CN110439270A - A kind of post-cast strip exempts to tear support system construction method open - Google Patents

A kind of post-cast strip exempts to tear support system construction method open Download PDF

Info

Publication number
CN110439270A
CN110439270A CN201910728995.6A CN201910728995A CN110439270A CN 110439270 A CN110439270 A CN 110439270A CN 201910728995 A CN201910728995 A CN 201910728995A CN 110439270 A CN110439270 A CN 110439270A
Authority
CN
China
Prior art keywords
post
cast strip
adjustable
support
leger
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910728995.6A
Other languages
Chinese (zh)
Inventor
钟录平
臧言礼
张海堂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Shanghai Baoye Group Nanjing Construction Co Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Shanghai Baoye Group Nanjing Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd, Shanghai Baoye Group Nanjing Construction Co Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201910728995.6A priority Critical patent/CN110439270A/en
Publication of CN110439270A publication Critical patent/CN110439270A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/36Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for floors, ceilings, or roofs of plane or curved surfaces end formpanels for floor shutterings
    • E04G11/48Supporting structures for shutterings or frames for floors or roofs
    • E04G11/486Dropheads supporting the concrete after removal of the shuttering; Connecting means on beams specially adapted for dropheads
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G25/00Shores or struts; Chocks
    • E04G25/04Shores or struts; Chocks telescopic
    • E04G25/06Shores or struts; Chocks telescopic with parts held together by positive means
    • E04G25/065Shores or struts; Chocks telescopic with parts held together by positive means by a threaded nut

Abstract

Exempt to tear support system construction method open the invention discloses a kind of post-cast strip, the following steps are included: 1) carry out ground unwrapping wire snap the line according to support scaffolding plan layout drawing and post-cast strip position, first set up post-cast strip position independence support system, special complete is adjustable shores for setting at the top of independent support system central post, then sets up other position support systems of post-cast strip two sides;2) the common adjustable jack leger in first Construction Later Casting Zone two sides, then Construction Later Casting Zone position leger;3) continuous laying is taken in platform beam-slab template laying;4) scaffold and form removable are carried out;5) in adjustable shore elongated stress horizontal steel tube is installed on short sleeve;6) late poured band support and template are removed.This invention ensures that late poured band support is not torn open, is not loose, and does not influence the support and form removable in other regions, solves the drawbacks of existing rear pouring tape construction method.

Description

A kind of post-cast strip exempts to tear support system construction method open
Technical field
The present invention relates to the construction method of the support system in architectural engineering, specially a kind of post-cast strip exempts to tear support system open Construction method.
Background technique
Independence support system in post-cast strip takes separation design, i.e. alter-pouring strips mould plate and support and other beam-slab templates at present And support separation carries out beam-slab template and support system is removed, post-cast strip after concreting is completed and reaches dismounting intensity Position template and support system retain;When the concrete construction of post-cast strip, first by post-cast strip two sides beam slab using double-pole scaffold into The capable reinforcing that returns back to top;It returns back to top and removes post-cast strip position template after reinforcing, formwork-support retains, then post-cast strip joint surface is carried out Dabbing processing, and clean out;Then branch alter-pouring strips mould plate pours post-cast strip concrete, and it is strong to reach design to post-cast strip concrete Support and template are removed after degree.There are differences in stress with original support for this construction method that returns back to top, and often return back to top not in time, It easily causes structure cantilever force and generates cracking, meanwhile, the construction workload that returns back to top is big, costly.
Summary of the invention
Constructing present invention aim to address existing post-cast strip independence support system, cumbersome, support system is removed, return back to top band The structure come realizes that late poured band support system does not tear open, do not return back to top there may be the hidden danger in crack.
To solve the above problems, present invention employs following technical solutions: a kind of post-cast strip exempts to tear support system construction party open Method, it is characterised in that the following steps are included:
1) unwrapping wire snap the line in ground is carried out according to support scaffolding plan layout drawing and post-cast strip position, first sets up post-cast strip portion The independent support system in position, special complete is adjustable shores for setting at the top of support post in independent support system, then sets up post-cast strip two Other position support systems of side;
2) template system is constructed, the first common adjustable jack leger in Construction Later Casting Zone two sides, then Construction Later Casting Zone position leger;
3) continuous laying is taken in platform beam-slab template laying, at the adjustable position of shoring of special complete using 300mm width edge angle mould Plate aperture is assembled, and adjustable top plate face of shoring is leveled according to mould floor elevation;
4) after the concreting of post-cast strip two sides is completed and reaches strength of mould stripping, scaffold and form removable is carried out, is removed simultaneously Post-cast strip it is dedicated it is adjustable shore connection fastener, horizontal transmission rod and template system, at this point, post-cast strip two sides beam slab load is by transverse direction Actuating system indirect transfer be changed into directly by it is dedicated it is adjustable shore stress, late poured band support is without removing, returning back to top, system is steady Calmly, power transmission is reasonable;
5) post-cast strip concrete construction, first it is dedicated it is adjustable shore the elongated stress horizontal steel tube of upper installation, re-lay flitch and wood After template, flitch and template are laid, then alter-pouring strips mould plate is used into hydraulic jack integral jacking and is adjacent to floor face;
6) post-cast strip concrete is poured, late poured band support and template are removed after intensity reaches design strength.
Post-cast strip above-mentioned exempts to tear support system construction method open, late poured band support and other position support systems in step 1) It is connected using interim girt, in order to enhance the overall stability of frame body.
Post-cast strip above-mentioned exempts to tear support system construction method open, other position support systems include supported rod erecting in step 1) With common jacking, supported rod erecting uses disk button or total sub-semigroup, and ordinary steel pipe scaffold can also be used in supported rod erecting, uses Disk button or total sub-semigroup construction are more convenient.
Post-cast strip above-mentioned exempts to tear support system construction method open, and special complete is adjustable in step 1) shores top plate and template face It flushes, special complete is adjustable to be shored including circular steel plate, and circular steel plate bottom end fixed vertical is provided with screw rod, is arranged on screw rod First for adjusting steel pipe short sleeve height is arranged in the steel pipe short sleeve connecting with other support systems, steel pipe short sleeve bottom Adjust lock, screw rod bottom be provided with adjusting screw rod height second adjust lock, solved by steel pipe short sleeve and other The connection of support system upright bar also solves horizontal force bar and the stress check calculation vertically shored, using steel pipe short sleeve can Moving up and down on screw rod is adjusted, template system absolute altitude can accurately be adjusted.
Support system construction method is exempted to tear open in post-cast strip above-mentioned, and in step 3) when leger is steel pipe, common jacking is big Cross bar is connect using right-angle coupler with adjustable shore of special complete with complete adjustable shore in post-cast strip;When leger is flitch or side When steel, adjustable the elongated horizontal steel tube of upper installation is shored as leger force rod, flitch or square steel be supported on horizontal steel dedicated Guan Shang, post-cast strip position leger are not required to disconnect with two sides template system leger.
The beneficial effects of the present invention are: this invention ensures that late poured band support is not torn open, is not loose, and do not influence other regions Support and form removable, solve the drawbacks of existing rear pouring tape construction method;It is solved and other supports by steel pipe short sleeve The connection of system upright bar, the stress check calculation for also solving horizontal force bar and vertically shoring, it is ensured that support system upright bar stress shape State is consistent, while the moving up and down on adjusting screw using short sleeve, can accurately be adjusted to template system absolute altitude, And lifting operation can be taken to alter-pouring strips mould plate, and it greatly facilitates alter-pouring strips mould plate and installs, compared with tradition returns back to top construction method, This method does not need to set up the support that returns back to top, and novel form, easy construction ensure that late poured band support system stress is constant, It is truly realized at post-cast strip concrete construction support may be implemented and do not tear open, is not loose, and be not required to set up the effect for the support that returns back to top again, it is right It accelerates construction progress, reduce construction cost, ensure that construction quality advantage is obvious.
Detailed description of the invention
Fig. 1 is support system of the present invention and template construction schematic diagram;
Fig. 2 shores schematic diagram after short sleeve connection fastener, horizontal transmission rod and template system are removed to be adjustable;
Fig. 3 is the secondary formwork horizontal steel tube scheme of installation in post-cast strip;
Fig. 4 is alter-pouring strips mould plate lifting diagram;
Fig. 5 is that special complete shores structural schematic diagram.
In the figure, it is marked as 1, common adjustable leger, 2, can commonly turn cross bar down, 3, common templates, 4, post-cast strip, 5, straight Angle fastener, 6, common jacking, 7, it is dedicated it is adjustable shore, 8, late poured band support upright bar, 9, supported rod erecting, 10, girt, 11, Post-cast strip leger, 12, the small cross bar in post-cast strip, 13, alter-pouring strips mould plate, 70, circular steel plate, 71, screw rod, 72, steel plate short sleeve, 73, first lock is adjusted, 74, second adjusts lock, 75, ribbed stiffener.
Specific embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is described in more detail.
A kind of post-cast strip is present embodiments provided to exempt to tear support system construction method open, it is characterised in that the following steps are included:
1) unwrapping wire snap the line in ground is carried out according to support scaffolding plan layout drawing and post-cast strip position, first sets up post-cast strip portion The independent support system in position, then other position support systems of post-cast strip two sides are set up, late poured band support and other position support systems It is connected using interim girt 11, other position support systems include supported rod erecting 9 and common jacking 6, and supported rod erecting 9 uses Ordinary steel pipe scaffold can also be used in disk button or total sub-semigroup, supported rod erecting 9, is applied using disk button or total sub-semigroup Work is more convenient;
2) special complete is adjustable shores 7 for setting at the top of late poured band support column, and special complete is adjustable to shore 7 top plates and 3 face of template It flushes, special complete is adjustable, and to shore 7 include with a thickness of 8mm, the circular steel plate 70 that diameter is 150mm, and 70 bottom end of circular steel plate is solid Surely it is vertically installed with the screw rod 71 that diameter is 37mm, circular steel plate 70 and screw rod connect 71 places of connecing and be provided with ribbed stiffener 75, screw rod 71 Upper that the steel pipe short sleeve 72 that diameter is 48mm is arranged at circular steel plate 70,72 bottom of steel pipe short sleeve is arranged for adjusting The first of 72 height of steel pipe short sleeve adjusts lock 73, and 71 bottom of screw rod is provided with the second adjusting lock of 71 height of adjusting screw rod 74, since short set 72 can move up and down in adjustable supports, jack-up construction is taken when installing alter-pouring strips mould plate, was both significantly facilitated Site operation, and can accomplish that template face is close to concrete surface, to ensure that post-cast strip concrete base flatness, such as Fig. 5 It is shown;
3) when template system is constructed, the first common adjustable jack leger 1 in Construction Later Casting Zone two sides, then the big cross in Construction Later Casting Zone position Bar 11, when common 1 leger is steel pipe, common jacking leger 1 and post-cast strip are complete adjustable to shore 7 and uses right-angle couplers 5 With it is complete it is adjustable shore steel pipe short sleeve 72 on 7 and connect, and 73 adjusting sleeves of lock are adjusted by 72 bottom first of steel pipe short sleeve Pipe height;When common leger 1 is flitch or square steel, elongated horizontal steel tube is installed on 7 short sleeves 72 in dedicated adjustable shore As leger force rod, flitch or square steel are supported on horizontal steel tube, post-cast strip position leger 11 and two sides template system Leger is not required to disconnect.
4) continuous laying is taken in platform beam-slab template laying, at adjustable 7 positions of shoring of special complete using 300mm or so width It is assembled to spend corner template aperture, adjustable top plate face of shoring can be leveled according to mould floor elevation, as shown in Figure 1;
5) after the concreting of post-cast strip two sides is completed and reaches strength of mould stripping, large area scaffold and form removable are carried out, together When remove the adjustable right-angle coupler 5 shored on short sleeve 72 in post-cast strip, horizontal transmission rod and template system, at this point, post-cast strip two Curb girder plate load by pass force crossly system indirect transfer be changed into directly by it is dedicated it is adjustable shore stress, late poured band support is without tearing open Remove, return back to top, stable system, power transmission it is reasonable, as shown in Figure 2;
6) when the concrete construction of post-cast strip, first in adjustable shore elongated stress horizontal steel tube should be installed on short sleeve 72, re-lays Flitch and plank sheathing, for convenient for site operation, short sleeve absolute altitude is lowered 50 ~ 100mm, after flitch, template are laid, then will Alter-pouring strips mould plate is using hydraulic jack integral jacking and is adjacent to floor face, tightens the first adjusting lock 73 on short sleeve and fixes, As shown in Fig. 3 Fig. 4;
7) post-cast strip concrete is poured, late poured band support and alter-pouring strips mould plate 13 are removed after intensity reaches design strength.
Although the present invention is described in detail referring to the foregoing embodiments, for those skilled in the art, It is still possible to modify the technical solutions described in the foregoing embodiments, or part of technical characteristic is carried out etc. With replacement, all within the spirits and principles of the present invention, any modification, equivalent replacement, improvement and so on should be included in this Within the protection scope of invention.

Claims (5)

1. a kind of post-cast strip exempts to tear support system construction method open, it is characterised in that the following steps are included:
1) unwrapping wire snap the line in ground is carried out according to support scaffolding plan layout drawing and post-cast strip position, first sets up post-cast strip portion The independent support system in position, special complete is adjustable shores for setting at the top of support post in independent support system, then sets up post-cast strip two Other position support systems of side;
2) template system is constructed, the first common adjustable jack leger in Construction Later Casting Zone two sides, then Construction Later Casting Zone position leger;
3) continuous laying is taken in platform beam-slab template laying, at the adjustable position of shoring of special complete using 300mm width edge angle mould Plate aperture is assembled, and dedicated adjustable top plate face of shoring is leveled according to mould floor elevation;
4) after the concreting of post-cast strip two sides is completed and reaches strength of mould stripping, scaffold and form removable is carried out, is removed simultaneously Post-cast strip is dedicated adjustable to shore connection fastener, horizontal transmission rod and template system;
5) post-cast strip concrete construction, first it is dedicated it is adjustable shore the elongated stress horizontal steel tube of upper installation, re-lay flitch and wood After template, flitch and template are laid, then alter-pouring strips mould plate is used into hydraulic jack integral jacking and is adjacent to floor face;
6) post-cast strip concrete is poured, late poured band support and template are removed after intensity reaches design strength.
2. a kind of post-cast strip according to claim 1 exempts to tear support system construction method open, it is characterised in that: after in step 1) The independent support of band is poured to connect with other position support systems using interim girt.
3. a kind of post-cast strip according to claim 1 exempts to tear support system construction method open, it is characterised in that: its in step 1) His position support system includes supported rod erecting and common jacking, and supported rod erecting uses disk button or total sub-semigroup.
4. a kind of post-cast strip according to claim 1 exempts to tear support system construction method open, it is characterised in that: step 1) special secondary school With it is complete it is adjustable shore top plate and flushed with template face, special complete is adjustable to be shored including circular steel plate, and circular steel plate bottom end is fixed It is vertically installed with screw rod, the steel pipe short sleeve connecting with other support systems, the setting of steel pipe short sleeve bottom are arranged on screw rod Lock is adjusted for adjusting the first of steel pipe short sleeve height, screw rod bottom is provided with the second adjusting lock of adjusting screw rod height Button.
5. a kind of post-cast strip according to claim 1 exempts to tear support system construction method open, it is characterised in that: in step 2 when When leger is steel pipe, common jacking leger and post-cast strip is complete adjustable shores using right-angle coupler and the adjustable top of special complete Support connection;When leger is flitch or square steel, in the dedicated adjustable elongated horizontal steel tube of upper installation of shoring as leger stress Bar, flitch or square steel are supported on horizontal steel tube, and post-cast strip position leger is not required to disconnect with two sides template system leger.
CN201910728995.6A 2019-08-08 2019-08-08 A kind of post-cast strip exempts to tear support system construction method open Pending CN110439270A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910728995.6A CN110439270A (en) 2019-08-08 2019-08-08 A kind of post-cast strip exempts to tear support system construction method open

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910728995.6A CN110439270A (en) 2019-08-08 2019-08-08 A kind of post-cast strip exempts to tear support system construction method open

Publications (1)

Publication Number Publication Date
CN110439270A true CN110439270A (en) 2019-11-12

Family

ID=68433856

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910728995.6A Pending CN110439270A (en) 2019-08-08 2019-08-08 A kind of post-cast strip exempts to tear support system construction method open

Country Status (1)

Country Link
CN (1) CN110439270A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111749458A (en) * 2020-06-30 2020-10-09 武汉一冶建筑安装工程有限责任公司 Post-cast strip inner frame formwork construction method and support system
CN112012480A (en) * 2020-08-25 2020-12-01 圣峰建设有限公司 Tool type independent formwork structure for post-cast strip and construction process
CN113027102A (en) * 2021-03-15 2021-06-25 武汉建工集团股份有限公司 Soft soil foundation construction support inner support construction operation platform and construction method
CN113073841A (en) * 2021-04-22 2021-07-06 中国十七冶集团有限公司 Modular assembly type post-cast strip independent supporting device and using method thereof
CN113107192A (en) * 2021-03-31 2021-07-13 中国五冶集团有限公司 Post-cast strip supporting method
CN113914524A (en) * 2021-11-10 2022-01-11 中建四局第六建设有限公司 Edge belt type independent support construction method for superposed floor of assembled structure system
CN114059762A (en) * 2021-12-03 2022-02-18 湖南中模云建筑科技有限公司 Hand rack table formwork free of disc detaching and foot buckling and construction method
CN114215345A (en) * 2021-12-23 2022-03-22 珠海华发人居生活研究院有限公司 Construction method for independent support bracket template of post-cast strip of top plate of reservoir

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111749458A (en) * 2020-06-30 2020-10-09 武汉一冶建筑安装工程有限责任公司 Post-cast strip inner frame formwork construction method and support system
CN112012480A (en) * 2020-08-25 2020-12-01 圣峰建设有限公司 Tool type independent formwork structure for post-cast strip and construction process
CN113027102A (en) * 2021-03-15 2021-06-25 武汉建工集团股份有限公司 Soft soil foundation construction support inner support construction operation platform and construction method
CN113027102B (en) * 2021-03-15 2022-06-07 武汉建工集团股份有限公司 Soft soil foundation construction support inner support construction operation platform and construction method
CN113107192A (en) * 2021-03-31 2021-07-13 中国五冶集团有限公司 Post-cast strip supporting method
CN113073841A (en) * 2021-04-22 2021-07-06 中国十七冶集团有限公司 Modular assembly type post-cast strip independent supporting device and using method thereof
CN113914524A (en) * 2021-11-10 2022-01-11 中建四局第六建设有限公司 Edge belt type independent support construction method for superposed floor of assembled structure system
CN114059762A (en) * 2021-12-03 2022-02-18 湖南中模云建筑科技有限公司 Hand rack table formwork free of disc detaching and foot buckling and construction method
CN114215345A (en) * 2021-12-23 2022-03-22 珠海华发人居生活研究院有限公司 Construction method for independent support bracket template of post-cast strip of top plate of reservoir

Similar Documents

Publication Publication Date Title
CN110439270A (en) A kind of post-cast strip exempts to tear support system construction method open
CN103556826A (en) Construction method of post-cast strip area and floor area supporting systems on two sides of post-cast strip area
CN103669865A (en) Stair construction method through shaped supports
CN103276893A (en) Novel composite structure for supporting rigid building template and construction method
CN109680930A (en) Early-dismantling support system construction method
CN104074142A (en) Box beam cast-in-place support whole-horizontal-moving construction method
CN107327050B (en) Disassembly-free basement exterior wall flanging unilateral formwork supporting device and construction method
CN111119071A (en) Construction method for assembling precast concrete segment box girder
CN105863253A (en) Integral formwork-supporting type asynchronous casting stairwell wall column formwork supporting system and construction method
CN210857279U (en) Post-cast concrete temporary support column
CN106032704A (en) Construction method for using concrete columns to support structures on both sides of post-pouring strip
JP2011157720A (en) Method for constructing railway reinforced concrete rigid-frame structure viaduct
CN110158951A (en) A kind of frame structure wooden template construction method entirely
CN111424948A (en) Construction method and construction platform for cantilever structure layer of high-rise building
CN111749457A (en) Early-support later-fixing early-dismantling formwork system and construction method thereof
CN216865972U (en) Template structure is pour to column cap
CN107299596B (en) Concrete support trestle plate lower supporting beam template system and construction method thereof
CN102900230A (en) Liftable reinforced concrete post-casting strip construction method
CN106522282B (en) A kind of liftable post-cast strip template structure and system and its construction method
CN212773451U (en) Post-cast strip template support system
CN203603462U (en) Post-cast strip beam plate formwork supporting structure
CN112796513A (en) Formwork supporting structure for post-cast strip and construction method
CN112746628A (en) Cast-in-place comprehensive pipe gallery formwork supporting structure and cast-in-place comprehensive pipe gallery construction method
CN111561150A (en) Post-cast strip supporting system
CN109184193A (en) A kind of early-dismantling formwork system and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination