installs conduit, in casting concrete in pile foundation pore-forming;
Step S4, after pile concrete solidification after, the pile crown surrounding earthwork is dug out, measure and identify need cut a stake position;
Step S5 cuts steel reinforcement cage using ring cutting method along mark;
Step S4 applies horizontal force to pile crown using digging machine, pile crown is separated with pile body.
Above-mentioned pile crown quickly abolishes construction technology, wherein in the step S1, using foaming agent to pearl cotton casing
Suitable for reading and lower mouth blocked.
Above-mentioned pile crown quickly abolishes construction technology, wherein in the step S1, the pearl cotton casing inner diameter is than master
Big 3~the 5mm of the outer diameter of muscle.
Above-mentioned pile crown quickly abolishes construction technology, wherein in the step S1, is consolidated pearl cotton casing using bandage
It is scheduled in main reinforcement.
Above-mentioned pile crown quickly abolishes construction technology, wherein the bandage is plastics bandage.
Above-mentioned pile crown quickly abolishes construction technology, wherein in the step S5, depth of cut is 18~22mm.
Foregoing invention is with the following advantages or beneficial effects:
The invention discloses a kind of pile crowns quickly to abolish construction technology, by cancelling steel reinforcement cage stake when steel reinforcement cage is bound
The tie hoop of head position, and reinforcing rib, and each master at steel reinforcement cage pile crown position are set in the top at steel reinforcement cage pile body position
It is arranged pearl cotton casing on muscle, and the suitable for reading of casing and lower mouth are blocked so that concrete and pile crown main reinforcement is isolated, makes
Soap-free emulsion polymeization intensity between concrete and pile crown reinforcing bar is obtained, to substantially reduce abolishing the construction period for pile crown, and is omitted big
The labour cost of amount had both accelerated the construction speed of pile foundation engineering, also saved the cost that pile crown abolishes construction, had very strong reality
The property used.
Detailed description of the invention
Upon reading the detailed description of non-limiting embodiments with reference to the following drawings, the present invention and its feature, outer
Shape and advantage will become more apparent.Identical label indicates identical part in all the attached drawings.Not can according to than
Example draws attached drawing, it is preferred that emphasis is shows the gist of the present invention.
Fig. 1 is the flow chart that pile crown quickly abolishes construction technology in the embodiment of the present invention;
Fig. 2 is the top view of steel reinforcement cage in the embodiment of the present invention;
Fig. 3 is the top view that the steel reinforcement cage of pearl cotton casing is equipped in the embodiment of the present invention;
Fig. 4 is the cross-sectional view of steel reinforcement cage in the embodiment of the present invention;
Fig. 5 is the structural schematic diagram of the steel reinforcement cage during pile crown is abolished in the embodiment of the present invention.
Specific embodiment
The structure in the present invention is further described with specific embodiment with reference to the accompanying drawing, but not as this
The restriction of invention.
As shown in Figure 1, the invention discloses a kind of pile crowns quickly to abolish construction technology, specifically, the construction technology includes
Following steps:
Step S1, banding steel cage 1 cancel the tie hoop 5 at 1 pile crown position 11 of steel reinforcement cage, and to 1 pile crown portion of steel reinforcement cage
Position 11 is handled.
Wherein, the step of handling 1 pile crown position 11 of steel reinforcement cage includes: in the top at 1 pile body position 12 of steel reinforcement cage
Reinforcing rib 3 is set, and is arranged pearl cotton casing 4 in each main reinforcement 2 at 1 pile crown position 11 of steel reinforcement cage, and by pearl cotton casing 4
Suitable for reading and lower mouth blocked;So as to will between the main reinforcement 2 and concrete at 1 pile crown position 11 of steel reinforcement cage carry out every
From so that not having the main reinforcement 2 and concrete binding at pile crown position 11, in the step of subsequent pile crown is abolished so as to shorten stake
Head abolishes the construction period.
In the present embodiment, due to eliminating the spiral hoop at 1 pile crown position 11 of steel reinforcement cage in 1 process of binding of steel reinforcement cage
Muscle is only provided with tie hoop 5 on 1 pile body position 12 of steel reinforcement cage, therefore does not have spiral shell in the step of subsequent pile crown is abolished
It revolves stirrup and so as to shorten abolishing the construction period for pile crown, and has saved the material cost of steel reinforcement cage 1 with concrete binding, and
Reinforcing rib 3 is set by the top in 1 pile body position 12 of steel reinforcement cage, can solve due to eliminating 1 pile crown position 11 of steel reinforcement cage
Tie hoop caused by the unstable problem in 1 pile crown position 11 of steel reinforcement cage.
In a preferred embodiment of the invention, the suitable for reading of casing 4 and lower mouth are blocked using foaming agent.
In a preferred embodiment of the invention, above-mentioned 4 internal diameter of casing is 3~5mm bigger than the outer diameter of main reinforcement 2.
In a preferred embodiment of the invention, casing 4 is fixed in main reinforcement 2 using plastics bandage.
Step S2, after the examination of pile foundation pore-forming 1, in installing above-mentioned steel reinforcement cage 1 in pile foundation pore-forming 1;Form such as Fig. 2~4
Shown in structure.
Step S3 installs conduit, in casting concrete in pile foundation pore-forming 1.
Step S4, after pile concrete solidification after, the pile crown surrounding earthwork is dug out, measure and identify need cut a stake position.
Step S5 cuts steel reinforcement cage 1 using ring cutting method along mark, and depth of cut is 18~22mm.
Step S6 applies horizontal force to pile crown using digging machine, pile crown is separated with pile body;Due to eliminating reinforcing bar
The tie hoop at 1 pile crown position 11 of cage, and pearl cotton-padded covering is used between the main reinforcement 2 and concrete at 1 pile crown position 11 of steel reinforcement cage
Pipe 4 is isolated, therefore soap-free emulsion polymeization intensity between pile crown reinforcing bar and concrete, so being applied using digging machine to pile crown horizontal
Power can integrally push over pile crown along ring cutting gap, so that pile crown is separated with pile body, structure as shown in Figure 5.
It should be appreciated by those skilled in the art that those skilled in the art are combining the prior art and above-described embodiment can be with
Realize change case, this will not be repeated here.Such change case does not affect the essence of the present invention, and it will not be described here.
Presently preferred embodiments of the present invention is described above.It is to be appreciated that the invention is not limited to above-mentioned
Particular implementation, devices and structures not described in detail herein should be understood as gives reality with the common mode in this field
It applies;Anyone skilled in the art, without departing from the scope of the technical proposal of the invention, all using the disclosure above
Methods and technical content many possible changes and modifications are made to technical solution of the present invention, or be revised as equivalent variations etc.
Embodiment is imitated, this is not affected the essence of the present invention.Therefore, anything that does not depart from the technical scheme of the invention, foundation
Technical spirit of the invention any simple modifications, equivalents, and modifications made to the above embodiment, still fall within the present invention
In the range of technical solution protection.
Claims (6)
1. a kind of pile crown quickly abolishes construction technology, which comprises the steps of:
Step S1, banding steel cage, cancel steel reinforcement cage pile crown position tie hoop, and to steel reinforcement cage pile crown position at
Reason;
Wherein, the step of handling steel reinforcement cage pile crown position includes: that reinforcing rib is arranged in the top at steel reinforcement cage pile body position,
And pearl cotton casing is arranged in each main reinforcement at steel reinforcement cage pile crown position, and the suitable for reading of pearl cotton casing and lower mouth is equal
It is blocked;
Step S2 installs steel reinforcement cage after the examination of pile foundation pore-forming in Yu Suoshu pile foundation pore-forming;
Step S3 installs conduit, in casting concrete in pile foundation pore-forming;
Step S4, after pile concrete solidification after, the pile crown surrounding earthwork is dug out, measure and identify need cut a stake position;
Step S5 cuts steel reinforcement cage using ring cutting method along mark;
Step S4 applies horizontal force to pile crown using digging machine, pile crown is separated with pile body.
2. pile crown as described in claim 1 quickly abolishes construction technology, which is characterized in that in the step S1, using hair
Infusion blocks the suitable for reading of pearl cotton casing and lower mouth.
3. pile crown as described in claim 1 quickly abolishes construction technology, which is characterized in that in the step S1, the treasure
Pearl cotton-padded covering bore is 3~5mm bigger than the outer diameter of main reinforcement.
4. pile crown as described in claim 1 quickly abolishes construction technology, which is characterized in that in the step S1, using tying up
Pearl cotton casing is fixed in main reinforcement by band.
5. pile crown as claimed in claim 4 quickly abolishes construction technology, which is characterized in that the bandage is plastics bandage.
6. pile crown as described in claim 1 quickly abolishes construction technology, which is characterized in that in the step S5, cutting is deep
Degree is 18~22mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910906403.5A CN110485421A (en) | 2019-09-24 | 2019-09-24 | A kind of pile crown quickly abolishes construction technology |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910906403.5A CN110485421A (en) | 2019-09-24 | 2019-09-24 | A kind of pile crown quickly abolishes construction technology |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110485421A true CN110485421A (en) | 2019-11-22 |
Family
ID=68559240
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910906403.5A Pending CN110485421A (en) | 2019-09-24 | 2019-09-24 | A kind of pile crown quickly abolishes construction technology |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110485421A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111424663A (en) * | 2020-03-26 | 2020-07-17 | 中电建十一局工程有限公司 | Environment-friendly and efficient pile head breaking method |
CN114875912A (en) * | 2022-05-29 | 2022-08-09 | 中国五冶集团有限公司 | Reinforcing steel bar protection method for hydraulic pile breaking head |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104631460A (en) * | 2015-01-15 | 2015-05-20 | 中铁十局集团建筑工程有限公司 | Girdling splitting type integral pile breaking method |
CN207092073U (en) * | 2017-08-07 | 2018-03-13 | 中国建筑西南勘察设计研究院有限公司 | A kind of protection sleeve pipe of pile crown steel reinforcement cage cage bar |
CN108086306A (en) * | 2017-11-20 | 2018-05-29 | 浙江省地矿建设有限公司 | A kind of pile crown concrete construction and cut method |
CN109024597A (en) * | 2018-07-18 | 2018-12-18 | 中铁城建集团第三工程有限公司 | It is a kind of to accelerate the casing and its construction method that pile crown is abolished |
-
2019
- 2019-09-24 CN CN201910906403.5A patent/CN110485421A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104631460A (en) * | 2015-01-15 | 2015-05-20 | 中铁十局集团建筑工程有限公司 | Girdling splitting type integral pile breaking method |
CN207092073U (en) * | 2017-08-07 | 2018-03-13 | 中国建筑西南勘察设计研究院有限公司 | A kind of protection sleeve pipe of pile crown steel reinforcement cage cage bar |
CN108086306A (en) * | 2017-11-20 | 2018-05-29 | 浙江省地矿建设有限公司 | A kind of pile crown concrete construction and cut method |
CN109024597A (en) * | 2018-07-18 | 2018-12-18 | 中铁城建集团第三工程有限公司 | It is a kind of to accelerate the casing and its construction method that pile crown is abolished |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111424663A (en) * | 2020-03-26 | 2020-07-17 | 中电建十一局工程有限公司 | Environment-friendly and efficient pile head breaking method |
CN114875912A (en) * | 2022-05-29 | 2022-08-09 | 中国五冶集团有限公司 | Reinforcing steel bar protection method for hydraulic pile breaking head |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110485421A (en) | A kind of pile crown quickly abolishes construction technology | |
CN106400802B (en) | A kind of drilled pile pile crown is pre-buried to exempt from the whole quickly lifting method of ring cutting that drills | |
CN102926380A (en) | Bridge cast-in-place pile chiseling-free pile head and construction method thereof | |
CN204343285U (en) | A kind of pile foundation pile crown entirety abolishes structure | |
CN205225271U (en) | Shield constructs portal collar tie beam structure suitable for shield constructs end not to be had with solid | |
CN109853566A (en) | A kind of filling pile head restructuring bankrupt and device using high compression swelling | |
JP6284255B1 (en) | Pile cap and pile drawing method | |
CN106958245A (en) | The quick structure and method for abolishing concrete pile head | |
CN108005060A (en) | Filling pile head reinforcing bar protective device and its construction method | |
CN108442365A (en) | A kind of anti-clogging strengthening water penetration pile and construction method | |
CN104343115A (en) | Structure and method for integrally breaking pile head of pile foundation | |
CN106968251A (en) | A kind of concrete filling pile head abolishes device and its construction method | |
CN206859222U (en) | The quick structure for abolishing concrete pile head | |
JP5311453B2 (en) | Ground reinforcement method | |
CN107059909A (en) | A kind of bridge foundation and substructure construction method | |
CN212079326U (en) | Embedded grouting pipe for tunnel door ring beam of subway station | |
CN108035342A (en) | Filling pile head construction method | |
JP2009174302A (en) | Pile head treating method | |
JPS6047119A (en) | Vibration and noise-free breaking of head of cast-in-place pile | |
CN207436063U (en) | Friction pile churning driven fast pore-creating edger | |
CN202899122U (en) | Bridge cast-in-place pile non-chisel pile head | |
CN107460873B (en) | Manual digging pile construction method | |
JP5790091B2 (en) | Construction method of underground wall and method for extracting core material of underground wall | |
CN207878453U (en) | Filling pile head reinforcing bar protective device | |
CN106192998A (en) | A kind of steel pile casting adds outer shield structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20191122 |