CN110259134A - A kind of ground pump pipe mounting structure and method - Google Patents
A kind of ground pump pipe mounting structure and method Download PDFInfo
- Publication number
- CN110259134A CN110259134A CN201910703264.6A CN201910703264A CN110259134A CN 110259134 A CN110259134 A CN 110259134A CN 201910703264 A CN201910703264 A CN 201910703264A CN 110259134 A CN110259134 A CN 110259134A
- Authority
- CN
- China
- Prior art keywords
- ground pump
- air shaft
- mounting structure
- ground
- wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 11
- 238000009434 installation Methods 0.000 claims abstract description 22
- 229910000831 Steel Inorganic materials 0.000 claims description 5
- 239000010959 steel Substances 0.000 claims description 5
- 239000004744 fabric Substances 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 5
- 238000005457 optimization Methods 0.000 description 8
- 230000015572 biosynthetic process Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000009423 ventilation Methods 0.000 description 2
- 238000009435 building construction Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F16—ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
- F16L—PIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
- F16L3/00—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets
- F16L3/08—Supports for pipes, cables or protective tubing, e.g. hangers, holders, clamps, cleats, clips, brackets substantially surrounding the pipe, cable or protective tubing
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
The invention discloses a kind of ground pump pipe mounting structure and methods, wherein mounting structure includes U-shaped connector, ground pump tube guide piece and hollow sleeve, there are two hollow sleeve is set, the U-shaped connector includes the quarter butt that two stocks disposed in parallel and both ends are connect with two stock one end respectively, two stocks and quarter butt are integrally formed to form the U-shaped connector, and two stock be pierced by from two hollow sleeves into air shaft respectively, on quarter butt is connected on the inside of wall, ground pump tube guide piece is fixed to be set on two stocks and is located in air shaft, there is the guide channel for just allowing ground pump line to be pierced by ground pump tube guide piece, the axial direction of guide channel and the axial direction of air shaft are identical.By the mounting structure, pump line has carried out preferable fixed installation over the ground, and since hollow sleeve is embedded in wall, after the completion of construction, stock can be extracted out, it is reusable convenient for removing, hollow sleeve is blocked so that its damaged caused by wall it is smaller controllable.
Description
Technical field
The invention belongs to technical field of building construction more particularly to a kind of ground pump pipe mounting structure and methods.
Background technique
With the development of society, the height of modern architecture is higher and higher, and the concreting of skyscraper just needs to adopt
Concreting is carried out with the mode of ground pump, the fixed installation of ground pump line is the key that concrete conveyance, over the ground the installation of pump line
Fixed form is each has something to recommend him, but existing fixed form causes different journeys to concrete floor and hole to varying degrees
The damage of degree, it is therefore desirable to it is related to a kind of can reduce and finished product floor is destroyed, it is easy to operate, and can guarantee ground pump line installation jail
Solid ground pump pipe mounting structure and method.
Summary of the invention
In view of the above shortcomings of the prior art, the technical problems to be solved by the present invention are: how to provide a kind of energy reduction
Finished product floor is destroyed, it is easy to operate, and can guarantee the ground pump pipe mounting structure that ground pump line firmly installs.
In order to solve the above-mentioned technical problem, present invention employs the following technical solutions:
A kind of ground pump pipe mounting structure, including U-shaped connector, ground pump tube guide piece and hollow sleeve, the hollow sleeve are equipped with
Two, be embedded in the wall being connected with air shaft in parallel, the both ends of hollow sleeve respectively with wall inner space and ventilation
Vertical shaft communicates, and the U-shaped connector includes the quarter butt that two stocks disposed in parallel and both ends are connect with two stock one end respectively,
Two stocks and quarter butt are integrally formed to form the U-shaped connector, and two stocks are pierced by respectively to ventilation from two hollow sleeves and erect
In well, quarter butt is connected on wall inside, and the ground pump tube guide piece is fixed to be set on two stocks and be located in air shaft,
Have on the ground pump tube guide piece and just allows the guide channel that is pierced by of ground pump line, the axial direction of the guide channel and logical
The axial direction of wind vertical shaft is identical.
It is such, by being embedded to hollow sleeve in the wall being connected with air shaft in advance, poured in the concrete of wall
After the completion of building, two stocks of U-shaped connector are pierced by from hollow sleeve into air shaft, and fixation is arranged on two stocks
Pump line installs the ground pump tube guide piece playing the guiding role over the ground, in this way, when Construction of High-rise, on each layer of wall
The mounting structure is set, so that guide channel upward direct service layer of the ground pump line along the ground pump tube guide piece of each layer, by this
Pump line has carried out preferable fixed installation to mounting structure over the ground, and since hollow sleeve is embedded in wall, after the completion of construction,
Stock can be extracted out, convenient for remove, it is reusable, hollow sleeve is blocked so that its damaged caused by wall it is smaller
Controllably.
As optimization, the ground pump tube guide piece includes two V-type guide pads, and it is long that two V-type guide pads are set in two
On bar, and the opening face of two V-type guide pads is to form the guide channel being just passed through for ground pump line.
It is such, ground pump tube guide piece is formed by two V-type guide pads, what the opening formation of the two was passed through for ground pump line
Guide channel can be applicable in the ground pump line of different thicknesses, all have preferable limit effect to different ground pump lines.
A V-type guide pad of relatively close wall and it is additionally provided with pad between the walls as optimization, in two V-type guide pads
Block, the cushion block are set on two stocks by the perforation that it is opened up.
It is such, by be arranged cushion block, adjustable ground pump line between wall at a distance from, prevent it from excessively connecing with wall
Closely, it is unfavorable for subsequent installation.
As optimization, the stock is with externally threaded screw rod, and stock outer end is also arranged with pressing plate, and the pressing plate is used for
Two V-type guide pads and cushion block are pressed in outer wall, and is located on the outside of pressing plate on stock and is also bolted with for screwing pressure
The nut of plate.
It is such, by setting pressing plate and nut, ground pump tube guide piece can be locked on stock, be conducive to fixed ground pump
The position of pipe.
As optimization, on the inside of the quarter butt and wall between there is gap, be arranged in the gap at least two it is parallel
Steel pipe.
It is such, it by the way that steel pipe is arranged, and is folded between quarter butt and wall inside, quarter butt is avoided directly to contact with wall,
It can play the role of dispersive stress, reduce to the damage on the inside of wall.
The present invention also provides the installation methods of a kind of ground pump line, comprising the following steps:
Step 1) builds pump line installation with being at least arranged one on the wall being connected with air shaft vertical section at each layer in advance
Structure, and at least one ground pump pipe mounting structure is also preset on the bottom of the building plate that the first floor is connected with air shaft horizontal segment,
And the axial direction of the guide channel of each ground pump pipe mounting structure in air shaft vertical section is respectively positioned on same straight line;
Step 2 is located to be arranged at air shaft hole in work layer and fixes foot prop;
Step 3), by ground pump line outside the hole that the horizontal segment and vertical section of air shaft successively extend out to air shaft, and by
The fixation foot prop being arranged in step 2 is fixed, wherein pump line be guiding along each ground pump pipe mounting structure in air shaft
What channel was walked;
The ground pump line being pierced by step 4), step 3) passes through after fixed foot prop is fixed to be connect with cloth system, completes ground pump line
Installation is fixed.
Such, the installation for solving the disadvantage that ground pump line by this installation method loosely, and is reduced to wall
Damage, there is simple, practical, easy to demolition advantage.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the embodiment of the present invention;
Fig. 2 is the scheme of installation of the embodiment of the present invention.
Specific embodiment
Below with reference to example attached drawing, the present invention is described in further detail.
When specific implementation: referring to Fig. 1 and Fig. 2, a kind of ground pump pipe mounting structure, including U-shaped connector 1, pump line guiding
Part and hollow sleeve 2, the hollow sleeve 2 are embedded in the wall 4 being connected with air shaft 3, hollow sleeve in parallel there are two setting
The both ends of pipe 2 are communicated with wall inner space and air shaft respectively, and the U-shaped connector 1 includes two stocks 5 disposed in parallel
And the quarter butt 6 that both ends are connect with two stock one end respectively, two stocks 5 form the U-shaped connector 1 with the integrated molding of quarter butt 6,
And two stock 5 be pierced by from two hollow sleeves 2 into air shaft 3 respectively, on quarter butt 6 is connected on the inside of wall, the ground pump
Tube guide piece is fixed to be set on two stocks and is located in air shaft 3, is had on the ground pump tube guide piece and is just allowed ground
The guide channel that pump line 7 is pierced by, the axial direction of the guide channel and the axial direction of air shaft are identical.
It is such, by being embedded to hollow sleeve in the wall being connected with air shaft in advance, poured in the concrete of wall
After the completion of building, two stocks of U-shaped connector are pierced by from hollow sleeve into air shaft, and fixation is arranged on two stocks
Pump line installs the ground pump tube guide piece playing the guiding role over the ground, in this way, when Construction of High-rise, on each layer of wall
The mounting structure is set, so that guide channel upward direct service layer of the ground pump line along the ground pump tube guide piece of each layer, by this
Pump line has carried out preferable fixed installation to mounting structure over the ground, and since hollow sleeve is embedded in wall, after the completion of construction,
Stock can be extracted out, convenient for remove, it is reusable, hollow sleeve is blocked so that its damaged caused by wall it is smaller
Controllably.
As optimization, the ground pump tube guide piece includes two V-type guide pads 8, and two V-type guide pads 8 are set in two
On stock, and the opening face of two V-type guide pads is to form the guide channel being just passed through for ground pump line.
It is such, ground pump tube guide piece is formed by two V-type guide pads, what the opening formation of the two was passed through for ground pump line
Guide channel can be applicable in the ground pump line of different thicknesses, all have preferable limit effect to different ground pump lines.
A V-type guide pad of relatively close wall and it is additionally provided with pad between the walls as optimization, in two V-type guide pads
Block 9, the cushion block 9 are set on two stocks by the perforation that it is opened up.
It is such, by be arranged cushion block, adjustable ground pump line between wall at a distance from, prevent it from excessively connecing with wall
Closely, it is unfavorable for subsequent installation.
As optimization, the stock 5 is with externally threaded screw rod, and stock outer end is also arranged with pressing plate 10, the pressing plate
10 for being pressed on outer wall for two V-type guide pads 8 and cushion block 9, and is located at 10 outside of pressing plate on stock and is also bolted with
For screwing the nut of pressing plate.
It is such, by setting pressing plate and nut, ground pump tube guide piece can be locked on stock, be conducive to fixed ground pump
The position of pipe.
As optimization, on the inside of the quarter butt and wall between there is gap, be arranged in the gap at least two it is parallel
Steel pipe 11.
It is such, it by the way that steel pipe is arranged, and is folded between quarter butt and wall inside, quarter butt is avoided directly to contact with wall,
It can play the role of dispersive stress, reduce to the damage on the inside of wall.
The present invention also provides the installation methods of a kind of ground pump line, comprising the following steps:
Step 1) builds pump line installation with being at least arranged one on the wall being connected with air shaft vertical section at each layer in advance
Structure 12, and at least one ground pump pipe mounting structure is also preset on the bottom of the building plate that the first floor is connected with air shaft horizontal segment
12, and the axial direction of the guide channel for each ground pump pipe mounting structure being located in air shaft vertical section is respectively positioned on same straight line
On;
Step 2 is located to be arranged at air shaft hole in work layer and fixes foot prop 13;
Step 3), by ground pump line outside the hole that the horizontal segment and vertical section of air shaft successively extend out to air shaft, and by
The fixation foot prop 13 that is arranged in step 2 is fixed, wherein pump line be leading along each ground pump pipe mounting structure in air shaft
It is walked to channel;
The ground pump line being pierced by step 4), step 3) passes through after fixed foot prop is fixed to be connect with cloth system 14, completes ground pump line
Installation fix.
Such, the installation for solving the disadvantage that ground pump line by this installation method loosely, and is reduced to wall
Damage, there is simple, practical, easy to demolition advantage.
Claims (6)
1. a kind of ground pump pipe mounting structure, it is characterised in that: described including U-shaped connector, ground pump tube guide piece and hollow sleeve
It there are two hollow sleeve is set, is embedded in the wall being connected with air shaft in parallel, the both ends of hollow sleeve are respectively and in wall
Side space and air shaft communicate, the U-shaped connector include two stocks disposed in parallel and both ends respectively with two stocks one
The quarter butt of connection is held, two stocks and quarter butt are integrally formed to form the U-shaped connector, and two stocks are respectively from two hollow sleeves
It is pierced by into air shaft, quarter butt is connected on wall inside, and the ground pump tube guide piece fixation is set on two stocks and position
There is the guide channel for just allowing ground pump line to be pierced by, the guide channel in air shaft, on the ground pump tube guide piece
Axial direction it is identical as the axial direction of air shaft.
2. a kind of ground pump pipe mounting structure according to claim 1, it is characterised in that: the ground pump tube guide piece includes two
A V-type guide pad, two V-type guide pads are set on two stocks, and the opening face of two V-type guide pads is to form for ground
The guide channel that pump line is just passed through.
3. a kind of ground pump pipe mounting structure according to claim 2, it is characterised in that: opposite in two V-type guide pads to lean on
One V-type guide pad of nearly wall and it is additionally provided with cushion block between the walls, the cushion block is set in two by the perforation that it is opened up
On stock.
4. a kind of ground pump pipe mounting structure according to claim 2, it is characterised in that: the stock is with externally threaded
Screw rod, stock outer end are also arranged with pressing plate, and the pressing plate is used to two V-type guide pads and cushion block being pressed on outer wall,
And it is located at the nut being also bolted on the outside of pressing plate for screwing pressing plate on stock.
5. a kind of ground pump pipe mounting structure according to claim 1, it is characterised in that: have between on the inside of the quarter butt and wall
There is gap, at least two parallel steel pipes are arranged in the gap.
6. a kind of ground pump line installation method is installed using any ground pump pipe mounting structure of claim 1 ~ 5, special
Sign is, comprising the following steps:
Step 1) builds pump line installation with being at least arranged one on the wall being connected with air shaft vertical section at each layer in advance
Structure, and at least one ground pump pipe mounting structure is also preset on the bottom of the building plate that the first floor is connected with air shaft horizontal segment,
And the axial direction of the guide channel of each ground pump pipe mounting structure in air shaft vertical section is respectively positioned on same straight line;
Step 2 is located to be arranged at air shaft hole in work layer and fixes foot prop;
Step 3), by ground pump line outside the hole that the horizontal segment and vertical section of air shaft successively extend out to air shaft, and by
The fixation foot prop being arranged in step 2 is fixed, wherein pump line be guiding along each ground pump pipe mounting structure in air shaft
What channel was walked;
The ground pump line being pierced by step 4), step 3) passes through after fixed foot prop is fixed to be connect with cloth system, completes ground pump line
Installation is fixed.
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910703264.6A CN110259134A (en) | 2019-07-31 | 2019-07-31 | A kind of ground pump pipe mounting structure and method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910703264.6A CN110259134A (en) | 2019-07-31 | 2019-07-31 | A kind of ground pump pipe mounting structure and method |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN110259134A true CN110259134A (en) | 2019-09-20 |
Family
ID=67912600
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201910703264.6A Pending CN110259134A (en) | 2019-07-31 | 2019-07-31 | A kind of ground pump pipe mounting structure and method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN110259134A (en) |
Citations (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4998691A (en) * | 1990-01-23 | 1991-03-12 | Baker Hughes Incorporated | U-shaped pipe clamping system |
| CN201109014Y (en) * | 2007-12-03 | 2008-09-03 | 青岛港(集团)有限公司 | Conduit butt-joint rapid alignment device |
| CN104727554A (en) * | 2015-01-29 | 2015-06-24 | 天津二十冶建设有限公司 | Concrete introduction device for concrete jacking construction and method of use thereof |
| CN204590632U (en) * | 2015-04-30 | 2015-08-26 | 张洁 | Pump concrete carrier pipe shock bracket is dragged in a kind of building site |
| CN204852619U (en) * | 2015-07-24 | 2015-12-09 | 中建四局第一建筑工程有限公司 | Can have enough to meet need pump line fixing device of use |
| CN207686313U (en) * | 2017-11-27 | 2018-08-03 | 中建一局集团第五建筑有限公司 | Pressure-relieving reinforcing device for high-pressure pump pipe of bending section |
| CN108385982A (en) * | 2018-03-15 | 2018-08-10 | 广厦建设集团有限责任公司 | A kind of Super High concrete pumping pipe and its installation method |
| CN208024956U (en) * | 2018-03-20 | 2018-10-30 | 厦门特房建设工程集团有限公司 | A kind of combined type pump line bracing means |
| CN208473311U (en) * | 2018-05-29 | 2019-02-05 | 山东天齐置业集团股份有限公司 | A kind of concreting pump line support construction |
| CN208487274U (en) * | 2018-07-04 | 2019-02-12 | 中铁建设集团有限公司 | A turnaroundable ground pump riser reinforcement device |
| CN210342702U (en) * | 2019-07-31 | 2020-04-17 | 中冶建工集团有限公司 | Ground pump pipe mounting structure |
-
2019
- 2019-07-31 CN CN201910703264.6A patent/CN110259134A/en active Pending
Patent Citations (11)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US4998691A (en) * | 1990-01-23 | 1991-03-12 | Baker Hughes Incorporated | U-shaped pipe clamping system |
| CN201109014Y (en) * | 2007-12-03 | 2008-09-03 | 青岛港(集团)有限公司 | Conduit butt-joint rapid alignment device |
| CN104727554A (en) * | 2015-01-29 | 2015-06-24 | 天津二十冶建设有限公司 | Concrete introduction device for concrete jacking construction and method of use thereof |
| CN204590632U (en) * | 2015-04-30 | 2015-08-26 | 张洁 | Pump concrete carrier pipe shock bracket is dragged in a kind of building site |
| CN204852619U (en) * | 2015-07-24 | 2015-12-09 | 中建四局第一建筑工程有限公司 | Can have enough to meet need pump line fixing device of use |
| CN207686313U (en) * | 2017-11-27 | 2018-08-03 | 中建一局集团第五建筑有限公司 | Pressure-relieving reinforcing device for high-pressure pump pipe of bending section |
| CN108385982A (en) * | 2018-03-15 | 2018-08-10 | 广厦建设集团有限责任公司 | A kind of Super High concrete pumping pipe and its installation method |
| CN208024956U (en) * | 2018-03-20 | 2018-10-30 | 厦门特房建设工程集团有限公司 | A kind of combined type pump line bracing means |
| CN208473311U (en) * | 2018-05-29 | 2019-02-05 | 山东天齐置业集团股份有限公司 | A kind of concreting pump line support construction |
| CN208487274U (en) * | 2018-07-04 | 2019-02-12 | 中铁建设集团有限公司 | A turnaroundable ground pump riser reinforcement device |
| CN210342702U (en) * | 2019-07-31 | 2020-04-17 | 中冶建工集团有限公司 | Ground pump pipe mounting structure |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103114863B (en) | Tunnel secondary lining back arch grouting pipe reserving system | |
| CN209040125U (en) | A foundation pit support device | |
| CN203247842U (en) | Reinforcing device of concrete structure expansion joint formwork | |
| CN203755676U (en) | Perpendicularity control tool for wall column | |
| CN202509764U (en) | Template bracing structure for constructional column | |
| CN110259134A (en) | A kind of ground pump pipe mounting structure and method | |
| CN204529015U (en) | A kind of V-type elevator wall-attached frame | |
| CN216238571U (en) | Support device for well template in groove | |
| CN108390307B (en) | A construction method for wiring box installation points | |
| CN213745230U (en) | Anti-seismic support for heat-preservation ventilation air-conditioning pipeline | |
| CN105442832A (en) | Formwork for concrete guide wall | |
| CN204531391U (en) | Pitched roof template system | |
| CN105586987B (en) | Open trench tunnel open type agent structure side wall Bailey bracket formwork and its construction technology | |
| CN104675095A (en) | Adjustable steel pipe support | |
| CN209244225U (en) | A kind of hound of adjustable length | |
| CN107675795A (en) | A kind of assembled wallboard dry type attachment structure and its assembly method | |
| CN106284978A (en) | A kind of movement joint both sides shear wall synchronous construction technique and canalization template | |
| CN208294085U (en) | A kind of concrete side wall is without to wearing structure split bolt formwork | |
| CN211974339U (en) | A window sill formwork support device | |
| CN212480374U (en) | A water stop pipe | |
| CN209228050U (en) | With the wall split bolt structure of cable bearer linkage function in pipe gallery | |
| CN205531285U (en) | Scaffold frame is encorbelmented shaped steel and is reserved bolt hole and establish structure | |
| CN106013552A (en) | Energy-saving curtain wall based on steel and aluminum sheath core and locating corner braces | |
| CN109457909A (en) | A kind of quick-assembling arrangement of reinforcement cast-in-place concrete floor construction device and application method | |
| CN119531412B (en) | A formwork support sliding assembly and construction method for underground comprehensive pipe gallery construction |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190920 |