CN110424548B - Steel pipe concrete column-beamless floor connecting node and construction method thereof - Google Patents
Steel pipe concrete column-beamless floor connecting node and construction method thereof Download PDFInfo
- Publication number
- CN110424548B CN110424548B CN201910801865.0A CN201910801865A CN110424548B CN 110424548 B CN110424548 B CN 110424548B CN 201910801865 A CN201910801865 A CN 201910801865A CN 110424548 B CN110424548 B CN 110424548B
- Authority
- CN
- China
- Prior art keywords
- steel
- steel pipe
- column
- steel plate
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Rod-Shaped Construction Members (AREA)
Abstract
Description
技术领域Technical field
本发明涉及建筑结构中的耗能减震控制技术领域,尤其涉及一种低损伤易修复的钢管混凝土柱-无梁楼盖连接节点。The invention relates to the technical field of energy consumption and shock absorption control in building structures, and in particular to a low-damage and easy-to-repair steel tube concrete column-beamless floor connection node.
背景技术Background technique
由无梁楼盖和钢管混凝土柱组成的板柱结构由于具有楼层净空高,建筑使用空间大等优点,在建筑结构中得到了越来越广泛的应用。但在地震作用下,板柱连接节点容易发生冲切破坏,由此导致的楼板损伤较难修复;如果节点冲切破坏严重,甚至会引起整体结构倒塌。The slab-column structure composed of a beamless floor and a steel tube concrete column has been increasingly used in building structures due to its advantages such as high floor clearance and large building space. However, under the action of earthquakes, plate-column connection nodes are prone to punching damage, and the resulting damage to the floor is difficult to repair; if the node punching damage is severe, it may even cause the collapse of the entire structure.
发明内容Contents of the invention
本发明目的在于针对现有技术中的不足,提出了一种低损伤易修复的钢管混凝土柱-无梁楼盖连接节点。The purpose of the present invention is to propose a low-damage and easy-to-repair steel tube concrete column-beamless floor connection node in view of the deficiencies in the prior art.
为了解决上述的技术问题,本发明的技术方案如下:In order to solve the above technical problems, the technical solutions of the present invention are as follows:
一种钢管混凝土柱-无梁楼盖连接节点,与钢管混凝土柱相连的钢筋混凝土楼板的部分区域用铸钢件代替,该区域的宽度为钢管混凝土柱宽度的4-6倍;A concrete-filled steel tube column-beamless floor connection node, in which part of the reinforced concrete floor connected to the concrete-filled steel tube column is replaced by a steel casting, and the width of this area is 4-6 times the width of the concrete-filled steel tube column;
所述铸钢件由中心钢管和正交钢板网格组成;所述正交钢板网格设置在中心钢管的四个侧面处,并且正交钢板网格中与中心钢管侧面相连的钢板段,在上端和下端分别设置有弧形凹槽,形成削弱区段;The steel casting is composed of a central steel pipe and an orthogonal steel plate grid; the orthogonal steel plate grid is arranged on the four sides of the central steel pipe, and the steel plate segments in the orthogonal steel plate grid connected to the sides of the central steel pipe are The upper end and lower end are respectively provided with arc-shaped grooves to form weakened sections;
所述中心钢管与柱钢管通过法兰连接;柱钢管内浇筑混凝土形成所述钢管混凝土柱,所述正交钢板网格的最外围钢板上开有圆孔,周边楼板的钢筋穿过圆孔,并通过螺栓锚固在钢板上。The central steel pipe and the column steel pipe are connected through flanges; concrete is poured into the column steel pipe to form the steel tube concrete column. There are round holes on the outermost steel plate of the orthogonal steel plate grid, and the steel bars of the peripheral floor plates pass through the round holes. And anchored to the steel plate through bolts.
本发明还提供了如上所述的钢管混凝土柱-无梁楼盖连接节点的施工方法,包括以下步骤:The present invention also provides a construction method for the steel tube concrete column-beamless floor connection node as mentioned above, which includes the following steps:
1)根据楼板厚度、柱子截面尺寸,设计铸钢件并制作相应的浇铸模具;1) According to the thickness of the floor slab and the cross-sectional size of the column, design the steel casting and make the corresponding casting mold;
2)在模具上整体浇铸铸钢件;2) Cast the steel casting integrally on the mold;
3)在铸钢件的中心钢管上焊接法兰;3) Weld the flange on the central steel pipe of the steel casting;
4)根据楼板钢筋的位置,确定出正交钢板网格最外围钢板对应圆孔的位置并完成钻孔;4) According to the position of the floor steel bars, determine the position of the corresponding circular hole in the outermost steel plate of the orthogonal steel plate grid and complete the drilling;
5)楼板支模,同时将铸钢件定位;5) Support the floor slab and position the steel castings at the same time;
6)将楼板的钢筋穿过正交钢板网格最外围钢板并通过螺栓锚固;6) Pass the steel bars of the floor slab through the outermost steel plate of the orthogonal steel plate grid and anchor it with bolts;
7)将中心钢管与柱钢管通过法兰连接;7) Connect the central steel pipe and column steel pipe through flanges;
8)浇筑楼板和柱子混凝土。待混凝土强度达到要求后,在铸钢件上盖上钢盖板。8) Pour concrete for floor slabs and columns. After the concrete strength reaches the required level, the steel casting is covered with a steel cover plate.
本发明相对于现有技术具有以下优点及突出效果:Compared with the existing technology, the present invention has the following advantages and outstanding effects:
本发明提出的低损伤易修复的钢管混凝土柱-无梁楼盖连接节点的突出特点是对铸钢件中与中心钢管相连的钢板段截面进行削弱,从而保证在地震作用下,结构屈服只发生在该削弱区段,楼板其他区域可免遭破坏,结构易于修复。本发明加强了钢管混凝土柱-无梁楼盖连接节点的抗冲切破坏性能,在多层建筑中具有广阔的应用前景。The outstanding feature of the low-damage and easy-to-repair concrete-filled steel tube column-beamless floor connection node proposed by the present invention is to weaken the section of the steel plate section connected to the central steel pipe in the steel casting, thereby ensuring that the structural yield only occurs under earthquake action. In this weakened section, other areas of the floor slab can be protected from damage and the structure can be easily repaired. The invention enhances the punching shear resistance of the steel tube concrete column-beamless floor connection node, and has broad application prospects in multi-story buildings.
附图说明Description of the drawings
图1为楼板立体图;Figure 1 is a three-dimensional view of the floor;
图2为楼板透视立体图;Figure 2 is a perspective view of the floor;
图3、图4分别为铸钢件立体图与平面图;Figures 3 and 4 are respectively a three-dimensional view and a plan view of the steel casting;
图5为铸钢件细部构造图;Figure 5 is a detailed structural diagram of the steel casting;
图6为铸钢件最外围钢板与钢筋连接构造图;Figure 6 is a structural diagram of the connection between the outermost steel plate and steel bars of the steel casting;
图中:1-楼板;2-钢管混凝土柱;3-钢盖板;4-法兰;5-钢筋;6-中心钢管;7-正交钢板;8-最外围钢板;9-截面削弱区;10-螺栓。In the picture: 1 - floor slab; 2 - concrete filled steel tube column; 3 - steel cover plate; 4 - flange; 5 - steel bar; 6 - central steel pipe; 7 - orthogonal steel plate; 8 - outermost steel plate; 9 - section weakened area ;10-bolt.
具体实施方法Specific implementation methods
以下结合附图,对本发明的具体实施方法作进一步描述。The specific implementation methods of the present invention will be further described below in conjunction with the accompanying drawings.
参考图1-图6,一种低损伤易修复的钢筋混凝土柱-无梁楼盖连接节点,与柱2相连的钢筋混凝土楼板1的部分区域用铸钢件代替,该区域的宽度为柱2宽度的4-6倍,如图1、图2。该铸钢件由中心钢管6和正交钢板网格7组成,如图3、图4。所述正交钢板网格7设置在中心钢管6的四个侧面处,并且正交钢板网格7中与中心钢管6侧面相连的钢板段,在上端和下端分别设置有弧形凹槽,形成削弱区段9;这样可以保证屈服只发生在该削弱区段9,楼板1其他区域可免遭破坏,结构易于修复,如图5。Referring to Figures 1 to 6, a low-damage and easy-to-repair reinforced concrete column-beamless floor connection node is used. Part of the reinforced concrete floor 1 connected to column 2 is replaced with steel castings. The width of this area is column 2. 4-6 times the width, as shown in Figure 1 and Figure 2. The steel casting is composed of a central steel pipe 6 and an orthogonal steel plate grid 7, as shown in Figures 3 and 4. The orthogonal steel plate grid 7 is arranged on the four sides of the central steel pipe 6, and the steel plate sections in the orthogonal steel plate grid 7 connected to the sides of the central steel pipe 6 are respectively provided with arcuate grooves at the upper and lower ends to form Weakened section 9; this can ensure that yielding only occurs in this weakened section 9, other areas of the floor 1 can be protected from damage, and the structure can be easily repaired, as shown in Figure 5.
铸钢件的中心钢管6与柱钢管通过法兰4连接;钢管6内浇筑混凝土形成钢管混凝土柱2,保证楼板1的剪力和弯矩能够可靠地传递给柱子2。所述正交钢板网格7的最外围钢板8上开有圆孔,周边楼板的钢筋5穿过圆孔,并通过螺栓10锚固在钢板上,如图6。The central steel pipe 6 of the steel casting is connected to the column steel pipe through a flange 4; concrete is poured into the steel pipe 6 to form a concrete-filled steel tube column 2, ensuring that the shear force and bending moment of the floor slab 1 can be reliably transmitted to the column 2. There are round holes in the outermost peripheral steel plate 8 of the orthogonal steel plate grid 7, and the steel bars 5 of the peripheral floor pass through the round holes and are anchored to the steel plate through bolts 10, as shown in Figure 6.
本发明的施工方法包括以下步骤:The construction method of the present invention includes the following steps:
(1)工厂预制阶段。首先,根据楼板1厚度、柱子2截面尺寸,设计铸钢件并制作相应的浇铸模具。然后,在模具上整体浇铸铸钢件。接着,在铸钢件的中心钢管6上焊接法兰4。紧接着,根据楼板钢筋5的位置,确定出该铸钢件最外围钢板8对应圆孔的位置并完成钻孔。(1) Factory prefabrication stage. First, according to the thickness of the floor slab 1 and the cross-sectional size of the column 2, the steel castings are designed and the corresponding casting molds are made. The steel casting is then integrally cast on the mould. Next, the flange 4 is welded to the central steel pipe 6 of the steel casting. Then, according to the position of the floor steel bars 5, the position of the corresponding circular hole in the outermost steel plate 8 of the steel casting is determined and the drilling is completed.
(2)现场施工阶段。楼板1支模,同时将铸钢件定位。将楼板1的钢筋5穿过正交钢板网格7的最外围钢板8并通过螺栓10锚固;然后,将铸钢件的中心钢管6与柱钢管通过法兰4连接;接着,浇筑楼板1和柱子2混凝土。待混凝土强度达到要求后,在铸钢件上盖上钢板3,即完成该钢管混凝土柱-无梁楼盖连接节点的施工。(2) On-site construction stage. 1 formwork for the floor slab, and position the steel castings at the same time. Pass the steel bars 5 of the floor slab 1 through the outermost steel plate 8 of the orthogonal steel plate grid 7 and anchor it with bolts 10; then, connect the central steel pipe 6 of the steel casting to the column steel pipe through the flange 4; then, pour the floor slab 1 and Pillars 2 concrete. After the concrete strength reaches the requirement, the steel plate 3 is covered on the steel casting, and the construction of the concrete-filled steel tube column-beamless floor connection node is completed.
上文所述,仅为本发明较佳的实施范例,不能依此限定本发明实施的范围。即依本发明专利范围及说明书内容所作的等效变化与修饰,皆应仍属本发明涵盖的范围内。The above descriptions are only preferred implementation examples of the present invention and cannot be used to limit the scope of the present invention. That is, equivalent changes and modifications made based on the patent scope of the present invention and the content of the description should still be within the scope of the present invention.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910801865.0A CN110424548B (en) | 2019-08-28 | 2019-08-28 | Steel pipe concrete column-beamless floor connecting node and construction method thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910801865.0A CN110424548B (en) | 2019-08-28 | 2019-08-28 | Steel pipe concrete column-beamless floor connecting node and construction method thereof |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110424548A CN110424548A (en) | 2019-11-08 |
CN110424548B true CN110424548B (en) | 2023-12-29 |
Family
ID=68417849
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910801865.0A Active CN110424548B (en) | 2019-08-28 | 2019-08-28 | Steel pipe concrete column-beamless floor connecting node and construction method thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110424548B (en) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111535452B (en) * | 2020-05-26 | 2022-02-11 | 华北理工大学 | Slab-column joint connection structure, concrete-filled steel tubular slab-column structure and construction method |
CN112267571B (en) * | 2020-11-11 | 2022-02-01 | 吉林建筑科技学院 | Prefabricated section steel concrete column and profiled steel sheet composite board connecting joint and construction method |
CN113389312B (en) * | 2021-07-30 | 2025-01-24 | 南通欧本建筑科技有限公司 | A kind of carapace column beamless floor node |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2130106C1 (en) * | 1996-03-19 | 1999-05-10 | Арасланов Зинатула Гайнатдинович | Methods for embodying structural system of fully prefabricated civic building |
CN105735541A (en) * | 2016-03-24 | 2016-07-06 | 金天德 | Steel structure girderless floor slab column structure |
CN107130721A (en) * | 2017-07-10 | 2017-09-05 | 南京工业大学 | Anti die-cut concrete rectangle column slab node and concrete slab node |
CN108571070A (en) * | 2018-05-24 | 2018-09-25 | 福建工程学院 | A kind of Prefabricated concrete-filled steel tube ring beam connection structure and construction method |
CN210713231U (en) * | 2019-08-28 | 2020-06-09 | 华侨大学 | Steel core concrete column-no beam superstructure connected node |
-
2019
- 2019-08-28 CN CN201910801865.0A patent/CN110424548B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
RU2130106C1 (en) * | 1996-03-19 | 1999-05-10 | Арасланов Зинатула Гайнатдинович | Methods for embodying structural system of fully prefabricated civic building |
CN105735541A (en) * | 2016-03-24 | 2016-07-06 | 金天德 | Steel structure girderless floor slab column structure |
CN107130721A (en) * | 2017-07-10 | 2017-09-05 | 南京工业大学 | Anti die-cut concrete rectangle column slab node and concrete slab node |
CN108571070A (en) * | 2018-05-24 | 2018-09-25 | 福建工程学院 | A kind of Prefabricated concrete-filled steel tube ring beam connection structure and construction method |
CN210713231U (en) * | 2019-08-28 | 2020-06-09 | 华侨大学 | Steel core concrete column-no beam superstructure connected node |
Also Published As
Publication number | Publication date |
---|---|
CN110424548A (en) | 2019-11-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105908621B (en) | It is a kind of to damage controllable Self-resetting precast segment steel-pipe assembly concrete pier and the practice | |
CN109252727B (en) | Shock insulation layer rubber support, column, beam and plate system integrated assembly node and method | |
CN104652705B (en) | Prefabricated and assembly type steel reinforced concrete column with high-performance concrete frame and construction method | |
CN104594561A (en) | Prefabricated reinforced concrete column with high-performance concrete frame and construction method | |
CN110424548B (en) | Steel pipe concrete column-beamless floor connecting node and construction method thereof | |
CN216740039U (en) | Self-resetting fabricated composite structure beam column side node with floor | |
CN204385886U (en) | Villages and small towns low layer assembling damping architectural structure system | |
CN108571070A (en) | A kind of Prefabricated concrete-filled steel tube ring beam connection structure and construction method | |
CN114718186A (en) | Partially using ECC section steel concrete column-steel beam assembly structure and assembly method | |
CN108086488A (en) | Assembled frame-shear structure wall splitlevel connection structure and assembling method | |
CN107882179A (en) | Modular prefabricated steel-concrete combined frame structure | |
CN108265823A (en) | Assembly concrete-filled steel tube column-isolated footing-concrete collar tie beam L-shaped connecting node | |
CN115680116A (en) | Assembled frame beam column connecting node and construction method thereof | |
CN108625491B (en) | Assembled H profile steel column-isolated footing-concrete collar tie beam L shape connecting node | |
CN208105477U (en) | Assembly concrete-filled steel tube column-isolated footing-concrete collar tie beam L shape connecting node | |
CN209227836U (en) | Prefabricated concrete structure wall-column full steel key connection structure | |
CN112854442B (en) | Self-resetting combined node connecting structure and assembling method for beam column of assembled concrete frame | |
CN207260378U (en) | A kind of assembled frame-shear structure curved scissors type combines keyway connection structure | |
CN210713231U (en) | Steel core concrete column-no beam superstructure connected node | |
CN209443360U (en) | A kind of concrete pier of steel tube | |
CN208023735U (en) | Assembly concrete-filled steel tube column-isolated footing-concrete collar tie beam T shape connecting nodes | |
CN106337512A (en) | The bottom reinforced concrete-filled steel tubular frame high-strength concrete composite shear wall and manufacturing method | |
CN207525906U (en) | A kind of assembled frame-shear structure wall splitlevel connection structure | |
CN110258819B (en) | Connecting node of reinforced concrete column and flat slab and construction method thereof | |
CN104532952A (en) | Short angle iron connection type reinforced concrete assembling integrated frame and construction method thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
OL01 | Intention to license declared | ||
OL01 | Intention to license declared | ||
EE01 | Entry into force of recordation of patent licensing contract | ||
EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20191108 Assignee: Lubanyuan Group Co.,Ltd. Assignor: HUAQIAO University Contract record no.: X2025980007100 Denomination of invention: A steel tube concrete column beamless floor connection node and its construction method Granted publication date: 20231229 License type: Open License Record date: 20250417 |