CN110284712A - A batch control method is connect in the pre-buried cup formula taper sheath progress template of having enough to meet the need of concrete structure - Google Patents
A batch control method is connect in the pre-buried cup formula taper sheath progress template of having enough to meet the need of concrete structure Download PDFInfo
- Publication number
- CN110284712A CN110284712A CN201910574286.7A CN201910574286A CN110284712A CN 110284712 A CN110284712 A CN 110284712A CN 201910574286 A CN201910574286 A CN 201910574286A CN 110284712 A CN110284712 A CN 110284712A
- Authority
- CN
- China
- Prior art keywords
- cup formula
- template
- screw rod
- buried
- connector sleeve
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 17
- 238000009416 shuttering Methods 0.000 claims abstract description 21
- 238000010276 construction Methods 0.000 claims abstract description 13
- 239000004570 mortar (masonry) Substances 0.000 claims abstract description 3
- 230000002265 prevention Effects 0.000 claims abstract description 3
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 230000003014 reinforcing effect Effects 0.000 claims description 3
- 238000009415 formwork Methods 0.000 abstract description 6
- 238000005516 engineering process Methods 0.000 abstract description 2
- 239000010410 layer Substances 0.000 description 11
- 239000011229 interlayer Substances 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005457 optimization Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G11/00—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
- E04G11/06—Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G17/00—Connecting or other auxiliary members for forms, falsework structures, or shutterings
- E04G17/14—Bracing or strutting arrangements for formwalls; Devices for aligning forms
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The invention belongs to the formwork erection of architectural engineering concrete structure outer, column and elevator stair position construction fields, it discloses one kind and connects a batch control method in the pre-buried cup formula taper sheath progress template of having enough to meet the need of concrete structure, it is in each layer template construction, horizontal location line is arranged in present template top, then by several pre-buried cup formula clamping systems are equidistantly horizontally disposed at floor respective heights, joint part mortar leakage prevention, running pulp are locked using cup formula clamping system;The cup formula clamping system includes cup formula connector sleeve, pre embedded bolt and support shuttering screw rod, pre embedded bolt and support shuttering screw rod docks and pass through fastening nut by cup formula connector sleeve and jackscrew is fixed.The method of the invention improves concrete wall operating efficiency during formwork erection, instead of the construction technology that original tradition is complicated, it is also more rigorous effective to the control of concrete quality simultaneously, so that the construction period is optimised and is can be effectively controlled, saves time cost and cost of labor and taper sheath can repeatedly have enough to meet the need.
Description
Technical field
The invention belongs to the formwork erection of architectural engineering concrete structure outer, column and elevator stair position construct field,
A batch control method is connect in the pre-buried cup formula taper sheath progress template of having enough to meet the need of concrete structure more particularly to one kind.
Background technique
Traditional shear wall formwork erection is all made of split bolt form and carries out formwork reinforcement construction, and for every interlayer exterior wall
Top mode locking similarly uses split bolt mode locking, although it can play good drawing when bearing concrete lateral pressure and other loads
Knot effect, but need in subsequent one layer of template construction to verify root position again and be reinforced, and strengthened edge not can guarantee
Tightly, there is running pulp hidden danger when connecing stubble check and correction deviation and concrete placings, substantially reduce exterior wall and elevator stair concrete impression quality.
Summary of the invention
Present invention seek to address that split bolt connects a batch faulting of slab ends, running pulp, pitted skin and other issues in each interlayer concrete, and then provide
It is a kind of concrete structure it is pre-buried have enough to meet the need cup formula taper sheath and carry out template connect a batch control method.
The present invention adopts the following technical scheme:
One kind concrete structure it is pre-buried have enough to meet the need cup formula taper sheath carry out template connect a batch control method, be in each layer template construction,
Horizontal location line is arranged in present template top, then locks at floor respective heights by being equidistantly horizontally disposed with several pre-buried cup formulas
Modular system locks joint part mortar leakage prevention, running pulp using cup formula clamping system;The cup formula clamping system includes the connection of cup formula
Set, pre embedded bolt and support shuttering screw rod, pre embedded bolt and support shuttering screw rod dock by cup formula connector sleeve and pass through fastening
Nut and jackscrew are fixed;Specific construction process is as follows:
Cup formula connector sleeve, support shuttering screw rod are screwed by horizontal equidistant progress pre embedded bolt and cup formula connector sleeve, pre embedded bolt
Cup formula connector sleeve is screwed on the outside of template, one template proximate of outside of cup formula connector sleeve is tight, and 3 types are utilized on the outside of cup formula connector sleeve
Card carries out mould locking and fixes;
After concrete placings, removes outer wall template and exposes reserved taper cup formula connector sleeve, be screwed into support shuttering screw rod again,
Subsequent one layer of template can be placed directly on support shuttering screw rod, and template proximate lower layer is made to have poured concrete exterior wall, then utilize cup formula
Connector sleeve, support shuttering screw rod and 3 type cards carry out mode locking reinforcing to template, flitch, steel pipe, it is ensured that upper former connects with lower layer's concrete
It is tight seamless at stubble, it improves concrete integral smoothness and connects a batch quality;
Formula taper sheath connector can reversely be removed with screw rod, can be utilized again after pre-buried use.
Cup formula clamping system is distributed pre-buried by 500mm spacing.
Pre embedded bolt is screwed into the length of cup formula taper sheath not less than 15mm;Support shuttering screw rod is screwed into the length of cup formula taper sheath
Degree is not less than 15mm, guarantees the connective stability of cup formula clamping system.
Compared with conventional template is reinforced, the method for the present invention is had the following beneficial effects:
1, it is more convenient to construct, easy to operate, can be used in turn, improve efficiency;
2, each interlayer of optimization template proofreads step, saves the duration;
3, the problems such as solving each interlayer concrete faulting of slab ends, running pulp, pitted skin improves concrete and connects a batch quality.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of cup formula clamping system;
Fig. 2 is that cup formula mode locking exterior wall reinforces schematic diagram (lower layer);
Fig. 3 is that cup formula mode locking exterior wall reinforces schematic diagram (upper layer);
In figure: 1- cup formula clamping system, 2- template, 3- flitch, 4- steel pipe, 5-3 type card, 6- split bolt, 7- exterior wall, the building 8-
Plate;11- fastening bolt, 12- fastening nut, 13- cup formula connector sleeve, 14- jackscrew, 15- pre embedded bolt, 16- support shuttering screw rod.
Specific embodiment
It is of the present invention to carry out template to connect a batch control method being using cup formula in the pre-buried cup formula taper sheath that has enough to meet the need of concrete structure
Clamping system is in the pre-buried setting of progress suitable for reading of each layer template.The cup formula clamping system includes by cup formula connector, pre embedded bolt
It is formed with support shuttering screw rod and standing finish.It needs that horizontal location line first is arranged on template top when template construction, by every 500mm
Spacing carries out pre embedded bolt and cup formula connector (the built-in long 30mm of screw thread) setting, pre embedded bolt are screwed into connector 15mm, supports
Template screw rod is equally screwed into 15mm on the outside of template, must be tight with template proximate on the outside of connector, and outside carries out 3 type cards and carries out
Mould locking is fixed.
After concrete placings, removes outer wall template and expose reserved cup formula taper sheath connector, be screwed into support shuttering again
Screw rod, subsequent one layer of template can be placed directly on support shuttering screw rod, so that template proximate lower layer has been poured concrete exterior wall, then utilize
Cup formula connector, support shuttering screw rod and 3 type cards carry out mode locking reinforcing to template, flitch, steel pipe, it is ensured that upper former and lower layer
Concrete joint part is tightly seamless, improves concrete integral smoothness and connects a batch quality.
Cup formula taper sheath connector can reversely be removed with screw rod, can be utilized again after pre-buried use.
Use of the method for the invention in engineering substantially increases concrete wall operating efficiency during formwork erection,
Instead of the construction technology that original tradition is complicated, at the same it is also more rigorous effective to the control of concrete quality, enable the construction period
Optimize and can be effectively controlled, main is to save time cost and cost of labor and taper sheath can repeatedly have enough to meet the need.
Claims (4)
1. a kind of connect a batch control method in the pre-buried cup formula taper sheath progress template of having enough to meet the need of concrete structure, which is characterized in that be each
When layer template construction, horizontal location line is arranged in present template top, then by equidistant horizontally disposed at floor respective heights
Several pre-buried cup formula clamping systems lock joint part mortar leakage prevention, running pulp using cup formula clamping system;The cup formula clamping system
Including cup formula connector sleeve, pre embedded bolt and support shuttering screw rod, pre embedded bolt and support shuttering screw rod pass through cup formula connector sleeve pair
It connects and passes through fastening nut and jackscrew is fixed;Specific construction process is as follows:
Cup formula connector sleeve, support shuttering screw rod are screwed by horizontal equidistant progress pre embedded bolt and cup formula connector sleeve, pre embedded bolt
Cup formula connector sleeve is screwed on the outside of template, one template proximate of outside of cup formula connector sleeve is tight, and 3 types are utilized on the outside of cup formula connector sleeve
Card carries out mould locking and fixes;
After concrete placings, removes outer wall template and exposes reserved taper cup formula connector sleeve, be screwed into support shuttering screw rod again,
Subsequent one layer of template can be placed directly on support shuttering screw rod, and template proximate lower layer is made to have poured concrete exterior wall, then utilize cup formula
Connector sleeve, support shuttering screw rod and 3 type cards carry out mode locking reinforcing to template, flitch, steel pipe, it is ensured that upper former connects with lower layer's concrete
It is tight seamless at stubble, it improves concrete integral smoothness and connects a batch quality;
Formula taper sheath connector can reversely be removed with screw rod, can be utilized again after pre-buried use.
2. the pre-buried cup formula taper sheath progress template of having enough to meet the need of concrete structure according to claim 1 connects a batch control method, special
Sign is that cup formula clamping system is distributed pre-buried by 500mm spacing.
3. the pre-buried cup formula taper sheath progress template of having enough to meet the need of concrete structure according to claim 1 connects a batch control method, special
Sign is that pre embedded bolt is screwed into the length of cup formula taper sheath not less than 15mm.
4. the pre-buried cup formula taper sheath progress template of having enough to meet the need of concrete structure according to claim 1 connects a batch control method, special
Sign is that support shuttering screw rod is screwed into the length of cup formula taper sheath not less than 15mm.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910574286.7A CN110284712A (en) | 2019-06-28 | 2019-06-28 | A batch control method is connect in the pre-buried cup formula taper sheath progress template of having enough to meet the need of concrete structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910574286.7A CN110284712A (en) | 2019-06-28 | 2019-06-28 | A batch control method is connect in the pre-buried cup formula taper sheath progress template of having enough to meet the need of concrete structure |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN110284712A true CN110284712A (en) | 2019-09-27 |
Family
ID=68019479
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201910574286.7A Pending CN110284712A (en) | 2019-06-28 | 2019-06-28 | A batch control method is connect in the pre-buried cup formula taper sheath progress template of having enough to meet the need of concrete structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN110284712A (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116026526A (en) * | 2023-02-24 | 2023-04-28 | 三一重型装备有限公司 | Balance detection device and rotor assembly balance adjustment method |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE2806473A1 (en) * | 1978-02-16 | 1979-08-23 | Dausend Hans Werner | Conical formwork spacer for concrete wall - has sealing cap inserted onto ring ledges in holes for mortar filling |
| CN103741944A (en) * | 2013-12-23 | 2014-04-23 | 上海建工五建集团有限公司 | Fixation assembly, template system comprising fixation assembly and wall pouring method |
| CN205840313U (en) * | 2016-07-22 | 2016-12-28 | 山西二建集团有限公司 | Exterior wall joint part plank sheathing installs structure |
| CN106836565A (en) * | 2017-02-15 | 2017-06-13 | 山西二建集团有限公司 | Three-section water stop screw rod control shear wall exterior wall connects a batch method |
| CN208310221U (en) * | 2018-05-02 | 2019-01-01 | 田世兵 | A kind of fixed device of side mode |
-
2019
- 2019-06-28 CN CN201910574286.7A patent/CN110284712A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE2806473A1 (en) * | 1978-02-16 | 1979-08-23 | Dausend Hans Werner | Conical formwork spacer for concrete wall - has sealing cap inserted onto ring ledges in holes for mortar filling |
| CN103741944A (en) * | 2013-12-23 | 2014-04-23 | 上海建工五建集团有限公司 | Fixation assembly, template system comprising fixation assembly and wall pouring method |
| CN205840313U (en) * | 2016-07-22 | 2016-12-28 | 山西二建集团有限公司 | Exterior wall joint part plank sheathing installs structure |
| CN106836565A (en) * | 2017-02-15 | 2017-06-13 | 山西二建集团有限公司 | Three-section water stop screw rod control shear wall exterior wall connects a batch method |
| CN208310221U (en) * | 2018-05-02 | 2019-01-01 | 田世兵 | A kind of fixed device of side mode |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116026526A (en) * | 2023-02-24 | 2023-04-28 | 三一重型装备有限公司 | Balance detection device and rotor assembly balance adjustment method |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN207131072U (en) | A kind of super thick shear wall corner template reinforcing device | |
| CN101265748B (en) | Tools type section steel fastener steel tube outer scaffold | |
| CN102493341A (en) | Construction method for hollow thin-walled high pier non-bracket formwork turnover of railway | |
| CN206616862U (en) | Formwork root bracing means | |
| CN209384451U (en) | An Easy-to-splice Shear Wall Connection Structure | |
| CN110206229A (en) | A kind of concrete column splicing structure and its construction method | |
| CN105201532A (en) | Ring excavation construction method for underground large-span spherical-cap-shaped dome under weak surrounding rock | |
| CN105781100A (en) | Template component for sidewall of subway station | |
| CN205804939U (en) | template assembly for subway station side wall | |
| CN217734853U (en) | Overload small clear distance beam adjustable disc buckle formwork support frame | |
| CN204875558U (en) | Shaped steel runs through inside and outside compound support formula bracket system of encorbelmenting | |
| CN116791750B (en) | Construction method for reverse newly-built column connection structure based on self-locking anchoring technology | |
| CN213359004U (en) | A stably spliced lifting wall | |
| CN210396093U (en) | Double-shear wall deformation joint steel formwork | |
| CN201891174U (en) | Stiff connecting node for ring girder and ring-shaped bracket column | |
| CN214996171U (en) | Prefabricated wall body support system | |
| CN203834683U (en) | Plate girder and wall connecting structure | |
| CN104234418A (en) | Early removal formwork for fabrication of reinforced concrete beams and construction method thereof | |
| CN204000936U (en) | Outer wall of basement single surface formwork system based on fastener type steel pipe earth anchor truss | |
| CN205894670U (en) | Template structure for concrete joint construction between floors | |
| CN109972510A (en) | A kind of assembled combined bridge deck system of the bar away from adjustable U-bolt connector | |
| CN112609979A (en) | Wall connecting piece erecting method for connecting ultrahigh external frame of external wall | |
| CN112627034A (en) | Synchronous construction method for turning over mold of high pier of bridge | |
| CN207144467U (en) | A kind of neighboring walls small space model sheetinstallat structure | |
| CN213539700U (en) | Basement outer wall internal stay draws unilateral formwork structure outward |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190927 |
|
| RJ01 | Rejection of invention patent application after publication |