CN110424265B - 一种桥梁预制构件跨内起梁直接吊装装置和吊装工艺方法 - Google Patents
一种桥梁预制构件跨内起梁直接吊装装置和吊装工艺方法 Download PDFInfo
- Publication number
- CN110424265B CN110424265B CN201910616965.6A CN201910616965A CN110424265B CN 110424265 B CN110424265 B CN 110424265B CN 201910616965 A CN201910616965 A CN 201910616965A CN 110424265 B CN110424265 B CN 110424265B
- Authority
- CN
- China
- Prior art keywords
- bridge
- lifting
- pier
- prefabricated part
- telescopic
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/62—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means comprising article-engaging members of a shape complementary to that of the articles to be handled
- B66C1/66—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means comprising article-engaging members of a shape complementary to that of the articles to be handled for engaging holes, recesses, or abutments on articles specially provided for facilitating handling thereof
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
- E01D21/06—Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections
Abstract
Description
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910616965.6A CN110424265B (zh) | 2019-07-09 | 2019-07-09 | 一种桥梁预制构件跨内起梁直接吊装装置和吊装工艺方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910616965.6A CN110424265B (zh) | 2019-07-09 | 2019-07-09 | 一种桥梁预制构件跨内起梁直接吊装装置和吊装工艺方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110424265A CN110424265A (zh) | 2019-11-08 |
CN110424265B true CN110424265B (zh) | 2021-11-26 |
Family
ID=68410399
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910616965.6A Active CN110424265B (zh) | 2019-07-09 | 2019-07-09 | 一种桥梁预制构件跨内起梁直接吊装装置和吊装工艺方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110424265B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112125160A (zh) * | 2020-08-19 | 2020-12-25 | 北京市政路桥股份有限公司 | 一种高大定点龙门架垂直提梁方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203383148U (zh) * | 2013-06-25 | 2014-01-08 | 宁波市政工程建设集团股份有限公司 | 一种预制小箱梁跨内起梁装置 |
CN204823647U (zh) * | 2015-06-18 | 2015-12-02 | 天津市飞奥达风能设备有限公司 | 一种圆管吊具 |
CN105908633A (zh) * | 2016-06-06 | 2016-08-31 | 中国葛洲坝集团第工程有限公司 | 跨河双层多幅桥梁分片钢箱梁的吊装方法 |
CN107974944A (zh) * | 2017-12-06 | 2018-05-01 | 浙江中建路桥设备有限公司 | 一种y型公铁两用桥梁桥面板吊装装置及吊装方法 |
CN108004929A (zh) * | 2017-12-06 | 2018-05-08 | 浙江中建路桥设备有限公司 | 一种h型公铁两用桥梁桥面板吊装装置及吊装方法 |
CN109653099A (zh) * | 2019-01-08 | 2019-04-19 | 中铁四局集团有限公司 | 一种下放梁段的扁担梁转接装置 |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102493353B (zh) * | 2011-12-23 | 2014-11-05 | 中铁大桥局股份有限公司 | 桥梁施工中大型设备的起吊方法及墩顶提升吊架 |
CN102718152A (zh) * | 2012-06-28 | 2012-10-10 | 中铁十三局集团第一工程有限公司 | 双索道缆索起重机架设预制梁结构 |
CN206873305U (zh) * | 2017-06-13 | 2018-01-12 | 中交第二航务工程局有限公司 | 一种大跨径变截面预制节段梁拼装施工结构 |
-
2019
- 2019-07-09 CN CN201910616965.6A patent/CN110424265B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203383148U (zh) * | 2013-06-25 | 2014-01-08 | 宁波市政工程建设集团股份有限公司 | 一种预制小箱梁跨内起梁装置 |
CN204823647U (zh) * | 2015-06-18 | 2015-12-02 | 天津市飞奥达风能设备有限公司 | 一种圆管吊具 |
CN105908633A (zh) * | 2016-06-06 | 2016-08-31 | 中国葛洲坝集团第工程有限公司 | 跨河双层多幅桥梁分片钢箱梁的吊装方法 |
CN107974944A (zh) * | 2017-12-06 | 2018-05-01 | 浙江中建路桥设备有限公司 | 一种y型公铁两用桥梁桥面板吊装装置及吊装方法 |
CN108004929A (zh) * | 2017-12-06 | 2018-05-08 | 浙江中建路桥设备有限公司 | 一种h型公铁两用桥梁桥面板吊装装置及吊装方法 |
CN109653099A (zh) * | 2019-01-08 | 2019-04-19 | 中铁四局集团有限公司 | 一种下放梁段的扁担梁转接装置 |
Non-Patent Citations (3)
Title |
---|
双机抬吊法在嘉闵高架小箱梁架设施工中的运用;袁春飞;《建设科技》;20150331;全文 * |
架桥机高低法架梁施工技术;刘永福;《施工技术》;20120331;全文 * |
绳锯法整体拆除既有跨线桥施工技术;王臻林;《桥涵工程》;20131231;全文 * |
Also Published As
Publication number | Publication date |
---|---|
CN110424265A (zh) | 2019-11-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN113846563B (zh) | 一种大跨度斜拉桥边跨及辅助跨钢桁梁架设的施工方法 | |
CN211689943U (zh) | 装配式墩柱模板翻转缓冲装置 | |
CN112627059A (zh) | 一种墩梁一体化架桥机和过孔施工方法 | |
CN110424265B (zh) | 一种桥梁预制构件跨内起梁直接吊装装置和吊装工艺方法 | |
CN105088970A (zh) | 一种波形钢腹板pc箱梁斜拉桥的施工方法 | |
CN112160246B (zh) | 组合梁安装方法 | |
JP4188170B2 (ja) | 鉄骨構造物の建方工法及びその装置 | |
CN106006455A (zh) | 可实现无脚手架搭设模板架的液压升降机 | |
CN212251443U (zh) | 旧厂房除尘管道改造安装专用管道移动吊装装置 | |
CN111155438A (zh) | 应用于钢塔柱的施工装备及其施工工艺 | |
JP2011069168A (ja) | 橋桁送出し工法、及び橋桁横取り工法 | |
KR100627102B1 (ko) | 리프팅트레블러를 이용한 프리캐스트 세그먼트교량상부시공방법 | |
CN103147401A (zh) | 一种自爬升门架的施工方法及其结构 | |
JP3238751U (ja) | 橋桁架設機 | |
CN215925692U (zh) | 一种超长多跨装配式一体化多功能架桥机 | |
CN201506686U (zh) | 一种跨墩门架 | |
CN114541775A (zh) | 一种多点控制边界索提升安装结构及方法 | |
CN211736432U (zh) | 一种建筑施工装置 | |
CN111021205A (zh) | 混凝土防撞护栏支模装置及制作方法 | |
CN208717748U (zh) | 一种大跨度钢混组合梁架桥机支腿装置 | |
CN207244453U (zh) | 一种悬索桥轻型锚碇门架装置 | |
CN112377672A (zh) | 旧厂房除尘管道改造安装方法及其专用的管道移动吊装装置 | |
CN215925665U (zh) | 一种自动同步顶推的挂篮结构 | |
JP4349995B2 (ja) | 橋梁の架設方法 | |
CN114172081B (zh) | 一种格构式车载移动跨越装置及使用方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20191227 Address after: No. 10, Huangjiazhuang, Changle Village, Gaoqiao Town, Haishu District, Ningbo City, Zhejiang Province Applicant after: Ningbo Yifan hoisting Co., Ltd Applicant after: Ningbo Yiding Heavy Industry Co., Ltd Applicant after: Ningbo Huihe Construction Co., Ltd Address before: No. 10, Huangjiazhuang, Changle Village, Gaoqiao Town, Haishu District, Ningbo City, Zhejiang Province Applicant before: Ningbo Yifan hoisting Co., Ltd |
|
GR01 | Patent grant | ||
GR01 | Patent grant |