CN110342396A - GRC composite wallboard lifting appliance and lifting construction method - Google Patents
GRC composite wallboard lifting appliance and lifting construction method Download PDFInfo
- Publication number
- CN110342396A CN110342396A CN201910748222.4A CN201910748222A CN110342396A CN 110342396 A CN110342396 A CN 110342396A CN 201910748222 A CN201910748222 A CN 201910748222A CN 110342396 A CN110342396 A CN 110342396A
- Authority
- CN
- China
- Prior art keywords
- grc
- composite wallboard
- grc composite
- wallboard
- embedded
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000002131 composite material Substances 0.000 title claims abstract description 110
- 238000010276 construction Methods 0.000 title claims abstract description 27
- 238000009434 installation Methods 0.000 claims description 21
- 229910000831 Steel Inorganic materials 0.000 claims description 3
- 239000010959 steel Substances 0.000 claims description 3
- 238000004519 manufacturing process Methods 0.000 abstract description 3
- 238000010586 diagram Methods 0.000 description 5
- 238000000034 method Methods 0.000 description 4
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C1/00—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
- B66C1/10—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
- B66C1/62—Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means comprising article-engaging members of a shape complementary to that of the articles to be handled
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
技术领域technical field
本发明涉及一种GRC复合墙板吊具及吊装施工方法。The invention relates to a GRC composite wall board hanger and a hoisting construction method.
背景技术Background technique
装配式建筑能够减少施工现场的湿作业工程,将工程主体拆分成各个构件,构件的制作主要在预制工厂完成,预制构件运输至现场后,现场对构件进行拼装。该施工方法极大地降低了施工现场对人力的需求,加快了施工速度,但是该方法对现场的机械吊装设备及吊装工艺提出了较高的要求。The prefabricated building can reduce the wet work on the construction site. The main body of the project is split into components. The production of the components is mainly completed in the prefabricated factory. After the prefabricated components are transported to the site, the components are assembled on site. This construction method greatly reduces the demand for manpower on the construction site and accelerates the construction speed, but this method puts forward higher requirements on the mechanical hoisting equipment and hoisting technology on site.
现有技术并未有对于GRC外墙复合墙板在施工过程中,如何进行吊装、固定和连接的工艺说明。施工单位依据外墙板的具体形式和连接方式根据自身的施工经验进行吊装施工,当面陌生的外墙板形式时,施工效率则受限于经验不足而降低。In the prior art, there is no technical description on how to hoist, fix and connect GRC exterior wall composite wall panels during construction. The construction unit carries out the hoisting construction according to the specific form and connection method of the external wall panel according to its own construction experience. When faced with an unfamiliar form of external wall panel, the construction efficiency is limited by the lack of experience.
现有技术中,GRC外墙复合墙板的吊装施工中,对未设有专门吊点的外墙板在吊装过程中不易起吊和安装的困难,对设有专门的吊点的GRC外墙复合墙板不仅造价高,可能导致安装效率低的问题。In the prior art, in the hoisting construction of GRC exterior wall composite wall panels, it is not easy to lift and install the exterior wall panels without special lifting points during the hoisting process. For GRC exterior wall composite panels with special lifting points Wall panels are not only expensive, but may also lead to low installation efficiency.
发明内容Contents of the invention
本发明提出一种GRC复合墙板吊具及吊装施工方法。The invention provides a GRC composite wallboard hanger and a hoisting construction method.
本发明解决技术问题所采用的方案是,一种GRC复合墙板吊具,包括水平基板,所述水平基板前后端分别焊接有前竖板、后竖板,水平基板上中部焊接有吊耳,前竖板、后竖板与水平基板底面之间围城容纳GRC复合墙板端部的区间,前竖板、后竖板之间的间距不小于GRC复合墙板的厚度,所述前竖板的长度大于GRC复合墙板上部的预埋固定螺栓至墙体上边缘的距离,所述前竖板左侧或右侧开设有用于容置预埋固定螺栓的横槽,横槽至水平基板下边缘距离大于上部的预埋固定螺栓至墙体上边缘距离。The solution adopted by the present invention to solve the technical problem is that a GRC composite wallboard hanger includes a horizontal base plate, the front and rear ends of the horizontal base plate are respectively welded with a front vertical plate and a rear vertical plate, and the upper middle of the horizontal base plate is welded with lifting lugs. The interval between the front vertical board, the rear vertical board and the bottom surface of the horizontal base plate is enclosed to accommodate the end of the GRC composite wall panel. The distance between the front vertical board and the rear vertical board is not less than the thickness of the GRC composite wall board. The length is greater than the distance from the pre-embedded fixing bolts on the top of the GRC composite wallboard to the upper edge of the wall, and the left or right side of the front vertical plate is provided with a transverse groove for accommodating the embedded fixing bolts, and the transverse groove is to the lower edge of the horizontal base plate The distance is greater than the distance from the upper embedded fixing bolt to the upper edge of the wall.
进一步的,横槽的长度部不大于前竖板宽度的三分之一。Further, the length of the transverse groove is not greater than one-third of the width of the front vertical plate.
进一步的,吊耳为一纵置的竖耳板,竖耳板上设置有吊孔。Further, the lifting lug is a vertical ear plate, and the vertical ear plate is provided with hanging holes.
进一步的,前竖板、后竖板之间的间距比GRC复合墙板的厚度大1-5mm。Further, the distance between the front riser and the rear riser is 1-5mm larger than the thickness of the GRC composite wallboard.
进一步的,水平基板、前竖板、后竖板、吊耳均为钢板且焊接为一体。Further, the horizontal base plate, the front vertical plate, the rear vertical plate, and the lifting lugs are all steel plates and welded as a whole.
一种GRC复合墙板吊具的吊装施工方法,包括以下步骤:A hoisting construction method of a GRC composite wallboard spreader, comprising the following steps:
步骤一:将吊具与GRC复合墙板上部预埋固定螺栓连接,将吊具的前竖板、后竖板分别放置于GRC复合墙板的两侧,缓慢插入GRC复合墙板上端部,当前竖板的上的横槽至复合墙板上部预埋固定螺栓处,将吊具侧移动,使得预埋螺栓卡入横槽最内侧;Step 1: Connect the spreader with the pre-embedded fixing bolts on the upper part of the GRC composite wallboard, place the front vertical plate and the rear vertical plate of the spreader on both sides of the GRC composite wallboard, and slowly insert them into the top of the GRC composite wallboard. Move the spreader from the horizontal groove on the vertical plate to the pre-embedded fixing bolt on the top of the composite wallboard, so that the embedded bolt is inserted into the innermost side of the horizontal groove;
步骤二:在GRC复合墙板的下部,捆绑吊带;Step 2: Tie the straps to the lower part of the GRC composite wall panel;
步骤三:取两个起重吊钩分别与吊带、吊具的吊耳连接后,对GRC复合墙板进型起吊,使GRC复合墙板缓慢升起,并在空中调整GRC复合墙板姿态至上端朝上的竖直状态;Step 3: Take the two lifting hooks and connect them to the lifting lugs of the sling and the sling respectively, and lift the GRC composite wall panel to make the GRC composite wall panel rise slowly, and adjust the attitude of the GRC composite wall panel to the top in the air The vertical state with the end facing up;
步骤四:调运呈竖直状态的GRC复合墙板至外墙面安装位置,进行复合墙板固定安装施工;Step 4: Transport the vertical GRC composite wallboard to the installation position on the outer wall, and carry out the fixed installation and construction of the composite wallboard;
步骤五:将GRC复合墙板下部预埋螺栓与主体结构预埋件连接;将GRC复合墙板固定螺栓与主体结构初步连接,螺栓不拧紧;通过下部预埋螺栓调整GRC复合墙板的水平、垂直度、位置及安装尺寸误差至符合设计要求;缓慢下放起重吊钩,水平移动吊具,使GRC复合墙板上部预埋固定螺栓移出吊具的横槽,放慢上提吊钩,将吊具移出GRC复合墙板上端;拧紧上部预埋固定螺栓与主体结构的连接螺母,调整GRC复合墙板的水平、垂直度、位置及安装尺寸误差至符合设计要求后,对复合墙板的上部及下部的预埋固定螺栓与主体结构的连接螺母进行终拧,完成安装施工。Step 5: Connect the pre-embedded bolts at the lower part of the GRC composite wallboard to the embedded parts of the main structure; initially connect the fixing bolts of the GRC composite wallboard to the main structure without tightening the bolts; adjust the level, The verticality, position and installation size errors meet the design requirements; slowly lower the lifting hook, move the spreader horizontally, so that the embedded fixing bolts on the top of the GRC composite wallboard move out of the horizontal groove of the lifter, slowly lift the hook, and move the spreader horizontally. Move the spreader out of the top of the GRC composite wallboard; tighten the upper pre-embedded fixing bolts and the connecting nuts of the main structure, adjust the level, verticality, position and installation dimension error of the GRC composite wallboard to meet the design requirements, and then fix the upper part of the composite wallboard And the pre-embedded fixing bolts at the lower part and the connecting nuts of the main structure are finally screwed to complete the installation and construction.
进一步的,步骤一至步骤三中的操作适用于对呈水平摆放姿态放置的GRC复合墙板进行吊装,若GRC复合墙板面积较小时或现场条件允许,可GRC复合墙板采用竖直摆放,此时不使用吊带,直接将吊具与GRC复合墙板连接后,通过起重吊钩将GRC复合墙板起吊至外墙面安装位置,进行复合墙板固定安装施工即可。Furthermore, the operations in steps 1 to 3 are suitable for hoisting the GRC composite wall panels placed in a horizontal posture. If the area of the GRC composite wall panels is small or the site conditions permit, the GRC composite wall panels can be placed vertically. , at this time, do not use the sling, directly connect the sling to the GRC composite wall panel, lift the GRC composite wall panel to the installation position on the outer wall through the lifting hook, and carry out the fixed installation and construction of the composite wall panel.
进一步的,在步骤一中,使得预埋螺栓卡入横槽最内侧后,通过螺母将GRC复合墙板与前竖板锁紧。Further, in step 1, after the embedded bolts are snapped into the innermost side of the transverse groove, the GRC composite wallboard and the front vertical board are locked with nuts.
与现有技术相比,本发明具有以下有益效果:结构简单,设计合理,使用方便,提高GRC外墙吊装施工效率,利用GRC外墙复合墙板自身的预埋固定螺丝作为起吊点,能够避免为外墙板单独设置专门的吊点预埋件,使得外墙板的结构更加简单,降低外墙板的设计、制作成本。Compared with the prior art, the present invention has the following beneficial effects: simple structure, reasonable design, convenient use, improved GRC exterior wall hoisting construction efficiency, using the pre-embedded fixing screws of the GRC exterior composite wallboard itself as the lifting point, which can avoid Separately set special embedded parts for hanging points for the exterior wall panels, which makes the structure of the exterior wall panels simpler and reduces the design and production costs of the exterior wall panels.
附图说明Description of drawings
下面结合附图对本发明专利进一步说明。Below in conjunction with accompanying drawing, the patent of the present invention is further described.
图1是吊具的结构示意图一;Fig. 1 is a structural schematic diagram one of the spreader;
图2是吊具的结构示意图二;Fig. 2 is a structural schematic diagram two of the spreader;
图3是GRC复合墙板起吊装备阶段的示意图;Figure 3 is a schematic diagram of the GRC composite wall panel lifting equipment stage;
图4是GRC复合墙板起吊装后调整姿态的示意图;Figure 4 is a schematic diagram of adjusting the attitude of the GRC composite wallboard after hoisting;
图5是GRC复合墙板起吊装后调整至竖直状态的示意图。Fig. 5 is a schematic diagram of adjusting the GRC composite wallboard to a vertical state after being hoisted.
图中:1-水平基板;2-吊耳;3-吊孔;4-后竖板;5-前竖板;6-GRC复合墙板;7-GRC复合墙板上部的预埋固定螺栓;8-横槽;9-吊带;10-GRC复合墙板吊具。In the figure: 1-horizontal base plate; 2-hanging lug; 3-hanging hole; 4-rear vertical board; 5-front vertical board; 6-GRC composite wallboard; 8-horizontal slot; 9-sling; 10-GRC composite wall panel spreader.
具体实施方式Detailed ways
下面结合附图和具体实施方式对本发明进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and specific embodiments.
如图1-5所示,一种GRC复合墙板吊具,包括水平基板,所述水平基板前后端分别焊接有前竖板、后竖板,水平基板上中部焊接有吊耳,前竖板、后竖板与水平基板底面之间围城容纳GRC复合墙板端部的区间,前竖板、后竖板之间的间距不小于GRC复合墙板的厚度,所述前竖板的长度大于GRC复合墙板上部的预埋固定螺栓至墙体上边缘的距离,所述前竖板左侧或右侧开设有用于容置预埋固定螺栓的横槽,横槽至水平基板下边缘距离大于上部的预埋固定螺栓至墙体上边缘距离。As shown in Figure 1-5, a GRC composite wallboard hanger includes a horizontal base plate, the front and rear vertical plates are welded to the front and rear ends of the horizontal base plate, the upper middle of the horizontal base plate is welded with lifting lugs, and the front vertical plate 1. The section between the rear vertical board and the bottom surface of the horizontal base plate encloses the end of the GRC composite wall panel, the distance between the front vertical board and the rear vertical board is not less than the thickness of the GRC composite wall board, and the length of the front vertical board is greater than that of the GRC composite wall board. The distance from the pre-embedded fixing bolts on the top of the composite wallboard to the upper edge of the wall, the left or right side of the front vertical plate is provided with a horizontal groove for accommodating the embedded fixing bolts, and the distance from the horizontal groove to the lower edge of the horizontal base plate is greater than that of the upper The distance from the pre-embedded fixing bolts to the upper edge of the wall.
在本实施例中,横槽的长度部不大于前竖板宽度的三分之一。In this embodiment, the length of the transverse groove is not greater than one-third of the width of the front vertical plate.
在本实施例中,吊耳为一纵置的竖耳板,竖耳板上设置有吊孔。In this embodiment, the lifting lug is a vertically placed vertical lug plate, and the vertical lug plate is provided with lifting holes.
在本实施例中,前竖板、后竖板之间的间距比GRC复合墙板的厚度大1-5mm。In this embodiment, the distance between the front riser and the rear riser is 1-5mm larger than the thickness of the GRC composite wallboard.
在本实施例中,水平基板、前竖板、后竖板、吊耳均为钢板且焊接为一体。In this embodiment, the horizontal base plate, the front vertical plate, the rear vertical plate, and the lifting lugs are all steel plates and welded as one.
一种GRC复合墙板吊具的吊装施工方法,包括以下步骤:A hoisting construction method of a GRC composite wallboard spreader, comprising the following steps:
步骤一:将吊具与GRC复合墙板上部预埋固定螺栓连接,将吊具的前竖板、后竖板分别放置于GRC复合墙板的两侧,缓慢插入GRC复合墙板上端部,当前竖板的上的横槽至复合墙板上部预埋固定螺栓处,将吊具侧移动,使得预埋螺栓卡入横槽最内侧;Step 1: Connect the spreader with the pre-embedded fixing bolts on the upper part of the GRC composite wallboard, place the front vertical plate and the rear vertical plate of the spreader on both sides of the GRC composite wallboard, and slowly insert them into the top of the GRC composite wallboard. Move the spreader from the horizontal groove on the vertical plate to the pre-embedded fixing bolt on the top of the composite wallboard, so that the embedded bolt is inserted into the innermost side of the horizontal groove;
步骤二:在GRC复合墙板的下部,捆绑吊带;Step 2: Tie the straps to the lower part of the GRC composite wall panel;
步骤三:取两个起重吊钩分别与吊带、吊具的吊耳连接后,对GRC复合墙板进型起吊,使GRC复合墙板缓慢升起,并在空中调整GRC复合墙板姿态至上端朝上的竖直状态;Step 3: Take the two lifting hooks and connect them to the lifting lugs of the sling and the sling respectively, and lift the GRC composite wall panel to make the GRC composite wall panel rise slowly, and adjust the attitude of the GRC composite wall panel to the top in the air The vertical state with the end facing up;
步骤四:调运呈竖直状态的GRC复合墙板至外墙面安装位置,进行复合墙板固定安装施工;Step 4: Transport the vertical GRC composite wallboard to the installation position on the outer wall, and carry out the fixed installation and construction of the composite wallboard;
步骤五:将GRC复合墙板下部预埋螺栓与主体结构预埋件连接;将GRC复合墙板固定螺栓与主体结构初步连接,螺栓不拧紧;通过下部预埋螺栓调整GRC复合墙板的水平、垂直度、位置及安装尺寸误差至符合设计要求;缓慢下放起重吊钩,水平移动吊具,使GRC复合墙板上部预埋固定螺栓移出吊具的横槽,放慢上提吊钩,将吊具移出GRC复合墙板上端;拧紧上部预埋固定螺栓与主体结构的连接螺母,调整GRC复合墙板的水平、垂直度、位置及安装尺寸误差至符合设计要求后,对复合墙板的上部及下部的预埋固定螺栓与主体结构的连接螺母进行终拧,完成安装施工。Step 5: Connect the pre-embedded bolts at the lower part of the GRC composite wallboard to the embedded parts of the main structure; initially connect the fixing bolts of the GRC composite wallboard to the main structure without tightening the bolts; adjust the level, The verticality, position and installation size errors meet the design requirements; slowly lower the lifting hook, move the spreader horizontally, so that the embedded fixing bolts on the top of the GRC composite wallboard move out of the horizontal groove of the lifter, slowly lift the hook, and move the spreader horizontally. Move the spreader out of the top of the GRC composite wallboard; tighten the upper pre-embedded fixing bolts and the connecting nuts of the main structure, adjust the level, verticality, position and installation dimension error of the GRC composite wallboard to meet the design requirements, and then fix the upper part of the composite wallboard And the pre-embedded fixing bolts at the lower part and the connecting nuts of the main structure are finally screwed to complete the installation and construction.
步骤一至步骤三中的操作适用于对呈水平摆放姿态放置的GRC复合墙板进行吊装,若GRC复合墙板面积较小时或现场条件允许,可GRC复合墙板采用竖直摆放,此时不使用吊带,直接将吊具与GRC复合墙板连接后,通过起重吊钩将GRC复合墙板起吊至外墙面安装位置,进行复合墙板固定安装施工即可。The operations in step 1 to step 3 are suitable for hoisting the GRC composite wall panels placed in a horizontal posture. If the area of the GRC composite wall panels is small or the site conditions permit, the GRC composite wall panels can be placed vertically. At this time Without the use of slings, directly connect the spreader to the GRC composite wall panel, lift the GRC composite wall panel to the installation position on the outer wall through the lifting hook, and then carry out the fixed installation of the composite wall panel.
在步骤一中,使得预埋螺栓卡入横槽最内侧后,通过螺母将GRC复合墙板与前竖板锁紧。In step 1, after the pre-embedded bolts are snapped into the innermost side of the transverse groove, the GRC composite wallboard and the front vertical board are locked with nuts.
上列较佳实施例,对本发明的目的、技术方案和优点进行了进一步详细说明,所应理解的是,以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above-listed preferred embodiments have further described the purpose, technical solutions and advantages of the present invention in detail. It should be understood that the above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Within the spirit and principles of the present invention, any modifications, equivalent replacements, improvements, etc., shall be included within the protection scope of the present invention.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910748222.4A CN110342396B (en) | 2019-08-14 | 2019-08-14 | GRC composite wallboard lifting appliance and lifting construction method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910748222.4A CN110342396B (en) | 2019-08-14 | 2019-08-14 | GRC composite wallboard lifting appliance and lifting construction method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN110342396A true CN110342396A (en) | 2019-10-18 |
| CN110342396B CN110342396B (en) | 2024-03-01 |
Family
ID=68184941
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201910748222.4A Active CN110342396B (en) | 2019-08-14 | 2019-08-14 | GRC composite wallboard lifting appliance and lifting construction method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN110342396B (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN114212659A (en) * | 2021-12-03 | 2022-03-22 | 中铁四局集团第二工程有限公司 | Construction method for hoisting prefabricated part |
| CN114809662A (en) * | 2022-05-19 | 2022-07-29 | 武汉林榔木建筑工程科技有限公司 | Automatic wallboard mounting device and mounting method |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0656354U (en) * | 1993-01-06 | 1994-08-05 | 住友金属鉱山株式会社 | Panel hanger |
| JP3014667U (en) * | 1995-02-10 | 1995-08-15 | 大和ハウス工業株式会社 | Panel lifting jig |
| JP2004108080A (en) * | 2002-09-20 | 2004-04-08 | Clion Co Ltd | Lifting tool for panel |
| JP2018071077A (en) * | 2016-10-25 | 2018-05-10 | 積水ハウス株式会社 | External panel hanger |
| CN210735990U (en) * | 2019-08-14 | 2020-06-12 | 厦门大学嘉庚学院 | GRC composite wallboard lifting appliance |
-
2019
- 2019-08-14 CN CN201910748222.4A patent/CN110342396B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JPH0656354U (en) * | 1993-01-06 | 1994-08-05 | 住友金属鉱山株式会社 | Panel hanger |
| JP3014667U (en) * | 1995-02-10 | 1995-08-15 | 大和ハウス工業株式会社 | Panel lifting jig |
| JP2004108080A (en) * | 2002-09-20 | 2004-04-08 | Clion Co Ltd | Lifting tool for panel |
| JP2018071077A (en) * | 2016-10-25 | 2018-05-10 | 積水ハウス株式会社 | External panel hanger |
| CN210735990U (en) * | 2019-08-14 | 2020-06-12 | 厦门大学嘉庚学院 | GRC composite wallboard lifting appliance |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN114212659A (en) * | 2021-12-03 | 2022-03-22 | 中铁四局集团第二工程有限公司 | Construction method for hoisting prefabricated part |
| CN114809662A (en) * | 2022-05-19 | 2022-07-29 | 武汉林榔木建筑工程科技有限公司 | Automatic wallboard mounting device and mounting method |
Also Published As
| Publication number | Publication date |
|---|---|
| CN110342396B (en) | 2024-03-01 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN112573344B (en) | Use method of hoisting and turning-over device for super-large concrete prefabricated stand plate | |
| CN109095343A (en) | Assembled hanger | |
| CN210735990U (en) | GRC composite wallboard lifting appliance | |
| CN110342396B (en) | GRC composite wallboard lifting appliance and lifting construction method | |
| CN206368541U (en) | A kind of prefabricated components Level tune component and its attachment structure | |
| CN209554635U (en) | A kind of GRC plate hangs drawing support frame | |
| CN207538483U (en) | A kind of steel box-girder suspender | |
| CN108086697B (en) | Precise positioning device and precise positioning method for embedded part hoisting | |
| CN107043072B (en) | Inverted beam integrated inner climbing tower crane support device and implementation method | |
| CN102535830A (en) | Machine position adhesion device for monolithic climbing scaffold for constructing prefabricated building | |
| CN101787687B (en) | Offshore oil drilling platform sledge block and hoisting technology thereof | |
| CN208948679U (en) | Assembled hanger | |
| CN204434076U (en) | Lifting hook capable of adjusting attitude of shield machine component in underground hoisting process of shield machine | |
| CN109733996B (en) | Lifting device with function of overturning prefabricated component and lifting method of prefabricated component | |
| CN111173300A (en) | A prefabricated structure | |
| CN217102768U (en) | Auxiliary overturning and erecting device for concrete prefabricated wall panel | |
| CN216583766U (en) | Size-adjustable laminated slab lifting appliance with lifting function | |
| CN210152143U (en) | Connecting structure for hoisting construction of concrete cladding panels | |
| CN103556837A (en) | Method for installing steel column on podium building | |
| CN210117163U (en) | Lifting appliance with function of side-turning prefabricated part | |
| CN201245406Y (en) | Hoisting tong for clamping arc wall panel | |
| CN212359092U (en) | Building templates fixing device | |
| CN217232717U (en) | Building expansion joint hoist and mount aluminium mould | |
| CN218344972U (en) | Balanced hoisting accessory of slidingtype superimposed sheet | |
| CN115010012B (en) | A reverse transportation installation method for an external support system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |