CN110401194A - A kind of fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy and method - Google Patents

A kind of fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy and method Download PDF

Info

Publication number
CN110401194A
CN110401194A CN201910754774.6A CN201910754774A CN110401194A CN 110401194 A CN110401194 A CN 110401194A CN 201910754774 A CN201910754774 A CN 201910754774A CN 110401194 A CN110401194 A CN 110401194A
Authority
CN
China
Prior art keywords
unit
switch
steam turbine
combined cycle
power supply
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910754774.6A
Other languages
Chinese (zh)
Inventor
牛利涛
何信林
彭金宁
兀鹏越
周峰旭
吴晋
罗俊然
罗勇
郭小勤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian Thermal Power Research Institute Co Ltd
Original Assignee
Xian Thermal Power Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian Thermal Power Research Institute Co Ltd filed Critical Xian Thermal Power Research Institute Co Ltd
Priority to CN201910754774.6A priority Critical patent/CN110401194A/en
Publication of CN110401194A publication Critical patent/CN110401194A/en
Pending legal-status Critical Current

Links

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02HEMERGENCY PROTECTIVE CIRCUIT ARRANGEMENTS
    • H02H9/00Emergency protective circuit arrangements for limiting excess current or voltage without disconnection
    • H02H9/02Emergency protective circuit arrangements for limiting excess current or voltage without disconnection responsive to excess current
    • H02H9/021Current limitation using saturable reactors
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J9/00Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting
    • H02J9/04Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source
    • H02J9/06Circuit arrangements for emergency or stand-by power supply, e.g. for emergency lighting in which the distribution system is disconnected from the normal source and connected to a standby source with automatic change-over, e.g. UPS systems

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The present invention discloses a kind of fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy and method; including three units; every unit is respectively arranged with a high-voltage auxiliary bus and for providing the working power inlet wire of work incoming power; working power inlet wire is connected to main transformer low-pressure side through current-limiting reactor, and current-limiting reactor both ends are parallel with high speed current-limiting protection switch;It is connected respectively by different backup power source incoming switches between the high-voltage auxiliary bus of any two units, the connection between the high-voltage auxiliary bus between unit is controlled by the on-off of backup power source incoming switch;Make full use of Combined cycle gas-steam turbine distributed energy station-service electric load in interim distribution, the feature that unit number is more, capacity is small, working power is derived from main transformer low-pressure side, double spare power supply is derived from adjacent unit high-voltage auxiliary bus, it solves existing station service and cuts the problems such as investment in allocation plan is more, and land occupation is wide and generator rotor angle is big fastly.

Description

A kind of fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy and method
Technical field
The invention belongs to the electrical design fields in Combined cycle gas-steam turbine distributed energy power station, and in particular to a kind of combustion The fast cutting system of three power supply of gas Steam Combined Cycle distributed energy and method.
Background technique
" large and medium-sized thermal power plant design specification " regulation: personal or important equipment safety will be directly influenced by having a power failure Load, it is necessary to which the backup power source automatically engaged is set.The fast cutting system design of conventional station service, usual working power are derived from this TV station The HV Auxiliary Transformer of unit, backup power source are derived from the starting spare transformer being separately provided, and auxiliary power change-over refers to The switching to work between incoming switch and standby inlet switch.Three kinds of switching mode point: normal switching, improper switching and accident Switching.The fast cutting system of this set needs to be separately provided HV Auxiliary Transformer, the spare change of starting and enclosed busbar.This system footprint It is more;It invests larger;Working power and backup power source generator rotor angle are big, and normal switching can only select series connection switching mode;Backup power source For external power supply, spend higher.A kind of foundation of Combined cycle gas-steam turbine cold, heat and power triple supply system is general in energy cascade utilization On the basis of thought, integrate a kind of distributed energy resource system of refrigeration, heat supply (heating and supplying hot water) and power generation process, there is machine The advantages that pool-size is small, takes up little area, number of units is more, flexible arrangement, high-efficient, is the main way of realization of China's distributed energy. But the fast cutting system implementation of traditional station service is not able to satisfy the needs in distributed energy power station.
Summary of the invention
In order to solve the problems in the existing technology, the object of the present invention is to provide a kind of Combined cycle gas-steam turbines point The fast cutting system of three power supply of the cloth energy and method make full use of Combined cycle gas-steam turbine distributed energy station-service electric load in rank The distribution of section property, the feature that unit number is more, capacity is small, working power are derived from main transformer low-pressure side, and double spare power supply is derived from adjacent unit High-voltage auxiliary bus solves existing station service and cuts the problems such as investment in allocation plan is more, and land occupation is wide and generator rotor angle is big fastly.
To achieve the goals above, the technical solution adopted by the present invention is that: a kind of Combined cycle gas-steam turbine distribution energy The fast cutting system of three power supply of source, which is characterized in that including three units, every unit is respectively arranged with a high-voltage auxiliary bus and use In providing the working power inlet wire of work incoming power, working power inlet wire is connected to main transformer low-pressure side through current-limiting reactor, limits Stream reactor both ends are parallel with high speed current-limiting protection switch;Respectively by spare between the high-voltage auxiliary bus of any two units Electric power incoming line switch connection controls the company between the high-voltage auxiliary bus between unit by the on-off of backup power source incoming switch Connect situation;When the work incoming switch of a certain unit is in "on" position, high-voltage auxiliary bus and other two unit Backup power source incoming switch between high-voltage auxiliary bus have one in quartile, and the standby electricity connected between other two unit Source incoming switch is in quartile.
When systems are functioning properly, high speed current-limiting protection switch is in "on" position, and current-limiting reactor no current passes through, and becomes Now to be lossless, no pressure drop does not generate magnetic flux leakage;When short trouble occurs for system, high speed current-limiting protection switch quick-speed turning on-off, Current-limiting reactor is put into, achievees the effect that limiting short-circuit current.
Further, when the work incoming switch of a certain unit is in "on" position, high-voltage auxiliary bus in addition Backup power source incoming switch between the high-voltage auxiliary bus of two units have one in quartile.
Further, a fast switching device is respectively arranged in each unit, in three units, for the height of some unit For pressing auxiliary bus bar, the high-voltage auxiliary bus of other two unit is standby by fast switching device realization two as backup power source With the setting of power supply priority.
Further, main transformer low-pressure side is to working power inlet wire using bus connection is poured, and backup power source inlet wire is using electricity Cable connection, working power and backup power source come from the same substation, using the identical mode of connection.
Further, the high-pressure side of the current-limiting reactor be provided with for overhaul isolation disconnecting switch, any two The backup power source incoming switch connected between the high-voltage auxiliary bus of unit is also in series with isolation switch.
The present invention also provides a kind of three power supply quick switch methods of Combined cycle gas-steam turbine distributed energy, including walk as follows It is rapid:
Step 1) combines the power output comprehensive analysis of gas turbine start up curve and different phase auxiliary system to go out different phase Station-service power load distributing situation, including the Combined cycle gas-steam turbine unit factory different with the unit on-load stage in the high disk of unit Power load distribution situation;Make full use of the characteristics of Combined cycle gas-steam turbine unit station-service load is in interim distribution, selection 2) capacity of work incoming switch and standby inlet switch, enters step after determining;
The voltage that HV auxiliary power s ystem is arranged in step 2) is identical as generator voltage and main transformer low-pressure side voltage, enters after determining Step 3);
Reactor is arranged between main transformer low-pressure side and work inlet wire in step 3), enters step 4) after determining;
Double spare power transfer device is arranged in electric room in step 4), cuts closing circuit fastly in electric power incoming line switch Middle setting latching logic prevents the three unit operations of same unit HV auxiliary power s ystem while load, enters step 5) after determining;
Step 5) double spare power supply fast switching device selects the priority of backup power source, realizes working power and backup power source one Between two-way switching or working power and backup power source two between two-way switching, improve the secondary circuit of fast cutting system.
Further, the station-service total load for counting every set unit, for confirming the capacity of work incoming switch;It calculates different Station-service maximum load under operating condition, for determining the capacity of standby inlet switch.
Further, in step 1) the station-service total load of every set unit be all high-tension motors and low pressure factory varying capacity it With;Work incoming switch capacity is the requirement for different phase station-service load and there are the allowances for being not less than 10%.
Further, step 2) mesohigh station service work incoming power is derived from main transformer low-pressure side, and double spare power supply is derived from The high-voltage auxiliary bus of adjacent unit.
Further, pass through the impedance of power system capacity, system impedance and main transformer in step 3), calculate main transformer low-pressure side short circuit Electric current is calculated the short circuit current of main transformer low-pressure side using nodal method, determines current-limiting reactor according to main transformer low-pressure side short circuit current Capacity.
Station service fast switching device mentioned in the present invention is worked as realizing auxiliary power change-over, fast switching device for judging Preceding operating status, and according to different orders execute it is different cut operation fastly, the analog quantity that fast switching device acquires has work The voltage of power supply, backup power source inlet wire and bus, the switch state of work incoming switch and standby inlet switch, working power The electric current of inlet wire and backup power source inlet wire, these are used to judge the operating status of station service electrical system;It is opened for executing work inlet wire It closes and the command drcuit of standby inlet switch breaking-closing operating, Fast Switch with Large Capacity FSR is known as high speed current-limiting protection switch, Main function is before short circuit current does not rise to peak value, and by its high-speed breaking, Fast Switch with Large Capacity has switch off time The features such as short, connecting-disconnecting function is strong, cheap.
Compared with prior art, the invention has the following beneficial technical effects: according to normal duty setting work into Wiretap has biggish allowance to can satisfy the oepration at full load simultaneously of two sets of units, does not need that high factory's change and Qi Beibian is arranged, It eliminates to open and is derived from problem where for variable power source, only increase reactor and large capacity switch, both reduce equipment investment, Occupied area is saved again.
Further, station service all is from spontaneous electricity, has saved the price difference of outer power purchase and self-generated electricity.
Further, working power and backup power source come from the same substation, due to using the identical mode of connection, solution Working power of having determined and the big problem of backup power source generator rotor angle.
Further, this system uses the fast butt formula of station service of double spare power supply, and is provided with special latching logic, High reliablity, flexible operation.
Detailed description of the invention
Fig. 1 is in the prior art containing the fast cutting system schematic diagram of station service for opening standby change;
Fig. 2 is the station-service load chart under Combined cycle gas-steam turbine distributed energy unit different conditions;
Fig. 3 is the fast cutting system schematic diagram of three power supplys of the invention;
Fig. 4 is the fast cutting system circuit breaker lock logic chart of three power supplys of the invention;
Fig. 5 is the fast cutting system of three power supplys of the invention and method flow diagram.
Specific embodiment
Below with reference to specific embodiment, the present invention is described in further detail, it is described be explanation of the invention and It is not to limit.
As shown in Figure 1, needing to be arranged special high pressure factory in the fast cutting system of traditional station service and becoming offer work inlet wire electricity Source is arranged special open and provides starting backup power source for change, and opening standby change high side power can be derived from and the same boosting of main transformer It stands or is derived from special route.The usual equipment arrangement of Combined cycle gas-steam turbine distributed energy project is concentrated, and unit number is more, Land occupation is few;For Combined cycle gas-steam turbine distributed energy project, there are deficiencies below for the fast cutting system of traditional station service: Fast cutting system needs to be separately provided HV Auxiliary Transformer, the spare change of starting and enclosed busbar, no matter opens standby variable power source and is derived from this Factory's booster stations or independent route, this system land occupation is more, invests larger;Working power and backup power source use different wiring Mode, two power supply generator rotor angles are big, and normal switching can only select series connection switching mode, have of short duration power loss during auxiliary Power switching, no Conducive to stable operation of unit;Backup power source is external power supply, is spent higher;And open standby variable power source and belong to outer power purchase, it is costly.
As shown in Fig. 2, the station-service load of typical Combined cycle gas-steam turbine distributed energy project is in interim distribution; First load peak appears in height and makes an inventory during fire, during about 60% revolving speed;Another load peak appear in it is grid-connected after During unit oepration at full load;The high load peak during fire of making an inventory is maximum.According to design specification, " large and medium-sized thermal power plant is set Meter specification " GB 50660-2011 design work incoming switch capacity be consider all station-service loads requirement and there are 10% or more allowance, therefore the capacity of the switch can meet two unit station-service loads simultaneously.
As shown in figure 3, being one embodiment of the invention, work incoming switch is mounted on working power inlet wire, is connected to Between high-voltage auxiliary bus and current-limiting reactor, in the present embodiment:
For No. 1 fast cutting system of unit station service: switch 9101 is work incoming switch, and 9100 be one inlet wire of backup power source Switch, 9300 be two incoming switch of backup power source;
For No. 2 fast cutting systems of unit station service: switch 9201 is work incoming switch, and 9200 be one inlet wire of backup power source Switch, 9100 be two incoming switch of backup power source;
For No. 3 fast cutting systems of unit station service: switch 9301 is work incoming switch, and 9300 be one inlet wire of backup power source Switch, 9200 be two incoming switch of backup power source;
Wherein 9100G, 9200G and 9300G are isolation switch;9101G, 9201G and 9301G disconnecting switch.
The fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy, Voltage Classes of HV Electrical Auxiliary and generator go out Mouth voltage and main transformer low-pressure side voltage are identical, and HV auxiliary power s ystem working power is derived from main transformer low-pressure side, and double spare power supply is derived from Reactor is arranged for limiting short-circuit electricity in the high-voltage auxiliary bus of adjacent unit between main transformer low-pressure side and working power inlet wire Stream.
As shown in figure 4, the station service of same unit while three units of band, work incoming switch and standby inlet switch It is easy overload, in addition excessive station-service load contact is unfavorable for stable operation of unit;Therefore, it is provided with latching logic, is prevented The station service of a certain unit while the station-service load of three units of band, in the present embodiment, the latching logic pass through DCS or hard Wiring realizes, latching logic as shown in Figure 4, first set fast cutting system by fast switching device, 9101 switches, 9100 switches and 9300 switch constitute, fast switching device be used for be responsible for 9101 switches and 9100 switch between being switched fast or 9101 switch and Handoff relation is not present between 9100 switches and 9300 switches in being switched fast between 9300 switches;Switch latching logic with the For a set of:
The combined floodgate condition of 9101 switches are as follows: when 9100 switch separating brakes and 9300 switches close a floodgate;9300 switch separating brakes and 9100 Switch closes a floodgate;9100 switches and the 9300 equal separating brakes of switch, the setting of this latching logic effectively avoid 9100 switches and 9300 from opening When Guan Jun closes a floodgate, fast switching device closes a floodgate to 9101 switches, causes the high-voltage Auxiliary system while three units of band of first set unit House load operation.
The combined floodgate conditions of 9100 switches are as follows: 9200 and 9300 switches in gate-dividing state, because if 9200 switches and Any one switch of 9300 switches reforms into the high-voltage Auxiliary system of first set unit simultaneously after 9100 switches close a floodgate in coincidence House load operation with three units.
The combined floodgate condition of 9300 switches is such that 9100 and 9200 switches in gate-dividing state, because if 9100 open It closes and reforms into the high-voltage Auxiliary system of first set unit after 9300 switches close a floodgate in coincidence with any one switch of 9200 switches The House load operation of three units of band simultaneously.
In addition, the closing locking logic of the closing locking reference logic switch 9101 of switch 9201 and switch 9301.
The present invention takes full advantage of that Combined cycle gas-steam turbine distributed energy project unit capacity is small, and voltage is low, unit The characteristics of number is more, and station-service load is in interim distribution.Working power and backup power source are taken respectively from main transformer low-pressure side and adjacent Unit bus does not need setting and opens standby become and the change of high factory.
Specifically as shown in figure 5, a kind of fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy and method, real Now include the following steps:
Step 1: counting the station-service total load (the sum of all high-tension motors and low pressure factory varying capacity) of every set unit, be used for The capacity for confirming work incoming switch, passes through the power output comprehensive analysis to gas turbine start up curve and different phase auxiliary system The station-service maximum load under different operating conditions is calculated, for determining the capacity of standby inlet switch, as shown in Fig. 2, through multiple Gas-steam combined cycle power plant calculates and actual measurement, and maximum load appears in unit height and makes an inventory during fire.High disk load is that SFC is dragged Dynamic combustion engine height makes an inventory fire to the station-service peak load of unit before set grid-connection, mainly includes SFC system loading, water system, oil system The sub-load of system and waste heat boiler.Work becomes, water system becomes, complex building becomes 25% estimation according to capacity.SFC transformer is pressed According to 90% estimation of capacity, excitation-transformation variable considers according to 30% power output.Height two water circulating pumps satisfactions of starting during fire of making an inventory are followed The requirement of ring water.
Step 2: selection Voltage Classes of HV Electrical Auxiliary is identical with generator outlet.High-voltage Auxiliary working power is derived from main transformer Low-pressure side, high-voltage Auxiliary backup power source one and power supply two are derived from the high-voltage auxiliary bus of adjacent unit.Main transformer low-pressure side extremely works Electric power incoming line uses cable connection using bus connection, backup power source inlet wire is poured, and setting disconnecting switch is for overhauling isolation.
Step 3: by the impedance of power system capacity, system impedance and main transformer, main transformer low-pressure side short circuit current is calculated, according to this Electric current determines that the capacity of reactor, reactor are used for limiting short-circuit current.
Step 4: for security reasons, not allowing the service power of three sets of units to be derived from same section of bus, therefore set Special latching logic is counted, which can realize by DCS or hardwire.
Step 5: fast switching device selects the fast switching device of double spare power supply, and device can select standby electricity with a distant place or on the spot After selection, normal switching, improper switching and the judging accident of work, backup power source may be implemented, two is spare in the priority in source Handoff relation is not present between power supply.Improve the secondary circuit of fast cutting system.
In the present embodiment, which uses three sets of one-to-one Combined cycle gas-steam turbine units, realizes cold Thermoelectricity trilogy supply is typical Combined cycle gas-steam turbine distributed energy project.Based on the considerations of economy and convenience, factory It is 550 meters of the head of district, 80 meters wide, the design of the fast cutting system of station service is put forward new requirements.Gas electricity generator capacity is 51MW, electricity Pressure is 10.5kV, and GCB is arranged in generator outlet.Based on the considerations of economy and practicability, the grade that HV auxiliary power s ystem is arranged is 10.5kV is identical as generator outlet voltage and main transformer low-pressure side voltage.According to station-service load statistical form, statistics obtains single set machine Group station-service total load 11920kW selects work incoming switch, capacity 721A according to 10% allowance;It unites according to the above principle Meter, peak load 7340kW select interconnection switches 9100 and 9300, capacity 444A according to 10% allowance.
As shown in figure 3, high-voltage Auxiliary working power is derived from main transformer low-pressure side, high-voltage Auxiliary backup power source one and power supply two are taken From the high-voltage auxiliary bus of adjacent unit.Main transformer low-pressure side to working power inlet wire using pours bus connection, backup power source into Line uses cable connection, and setting disconnecting switch is for overhauling isolation.
Setting reactor parallel connection large capacity, which switchs, between main transformer low-pressure side and work inlet wire is used for limiting short-circuit current.According to On the basis of being 100MVA according to power system capacity, system impedance Z1=0.0349, Z2=0.0349, Z3=0.0508, main transformer capacity is 100000kVA, Ud=13.88% calculate the short circuit current of main transformer low-pressure side using nodal method, according to " power engineering is electrically set Count handbook: electrical primary part " selection reactor model, select reactor for 0.303 Ω, reactance Rate 5%.Full factory's setting Three sets of fast switching devices, every set fast switching device realize the auxiliary Power switching of this TV station unit.
Every set system is made of working power, backup power source one and backup power source two.One is arranged on every set fast switching device Conversion handle is used to select the priority of backup power source, can also select backup power source in the priority of DCS selection backup power source One is two-way switching between working power and backup power source one when being main, and backup power source two is selected to refer to working power and spare Two-way switching between power supply two, backup power source one and backup power source two do not have handoff relation.As shown in figure 3, in figure most No. 1 unit in left side, working power are derived from 1 main transformer low-pressure side, and backup power source one is No. 2 unit high voltage bus section bus, that is, 10kV II sections, backup power source two be No. 3 unit high voltage bus section bus, that is, III sections of 10kV, first set fast switching device by switch 9101, 9100 and 9300 compositions, busbar voltage are derived from voltage transformer 91PT, and work primary voltage is derived from voltage transformer 9101PT, standby The voltage transformer 92PT of II sections of buses of 10kV connection is derived from one voltage of inlet wire, spare two voltage of inlet wire is derived from 10kV III The voltage transformer 93PT of section bus connection;
When it is main for selecting backup power source one, refer to the switching between switch 9101 and 9100;
When it is main for selecting backup power source two, refer to the switching between switch 9101 and 9300.
By taking above-mentioned distribution Combined cycle gas-steam turbine distributed energy project as an example, the station service designed using this method is fast Cutting system saves full factory and saves three Tai Gao factories change expense (about 720,000 yuan of separate unit 12500KVA transformer) altogether, saves one Platform opens standby change expense (about 1,050,000 yuan of separate unit 25000KVA transformer), an interval 110kV GIS (400,000), and increase expense is Three sets of reactors and large capacity switch (20,000+large capacity of reactor switch 200,000), it is total to save money about 2,950,000.In addition it saves Liao Santaigao factory becomes, opens the construction land at standby change and an interval GIS, effectively alleviates the situation of soil anxiety.Station service It all is from spontaneous electricity, has saved the price difference of outer power purchase and self-generated electricity.Working power and backup power source come from the same power transformation It stands, due to using the identical mode of connection, solves the problems, such as that working power and backup power source generator rotor angle are big.Further, this system Using the fast butt formula of the station service of double spare power supply, and be provided with special latching logic, improve station service reliability and The flexibility of operation.
The above is only presently preferred embodiments of the present invention, is not intended to limit the invention in any way, it is all according to the present invention Technical spirit any simple modification to the above embodiments, change and equivalent structural changes, still fall within skill of the present invention In the protection scope of art scheme.

Claims (10)

1. a kind of fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy, which is characterized in that including three units, often Platform unit is respectively arranged with a high-voltage auxiliary bus and for providing the working power inlet wire of work incoming power, working power into Line is connected to main transformer low-pressure side through current-limiting reactor, and current-limiting reactor both ends are parallel with high speed current-limiting protection switch;Any two It is connected respectively by backup power source incoming switch between the high-voltage auxiliary bus of unit, passes through the on-off of backup power source incoming switch Control the connection between the high-voltage auxiliary bus between unit.
2. a kind of fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy according to claim 1, feature It is, when the work incoming switch of a certain unit is in "on" position, the height of high-voltage auxiliary bus and other two unit Pressure auxiliary bus bar between backup power source incoming switch have one in quartile.
3. a kind of fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy according to claim 1, feature Be, be respectively arranged with a fast switching device in each unit, in three units, for some unit high-voltage auxiliary bus and Speech, the high-voltage auxiliary bus of other two unit realize two backup power source priority by fast switching device as backup power source Setting.
4. a kind of fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy according to claim 1, feature It is, main transformer low-pressure side to working power inlet wire uses cable connection, work electricity using bus connection, backup power source inlet wire is poured Source and backup power source come from the same substation, using the identical mode of connection.
5. a kind of fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy according to claim 1, feature It is, the high-pressure side of the current-limiting reactor is provided with the disconnecting switch for overhauling isolation, the high pressure factory of any two units Isolation switch is also in series with the backup power source incoming switch connected between bus.
6. a kind of three power supply quick switch method of Combined cycle gas-steam turbine distributed energy, which comprises the steps of:
Step 1) goes out the factory of different phase in conjunction with the power output comprehensive analysis of gas turbine start up curve and different phase auxiliary system With power load distributing situation, including the Combined cycle gas-steam turbine unit station service different with the unit on-load stage in the high disk of unit Power load distributing situation;The characteristics of Combined cycle gas-steam turbine unit station-service load is in interim distribution is made full use of, work is selected 2) capacity of incoming switch and standby inlet switch enters step after determining;
The voltage that HV auxiliary power s ystem is arranged in step 2) is identical as generator voltage and main transformer low-pressure side voltage, enters step after determining 3);
Reactor is arranged between main transformer low-pressure side and work inlet wire in step 3), enters step 4) after determining;
Double spare power transfer device is arranged in electric room in step 4), sets in cutting in closing circuit fastly for electric power incoming line switch Latching logic is set, the three unit operations of same unit HV auxiliary power s ystem while load is prevented, is entered step 5) after determining;
Step 5) double spare power supply fast switching device selects the priority of backup power source, realizes between working power and backup power source one Two-way switching or working power and backup power source two between two-way switching, improve the secondary circuit of fast cutting system.
7. three power supply quick switch method of a kind of Combined cycle gas-steam turbine distributed energy according to claim 6, feature It is, the station-service total load of every set unit is counted, for confirming the capacity of work incoming switch;It calculates under different operating conditions Station-service maximum load, for determining the capacity of standby inlet switch.
8. three power supply quick switch method of a kind of Combined cycle gas-steam turbine distributed energy according to claim 6, feature It is, the station-service total load of every set unit is the sum of all high-tension motors and low pressure factory varying capacity in step 1);Work inlet wire Contact capacity is the requirement for different phase station-service load and there are the allowances for being not less than 10%.
9. three power supply quick switch method of a kind of Combined cycle gas-steam turbine distributed energy according to claim 6, feature It is, step 2) mesohigh station service work incoming power is derived from main transformer low-pressure side, and double spare power supply is derived from the height of adjacent unit Press auxiliary bus bar.
10. three power supply quick switch method of a kind of Combined cycle gas-steam turbine distributed energy according to claim 6, feature It is, passes through the impedance of power system capacity, system impedance and main transformer in step 3), main transformer low-pressure side short circuit current is calculated, using section Point method calculates the short circuit current of main transformer low-pressure side, and the capacity of current-limiting reactor is determined according to main transformer low-pressure side short circuit current.
CN201910754774.6A 2019-08-15 2019-08-15 A kind of fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy and method Pending CN110401194A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910754774.6A CN110401194A (en) 2019-08-15 2019-08-15 A kind of fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910754774.6A CN110401194A (en) 2019-08-15 2019-08-15 A kind of fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy and method

Publications (1)

Publication Number Publication Date
CN110401194A true CN110401194A (en) 2019-11-01

Family

ID=68328533

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910754774.6A Pending CN110401194A (en) 2019-08-15 2019-08-15 A kind of fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy and method

Country Status (1)

Country Link
CN (1) CN110401194A (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110854925A (en) * 2019-11-04 2020-02-28 中国能源建设集团华东电力试验研究院有限公司 One-time voltage-on synchronous nuclear phase inspection system and inspection method for electrical system
CN111900735A (en) * 2020-07-07 2020-11-06 西安热工研究院有限公司 Multi-power-supply parallel type factory power supply system and parallel method thereof
CN112564101A (en) * 2020-12-08 2021-03-26 华能巢湖发电有限责任公司 Control method for external electricity purchase in starting and stopping process of unit
CN112865077A (en) * 2021-01-13 2021-05-28 西安热工研究院有限公司 Locking method for factory power supply system switch in hand-pulling mode
CN112993948A (en) * 2021-02-23 2021-06-18 广西电网有限责任公司电力科学研究院 Circuit and method for preventing relay protection misoperation in loop closing operation
CN113224750A (en) * 2021-04-28 2021-08-06 中国能源建设集团广东省电力设计研究院有限公司 Novel high-voltage standby power supply leading method of gas-steam combined cycle power station
CN114165730A (en) * 2021-12-06 2022-03-11 武汉科技大学 One-key pressurization intelligent control method for mixed gas

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101860075A (en) * 2010-05-28 2010-10-13 上海龙净环保科技工程有限公司 Three-power supply automatic switching device
CN103326457A (en) * 2013-06-02 2013-09-25 深圳市广前电力有限公司 Control method and control device based on gas-steam integral unit security segment interlock automatic switch
CN104242455A (en) * 2014-09-24 2014-12-24 天津大学 110 kV substation protection and control action cooperation strategy suitable for DG (distributed generation) accessing
CN105449673A (en) * 2015-12-16 2016-03-30 广东电网有限责任公司中山供电局 Control method and system for converting paralleling operation into separated operation for dual-bus section substation
CN108134387A (en) * 2018-01-05 2018-06-08 中国电力工程顾问集团东北电力设计院有限公司 A kind of novel unit service power fast switch over method
CN210111608U (en) * 2019-08-15 2020-02-21 西安热工研究院有限公司 Gas and steam combined cycle distributed energy three-power-source quick switching system

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101860075A (en) * 2010-05-28 2010-10-13 上海龙净环保科技工程有限公司 Three-power supply automatic switching device
CN103326457A (en) * 2013-06-02 2013-09-25 深圳市广前电力有限公司 Control method and control device based on gas-steam integral unit security segment interlock automatic switch
CN104242455A (en) * 2014-09-24 2014-12-24 天津大学 110 kV substation protection and control action cooperation strategy suitable for DG (distributed generation) accessing
CN105449673A (en) * 2015-12-16 2016-03-30 广东电网有限责任公司中山供电局 Control method and system for converting paralleling operation into separated operation for dual-bus section substation
CN108134387A (en) * 2018-01-05 2018-06-08 中国电力工程顾问集团东北电力设计院有限公司 A kind of novel unit service power fast switch over method
CN210111608U (en) * 2019-08-15 2020-02-21 西安热工研究院有限公司 Gas and steam combined cycle distributed energy three-power-source quick switching system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
罗俊然等: "燃气蒸汽联合循环分布式能源的电气整套启动", 《电工技术》, 10 May 2018 (2018-05-10), pages 121 - 125 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110854925A (en) * 2019-11-04 2020-02-28 中国能源建设集团华东电力试验研究院有限公司 One-time voltage-on synchronous nuclear phase inspection system and inspection method for electrical system
CN110854925B (en) * 2019-11-04 2021-06-08 中国能源建设集团华东电力试验研究院有限公司 One-time voltage-on synchronous nuclear phase inspection system and inspection method for electrical system
CN111900735A (en) * 2020-07-07 2020-11-06 西安热工研究院有限公司 Multi-power-supply parallel type factory power supply system and parallel method thereof
CN112564101A (en) * 2020-12-08 2021-03-26 华能巢湖发电有限责任公司 Control method for external electricity purchase in starting and stopping process of unit
CN112564101B (en) * 2020-12-08 2022-08-30 华能巢湖发电有限责任公司 Control method for external electricity purchase in starting and stopping process of unit
CN112865077A (en) * 2021-01-13 2021-05-28 西安热工研究院有限公司 Locking method for factory power supply system switch in hand-pulling mode
CN112865077B (en) * 2021-01-13 2023-08-08 西安热工研究院有限公司 Locking method of factory power system switch in hand-in-hand mode
CN112993948A (en) * 2021-02-23 2021-06-18 广西电网有限责任公司电力科学研究院 Circuit and method for preventing relay protection misoperation in loop closing operation
CN113224750A (en) * 2021-04-28 2021-08-06 中国能源建设集团广东省电力设计研究院有限公司 Novel high-voltage standby power supply leading method of gas-steam combined cycle power station
CN114165730A (en) * 2021-12-06 2022-03-11 武汉科技大学 One-key pressurization intelligent control method for mixed gas

Similar Documents

Publication Publication Date Title
CN110401194A (en) A kind of fast cutting system of three power supply of Combined cycle gas-steam turbine distributed energy and method
CN205231835U (en) Structure for large -scale thermal power factory unit high pressure service power each other is being equipped with
CN106655478A (en) Low-voltage emergency safety power supply system of household garbage power plant and control method of system
CN106816883B (en) three-phase unbalance adjusting system parallel input system, control method and device
CN206575222U (en) Waste-to-energy plant low pressure emergency security power system
Liu Analysis of Brazilian blackout on March 21st, 2018 and revelations to security for Hunan Grid
CN106251748A (en) A kind of electric power system fault analog
CN111416389A (en) Backpressure machine switching system
CN210111608U (en) Gas and steam combined cycle distributed energy three-power-source quick switching system
CN110912138A (en) Distribution network loop closing control method
CN106208153A (en) A kind of power plant subsidiary engine tracking power source system
CN102208811A (en) Wiring structure of distribution network containing microgrid
CN209375151U (en) A kind of multi-source complementation accumulation energy type power plant emergency power supply system
CN108011376B (en) Method for improving control capability of power grid in emergency state based on electric heat storage load
CN210957911U (en) High-voltage station service system
CN210123906U (en) Electric main wiring structure of distributed energy power station
CN207910471U (en) A kind of hybrid AC/DC power transmission systems containing specific load
CN203481825U (en) Optimized natural gas distribution-type energy main wiring circuit
CN206922422U (en) A kind of single line of power plant sends out line fault protection system
CN208489690U (en) A kind of become based on high factory has the voltage-regulating system for carrying transformer
CN216215851U (en) Backpressure generator control protection system
CN215733653U (en) Double-diesel power generation and distribution system suitable for offshore booster station
CN111404161A (en) Intelligent power consumption management and inter-station-area mutual-aid transfer system and method
CN111162530A (en) Power access system for accessing generator outlet to peak regulation facility
Zhu et al. Research and Implementation of Control Strategies for Multiple Transmission Modes in Yongren-Funing HVDC

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination