CN110469106A - A kind of high rise elevator well jacking formwork system and its construction method - Google Patents

A kind of high rise elevator well jacking formwork system and its construction method Download PDF

Info

Publication number
CN110469106A
CN110469106A CN201910866212.0A CN201910866212A CN110469106A CN 110469106 A CN110469106 A CN 110469106A CN 201910866212 A CN201910866212 A CN 201910866212A CN 110469106 A CN110469106 A CN 110469106A
Authority
CN
China
Prior art keywords
supporting mechanism
hydraulic
template
jacking
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910866212.0A
Other languages
Chinese (zh)
Inventor
魏百峰
赵涛
李�根
武文心
罗琦
葸克业
王永科
辛志磊
马宏锋
李亮兵
展学洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GANSU 7TH CONSTRUCTION GROUP CO Ltd
Original Assignee
GANSU 7TH CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GANSU 7TH CONSTRUCTION GROUP CO Ltd filed Critical GANSU 7TH CONSTRUCTION GROUP CO Ltd
Priority to CN201910866212.0A priority Critical patent/CN110469106A/en
Publication of CN110469106A publication Critical patent/CN110469106A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/22Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/22Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor
    • E04G11/24Construction of lifting jacks or climbing rods for sliding forms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/24Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
    • E04G3/246Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons following the inside contour of a building
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G2003/286Mobile scaffolds; Scaffolds with mobile platforms mobile vertically

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Types And Forms Of Lifts (AREA)

Abstract

本发明公开一种高层电梯井顶升模架体系及其施工方法,包括底部支撑机构、竖向顶升液压装置、上部支撑机构、模板支承装置和控制系统,底部支撑机构和上部支撑机构之间通过竖向顶升液压装置连接,竖向顶升液压装置用于顶升上部支撑机构及提升底部支撑机构,上部支撑机构的顶部设置模板支承装置,模板可拆卸的安装在模板支承装置外周,竖向顶升液压装置、上部支撑机构和底部支撑机构均与控制系统电联接。该高层电梯井顶升模架体系及其施工方法,模板安装、拆除时无需单独拆除,可随液压提升体统整体提升,达到了高层建筑电梯井道内剪力墙机械化、智能化施工,提高了其安全性与可靠性。

The invention discloses a high-rise elevator shaft jacking formwork system and a construction method thereof, including a bottom support mechanism, a vertical jacking hydraulic device, an upper support mechanism, a formwork support device and a control system, and a gap between the bottom support mechanism and the upper support mechanism. It is connected by a vertical lifting hydraulic device. The vertical lifting hydraulic device is used to lift the upper support mechanism and lift the bottom support mechanism. The top of the upper support mechanism is provided with a formwork support device. The formwork is detachably installed on the outer periphery of the formwork support device. The jacking hydraulic device, the upper support mechanism and the bottom support mechanism are all electrically connected with the control system. The high-rise elevator shaft jacking formwork system and its construction method do not need to be dismantled separately when the formwork is installed and removed, and can be lifted as a whole with the hydraulic lifting system, which achieves the mechanized and intelligent construction of the shear wall in the elevator shaft of a high-rise building, and improves its performance. Safety and reliability.

Description

一种高层电梯井顶升模架体系及其施工方法A high-rise elevator shaft jacking formwork system and its construction method

技术领域technical field

本发明涉及高层电梯井技术领域,特别是涉及一种高层电梯井顶升模架体系及其施工方法。The invention relates to the technical field of high-rise elevator shafts, in particular to a high-rise elevator shaft jacking formwork system and a construction method thereof.

背景技术Background technique

现有的高层建筑电梯井施工主要是使用钢管脚手架作为支承,木模板或钢模板作为模板体系。随着建筑的身高逐层进行施工脚手架的搭设。存在脚手架反复搭设、操作风险大、劳动成本较高、操作困难、机械化程度低风险高、高空坠物和高空打击高、模板重量大等一系列缺点。Existing high-rise building elevator shaft construction mainly uses steel pipe scaffolding as a support, and wood formwork or steel formwork as a formwork system. With the height of the building, the construction scaffolding is erected layer by layer. There are a series of shortcomings such as repeated scaffolding, high operational risk, high labor cost, difficult operation, low degree of mechanization, high risk, high falling objects and high impact, and heavy template weight.

发明内容Contents of the invention

本发明的目的是提供一种高层电梯井顶升模架体系及其施工方法,以解决上述现有技术存在的问题,模板安拆方便、快捷,可实现安全、快捷的施工理念,达到了高层建筑电梯井道内剪力墙机械化、智能化施工,提高了其安全性与可靠性。The object of the present invention is to provide a high-rise elevator shaft jacking formwork system and its construction method to solve the above-mentioned problems in the prior art. The mechanized and intelligent construction of the shear wall in the elevator shaft of the building improves its safety and reliability.

为实现上述目的,本发明提供了如下方案:本发明提供一种高层电梯井顶升模架体系,包括底部支撑机构、竖向顶升液压装置、上部支撑机构、模板支承装置和控制系统,所述底部支撑机构和上部支撑机构之间通过竖向顶升液压装置连接,所述竖向顶升液压装置用于顶升所述上部支撑机构及提升所述底部支撑机构,所述上部支撑机构的顶部设置所述模板支承装置,模板可拆卸的安装在所述模板支承装置外周,所述竖向顶升液压装置、上部支撑机构和底部支撑机构均与所述控制系统电联接。In order to achieve the above object, the present invention provides the following solution: The present invention provides a high-rise elevator shaft jacking formwork system, including a bottom support mechanism, a vertical jacking hydraulic device, an upper support mechanism, a formwork support device and a control system. The bottom support mechanism and the upper support mechanism are connected through a vertical jacking hydraulic device, and the vertical jacking hydraulic device is used to lift the upper support mechanism and lift the bottom support mechanism, and the upper support mechanism The formwork support device is arranged on the top, and the formwork is detachably installed on the outer periphery of the formwork support device. The vertical jacking hydraulic device, the upper support mechanism and the bottom support mechanism are all electrically connected to the control system.

进一步地,所述底部支撑机构包括底梁、底架、横梁和牛腿梁,所述底梁安装在所述底架的两端部,所述牛腿梁置于所述底梁内,液压系统的液压杆一端与所述牛腿梁通过螺栓固定连接,液压系统的液压缸筒与所述底梁螺栓固定连接;所述底架安装在所述横梁的固定槽内,所述横梁的顶部安装有机架,所述竖向顶升液压装置的底部与所述底部支撑机构固定连接。Further, the bottom support mechanism includes a bottom beam, a bottom frame, a cross beam and a corbel, the bottom beam is installed at both ends of the bottom frame, the corbels are placed in the bottom beam, and the hydraulic system One end of the hydraulic rod is fixedly connected to the corbel beam by bolts, and the hydraulic cylinder of the hydraulic system is fixedly connected to the bottom beam by bolts; the bottom frame is installed in the fixing groove of the beam, and the top of the beam is installed There is a frame, and the bottom of the vertical lifting hydraulic device is fixedly connected with the bottom supporting mechanism.

进一步地,所述液压系统的外部安装有小油缸盖板,所述液压系统的油管出口位于所述小油缸盖板上且面向所述横梁内侧。Further, a small oil cylinder cover is installed on the outside of the hydraulic system, and the oil pipe outlet of the hydraulic system is located on the small oil cylinder cover and faces the inside of the beam.

进一步地,所述上部支撑机构包括上梁、上架、横梁和牛腿梁,所述上梁安装在所述上架的两端部,所述牛腿梁置于所述上梁内,液压系统的液压杆一端与所述牛腿梁通过螺栓固定连接,液压系统的液压缸筒与所述上梁螺栓固定连接;所述上架安装在所述横梁的固定槽内,所述横梁的顶部安装有机架,所述竖向顶升液压装置的顶部与所述上部支撑机构固定连接。Further, the upper support mechanism includes an upper beam, an upper frame, a cross beam and a corbel, the upper beam is installed at both ends of the upper frame, the corbel is placed in the upper beam, and the hydraulic pressure of the hydraulic system One end of the rod is fixedly connected to the corbel beam by bolts, and the hydraulic cylinder of the hydraulic system is fixedly connected to the upper beam by bolts; the upper frame is installed in the fixing groove of the beam, and the top of the beam is installed with a frame , the top of the vertical jacking hydraulic device is fixedly connected with the upper supporting mechanism.

进一步地,所述液压系统的外部安装有小油缸盖板,所述液压系统的油管出口位于所述小油缸盖板上且面向所述横梁内侧。Further, a small oil cylinder cover is installed on the outside of the hydraulic system, and the oil pipe outlet of the hydraulic system is located on the small oil cylinder cover and faces the inside of the beam.

进一步地,所述底部支撑机构和上部支撑机构的机架上分别焊接有下导向座和上导向座,两个导向座上相对应的开设有导向孔,导向轴穿设在两个导向座上开设的导向孔内,所述导向轴的底部与所述下导向座连接为一整体。Further, a lower guide seat and an upper guide seat are respectively welded on the frame of the bottom support mechanism and the upper support mechanism, and guide holes are correspondingly opened on the two guide seats, and the guide shafts pass through the two guide seats In the opened guide hole, the bottom of the guide shaft is connected with the lower guide seat as a whole.

进一步地,所述上部支撑机构的上导向座上固定有所述模板支承装置,所述模板支承装置包括四个中心对称布置的立柱,四个所述立柱的顶部焊接有呈井字型搭建的工字钢,各工字钢的交叉点通过抱箍固定,且各工字钢的末端安装有模板滑动吊钩,所述模板滑动吊钩用于吊紧模板。Further, the template support device is fixed on the upper guide seat of the upper support mechanism, and the template support device includes four columns symmetrically arranged in the center, and the tops of the four columns are welded with a well-shaped structure. I-beams, the intersection points of each I-beam are fixed by hoops, and formwork sliding hooks are installed at the end of each I-beam, and the formwork sliding hooks are used to hang the formwork.

进一步地,四个所述立柱之间架设有操作平台,所述操作平台的四周设置防护翻板。Further, an operation platform is erected between the four columns, and protective flaps are arranged around the operation platform.

本发明还提供一种高层电梯井顶升模架体系的施工方法,应用于上述的高层电梯井顶升模架提下,包括以下步骤:The present invention also provides a construction method for a high-rise elevator shaft jacking formwork system, which is applied to the lifting of the above-mentioned high-rise elevator shaft jacking formwork system, including the following steps:

1)首先浇筑第一层电梯井主体结构,在墙面上预留两个方形孔作为牛腿梁的支承孔洞;1) First pour the main structure of the elevator shaft on the first floor, and reserve two square holes on the wall as the supporting holes for the corbel beam;

2)组装底部支撑机构,将底部支撑机构中的底梁、底架、牛腿梁和横梁进行组装固定;2) Assemble the bottom support mechanism, and assemble and fix the bottom beam, underframe, corbel beam and cross beam in the bottom support mechanism;

3)在组装好的底部支撑机构顶部通过螺栓固定安装竖向顶升液压装置;3) Install a vertical jacking hydraulic device on the top of the assembled bottom support mechanism through bolts;

4)组装上部支撑机构,将组装好的上部支撑机构安装在竖向顶升液压装置的顶部;4) Assemble the upper supporting mechanism, and install the assembled upper supporting mechanism on the top of the vertical jacking hydraulic device;

5)安装导向轴,在上部支撑机构和底部支撑机构上分别焊接导向座,然后将导向轴安装在两个导向座之间,并将导向轴的底部与下部导向座连接为一个整体;5) Install the guide shaft, weld the guide seat on the upper support mechanism and the bottom support mechanism respectively, then install the guide shaft between the two guide seats, and connect the bottom of the guide shaft with the lower guide seat as a whole;

6)安装模板支承装置,将模板支承装置安装在上部支撑机构上,然后再吊装模板;6) Install the formwork support device, install the formwork support device on the upper support mechanism, and then hoist the formwork;

7)安装电机和线路,安装液压系统的电机,添加液压油,并连接线路;安装后进行调试,使竖向顶升液压装置到位,调试合格后进行模板固定加强;7) Install the motor and circuit, install the motor of the hydraulic system, add hydraulic oil, and connect the circuit; debug after installation to make the vertical lifting hydraulic device in place, and fix and strengthen the formwork after the debugging is qualified;

8)浇筑本层混凝土后,将模板拆除,利用滑动吊钩将模板向内收缩,然后收缩上部支撑机构的四个牛腿梁,启动竖向顶升液压装置将上部支撑机构顶升到下一层,顶升到位后伸出牛腿梁;然后收缩底部支撑机构的四个牛腿梁,启动竖向顶升液压装置,将底部支撑机构整体提升一层后伸出牛腿梁;利用滑动吊钩将模板向外滑动,滑动到施工位置,将模板支承固定,进行主体施工;8) After pouring the concrete of this layer, remove the formwork, use the sliding hook to shrink the formwork inward, then shrink the four corbel beams of the upper support mechanism, and start the vertical jacking hydraulic device to lift the upper support mechanism to the next level. After the jacking is in place, extend the corbels; then shrink the four corbels of the bottom support mechanism, start the vertical jacking hydraulic device, lift the bottom support mechanism as a whole and extend the corbels; use the sliding crane The hook slides the formwork outward, slides to the construction position, supports and fixes the formwork, and carries out the main construction;

9)循环步骤8)直至完成整个建筑物电梯间主体施工后,进行拆除。9) Repeat step 8) until the construction of the main body of the elevator room of the entire building is completed, and then dismantle it.

本发明相对于现有技术取得了以下技术效果:Compared with the prior art, the present invention has achieved the following technical effects:

1、模板采用集成式铝合金新型组合模板,模架体系结构轻量化,模板拼缝少,轻质高强,砼的观感质量高,可实现循环利用。1. The formwork adopts a new type of integrated aluminum alloy formwork. The formwork structure is lightweight, the formwork has fewer joints, light weight and high strength, and the appearance quality of concrete is high, which can realize recycling.

2、通过采用液压整体提升技术,使高层电梯井顶升模架体系整体提升,解决了传统脚手架搭拆复杂、模板安装不便、井道内垃圾不宜清除等问题,提高了文明施工形象。2. By adopting the hydraulic overall lifting technology, the lifting formwork system of the high-rise elevator shaft is lifted as a whole, which solves the problems of complex erection and disassembly of traditional scaffolding, inconvenient installation of formwork, and unsuitable removal of garbage in the shaft, and improves the image of civilized construction.

3、高层电梯井顶升模架体系配套安装专业防护装置及安全装置,实现上下牛腿梁互相自锁,保证高层电梯井顶升模架体系的稳定性。3. The high-rise elevator shaft jacking formwork system is equipped with professional protective devices and safety devices to realize the mutual self-locking of the upper and lower corbels and ensure the stability of the high-rise elevator shaft jacking formwork system.

4、高层电梯井顶升模架体系采用液压智能操作控制系统,可有效实现液压系统全自动控制,实现液压系统同步性,提高远距离传输的可靠性,保证砼质量和安全质量。4. The hydraulic intelligent operation control system is adopted in the lifting formwork system of the high-rise elevator shaft, which can effectively realize the automatic control of the hydraulic system, realize the synchronization of the hydraulic system, improve the reliability of long-distance transmission, and ensure the quality and safety of concrete.

附图说明Description of drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the following will briefly introduce the accompanying drawings required in the embodiments. Obviously, the accompanying drawings in the following description are only some of the present invention. Embodiments, for those of ordinary skill in the art, other drawings can also be obtained based on these drawings without any creative effort.

图1为高层电梯井提升模架体系整体结构示意图;Figure 1 is a schematic diagram of the overall structure of the high-rise elevator shaft hoisting formwork system;

图2为电梯井主体浇筑图;Fig. 2 is the pouring diagram of the main body of the elevator shaft;

图3为底部支撑机构的结构示意图一;Fig. 3 is a structural schematic diagram 1 of the bottom support mechanism;

图4为底部支撑机构的结构示意图二;Fig. 4 is a structural schematic diagram 2 of the bottom support mechanism;

图5为液压系统设置方式示意图;Fig. 5 is a schematic diagram of the hydraulic system setting method;

图6为底部支撑机构、竖向顶升液压装置以及上部支撑机构的位置设置示意图;Fig. 6 is a schematic diagram of the position setting of the bottom support mechanism, the vertical jacking hydraulic device and the upper support mechanism;

图7为导向轴安装位置示意图;Figure 7 is a schematic diagram of the installation position of the guide shaft;

图8为模板支承装置安装位置示意图;Figure 8 is a schematic diagram of the installation position of the template support device;

图9为模板支承装置结构组成图;Fig. 9 is a structural composition diagram of the formwork supporting device;

图10为高层电梯井顶升模架体系的状态一的剖视图;Fig. 10 is the sectional view of the state one of high-rise elevator shaft jacking formwork system;

图11为高层电梯井顶升模架体系的状态二的轴测图;Fig. 11 is the axonometric view of the state two of the high-rise elevator shaft jacking formwork system;

图12为高层电梯井顶升模架体系的状态二的剖视图;Fig. 12 is the sectional view of the state two of high-rise elevator shaft jacking formwork system;

其中,1底部支撑机构;11底梁;12底架;13牛腿梁;14横梁;15小油缸盖板;16连接法兰;17液压杆;18液压缸筒;19机架;2竖向顶升液压装置;3上部支撑机构;4模板支承装置;41立柱;42操作平台;43工字钢;44模板滑动吊钩;45抱箍;46防护翻板;5模板;6导向轴;7支承孔洞。Among them, 1 bottom support mechanism; 11 bottom beam; 12 bottom frame; 13 corbel beam; 14 beam; 15 small oil cylinder cover; 16 connecting flange; Jacking hydraulic device; 3 upper support mechanism; 4 template supporting device; 41 column; 42 operating platform; 43 I-beam; 44 template sliding hook; 45 hoop; 46 protective flap; 5 template; 6 guide shaft; Support holes.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

本发明的目的是提供一种高层电梯井顶升模架体系及其施工方法,以解决上述现有技术存在的问题,模板安拆方便、快捷,可实现安全、快捷的施工理念,达到了高层建筑电梯井道内剪力墙机械化、智能化施工,提高了其安全性与可靠性。The object of the present invention is to provide a high-rise elevator shaft jacking formwork system and its construction method to solve the above-mentioned problems in the prior art. The mechanized and intelligent construction of the shear wall in the elevator shaft of the building improves its safety and reliability.

为使本发明的上述目的、特征和优点能够更加明显易懂,下面结合附图和具体实施方式对本发明作进一步详细的说明。In order to make the above objects, features and advantages of the present invention more comprehensible, the present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments.

如图1-12所示,本发明提供一种高层电梯井顶升模架体系,包括底部支撑机构1、竖向顶升液压装置2、上部支撑机构3、模板支承装置4和控制系统,底部支撑机构1和上部支撑机构3之间通过竖向顶升液压装置2连接,竖向顶升液压装置2用于顶升上部支撑机构3及提升底部支撑机构1,模板5可拆卸的安装在模板支承装置4外周,竖向顶升液压装置2、上部支撑机构3和底部支撑机构1均与控制系统电联接。As shown in Figures 1-12, the present invention provides a high-rise elevator shaft jacking formwork system, including a bottom support mechanism 1, a vertical jacking hydraulic device 2, an upper support mechanism 3, a formwork support device 4 and a control system, the bottom The support mechanism 1 and the upper support mechanism 3 are connected by a vertical jacking hydraulic device 2. The vertical jacking hydraulic device 2 is used to lift the upper support mechanism 3 and the bottom support mechanism 1. The template 5 is detachably installed on the template The outer periphery of the support device 4, the vertical jacking hydraulic device 2, the upper support mechanism 3 and the bottom support mechanism 1 are all electrically connected with the control system.

底部支撑机构1包括底梁11、底架12、横梁14和牛腿梁13,底梁11安装在底架12的两端部,牛腿梁13置于底梁11内,液压系统的液压杆17一端与牛腿梁13通过螺栓固定连接,液压系统的液压缸筒18与底梁11螺栓固定连接;底架12安装在横梁14的固定槽内,横梁14的顶部安装有机架19,竖向顶升液压装置2的底部与底部支撑机构1固定连接;当液压杆17驱动牛腿梁13外伸时,牛腿梁13卡在电梯井主体的支承孔洞7中,实现底部支撑机构1的定位,上部支撑机构3与底部支撑机构1的工作原理相同。液压系统的外部安装有小油缸盖板15,液压系统的油管出口位于小油缸盖板15上且面向横梁14内侧。上部支撑机构3与底部支撑机构1的结构组成一致。Bottom support mechanism 1 includes bottom beam 11, bottom frame 12, crossbeam 14 and corbel 13, bottom beam 11 is installed on the two ends of bottom frame 12, corbel 13 is placed in bottom beam 11, hydraulic pressure rod 17 of hydraulic system One end is fixedly connected with the corbel beam 13 by bolts, and the hydraulic cylinder 18 of the hydraulic system is fixedly connected with the bottom beam 11 by bolts; The bottom of the jacking hydraulic device 2 is fixedly connected with the bottom support mechanism 1; when the hydraulic rod 17 drives the corbel beam 13 to extend outward, the corbel beam 13 is stuck in the support hole 7 of the main body of the elevator shaft to realize the positioning of the bottom support mechanism 1 , the upper support mechanism 3 and the bottom support mechanism 1 have the same working principle. The outside of the hydraulic system is equipped with a small oil cylinder cover plate 15, and the oil pipe outlet of the hydraulic system is located on the small oil cylinder cover plate 15 and faces the inside of the crossbeam 14. The upper support mechanism 3 has the same structure as the bottom support mechanism 1 .

底部支撑机构1和上部支撑机构3的机架19上分别焊接有下导向座和上导向座,两个导向座上相对应的开设有导向孔,导向轴6穿设在两个导向座上开设的导向孔内,导向轴6的底部与下导向座连接为一整体。The bottom support mechanism 1 and the frame 19 of the upper support mechanism 3 are respectively welded with a lower guide seat and an upper guide seat. The two guide seats are correspondingly provided with guide holes, and the guide shaft 6 is set on the two guide seats. In the guide hole, the bottom of the guide shaft 6 is connected as a whole with the lower guide seat.

上部支撑机构3的上导向座上固定有模板支承装置4,模板支承装置4包括四个中心对称布置的立柱41,四个立柱41的顶部焊接有呈井字型搭建的工字钢43,各工字钢43的交叉点通过抱箍45固定,且各工字钢43的末端安装有模板滑动吊钩44,模板滑动吊钩44用于吊紧模板5。四个立柱41之间架设有操作平台42,操作平台42的四周设置防护翻板46。A formwork supporting device 4 is fixed on the upper guide seat of the upper supporting mechanism 3, and the formwork supporting device 4 includes four columns 41 arranged symmetrically in the center. The intersection point of I-beam 43 is fixed by hoop 45, and the end of each I-beam 43 is equipped with template sliding hook 44, and template sliding hook 44 is used for hanging template 5 tightly. An operating platform 42 is erected between the four uprights 41 , and protective flaps 46 are arranged around the operating platform 42 .

该高层电梯井顶升模架体系的工作原理为:通过将液压提升系统、智能控制系统、模板体系、防护装置灵活的连接为一个整体。高层电梯井顶升模架体系随建筑物的施工逐层进行爬升,当模板支承层混凝土浇筑完毕后,拆除模板5,收缩上部4个牛腿梁13,收缩完毕后,启动竖向顶升油缸,顶升到下一层,顶升到位后,伸出牛腿梁13;然后,收缩下部4个牛腿梁13,收缩完毕后,启动竖向顶升油缸,将下部整体提升一层,提升到位后伸出牛腿梁13,重新支承模板。如此反复进行操作,完成整个建筑物电梯井主体施工后,进行拆除。The working principle of the high-rise elevator shaft jacking formwork system is as follows: through the flexible connection of hydraulic lifting system, intelligent control system, formwork system and protective device as a whole. The high-rise elevator shaft jacking formwork system climbs up floor by floor with the construction of the building. After the formwork supporting layer concrete is poured, the formwork 5 is removed, and the upper four corbels 13 are contracted. After the contraction is completed, the vertical jacking cylinder is activated. , jacking up to the next floor, after the jacking is in place, stretch out the corbels 13; then, contract the four corbels 13 in the lower part, after the contraction is completed, start the vertical jacking oil cylinder, lift the lower part as a whole, and lift Stretch corbel beam 13 after putting in place, support formwork again. The operation is repeated in this way, and after the construction of the main body of the elevator shaft of the whole building is completed, the demolition is carried out.

进一步地,该高层电梯井顶升模架系统的施工方法如下:Further, the construction method of the high-rise elevator shaft jacking formwork system is as follows:

1)首先浇筑第一层电梯井主体结构,在墙面上预留2个300X300的方形孔,作为牛腿梁13的支承孔洞7,孔洞间间距为400mm。1) First pour the main structure of the elevator shaft on the first floor, reserve two 300X300 square holes on the wall as the supporting holes 7 of the corbel beam 13, and the distance between the holes is 400mm.

2)组装底部支承机构2) Assemble the bottom support mechanism

首先,将底梁11安装在底架12两端部,底梁11上的两个孔分别与底架12端部的两个孔相对应,采用销轴进行连接;然后,将牛腿梁13置于底梁11内,使用M30x80mm的螺栓与液压系统的液压杆17连接,使用M30x80mm的螺栓将液压系统的液压缸筒18与底梁11进行连接;其次,将小油缸盖板15安装在液压系统外部,作为保护装置,小油缸盖板15上的油管出口面向横梁14内侧;再次,将底架12安装在横梁14宽为180mm槽内,底架12中间的两个孔分别与横梁14的两个连接孔相对应,采用销轴将底梁11、底架12、小油缸盖板15连接在一起;最后,将机架19的四个连接段使用M16x100mm的螺栓分别与底架12上的连接段相连,形成一个完整的底部支承机构。First, the bottom beam 11 is installed on both ends of the bottom frame 12, and the two holes on the bottom beam 11 correspond to the two holes at the ends of the bottom frame 12 respectively. Connect the pin shaft; then, place the corbel beam 13 in the bottom beam 11, use M30x80mm bolts to connect with the hydraulic rod 17 of the hydraulic system, and use M30x80mm bolts to connect the hydraulic cylinder barrel 18 of the hydraulic system with the bottom beam 11 Secondly, the small oil cylinder cover plate 15 is installed on the outside of the hydraulic system, and as a protection device, the oil pipe outlet on the small oil cylinder cover plate 15 faces the inside of the crossbeam 14; again, the underframe 12 is installed in the crossbeam 14 wide and is 180mm in the groove. The two holes in the middle of the frame 12 are respectively corresponding to the two connection holes of the crossbeam 14. The pin shaft connects the bottom beam 11, the bottom frame 12, and the small oil cylinder cover plate 15 together; finally, the four connection sections of the frame 19 are respectively connected with the connection sections on the bottom frame 12 using M16x100mm bolts to form a complete Bottom support mechanism.

3)安装竖向顶升液压装置23) Install vertical jacking hydraulic device 2

安装三级竖向顶升液压装置,使用6个M16x30mm的螺栓将底部支承机构与三级竖向顶升液压装置底部连接,底部支撑机构1的横梁14中部设置有连接法兰16,竖向顶升液压装置2的底部与连接法兰16固定连接。Install the three-stage vertical jacking hydraulic device, use 6 M16x30mm bolts to connect the bottom support mechanism with the bottom of the three-stage vertical jacking hydraulic device, the middle part of the crossbeam 14 of the bottom support mechanism 1 is provided with a connecting flange 16, vertical jacking The bottom of the lifting hydraulic device 2 is fixedly connected with the connecting flange 16 .

4)组装、安装上部支承机构4) Assemble and install the upper supporting mechanism

首先,将上梁安装在底架12两端部,上梁上的两个孔分别与底架12端部的两个孔相对应,采用销轴进行连接;然后,将牛腿梁13置于上梁内,使用M30x80mm的螺栓与液压系统的液压杆17连接,使用M30x80mm的螺栓将液压系统的液压缸筒18与底梁11进行连接;其次,将小油缸盖板15安装在液压系统外部,作为保护装置,小油缸盖板15上的油管出口面向横梁14内侧;再次,将底架12安装在横梁14宽为180mm槽内,底架12中间的两个孔分别与横梁14的两个连接孔相对应,采用销轴将底梁11、底架12、小油缸盖板15连接在一起;最后,将机架19的四个连接段使用M16x100mm的螺栓分别与底架12上的连接段相连,形成一个完整的上部支承机构。使用6个M16x30mm的螺栓将上部支承机构与三级竖向顶升液压装置上部连接。First, the upper beam is installed on both ends of the chassis 12, and the two holes on the upper beam correspond to the two holes at the ends of the chassis 12 respectively. The pin shaft is connected; then, place the corbel beam 13 in the upper beam, use M30x80mm bolts to connect with the hydraulic rod 17 of the hydraulic system, and use M30x80mm bolts to connect the hydraulic cylinder barrel 18 of the hydraulic system with the bottom beam 11; Secondly, the small oil cylinder cover plate 15 is installed on the outside of the hydraulic system. As a protection device, the outlet of the oil pipe on the small oil cylinder cover plate 15 faces the inside of the crossbeam 14; again, the bottom frame 12 is installed in the 180mm groove of the crossbeam 14, and the bottom frame The two holes in the middle of 12 correspond to the two connecting holes of the beam 14 respectively. The pin shaft connects the bottom beam 11, the bottom frame 12, and the small oil cylinder cover plate 15 together; finally, the four connection sections of the frame 19 are respectively connected with the connection sections on the bottom frame 12 using M16x100mm bolts to form a complete Upper supporting mechanism. Use 6 M16x30mm bolts to connect the upper support mechanism with the upper part of the three-stage vertical jacking hydraulic device.

5)安装导向轴65) Install guide shaft 6

首先,将两个导向座分别焊接在上、下部支承机构上;然后,将导向轴6安装在上下导向座中,底部使用M16x200mm螺栓将导向轴6下部与下部导向座连接为一个整体。First, weld the two guide seats on the upper and lower supporting mechanisms respectively; then, install the guide shaft 6 in the upper and lower guide seats, and use M16x200mm bolts at the bottom to connect the lower part of the guide shaft 6 and the lower guide seat as a whole.

6)安装模板支承装置6) Install formwork support device

使用16个M16x30mm的螺栓,将模板支承装置4的4个立柱41分别与上部支承机构上预留的4个连接板连接。Use 16 M16x30mm bolts to connect the four columns 41 of the formwork supporting device 4 with the reserved four connecting plates on the upper supporting mechanism respectively.

7)安装模板57) Install Template 5

使用电动葫芦或手动葫芦、钢丝绳等一端与铝合金模板5上的吊钩进行固定,另一端使用M16x30mm的螺栓与模板5支承结构上的滑动吊钩进行连接。Use an electric hoist or manual hoist, wire rope, etc. to fix one end to the hook on the aluminum alloy formwork 5, and use M16x30mm bolts to connect the other end to the sliding hook on the support structure of the formwork 5.

8)安装电机及线路8) Install the motor and circuit

安装液压系统电机,添加46#液压油,并连接线路。Install the hydraulic system motor, add 46# hydraulic oil, and connect the line.

9)调试9) debugging

首次安装后进行调试,使液压装置到位,调试合格后进行模板5固定加强。After the first installation, carry out debugging to make the hydraulic device in place. After the debugging is qualified, the formwork 5 is fixed and strengthened.

10)浇筑本层混凝土,首先将模板5拆除,利用滑动吊钩将模板5向内收缩至最佳位置;然后,收缩上部4个牛腿梁13,收缩完毕后,启动竖向顶升油缸,顶升到下一层,顶升到位后,伸出牛腿梁13;其次,收缩收缩下部4个牛腿梁13,收缩完毕后,启动竖向顶升油缸,将下部整体提升一层,提升到位后伸出牛腿梁13,利用滑动吊钩将模板5向外滑动,滑动到施工位置,将模板5支承固定,进行主体施工。10) To pour the concrete of this layer, first remove the formwork 5, and use the sliding hook to shrink the formwork 5 inward to the best position; then, shrink the upper four corbels 13, and after the contraction is completed, start the vertical jacking cylinder, Jacking up to the next floor, after the jacking is in place, stretch out the corbels 13; secondly, contract the four corbels 13 in the lower part, and after the contraction is completed, start the vertical jacking cylinder to raise the lower part as a whole to lift After being put in place, stretch out the corbel beam 13, use the sliding hook to slide the formwork 5 outwards, slide to the construction position, support and fix the formwork 5, and carry out the main body construction.

11)重复步骤10),如此反复进行操作,完成整个建筑物电梯间主体施工后,进行拆除。11) Repeat step 10), so that the operation is repeated, and after the construction of the main body of the elevator room of the whole building is completed, the demolition is carried out.

本发明提出的高层电梯井顶升模架体系及其施工方法,通过将液压提升系统、智能控制系统、模板体系、防护装置灵活的连接为一个整体。模板安装、拆除时无需单独拆除,可随液压提升体统整体提升。高层电梯井顶升模架体系随建筑物的施工逐层进行爬升,爬升过程中稳定性强,模板5安拆方便、快捷,可实现安全、快捷的施工理念,达到了高层建筑电梯井道内剪力墙机械化、智能化施工,提高了其安全性与可靠性。The high-rise elevator shaft jacking formwork system and construction method proposed by the present invention are integrated into a whole by flexibly connecting a hydraulic lifting system, an intelligent control system, a formwork system, and a protective device. There is no need to dismantle the template separately when installing and removing it, and it can be lifted as a whole with the hydraulic lifting system. The high-rise elevator shaft jacking formwork system climbs up floor by floor with the construction of the building. The stability is strong during the climbing process. The mechanized and intelligent construction of the force wall improves its safety and reliability.

本发明中应用了具体个例对本发明的原理及实施方式进行了阐述,以上实施例的说明只是用于帮助理解本发明的方法及其核心思想;同时,对于本领域的一般技术人员,依据本发明的思想,在具体实施方式及应用范围上均会有改变之处。综上所述,本说明书内容不应理解为对本发明的限制。In the present invention, specific examples have been used to illustrate the principle and implementation of the present invention. The description of the above embodiments is only used to help understand the method and core idea of the present invention; meanwhile, for those of ordinary skill in the art, according to the present invention The idea of the invention will have changes in the specific implementation and scope of application. In summary, the contents of this specification should not be construed as limiting the present invention.

Claims (9)

1. a kind of high rise elevator well jacking formwork system, it is characterised in that: including bottom supporting mechanism, vertically jack hydraulic dress It sets, upper supporting mechanism, template supporting device and control system, passes through between the bottom supporting mechanism and upper supporting mechanism Vertical jacking hydraulic device connection, the vertical jacking hydraulic device is for jacking the upper supporting mechanism and promoting the bottom The template supporting device is arranged in portion's supporting mechanism, the top of the upper supporting mechanism, and template is detachably arranged in described Template supporting device periphery, the vertical jacking hydraulic device, upper supporting mechanism and bottom supporting mechanism with the control System electrically connects.
2. high rise elevator well jacking formwork system according to claim 1, it is characterised in that: the bottom supporting mechanism packet Bottom beam, chassis, crossbeam and bracket beam are included, the bottom beam is mounted on the both ends of the chassis, and the bracket beam is placed in the bottom In beam, hydraulic stem one end and the bracket beam of hydraulic system are bolted to connection, the hydraulic cylinder of hydraulic system and institute Bottom beam bolt is stated to be fixedly connected;The chassis is mounted in the fixing groove of the crossbeam, and organic frame is installed at the top of the crossbeam, The bottom of the vertical jacking hydraulic device is fixedly connected with the bottom supporting mechanism.
3. high rise elevator well jacking formwork system according to claim 2, it is characterised in that: the outside of the hydraulic system Small oil tank cover board is installed, the oil pipe outlet of the hydraulic system is located on the small oil tank cover board and towards in the crossbeam Side.
4. high rise elevator well jacking formwork system according to claim 1, it is characterised in that: the upper supporting mechanism packet Upper beam, restocking, crossbeam and bracket beam are included, the upper beam is mounted on the both ends of the restocking, and the bracket beam is placed on described In beam, hydraulic stem one end and the bracket beam of hydraulic system are bolted to connection, the hydraulic cylinder of hydraulic system and institute Beam bolt is stated to be fixedly connected;The restocking is mounted in the fixing groove of the crossbeam, and organic frame is installed at the top of the crossbeam, The top of the vertical jacking hydraulic device is fixedly connected with the upper supporting mechanism.
5. high rise elevator well jacking formwork system according to claim 4, it is characterised in that: the outside of the hydraulic system Small oil tank cover board is installed, the oil pipe outlet of the hydraulic system is located on the small oil tank cover board and towards in the crossbeam Side.
6. high rise elevator well jacking formwork system according to claim 1, it is characterised in that: the bottom supporting mechanism and Lower guide holder and upper guide holder are respectively welded in the rack of upper supporting mechanism, corresponding offer is led on two guide holders Xiang Kong, guiding axis are threaded through in the pilot hole opened up on two guide holders, and the bottom of the guiding axis and the lower guide holder connect It connects and is integral.
7. high rise elevator well jacking formwork system according to claim 6, it is characterised in that: the upper supporting mechanism The template supporting device is fixed on upper guide holder, the template supporting device includes four columns being centrosymmetrically arranged, The I-steel built in intersecting parallels is welded at the top of four columns, the crosspoint of each I-steel is fixed by anchor ear, and The end of each I-steel is equipped with template sliding suspension hook, and the template sliding suspension hook is for hanging tight template.
8. high rise elevator well jacking formwork system according to claim 7, it is characterised in that: a structure of an essay for four columns Equipped with operating platform, the surrounding setting protection turnover panel of the operating platform.
9. a kind of construction method of high rise elevator well jacking formwork system is applied to height of any of claims 1-8 Layer elevator jacking formwork is put, which comprises the following steps:
1) first layer elevator main structure is poured first, and support holes of two square holes as bracket beam are reserved on metope Hole;
2) bottom supporting mechanism is assembled, bottom beam, chassis, bracket beam and the crossbeam in the supporting mechanism of bottom are subjected to assembling fixation;
3) the vertical jacking hydraulic device of installation is bolted at the top of assembled bottom supporting mechanism;
4) upper supporting mechanism is assembled, assembled upper supporting mechanism is mounted on to the top of vertical jacking hydraulic device;
5) guiding axis is installed, guide holder is respectively welded in upper supporting mechanism and bottom supporting mechanism, then pacifies guiding axis An entirety is connected as between two guide holders, and by the bottom of guiding axis and lower part guide holder;
6) template supporting device is mounted in upper supporting mechanism by installation template supporting arrangement, then lifts template again;
7) motor and route are installed, the motor of hydraulic system is installed, adds hydraulic oil, and connection line;It is debugged after installation, Make vertically to jack hydraulic device in place, the fixed reinforcement of template is carried out after debugging is qualified;
8) after pouring this layer concrete, by form removable, using sliding suspension hook then template is shunk into upper support to contract Four bracket beams of mechanism start vertical jacking hydraulic device and jack upper supporting mechanism to next layer, jack and extend back in place Bracket beam out;Then four bracket beams for shrinking bottom supporting mechanism start vertical jacking hydraulic device, by bottom supporting mechanism Bracket beam is stretched out after whole one layer of promotion;Template is slid in and out using sliding suspension hook, construction location is slided into, by pattern board supporting It is fixed, carry out main body construction;
9) circulation step 8) until after completion whole building escalator main body construction, it is removed.
CN201910866212.0A 2019-09-09 2019-09-09 A kind of high rise elevator well jacking formwork system and its construction method Pending CN110469106A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910866212.0A CN110469106A (en) 2019-09-09 2019-09-09 A kind of high rise elevator well jacking formwork system and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910866212.0A CN110469106A (en) 2019-09-09 2019-09-09 A kind of high rise elevator well jacking formwork system and its construction method

Publications (1)

Publication Number Publication Date
CN110469106A true CN110469106A (en) 2019-11-19

Family

ID=68514072

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910866212.0A Pending CN110469106A (en) 2019-09-09 2019-09-09 A kind of high rise elevator well jacking formwork system and its construction method

Country Status (1)

Country Link
CN (1) CN110469106A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984555A (en) * 2019-11-25 2020-04-10 北京杏林伟业电梯工程有限公司 Scaffold for elevator well
CN113027167A (en) * 2021-03-19 2021-06-25 中建八局天津建设工程有限公司 Environment-friendly demolition method for high-rise building
US20210245997A1 (en) * 2020-02-12 2021-08-12 Kone Corporation Movable machine room, elevator arrangement and method for constructing elevator
CN113565311A (en) * 2021-08-09 2021-10-29 中建三局集团有限公司 Detachable steel structure scaffold for elevator shaft
CN113738065A (en) * 2021-09-09 2021-12-03 江苏省方正电梯有限公司 Integrated steel structure assembly type modularized elevator shaft
CN114412164A (en) * 2022-03-14 2022-04-29 安徽中嘉环保建材科技有限公司 Building composite aluminum template
CN114673344A (en) * 2022-04-22 2022-06-28 中化学路桥建设有限公司 Self-lifting construction method and construction device for internal mold of elevator shaft of building
CN115613841A (en) * 2022-10-24 2023-01-17 中国一冶集团有限公司 Socket joint formula derrick operation protector that can climb

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201635390U (en) * 2009-04-10 2010-11-17 刘东轩 Automatic formwork supporting machine for high-rise building elevator shaft construction
CN102661039A (en) * 2012-05-11 2012-09-12 上海建工集团股份有限公司 Drum frame supporting power built-in integrated jacking steel platform formwork system and construction method
CN102704676A (en) * 2012-05-30 2012-10-03 徐州徐液液压科技有限公司 Jacking formwork mechanism
CN204781338U (en) * 2015-05-29 2015-11-18 武汉凡肯智能装备有限公司 A but, novel pin -connected panel supporting box roof beam that is used for intelligent hydraulic pressure jacking die carrier
CN210636796U (en) * 2019-09-09 2020-05-29 甘肃第七建设集团股份有限公司 High-rise elevator shaft jacking formwork system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201635390U (en) * 2009-04-10 2010-11-17 刘东轩 Automatic formwork supporting machine for high-rise building elevator shaft construction
CN102661039A (en) * 2012-05-11 2012-09-12 上海建工集团股份有限公司 Drum frame supporting power built-in integrated jacking steel platform formwork system and construction method
CN102704676A (en) * 2012-05-30 2012-10-03 徐州徐液液压科技有限公司 Jacking formwork mechanism
CN204781338U (en) * 2015-05-29 2015-11-18 武汉凡肯智能装备有限公司 A but, novel pin -connected panel supporting box roof beam that is used for intelligent hydraulic pressure jacking die carrier
CN210636796U (en) * 2019-09-09 2020-05-29 甘肃第七建设集团股份有限公司 High-rise elevator shaft jacking formwork system

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110984555A (en) * 2019-11-25 2020-04-10 北京杏林伟业电梯工程有限公司 Scaffold for elevator well
US20210245997A1 (en) * 2020-02-12 2021-08-12 Kone Corporation Movable machine room, elevator arrangement and method for constructing elevator
US11731857B2 (en) * 2020-02-12 2023-08-22 Kone Corporation Movable machine room, elevator arrangement and method for constructing elevator
CN113027167A (en) * 2021-03-19 2021-06-25 中建八局天津建设工程有限公司 Environment-friendly demolition method for high-rise building
CN113565311A (en) * 2021-08-09 2021-10-29 中建三局集团有限公司 Detachable steel structure scaffold for elevator shaft
CN113565311B (en) * 2021-08-09 2022-08-02 中建三局集团有限公司 Detachable steel structure scaffold for elevator shaft
CN113738065A (en) * 2021-09-09 2021-12-03 江苏省方正电梯有限公司 Integrated steel structure assembly type modularized elevator shaft
CN114412164A (en) * 2022-03-14 2022-04-29 安徽中嘉环保建材科技有限公司 Building composite aluminum template
CN114673344A (en) * 2022-04-22 2022-06-28 中化学路桥建设有限公司 Self-lifting construction method and construction device for internal mold of elevator shaft of building
CN114673344B (en) * 2022-04-22 2022-12-02 中化学建设集团有限公司 Self-lifting construction method and construction device for internal mold of elevator shaft of building
CN115613841A (en) * 2022-10-24 2023-01-17 中国一冶集团有限公司 Socket joint formula derrick operation protector that can climb

Similar Documents

Publication Publication Date Title
CN110469106A (en) A kind of high rise elevator well jacking formwork system and its construction method
US12209425B2 (en) Method for entire removal of space truss and assistive support mechanism
CN206692235U (en) A kind of steel structure dome lifts by crane erecting device
CN102661039A (en) Drum frame supporting power built-in integrated jacking steel platform formwork system and construction method
CN204644884U (en) High pier over-form construction reinforced bar installs mobile stock
CN212689520U (en) Quick docking operation platform
CN210636796U (en) High-rise elevator shaft jacking formwork system
CN207048345U (en) Construction discharge platform device
CN107055367A (en) The central jack-up system of internally climbing tower crane
CN102767282A (en) Assembly-type high-formwork construction method for cantilever of oversized special-shaped conversion layer
CN116411517A (en) Concrete beam bracket-free integral lifting construction method
CN115788012A (en) Hydraulic climbing formwork integral climbing and sliding device and method suitable for inclined wall construction
CN106869479A (en) Bailey bracket sliding formwork system construction method
CN109944164A (en) Self-elevating hollow thin-wall pier roller die system and construction method thereof
CN201635390U (en) Automatic formwork supporting machine for high-rise building elevator shaft construction
CN111335172A (en) Movable pier column beam prestressed tension hanger construction platform and construction method
CN219031629U (en) Lifting equipment for indoor plate installation
CN108625800B (en) Multifunctional derrick for shaft construction
CN208122298U (en) A kind of whole formwork system for structure missing layer
CN117802883A (en) Cable tower cross brace and cross beam profile steel skeleton integrated construction method
CN113585860B (en) Method for assembling and disassembling double-arm holding pole
CN112279121A (en) Method for dismantling tower crane
CN216515179U (en) Movable trolley for mounting and dismounting bridge guardrail template
CN210620081U (en) Cantilever crane device suitable for dismantling external scaffold of assembled high-rise residence
CN1104704A (en) Method and apparatus for integrally self-lifting scaffold

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20191119