CN110397304A - A kind of construction wall bracing means - Google Patents

A kind of construction wall bracing means Download PDF

Info

Publication number
CN110397304A
CN110397304A CN201910684512.7A CN201910684512A CN110397304A CN 110397304 A CN110397304 A CN 110397304A CN 201910684512 A CN201910684512 A CN 201910684512A CN 110397304 A CN110397304 A CN 110397304A
Authority
CN
China
Prior art keywords
plate
bracing means
construction wall
wall
fixedly connected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910684512.7A
Other languages
Chinese (zh)
Other versions
CN110397304B (en
Inventor
田亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ANHUI HUARUI WATER CONSERVANCY Co.,Ltd.
Original Assignee
田亮
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 田亮 filed Critical 田亮
Priority to CN201910684512.7A priority Critical patent/CN110397304B/en
Publication of CN110397304A publication Critical patent/CN110397304A/en
Application granted granted Critical
Publication of CN110397304B publication Critical patent/CN110397304B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements
    • E04G23/0222Replacing or adding wall ties

Abstract

The present invention relates to building fields, it in particular is a kind of construction wall bracing means, plate is stretched out including bottom plate, patch wallboard, spring loop bar, slide and left and right, the present invention can be by wall reinforcement, and the present invention will not be thoroughly fixed on the wall, expand with heat and contract with cold, earthquake when, slight deformation can occur for wall, avoid thoroughly being fixed on the wall and damage to wall.Patch wallboard is fixedly connected on rear side of the bottom plate, the left and right ends of patch wallboard are fixedly connected to spring loop bar, compressed spring is socketed on two spring loop bars, the lower end of slide is slidably connected at the middle part of bottom plate in the longitudinal direction, the left and right ends of slide are fixedly connected to left and right and stretch out plate, two or so stretching plates are slidably connected at respectively on two spring loop bars, slide fixed setting, and two compressed springs are respectively positioned on patch wallboard and stretch out between plate with corresponding left and right.

Description

A kind of construction wall bracing means
Technical field
The present invention relates to building fields, are in particular a kind of construction wall bracing means.
Background technique
A kind of wall reinforcement construction of CN201821465910.7 disclosed in application number, the utility model disclose a kind of wall Reinforcing construction, comprising: wall, multiple material grid, fixing piece one, screed;The multiple material grid is fixed on institute by fixing piece one It states on wall;The screed is covered on the outside of the multiple material grid;The multiple material grid is by several longitudinal limbs and several Vertically alternately continuous arrangement is constituted a transverse direction limb, and is integrally formed by resin solidification;The fixing piece one includes: anchorage and riveting Nail;Wherein two adjacent sides of the anchorage open up fluted, and the longitudinal direction limb and the lateral limb are fixed in the groove; The multiple material grid is fixed on the wall by the rivet through the anchorage;It further include fixing piece two, bottom plate;The wall Body is fixedly connected by the way that the fixing piece two is vertical with the bottom plate.The wall reinforcement structure of utility model design is not only reinforced Effect is good, and will not damage to original wall body structure, and easy to operate, durability is good.But this construction can not adapt to Expand with heat and contract with cold, earthquake when, wall can there is a situation where slight deformations.
Summary of the invention
The present invention provides a kind of construction wall bracing means, its advantages be the present invention can by wall reinforcement, and The present invention will not be thoroughly fixed on the wall, expand with heat and contract with cold, earthquake when, slight deformation can occur for wall, avoid thorough fixation Wall is damaged on wall.
The present invention relates to building fields, are in particular a kind of construction wall bracing means, including bottom plate, patch wallboard, Plate is stretched out in spring loop bar, slide and left and right, and the present invention can be by wall reinforcement, and the present invention will not thoroughly be fixed on wall On, expand with heat and contract with cold, earthquake when, slight deformation can occur for wall, avoid thoroughly being fixed on the wall and damage to wall.
Patch wallboard is fixedly connected on rear side of the bottom plate, the left and right ends for pasting wallboard are fixedly connected to spring loop bar, Compressed spring is socketed on two spring loop bars, the lower end of slide is slidably connected at the middle part of bottom plate in the longitudinal direction, sliding The left and right ends of seat are fixedly connected to left and right and stretch out plate, and two or so stretching plates are slidably connected at two spring loop bars respectively On, slide fixed setting, two compressed springs are respectively positioned on patch wallboard and stretch out between plate with corresponding left and right.
The construction wall bracing means further includes trapezoidal sliding rail, is provided with trapezoidal sliding rail in the middle part of bottom plate, under slide End is slidably connected on trapezoidal sliding rail.
The construction wall bracing means further includes nut I, and the front end of two spring loop bars has been connected through a screw thread spiral shell Female I, two nut I keep off the front side that plate is stretched out at two or so respectively.
The construction wall bracing means further includes L shape connecting column, foundation bolt and ground fixed strip, and the front end of slide is solid Surely it is connected with L shape connecting column, the front lower portion of L shape connecting column is fixedly connected with ground fixed strip, and ground fixed strip passes through two Foundation bolt is fixedly connected on the ground.
The construction wall bracing means further includes column, rear baffle and nut II through walls, is pasted fixed in the middle part of the rear side of wallboard It is connected with column through walls, rear baffle is plugged on column through walls, the rear end of column through walls has been connected through a screw thread nut II, and nut II is located at The rear side of rear baffle.
The construction wall bracing means further includes horizontal slide track bar, perpendicular slide track bar and oblique hack lever, the left and right two of horizontal slide track bar End is fixedly connected to oblique hack lever, and the lower end of two oblique hack levers is respectively fixedly connected in the left and right ends of bottom plate, horizontal slide track bar Middle part is fixedly connected with perpendicular slide track bar.
The construction wall bracing means further includes sliding sleeve, telescopic rod II, middle sliding block and diagonal control arm, and sliding sleeve left and right settings has Two, two sliding sleeves are slidably connected at the left and right ends of horizontal slide track bar respectively, telescopic rod II be can free adjustment length bar Body, there are two telescopic rod II left and right settings, and the lower end of two telescopic rod II is hingedly connected on two sliding sleeves, and middle sliding block is sliding Dynamic to be connected on perpendicular slide track bar, the left and right ends of middle sliding block are hingedly connected with diagonal control arm, and the outer end of two diagonal control arms dips down Tiltedly, the outer end of two diagonal control arms is hingedly connected on two sliding sleeves.
The construction wall bracing means further includes top plate, slide opening, front plate, threaded stud, nut III, rear plate, spiral shell The front end downside of pit plate and screw, top plate is fixedly connected with front plate, and the left and right ends of front plate are fixedly connected to spiral shell Line short column, the upper end of two telescopic rod II are rotatably connected on respectively in two threaded studs, pass through spiral shell in two threaded studs Line is connected with nut III, and two nut III keep off the front side in two telescopic rod II respectively, are provided with slide opening in the middle part of top plate, after Clamping plate is located at the rear side of front plate, and the upper end of rear plate is slidably connected on slide opening, and the left and right ends of top plate rear end are fixed to be connected It is connected to screw thread orifice plate, screw has been connected through a screw thread on two screw thread orifice plates, after two screws withstand on rear plate Side.
The construction wall bracing means further includes telescopic rod I, and the lower end of telescopic rod I is hingedly connected on L shape connecting column, The upper end of telescopic rod I is hingedly connected to the front side of middle sliding block.
The telescopic rod I and telescopic rod II is two-part structure, telescopic rod I and telescopic rod II by a hollow thick bar With a solid thin bar composition, solid thin bar is inserted in hollow thick bar, is provided with fastening screw in hollow thick bar, solid thin bar and It is fixed between hollow thick bar by fastening screw.
A kind of construction wall bracing means of the invention has the beneficial effect that
A kind of construction wall bracing means of the present invention, the present invention can be by wall reinforcement, and the present invention will not thoroughly consolidate Be scheduled on wall, expand with heat and contract with cold, earthquake when, slight deformation can occur for wall, avoid thoroughly being fixed on the wall and make to wall At damage.
Expand with heat and contract with cold, earthquake when, slight deformation can occur for wall, since patch wallboard can slide back and forth, and then can be with The slight deformation that wall occurs is adapted to, avoids thoroughly being fixed on the wall wall is damaged.
Rear baffle and patch wallboard clamp the front and rear sides of wall, and wall is further reinforced.
When wall has the tendency that toppling over to patch wallboard direction,
Top plate gives wall downward power, at this moment wall give power downwards penetrated so that wall is more stable The trend toppled over is eliminated on ground.
Detailed description of the invention
The present invention will be further described in detail with specific implementation method with reference to the accompanying drawing.
Fig. 1 is a kind of overall structure diagram one of construction wall bracing means of the present invention;
Fig. 2 is a kind of overall structure diagram two of construction wall bracing means of the present invention;
Fig. 3 is the structural schematic diagram one of bottom plate;
Fig. 4 is the structural schematic diagram two of bottom plate;
Fig. 5 is the structural schematic diagram of slide;
Fig. 6 is the structural schematic diagram of horizontal slide track bar;
Fig. 7 is the structural schematic diagram of sliding sleeve, telescopic rod II and middle sliding block;
Fig. 8 is the structural schematic diagram one of top plate;
Fig. 9 is the structural schematic diagram two of top plate;
Figure 10 is the structural schematic diagram of wall.
In figure: bottom plate 1;Trapezoidal sliding rail 101;Paste wallboard 102;Spring loop bar 103;Nut I104;Column 105 through walls;After keep off Plate 106;Nut II107;Slide 2;Plate 201 is stretched out in left and right;L shape connecting column 202;Foundation bolt 203;Ground fixed strip 204;It stretches Contracting bar I205;Horizontal slide track bar 3;Perpendicular slide track bar 301;Oblique hack lever 302;Sliding sleeve 4;Telescopic rod II5;Middle sliding block 6;Diagonal control arm 601;Top Plate 7;Slide opening 701;Front plate 702;Threaded stud 703;Nut III704;Rear plate 705;Screw thread orifice plate 706;Screw 707; Wall 8.
Specific embodiment
In the description of the present invention, it is to be understood that, term " center ", " longitudinal direction ", " transverse direction ", "upper", "lower", The orientation or positional relationship of the instructions such as "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside" is It is based on the orientation or positional relationship shown in the drawings, is merely for convenience of description of the present invention and simplification of the description, rather than instruction or dark Show that signified device or element must have a particular orientation, be constructed and operated in a specific orientation, therefore should not be understood as pair Limitation of the invention.In addition, term " first ", " second " etc. are used for description purposes only, it is not understood to indicate or imply phase To importance or implicitly indicate the quantity of indicated technical characteristic.The feature for defining " first ", " second " etc. as a result, can To explicitly or implicitly include one or more of the features.In the description of the present invention, unless otherwise indicated, " multiple " It is meant that two or more.
Specific embodiment 1:
Illustrate present embodiment below with reference to Fig. 1-10, the present invention relates to building fields, are in particular a kind of buildings Plate 201 is stretched out in wall reinforcement device, including bottom plate 1, patch wallboard 102, spring loop bar 103, slide 2 and left and right, and the present invention can be with By wall reinforcement, and the present invention will not be thoroughly fixed on wall 8, expand with heat and contract with cold, earthquake when, wall 8 can occur slightly Deformation, avoids thoroughly being fixed on wall 8 and damages to wall.
The rear side of the bottom plate 1 is fixedly connected with patch wallboard 102, and the left and right ends of patch wallboard 102 are fixedly connected to bullet Spring loop bar 103 is socketed with compressed spring on two spring loop bars 103, and the lower end of slide 2 is slidably connected in the longitudinal direction The middle part of bottom plate 1, the left and right ends of slide 2 are fixedly connected to left and right and stretch out plate 201, and two or so stretching plates 201 are slided respectively Dynamic to be connected on two spring loop bars 103, slide 2 is fixedly installed, two compressed springs be respectively positioned on patch wallboard 102 with it is corresponding Left and right is stretched out between plate 201.In use, by fitting on one side for wallboard 102 and wall 8 is pasted, and slide 2 is fixed on ground On, slide 2 can slide back and forth on bottom plate 1, and slide 2 is closer at a distance from patch wallboard 102, on two spring loop bars 103 The compressed degree of compressed spring is bigger, so paste wallboard 102 give wall 8 dynamics it is bigger, prevent 8 run-off the straight of wall and Topple over, expand with heat and contract with cold, earthquake when, slight deformation can occur for wall 8, since patch wallboard 102 can slide back and forth, and then can be with The slight deformation that wall 8 occurs is adapted to, avoids thoroughly being fixed on wall 8 wall is damaged.
Specific embodiment 2:
Illustrate present embodiment below with reference to Fig. 1-10, the construction wall bracing means further includes trapezoidal sliding rail 101, bottom The middle part of plate 1 is provided with trapezoidal sliding rail 101, and the lower end of slide 2 is slidably connected on trapezoidal sliding rail 101.Slide 2 is by trapezoidal The adjustment realized slide 2 and paste distance between wallboard 102 is slid back and forth on sliding rail 101.
Specific embodiment 3:
Illustrating present embodiment below with reference to Fig. 1-10, the construction wall bracing means further includes nut I104, and two The front end of spring loop bar 103 has been connected through a screw thread nut I104, and two nut I104 are kept off respectively in two or so stretching plates 201 front side.Two nuts play the role of stopping two or so stretching plates 201, prevent left and right from stretching out plate 201 and are detached from relatively The spring loop bar 103 answered.
Specific embodiment 4:
Illustrate present embodiment below with reference to Fig. 1-10, the construction wall bracing means further include L shape connecting column 202, Foundation bolt 203 and ground fixed strip 204, the front end of slide 2 are fixedly connected with L shape connecting column 202, before L shape connecting column 202 End lower part is fixedly connected with ground fixed strip 204, and ground fixed strip 204 is fixedly connected on ground by two foundation bolts 203 On.Ground fixed strip 204 is fixedly connected on the ground by two foundation bolts 203, and then by the position of L shape connecting column 202 It is fixed, and then slide 2 and the relative position on ground are fixed.
Specific embodiment 5:
Illustrate present embodiment below with reference to Fig. 1-10, the construction wall bracing means further includes column 105, afterwards gear through walls Plate 106 and nut II107 are pasted and are fixedly connected with column 105 through walls in the middle part of the rear side of wallboard 102, keep off after being plugged on column 105 through walls Plate 106, the rear end of column 105 through walls have been connected through a screw thread nut II107, and nut II107 is located at the rear side of rear baffle 106.Make Used time drills out the hole of a correspondence column 105 through walls on wall 8, and column 105 through walls is passed through this hole through the another of wall Side, so that rear baffle 106 and the other side of wall fit, after turn nut II107 makes rear baffle 106 be fitted in wall 8 Side, at this moment rear baffle 106 and patch wallboard 102 clamp the front and rear sides of wall 8, and wall 8 is further reinforced.
Specific embodiment 6:
Illustrate present embodiment below with reference to Fig. 1-10, the construction wall bracing means further includes horizontal slide track bar 3, perpendicular cunning Rail bar 301 and oblique hack lever 302, the left and right ends of horizontal slide track bar 3 are fixedly connected to oblique hack lever 302, under two oblique hack levers 302 End is respectively fixedly connected in the left and right ends of bottom plate 1, and the middle part of horizontal slide track bar 3 is fixedly connected with perpendicular slide track bar 301.
The construction wall bracing means further includes sliding sleeve 4, telescopic rod II5, middle sliding block 6 and diagonal control arm 601, and sliding sleeve 4 is left There are two right settings, and two sliding sleeves 4 are slidably connected at the left and right ends of horizontal slide track bar 3 respectively, and telescopic rod II5 is freely to adjust The body of rod of length is saved, there are two telescopic rod II5 left and right settings, and the lower end of two telescopic rod II5 is hingedly connected in two cunnings On set 4, middle sliding block 6 is slidably connected on perpendicular slide track bar 301, and the left and right ends of middle sliding block 6 are hingedly connected with diagonal control arm 601, The outer end of two diagonal control arms 601 tilts down, and the outer end of two diagonal control arms 601 is hingedly connected on two sliding sleeves 4.Middle cunning Block 6 can vertical sliding, middle sliding block 6 can be by two tiltedly in vertical sliding on perpendicular slide track bar 301 on perpendicular slide track bar 301 Connecting rod 601 drives two sliding sleeves 4 close to each other or respectively far from sliding.
The construction wall bracing means further includes top plate 7, slide opening 701, front plate 702, threaded stud 703, nut The front end downside of III704, rear plate 705, screw thread orifice plate 706 and screw 707, top plate 7 is fixedly connected with front plate 702, preceding The left and right ends of clamping plate 702 are fixedly connected to threaded stud 703, and the upper end of two telescopic rod II5 is rotatably connected on two respectively In a threaded stud 703, nut III704 is connected through a screw thread in two threaded studs 703, two nut III704 divide The front side of two telescopic rod II5, the middle part of top plate 7 slide opening 701 Dang be provided with, after rear plate 705 is located at front plate 702 Side, the upper end of rear plate 705 are slidably connected on slide opening 701, and the left and right ends of 7 rear end of top plate are fixedly connected to screw thread orifice plate 706, screw 707 has been connected through a screw thread on two screw thread orifice plates 706, and two screws 707 withstand on rear plate 705 Rear side.Rear plate 705 can slide on slide opening 701, adjust the spacing between front plate 702 and rear plate 705, in use, Top plate 7 is ridden over to the upper end of wall 8, and front plate 702 and rear plate 705 is made to be fitted in the front and back of 8 upper end of wall respectively Two sides, two screws 707 of turn withstand on the rear side of rear plate 705, so that front plate 702 and rear plate 705 are by 8 upper end of wall It clamps;It when sliding block 6 moves up in the middle, drives two sliding sleeves 4 close to each other, is stretched when two sliding sleeves 4 are close to each other by two Contracting bar II5 drives front plate 702 and top plate 7 to move down, so that top plate 7 gives wall 8 downward power, at this moment wall 8 Give power downwards so that wall 8 is more stable.Two adjustable effects of telescopic rod II5 length are to adapt to difference The wall 8 of height, when front plate 702 is mounted on different walls 8 in different height, two telescopic rod II5 can be into Row adapts to.
Specific embodiment 7:
Illustrate present embodiment below with reference to Fig. 1-10, the construction wall bracing means further includes telescopic rod I205, is stretched The lower end of contracting bar I205 is hingedly connected on L shape connecting column 202, before the upper end of telescopic rod I205 is hingedly connected to middle sliding block 6 Side.When wall 8 has the tendency that toppling over to patch 102 direction of wallboard, opposite 202 forward slip of slide 2 and L shape connecting column of bottom plate 1, And then sliding block 6 moves up at this moment telescopic rod I205 promotion, so that driving two sliding sleeves 4 close to each other, two sliding sleeves 4 are mutual Close to when drive front plates 702 and top plate 7 to move down by two telescopic rod II5 so that top plate 7 give wall 8 to Under power, at this moment wall 8 give power downwards so that wall 8 it is more stable penetrate ground, the trend toppled over is disappeared It removes.The adjustable effect of telescopic rod I205 length is to adapt to the difference of the relative position of bottom plate 1 and slide 2.
Specific embodiment 8:
Illustrating present embodiment below with reference to Fig. 1-10, the telescopic rod I205 and telescopic rod II5 are two-part structure, Telescopic rod I205 and telescopic rod II5 is made of a hollow thick bar and a solid thin bar, and solid thin bar is inserted in hollow thick bar It is interior, it is provided with fastening screw in hollow thick bar, is fixed between solid thin bar and hollow thick bar by fastening screw.It realizes to adjust and stretch The length of contracting bar I205 and telescopic rod II5.
The working principle of the invention: in use, by fitting on one side for wallboard 102 and wall 8 is pasted, and slide 2 is consolidated Fixed slide 2 can slide back and forth on bottom plate 1 on the ground, closer, the two spring loop bars at a distance from patch wallboard 102 of slide 2 The compressed degree of compressed spring on 103 is bigger, so paste wallboard 102 give wall 8 dynamics it is bigger, prevent wall 8 send out Raw inclination and topple over, expand with heat and contract with cold, earthquake when, slight deformation can occur for wall 8, since patch wallboard 102 can slide back and forth, And then it is adapted to the slight deformation of the generation of wall 8, it avoids thoroughly being fixed on wall 8 wall is damaged.Slide 2 passes through The adjustment realized slide 2 and paste distance between wallboard 102 is being slid back and forth on trapezoidal sliding rail 101.Two nuts play resistance The effect of two or so stretching plates 201 of gear prevents left and right from stretching out plate 201 and is detached from corresponding spring loop bar 103.Ground fixed strip 204 are fixedly connected on the ground by two foundation bolts 203, and then the position of L shape connecting column 202 is fixed, and then will slide Seat 2 and the relative position on ground are fixed.In use, the hole of a correspondence column 105 through walls is drilled out on wall 8, by column through walls 105 pass through this hole through the other side of wall, so that rear baffle 106 and the other side of wall fit, turn nut II107 makes The rear side that rear baffle 106 is fitted in wall 8 is obtained, at this moment rear baffle 106 and patch wallboard 102 clamp the front and rear sides of wall 8, will Wall 8 is further reinforced.Middle sliding block 6 can on perpendicular slide track bar 301 vertical sliding, middle sliding block 6 it is vertical on perpendicular slide track bar 301 Two sliding sleeves 4 can be driven close to each other respectively by two diagonal control arms 601 when sliding or far from sliding.Rear plate 705 can To slide on slide opening 701, the spacing between front plate 702 and rear plate 705 is adjusted, in use, top plate 7 is ridden over wall 8 Upper end, and front plate 702 and rear plate 705 is made to be fitted in the front and rear sides of 8 upper end of wall, two top spiral shells of turn respectively Nail 707 withstands on the rear side of rear plate 705, so that front plate 702 and rear plate 705 clamp 8 upper end of wall;In the middle sliding block 6 to It when upper mobile, drives two sliding sleeves 4 close to each other, drives front plate by two telescopic rod II5 when two sliding sleeves 4 are close to each other 702 and top plate 7 move down so that top plate 7 gives wall 8 downward power, at this moment wall 8 give power downwards, So that wall 8 is more stable.Two adjustable effects of telescopic rod II5 length are the walls 8 for adapting to different height, work as fore-clamp When plate 702 is mounted on different walls 8 in different height, two telescopic rod II5 can be adapted to.When wall 8 is to patch When 102 direction of wallboard has the tendency that toppling over, opposite 202 forward slip of slide 2 and L shape connecting column of bottom plate 1, and then at this moment telescopic rod Sliding block 6 moves up in I205 promotion, so that driving two sliding sleeves 4 close to each other, passes through two when two sliding sleeves 4 are close to each other Telescopic rod II5 drives front plate 702 and top plate 7 to move down, so that top plate 7 gives wall 8 downward power, at this moment wall 8 give power downwards so that wall 8 it is more stable penetrate ground, the trend toppled over is eliminated.Telescopic rod I205 length Adjustable effect is to adapt to the difference of the relative position of bottom plate 1 and slide 2.
Certainly, above description is not limitation of the present invention, and the present invention is also not limited to the example above, the art The variations, modifications, additions or substitutions that those of ordinary skill is made within the essential scope of the present invention also belong to guarantor of the invention Protect range.

Claims (10)

1. a kind of construction wall bracing means, including bottom plate (1), patch wallboard (102), spring loop bar (103), slide (2) and a left side Right stretching plate (201), it is characterised in that: patch wallboard (102) is fixedly connected on rear side of the bottom plate (1), patch wallboard (102) Left and right ends are fixedly connected to spring loop bar (103), and compressed spring, slide (2) are socketed on two spring loop bars (103) Lower end be slidably connected at the middle part of bottom plate (1) in the longitudinal direction, the left and right ends of slide (2) are fixedly connected to left and right and stretch Ejecting plate (201), two or so stretching plates (201) are slidably connected at respectively on two spring loop bars (103), and slide (2) fixation is set It sets, two compressed springs are respectively positioned on patch wallboard (102) and stretch out between plate (201) with corresponding left and right.
2. a kind of construction wall bracing means according to claim 1, it is characterised in that: the construction wall bracing means Further include trapezoidal sliding rail (101), be provided in the middle part of bottom plate (1) trapezoidal sliding rail (101), the lower end of slide (2) is slidably connected at On trapezoidal sliding rail (101).
3. a kind of construction wall bracing means according to claim 2, it is characterised in that: the construction wall bracing means It further include (104) nut I, the front end of two spring loop bars (103) has been connected through a screw thread nut I (104), two nut I (104) front side that plate (201) are stretched out at two or so is kept off respectively.
4. a kind of construction wall bracing means according to claim 3, it is characterised in that: the construction wall bracing means It further include L shape connecting column (202), foundation bolt (203) and ground fixed strip (204), the front end of slide (2) is fixedly connected with L Shape connecting column (202), the front lower portion of L shape connecting column (202) are fixedly connected with ground fixed strip (204), ground fixed strip (204) it is fixedly connected on the ground by two foundation bolts (203).
5. a kind of construction wall bracing means according to claim 4, it is characterised in that: the construction wall bracing means Further include column through walls (105), rear baffle (106) and nut II (107), pastes to be fixedly connected in the middle part of the rear side of wallboard (102) and wear Wall column (105) is plugged with rear baffle (106) on column (105) through walls, and the rear end of column (105) through walls has been connected through a screw thread nut II (107), nut II (107) are located at the rear side of rear baffle (106).
6. a kind of construction wall bracing means according to claim 5, it is characterised in that: the construction wall bracing means It further include horizontal slide track bar (3), perpendicular slide track bar (301) and oblique hack lever (302), the left and right ends of horizontal slide track bar (3) are fixedly connected with Have oblique hack lever (302), the lower end of two oblique hack levers (302) is respectively fixedly connected in the left and right ends of bottom plate (1), horizontal slide track bar (3) perpendicular slide track bar (301) are fixedly connected in the middle part of.
7. a kind of construction wall bracing means according to claim 6, it is characterised in that: the construction wall bracing means It further include sliding sleeve (4), telescopic rod II (5), middle sliding block (6) and diagonal control arm (601), there are two sliding sleeve (4) left and right settings, two cunnings Set (4) is slidably connected at the left and right ends of horizontal slide track bar (3) respectively, telescopic rod II (5) be can free adjustment length the body of rod, There are two telescopic rod II (5) left and right settings, and the lower end of two telescopic rod II (5) is hingedly connected on two sliding sleeves (4), in Sliding block (6) is slidably connected on perpendicular slide track bar (301), and the left and right ends of middle sliding block (6) are hingedly connected with diagonal control arm (601), The outer end of two diagonal control arms (601) tilts down, and the outer end of two diagonal control arms (601) is hingedly connected in two sliding sleeves (4) On.
8. a kind of construction wall bracing means according to claim 7, it is characterised in that: the construction wall bracing means It further include top plate (7), slide opening (701), front plate (702), threaded stud (703), nut III (704), rear plate (705), spiral shell The front end downside of pit plate (706) and screw (707), top plate (7) is fixedly connected with front plate (702), front plate (702) Left and right ends are fixedly connected to threaded stud (703), and the upper end of two telescopic rod II (5) is rotatably connected on two screw threads respectively It on short column (703), has been connected through a screw thread nut III (704) on two threaded studs (703), two nut III (704) The front side in two telescopic rod II (5) is kept off respectively, is provided in the middle part of top plate (7) slide opening (701), before rear plate (705) is located at The rear side of clamping plate (702), the upper end of rear plate (705) are slidably connected on slide opening (701), the left and right ends of top plate (7) rear end It is fixedly connected to screw thread orifice plate (706), has been connected through a screw thread screw (707) on two screw thread orifice plates (706), two Screw (707) withstands on the rear side of rear plate (705).
9. a kind of construction wall bracing means according to claim 8, it is characterised in that: the construction wall bracing means It further include (205) telescopic rod I, the lower end of telescopic rod I (205) is hingedly connected on L shape connecting column (202), telescopic rod I (205) Upper end be hingedly connected to the front sides of middle sliding block (6).
10. a kind of construction wall bracing means according to claim 9, it is characterised in that: the telescopic rod I205 and stretch Contracting bar II (5) is two-part structure, and telescopic rod I (205) and telescopic rod II (5) are by a hollow thick bar and a solid slim Bar composition, solid thin bar are inserted in hollow thick bar, fastening screw are provided in hollow thick bar, between solid thin bar and hollow thick bar It is fixed by fastening screw.
CN201910684512.7A 2019-07-26 2019-07-26 Building wall reinforcing apparatus Active CN110397304B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910684512.7A CN110397304B (en) 2019-07-26 2019-07-26 Building wall reinforcing apparatus

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910684512.7A CN110397304B (en) 2019-07-26 2019-07-26 Building wall reinforcing apparatus

Publications (2)

Publication Number Publication Date
CN110397304A true CN110397304A (en) 2019-11-01
CN110397304B CN110397304B (en) 2021-07-13

Family

ID=68326189

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910684512.7A Active CN110397304B (en) 2019-07-26 2019-07-26 Building wall reinforcing apparatus

Country Status (1)

Country Link
CN (1) CN110397304B (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847786A (en) * 2019-11-23 2020-02-28 任宝泉 Foam metal noise insulation
CN110918239A (en) * 2019-12-10 2020-03-27 陶凤然 Broken recovery unit of lithium cell
CN110924324A (en) * 2019-12-02 2020-03-27 广西师范大学 Forest resumes ecological protection device that blocks
CN111910797A (en) * 2020-07-01 2020-11-10 浙江军天建筑装饰工程有限公司 Partition wall mounting structure and construction method thereof
CN112064819A (en) * 2020-09-21 2020-12-11 王�忠 Building main body structure with auxiliary assembly installing support
CN113006514A (en) * 2021-02-24 2021-06-22 上海建为历保科技股份有限公司 Ancient building green brick wall protection is with repairing device of rectifying

Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB909118A (en) * 1960-03-29 1962-10-24 Bristol Siddeley Engines Ltd Improvements in vehicles for use on land and in the air
FR2569750A1 (en) * 1984-08-31 1986-03-07 Fouchard Noel Method for converting a truss intended for increasing the height of a building without modifying the slope of the roof and beam capable of supporting the newly created floor
CN2480471Y (en) * 2001-04-16 2002-03-06 吴志峰 Rubber inlaid double-raw deformation corrector for floor or wall
GB2445942A (en) * 2007-01-24 2008-07-30 Lee John Slater A joist strut
US7739842B1 (en) * 2003-11-18 2010-06-22 Hodsdon Edwin R Method for anchor-free masonry wall bracing
US8136317B1 (en) * 2009-12-23 2012-03-20 Mccown Matthew S Assembly for straightening a basement's wall
CN205502621U (en) * 2016-04-02 2016-08-24 温州开祥建设有限公司 Reinforcing apparatus that is connected of assemblyization building wall and post
CN105940168A (en) * 2013-12-02 2016-09-14 多伦多大学管理委员会 System for mitigating the effects of seismic event
CN206319436U (en) * 2016-12-13 2017-07-11 河北工程大学 A kind of Self-resetting diagonal brace
US20170241148A1 (en) * 2016-02-18 2017-08-24 Donald E. Wheatley Method of straightening and reinforcing a block wall
CN206448546U (en) * 2017-02-17 2017-08-29 重庆水利电力职业技术学院 Architectural engineering seismic hardening plate
WO2018065911A1 (en) * 2016-10-05 2018-04-12 Morelli Enzo Process for the antiseismic reinforcement and consolidation of existing structures in reinforced concrete
CN207485010U (en) * 2017-09-30 2018-06-12 宿迁市第六建筑工程有限公司 A kind of building bracing means
CN207513218U (en) * 2017-10-10 2018-06-19 浙江华咨结构设计事务所有限公司 A kind of building reinforcing and shock absorption structure
CN207776485U (en) * 2017-12-06 2018-08-28 南京沃匠工程技术有限公司 A kind of novel work people construction wall bracing means
CN207920140U (en) * 2018-01-22 2018-09-28 吕超 A kind of bracing means of Old building
CN208184266U (en) * 2018-03-06 2018-12-04 今天建设有限公司 A kind of adjustable architectural engineering seismic hardening plate
CN208718166U (en) * 2018-08-23 2019-04-09 石家庄筑佳节能产品科技有限责任公司 A kind of prefabricated assembled movable partition wall plate, wall and partition plate moving structure
CN208870431U (en) * 2018-10-06 2019-05-17 杨雪梅 A kind of building structure strengthening device

Patent Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB909118A (en) * 1960-03-29 1962-10-24 Bristol Siddeley Engines Ltd Improvements in vehicles for use on land and in the air
FR2569750A1 (en) * 1984-08-31 1986-03-07 Fouchard Noel Method for converting a truss intended for increasing the height of a building without modifying the slope of the roof and beam capable of supporting the newly created floor
CN2480471Y (en) * 2001-04-16 2002-03-06 吴志峰 Rubber inlaid double-raw deformation corrector for floor or wall
US7739842B1 (en) * 2003-11-18 2010-06-22 Hodsdon Edwin R Method for anchor-free masonry wall bracing
GB2445942A (en) * 2007-01-24 2008-07-30 Lee John Slater A joist strut
US8136317B1 (en) * 2009-12-23 2012-03-20 Mccown Matthew S Assembly for straightening a basement's wall
CN105940168A (en) * 2013-12-02 2016-09-14 多伦多大学管理委员会 System for mitigating the effects of seismic event
US20170241148A1 (en) * 2016-02-18 2017-08-24 Donald E. Wheatley Method of straightening and reinforcing a block wall
CN205502621U (en) * 2016-04-02 2016-08-24 温州开祥建设有限公司 Reinforcing apparatus that is connected of assemblyization building wall and post
WO2018065911A1 (en) * 2016-10-05 2018-04-12 Morelli Enzo Process for the antiseismic reinforcement and consolidation of existing structures in reinforced concrete
CN206319436U (en) * 2016-12-13 2017-07-11 河北工程大学 A kind of Self-resetting diagonal brace
CN206448546U (en) * 2017-02-17 2017-08-29 重庆水利电力职业技术学院 Architectural engineering seismic hardening plate
CN207485010U (en) * 2017-09-30 2018-06-12 宿迁市第六建筑工程有限公司 A kind of building bracing means
CN207513218U (en) * 2017-10-10 2018-06-19 浙江华咨结构设计事务所有限公司 A kind of building reinforcing and shock absorption structure
CN207776485U (en) * 2017-12-06 2018-08-28 南京沃匠工程技术有限公司 A kind of novel work people construction wall bracing means
CN207920140U (en) * 2018-01-22 2018-09-28 吕超 A kind of bracing means of Old building
CN208184266U (en) * 2018-03-06 2018-12-04 今天建设有限公司 A kind of adjustable architectural engineering seismic hardening plate
CN208718166U (en) * 2018-08-23 2019-04-09 石家庄筑佳节能产品科技有限责任公司 A kind of prefabricated assembled movable partition wall plate, wall and partition plate moving structure
CN208870431U (en) * 2018-10-06 2019-05-17 杨雪梅 A kind of building structure strengthening device

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王枝胜、王鳌杰、崔彩萍: "《建筑工程事故处理与分析》", 30 August 2018 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847786A (en) * 2019-11-23 2020-02-28 任宝泉 Foam metal noise insulation
CN110847786B (en) * 2019-11-23 2020-12-04 滨州富创科技服务有限公司 Foam metal noise insulation
CN110924324A (en) * 2019-12-02 2020-03-27 广西师范大学 Forest resumes ecological protection device that blocks
CN110924324B (en) * 2019-12-02 2020-10-30 广西师范大学 Forest resumes ecological protection device that blocks
CN110918239A (en) * 2019-12-10 2020-03-27 陶凤然 Broken recovery unit of lithium cell
CN111910797A (en) * 2020-07-01 2020-11-10 浙江军天建筑装饰工程有限公司 Partition wall mounting structure and construction method thereof
CN111910797B (en) * 2020-07-01 2022-01-18 浙江军天建筑装饰工程有限公司 Partition wall mounting structure and construction method thereof
CN112064819A (en) * 2020-09-21 2020-12-11 王�忠 Building main body structure with auxiliary assembly installing support
CN112064819B (en) * 2020-09-21 2021-12-07 淮北淮海建设工程有限责任公司 Building main body structure with auxiliary assembly installing support
CN113006514A (en) * 2021-02-24 2021-06-22 上海建为历保科技股份有限公司 Ancient building green brick wall protection is with repairing device of rectifying
CN113006514B (en) * 2021-02-24 2022-08-05 上海建为历保科技股份有限公司 Ancient building green brick wall protection is with repairing device of rectifying

Also Published As

Publication number Publication date
CN110397304B (en) 2021-07-13

Similar Documents

Publication Publication Date Title
CN110397304A (en) A kind of construction wall bracing means
CN106088573A (en) A kind of assembled stretches mould bases
CN204126285U (en) Reinforcing bar binding locating rack
CN208966012U (en) Suitable for the building template quickly assembled
CN111809636B (en) But slope reinforcement device for civil engineering of automatically regulated reinforcing strength
CN105926961A (en) Method for reinforcing rectangular-section concrete columns through prestressed steel plate hoops
CN207267290U (en) Compressor wire tensioning equipment
CN206785104U (en) A kind of green Assembled enclosing wall being used repeatedly
CN205857709U (en) Air-conditioning template length governor motion and air-conditioning formwork support structure
CN213477202U (en) Green energy-conserving fire prevention steel construction for building
CN212002269U (en) Concrete beam side form reinforcing apparatus
CN207273541U (en) Prestressing force mortar Decorative hanging board molding die
CN208122301U (en) A kind of floor support plate supporting apparatus
CN207295716U (en) A kind of cantilever combined steel template
CN209384467U (en) A kind of curtain wall support regulating system on steel construction
CN205857710U (en) Air-conditioning formwork support structure
CN206487142U (en) A kind of hole sizing reinforcing template
CN207793864U (en) A kind of anchor of bridge expanssion joint
CN206091304U (en) Reinforcing apparatus of concrete structure expansion joint template
CN109018681A (en) A kind of assembled architecture wall stacking bracket
CN204960341U (en) A erecting tool for connecting reinforcement and swivel nut
CN206903203U (en) Side wall plate device
CN2219348Y (en) Dual-purpose adjustable shuttering beam
CN216262782U (en) Leveling device is used in anchor slab production
CN216740821U (en) Reinforcing and pressing device for steel plate for opening masonry wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20210625

Address after: 239001 Yaopu Industrial Park, Nanqiao District, Chuzhou City, Anhui Province

Applicant after: ANHUI HUARUI WATER CONSERVANCY Co.,Ltd.

Address before: No.1, East 1st ring road, Hantai District, Hanzhong City, Shaanxi Province

Applicant before: Tian Liang

GR01 Patent grant
GR01 Patent grant