CN110258642A - A kind of combined assembled underground structure of cut and cover method and its construction method - Google Patents

A kind of combined assembled underground structure of cut and cover method and its construction method Download PDF

Info

Publication number
CN110258642A
CN110258642A CN201910624049.7A CN201910624049A CN110258642A CN 110258642 A CN110258642 A CN 110258642A CN 201910624049 A CN201910624049 A CN 201910624049A CN 110258642 A CN110258642 A CN 110258642A
Authority
CN
China
Prior art keywords
side wall
prefabricated part
prefabricated
layer
slab
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910624049.7A
Other languages
Chinese (zh)
Inventor
徐军林
付先进
蒋晔
王鹏
刘玟君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Survey and Design Group Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201910624049.7A priority Critical patent/CN110258642A/en
Publication of CN110258642A publication Critical patent/CN110258642A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明属于地下工程建造领域,涉及一种明挖法复合装配式地下结构,底层板上设置有两个第一侧墙预制件,第一层板的两端分别支撑于两个第一侧墙预制件上;第一侧墙预制件通过企口与第二侧墙预制件连接;第二层板的两端分别支撑于两个第二侧墙预制上。本发明还提供一种明挖法复合装配式地下结构的施工方法,采用明挖法施工,先施工底层板,吊装第一侧墙预制件,浇筑第一侧墙现浇层;再完成第一层板的施工;然后吊装第二侧墙预制件,第二侧墙预制件的底部通过企口与第一侧墙预制件的顶部定位连接,浇筑第二侧墙现浇层;最后完成第二层板的施工。本发明较好实现了装配式地下结构,适用范围广,并能够提高装配式地下结构的整体受力性能。

The invention belongs to the field of underground engineering construction, and relates to an open-cut composite assembled underground structure. Two first side wall prefabricated parts are arranged on the bottom floor, and the two ends of the first floor are respectively supported on the two first side walls. On the prefabricated part; the first side wall prefabricated part is connected with the second side wall prefabricated part through a tongue and groove; the two ends of the second layer board are respectively supported on the two second side wall prefabricated parts. The present invention also provides a construction method of the open-cut composite assembly type underground structure. The open-cut method is adopted for construction. The bottom plate is constructed first, the first side wall prefabricated part is hoisted, and the first side wall cast-in-place layer is poured; then the first side wall is completed. The construction of the laminate; then hoist the second side wall prefabricated part, the bottom of the second side wall prefabricated part is positioned and connected with the top of the first side wall prefabricated part through the groove, and the second side wall cast-in-place layer is poured; finally the second side wall prefabricated part is completed. Laminate construction. The invention preferably realizes the assembled underground structure, has a wide application range, and can improve the overall mechanical performance of the assembled underground structure.

Description

一种明挖法复合装配式地下结构及其施工方法A kind of open-cut composite assembly underground structure and its construction method

技术领域technical field

本发明属于地下工程建造技术领域,具体涉及一种明挖法复合装配式地下结构及其施工方法。The invention belongs to the technical field of underground engineering construction, and in particular relates to an open-cut composite assembled underground structure and a construction method thereof.

背景技术Background technique

目前明挖法施工有内支撑基坑的地下结构采用的是传统的现浇钢筋混凝土结构施工技术,设计过程复杂,工作量大;现场施工过程中需要大量的多工种的劳动力,施工作业环境差,施工工序复杂,施工速度慢,受各种天气、气候的影响大,施工质量难以保证。同时在施工过程中还会产生很多废弃的建筑垃圾,既浪费资源又污染环境。现浇混凝土结构施工管控参差不齐,完成施工后往往因各方面原因导致混凝土结构外观或者内在经常出现各种质量缺陷,后期修复难度大,质量难以保证。At present, the open excavation method is used to construct the underground structure with internal support foundation pit using the traditional cast-in-place reinforced concrete structure construction technology, the design process is complicated, and the workload is large; the on-site construction process requires a lot of labor of various types, and the construction environment is poor. , The construction process is complicated, the construction speed is slow, and it is greatly affected by various weather and climate, so the construction quality is difficult to guarantee. At the same time, a lot of abandoned construction waste will be generated during the construction process, which not only wastes resources but also pollutes the environment. The construction control of cast-in-place concrete structures is uneven. After the completion of the construction, there are often various quality defects in the appearance or interior of the concrete structure due to various reasons. It is difficult to repair later and the quality is difficult to guarantee.

随着科技的进度,装备制造业的发展,越来越多的工作由机器替代人力,高技术代替劳动密集型、自动控制装备代替人工控制。在建筑工程领域所需要的各种构件(梁、板、柱、墙)将会逐渐在工厂批量化生产,然后运输到现场进行拼装完成。With the progress of science and technology and the development of equipment manufacturing industry, more and more jobs are replaced by machines, labor-intensive by high technology, and manual control by automatic control equipment. Various components (beams, slabs, columns, walls) required in the field of construction engineering will gradually be mass-produced in factories, and then transported to the site for assembly.

随着装配式技术的发展,地下结构也陆续出现了各种装配式设计、施工技术方案,有些仅适用于地下水少且采用放坡或者锚索(杆)开敞式明挖基坑,不适用于基坑采用内支撑、地下水丰富的地区;有些仅仅局部采用装配式结构,装配程度不高,装配效率低;有的预制构件体量大,对吊装、拼装设备要求极高。With the development of prefabricated technology, various prefabricated designs and construction technical schemes have emerged for underground structures, some of which are only suitable for open excavation foundation pits with less groundwater and grading or anchor cables (rods). In areas where internal support is used for foundation pits and the groundwater is abundant; some only partially adopt prefabricated structures, the degree of assembly is not high, and the assembly efficiency is low; some prefabricated components are large in size and require extremely high hoisting and assembly equipment.

发明内容Contents of the invention

为了克服上述现有技术存在的不足,本发明的目的是提供一种明挖法复合装配式地下结构及其施工方法,能够有效解决地下装配式结构防水问题以及结构整体性问题。In order to overcome the deficiencies of the above-mentioned prior art, the object of the present invention is to provide an open-cut composite assembled underground structure and its construction method, which can effectively solve the problems of waterproofing and structural integrity of the underground assembled structure.

为实现上述目的,本发明的技术方案为一种明挖法复合装配式地下结构,包括底层板、第一层板、第二层板、第一侧墙预制件、第二侧墙预制件和两个围护结构,两个围护结构之间从下往上依次设有底层板、第一层板和第二层板;所述底层板上设置有两个第一侧墙预制件,所述第一层板的两端分别支撑于两个第一侧墙预制件上;各所述第一侧墙预制件上均设有第二侧墙预制件,所述第一侧墙预制件通过企口与对应的所述第二侧墙预制件连接;所述第二层板的两端分别支撑于两个第二侧墙预制上。In order to achieve the above object, the technical solution of the present invention is an open-cut composite assembled underground structure, which includes a bottom slab, a first slab, a second slab, a first side wall prefabricated part, a second side wall prefabricated part and There are two enclosure structures, and the ground floor, the first floor and the second floor are arranged in sequence from bottom to top between the two enclosures; the bottom floor is provided with two first side wall prefabricated parts, so The two ends of the first layer board are respectively supported on two first side wall prefabricated parts; each of the first side wall prefabricated parts is provided with a second side wall prefabricated part, and the first side wall prefabricated parts pass through The groove is connected with the corresponding second side wall prefabrication; the two ends of the second layer board are respectively supported on the two second side wall prefabrication.

进一步地,所述第一侧墙预制件与对应的所述围护结构之间设有第一侧墙现浇层,所述第二侧墙预制件与对应的所述围护结构之间设有第二侧墙现浇层。Further, a first side wall cast-in-place layer is provided between the first side wall prefabricated part and the corresponding enclosure structure, and a first side wall cast-in-place layer is provided between the second side wall prefabricated part and the corresponding enclosure structure. There is a second side wall cast in place.

进一步地,所述底层板包括底纵梁预制件以及用于分别支撑两个第一侧墙预制件的两个底层板预制件;所述底纵梁预制件和所述底层板预制件均设置于混凝土换撑板上,所述底纵梁预制件设置于两个底层板预制件之间,所述底纵梁预制件与所述底层板预制件之间浇筑有底层板现浇连接段。Further, the bottom slab includes a bottom stringer prefabricated part and two bottom slab prefabricated parts for respectively supporting two first side wall prefabricated parts; the bottom stringer prefabricated part and the bottom slab prefabricated part On the concrete support plate, the bottom longitudinal beam prefabricated part is arranged between two bottom slab prefabricated parts, and a bottom slab cast-in-place connection section is poured between the bottom longitudinal beam prefabricated part and the bottom slab prefabricated part.

更进一步地,所述底层板预制件背离所述围护结构的一侧设有第一凹槽,所述底纵梁预制件上与所述第一凹槽相对的一侧设有第二凹槽,所述底层板现浇连接段位于所述第一凹槽与所述第二凹槽之间。Furthermore, a first groove is provided on the side of the prefabricated bottom plate away from the enclosure structure, and a second concave is provided on the side of the prefabricated bottom stringer opposite to the first groove. groove, and the cast-in-place connection section of the bottom plate is located between the first groove and the second groove.

进一步地,所述底纵梁预制件上设有第一中立柱,所述第一中立柱与所述底纵梁预制件之间浇筑有第一中立柱现浇连接段;所述上设有第一中纵梁,所述第一层板的中部支撑于所述第一中纵梁上。Further, the bottom longitudinal beam prefabricated part is provided with a first central column, and a first central column cast-in-place connection section is cast between the first central column and the bottom longitudinal beam prefabricated part; The first central longitudinal beam, the middle part of the first layer board is supported on the first central longitudinal beam.

进一步地,所述第一层板包括两个第一层板预制件,各所述第一层板预制件的一端支撑于第一中纵梁上,另一端支撑于第一侧墙预制件上,两个第一层板预制件上浇筑有第一层板现浇层。Further, the first layer slab includes two first layer slab prefabricated parts, one end of each first layer slab prefabricated part is supported on the first middle longitudinal beam, and the other end is supported on the first side wall prefabricated part , the cast-in-situ layer of the first layer slab is poured on the two first layer slab prefabricated parts.

进一步地,所述第一层板上设有第二中立柱,所述第二中立柱上设有第二中纵梁,所述第二层板的中部支撑于所述第二中纵梁上。Further, the first floor board is provided with a second central column, the second central column is provided with a second middle longitudinal beam, and the middle part of the second floor board is supported on the second middle longitudinal beam .

进一步地,所述第二层板包括两个第二层板预制件,各所述第二层板预制件的一端支撑于第二中纵梁上,另一端支撑于第二侧墙预制件上,两个第二层板预制件上浇筑有第二层板现浇层。Further, the second layer board includes two second layer board prefabricated parts, one end of each second layer board prefabricated part is supported on the second middle longitudinal beam, and the other end is supported on the second side wall prefabricated part , the cast-in-situ layer of the second layer slab is poured on the two second layer slab prefabricated parts.

本发明还提供一种明挖法复合装配式地下结构的施工方法,包括如下步骤:The present invention also provides a construction method of an open-cut composite assembled underground structure, comprising the following steps:

1)完成两个围护结构施工后,施工冠梁,采用明挖法施工,在两个围护结构之间边开挖边架设三道内支撑,开挖到基坑底;1) After the construction of the two enclosure structures is completed, the crown beam will be constructed using the open cut method, and three internal supports will be erected between the two enclosure structures while excavating, and excavated to the bottom of the foundation pit;

2)在基坑底先施工混凝土垫层,再在混凝土垫层上施工防水层,然后在防水层上施工混凝土换撑板,拆除最下面的一道内支撑;2) Construct a concrete cushion at the bottom of the foundation pit first, then construct a waterproof layer on the concrete cushion, then construct a concrete replacement support plate on the waterproof layer, and remove the bottom inner support;

3)吊装第一侧墙钢筋骨架,第一侧墙钢筋骨架的底部与混凝土换撑板上预留的钢筋进行搭接,顶部与围护结构定位连接;3) Hoisting the reinforcement skeleton of the first side wall, the bottom of the reinforcement skeleton of the first side wall is overlapped with the steel bars reserved on the concrete support plate, and the top is positioned and connected with the enclosure structure;

4)完成底层板的施工;4) Complete the construction of the bottom slab;

5)吊装第一侧墙预制件,第一侧墙预制件的底部与底层板定位连接,利用第一侧墙预制件、围护结构作为侧模板,在第一侧墙预制件与围护结构之间浇筑混凝土,与先前吊装的第一侧墙钢筋骨架形成第一侧墙现浇层;5) Hoist the prefabricated part of the first side wall, the bottom of the prefabricated part of the first side wall is positioned and connected with the bottom plate, and the prefabricated part of the first side wall and the enclosure structure are used as the side formwork, and the prefabricated part of the first side wall and the enclosure structure Concrete is poured in between to form the cast-in-situ layer of the first side wall with the steel skeleton of the first side wall hoisted previously;

6)完成第一中立柱、第一中纵梁的施工;6) Complete the construction of the first center column and the first center longitudinal beam;

7)完成第一层板的施工,然后拆除中间的一道内支撑;7) Complete the construction of the first floor, and then remove the inner support in the middle;

8)吊装第二侧墙钢筋骨架,第二侧墙钢筋骨架的底部与第一侧墙现浇层上预留的钢筋进行搭接,顶部与围护结构定位连接;吊装第二侧墙预制件,第二侧墙预制件的底部通过企口与第一侧墙预制件的顶部定位连接,利用第二侧墙预制件、围护结构作为侧模板,在第二侧墙预制件与围护结构之间浇筑混凝土,与先前吊装的第二侧墙钢筋骨架形成第二侧墙现浇层;8) Hoist the second side wall reinforcement skeleton, the bottom of the second side wall reinforcement skeleton is overlapped with the reserved steel bars on the first side wall cast-in-place layer, and the top is positioned and connected with the enclosure structure; hoist the second side wall prefabricated parts , the bottom of the second side wall prefabricated part is positioned and connected with the top of the first side wall prefabricated part through a groove, and the second side wall prefabricated part and the enclosure structure are used as side templates, and the second side wall prefabricated part and the enclosure structure Concrete is poured in between to form the cast-in-situ layer of the second side wall with the previously hoisted steel skeleton of the second side wall;

9)完成第二中立柱、第二中纵梁的施工;9) Complete the construction of the second center column and the second center longitudinal beam;

10)完成第二层板的施工,然后拆除最上面的一道内支撑。10) Complete the construction of the second layer, and then remove the top inner support.

进一步地,步骤4)中的底层板的具体施工步骤如下:在混凝土换撑板上吊装底纵梁预制件和底层板预制件,纵梁预制件两端预留的钢筋分别与两侧的底层板预制件上预留的钢筋绑扎搭接,在底纵梁预制件与底层板预制件之间浇筑混凝土形成底层板现浇连接段。Further, the specific construction steps of the bottom slab in step 4) are as follows: hoist the bottom stringer prefabricated part and the bottom slab prefabricated part on the concrete support slab, and the steel bars reserved at both ends of the The steel bars reserved on the prefabricated slab are bound and lapped, and concrete is poured between the prefabricated bottom longitudinal beam and the prefabricated bottom slab to form the cast-in-place connection section of the bottom slab.

进一步地,步骤7)中的第一层板的具体施工步骤如下:吊装第一层板预制件,第一层板预制件的一端支撑于第一中纵梁上,另一端支撑于第一侧墙预制件上;在第一层板预制件上浇筑混凝土形成第一层板现浇层。Further, the specific construction steps of the first layer slab in step 7) are as follows: hoisting the first layer prefabricated part, one end of the first layer prefabricated part is supported on the first middle longitudinal beam, and the other end is supported on the first side On the prefabricated part of the wall; pouring concrete on the prefabricated part of the first slab to form the cast-in-situ layer of the first slab.

进一步地,步骤10)中的第二层板的具体施工步骤如下:吊装第二层板预制件,第二层板预制件的一端支撑于第二中纵梁上,另一端支撑于第二侧墙预制件上;在第二层板预制件上浇筑混凝土形成第二层板现浇层。Further, the specific construction steps of the second layer slab in step 10) are as follows: hoisting the second layer slab prefabricated part, one end of the second layer slab prefabricated part is supported on the second middle longitudinal beam, and the other end is supported on the second side On the prefabricated part of the wall; pouring concrete on the prefabricated part of the second slab to form the cast-in-situ layer of the second slab.

与现有技术相比,本发明具有以下有益效果:Compared with the prior art, the present invention has the following beneficial effects:

(1)本发明提供的明挖法复合装配式地下结构及其施工方法适用范围广,(1) The open excavation method composite assembled underground structure and its construction method provided by the present invention have a wide range of applications,

且第一侧墙预制件和第二侧墙预制件通过企口连接,提高装配式结构的整体性;And the first side wall prefabricated part and the second side wall prefabricated part are connected by groove and groove, so as to improve the integrity of the prefabricated structure;

(2)本发明通过预制件与现浇层形成叠合结构,可以免去部分现场支模、架设脚手架等临时设施,节省工期,并能有效地提高装配式地下结构的防水性能以及整体受力性能;(2) The present invention forms a superimposed structure through the prefabricated parts and the cast-in-place layer, which can save some temporary facilities such as on-site formwork and erection of scaffolding, save the construction period, and can effectively improve the waterproof performance and overall force of the assembled underground structure performance;

(3)本发明采用合理的构件分块方案,可以减小单个预制件的尺寸以及重量,使得预制构件的尺寸及重量能够适应有支撑基坑的现场吊装、拼装要求,同时便于预制件的运输,并能较好实现产业化推广应用;(3) The present invention adopts a reasonable component block scheme, which can reduce the size and weight of a single prefabricated component, so that the size and weight of the prefabricated component can meet the requirements for on-site hoisting and assembly of a supported foundation pit, and at the same time facilitate the transportation of the prefabricated component , and can better realize the promotion and application of industrialization;

(4)本发明的侧墙预制件与层板预制件的连接处、层板预制件之间的连接处以及层板预制件与中纵梁的连接处均采用现浇“湿节点”,装配式地下结构的防水性、整体性好;(4) The joints between the side wall prefabricated parts and the laminate prefabricated parts, the joints between the laminate prefabricated parts and the joints between the laminate prefabricated parts and the central longitudinal beams of the present invention all adopt cast-in-place "wet joints". The water resistance and integrity of the type underground structure are good;

(5)本发明具有预制件尺寸标准化、减少设计工作量,提高生产效率,提升建筑质量,可以较好实现产业化,节省劳动力,节省模板及脚手架等,缩短工期、节能、改善从业者的工作环境等优点。(5) The present invention has the advantages of standardization of prefabricated parts size, reduction of design workload, improvement of production efficiency, improvement of construction quality, better realization of industrialization, saving labor, saving formwork and scaffolding, etc., shortening construction period, saving energy, and improving the work of practitioners environment and other advantages.

附图说明Description of drawings

为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其它的附图。In order to more clearly illustrate the technical solutions in the embodiments of the present invention or the prior art, the following will briefly introduce the drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description are only These are some embodiments of the present invention. Those skilled in the art can also obtain other drawings based on these drawings without creative work.

图1为本发明实施例提供的复合装配式地下结构的明挖示意图;Fig. 1 is the open-cut schematic diagram of the composite fabricated underground structure provided by the embodiment of the present invention;

图2为本发明实施例提供的复合装配式地下结构的明挖示意图;Fig. 2 is a schematic diagram of open excavation of a composite fabricated underground structure provided by an embodiment of the present invention;

图3为本发明实施例提供的复合装配式地下结构的明挖示意图;Fig. 3 is a schematic diagram of open excavation of a composite fabricated underground structure provided by an embodiment of the present invention;

图4为本发明实施例提供的复合装配式地下结构的明挖示意图;Fig. 4 is a schematic diagram of open excavation of a composite fabricated underground structure provided by an embodiment of the present invention;

图5为本发明实施例提供的复合装配式地下结构的明挖示意图;Fig. 5 is a schematic diagram of open excavation of a composite fabricated underground structure provided by an embodiment of the present invention;

图6为本发明实施例提供的复合装配式地下结构的明挖示意图;Fig. 6 is a schematic diagram of open excavation of a composite fabricated underground structure provided by an embodiment of the present invention;

图7为本发明实施例提供的复合装配式地下结构的明挖示意图;Fig. 7 is a schematic diagram of open excavation of the composite assembled underground structure provided by the embodiment of the present invention;

图8为本发明实施例提供的复合装配式地下结构的明挖示意图;Fig. 8 is a schematic diagram of open excavation of a composite fabricated underground structure provided by an embodiment of the present invention;

图9为本发明实施例提供的复合装配式地下结构的明挖示意图;Fig. 9 is a schematic diagram of open excavation of a composite fabricated underground structure provided by an embodiment of the present invention;

图10为本发明实施例提供的复合装配式地下结构的明挖示意图;Fig. 10 is a schematic diagram of open excavation of a composite fabricated underground structure provided by an embodiment of the present invention;

图11为本发明实施例提供的复合装配式地下结构的明挖示意图;Fig. 11 is a schematic diagram of open excavation of a composite fabricated underground structure provided by an embodiment of the present invention;

图12为本发明实施例提供的复合装配式地下结构的结构示意图;Fig. 12 is a structural schematic diagram of a composite fabricated underground structure provided by an embodiment of the present invention;

图中:1、围护结构,2、冠梁,3、内支撑,4、混凝土垫层,5、混凝土换撑板,6、第一侧墙钢筋骨架,7、底层板预制件,71、第一凹槽,8、底纵梁预制件,81、第二凹槽,9、底层板现浇连接段,10、第一侧墙预制件,11、牛腿,12、第一侧墙现浇层,13、第一中立柱,14、第一中立柱现浇连接段,15、第一中纵梁,16、第一层板预制件,17、第一层板现浇层,18、第二侧墙钢筋骨架,19、第二侧墙预制件,20、第二侧墙叠合层,21、第二中立柱,22、第二中纵梁,23、第二层板预制件,24、第二层板现浇层,25、回填土。In the figure: 1. Enclosure structure, 2. Crown beam, 3. Internal support, 4. Concrete cushion, 5. Concrete replacement slab, 6. Steel skeleton of the first side wall, 7. Prefabricated part of the bottom slab, 71, First groove, 8. Bottom longitudinal beam prefabricated part, 81. Second groove, 9. Bottom slab cast-in-place connection section, 10. First side wall prefabricated part, 11. Corbel, 12. First side wall in-situ Casting layer, 13, the first central column, 14, the first central column cast-in-place connection section, 15, the first middle longitudinal beam, 16, the first layer prefabricated part, 17, the first layer cast-in-place layer, 18, Second side wall reinforced skeleton, 19. Second side wall prefabricated part, 20. Second side wall laminated layer, 21. Second central column, 22. Second middle longitudinal beam, 23. Second floor prefabricated part, 24. The cast-in-place layer of the second layer slab, 25. Backfilling soil.

具体实施方式Detailed ways

下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其它实施例,都属于本发明保护的范围。The following will clearly and completely describe the technical solutions in the embodiments of the present invention with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only some, not all, embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by persons of ordinary skill in the art without making creative efforts belong to the protection scope of the present invention.

在本发明的描述中,需要理解的是,术语“中心”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In describing the present invention, it is to be understood that the terms "center", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", The orientations or positional relationships indicated by "top", "bottom", "inner", "outer", etc. are based on the orientations or positional relationships shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying References to devices or elements must have a particular orientation, be constructed, and operate in a particular orientation and therefore should not be construed as limiting the invention.

术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征;在本发明的描述中,除非另有说明,“多个”的含义是两个或两个以上。The terms "first" and "second" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance or implicitly specifying the quantity of indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of these features; in the description of the present invention, unless otherwise specified, the meaning of "plurality" is two or more.

实施例一Embodiment one

如图1-图12所示,本发明实施例提供一种明挖法复合装配式地下结构,包括底层板、第一层板、第二层板、第一侧墙预制件10、第二侧墙预制件19和两个围护结构1,两个围护结构1之间从下往上依次设有底层板、第一层板和第二层板;所述底层板上设置有两个第一侧墙预制件10,所述第一层板的两端分别支撑于两个第一侧墙预制件10上;各所述第一侧墙预制件10上均设有第二侧墙预制件19,所述第一侧墙预制件10通过企口与对应的所述第二侧墙预制件19连接;所述第二层板的两端分别支撑于两个第二侧墙预制上。本发明提供的明挖法复合装配式地下结构及其施工方法适用范围广,且第一侧墙预制件10和第二侧墙预制件19通过企口连接,提高装配式结构的整体性。As shown in Figures 1 to 12, an embodiment of the present invention provides an open-cut composite assembled underground structure, which includes a base plate, a first layer plate, a second layer plate, a first side wall prefabricated part 10, a second side wall Wall prefabricated parts 19 and two enclosure structures 1, between the two enclosure structures 1 are provided with a bottom plate, a first layer plate and a second layer plate in sequence from bottom to top; the bottom plate is provided with two second A side wall prefabricated part 10, the two ends of the first layer board are respectively supported on two first side wall prefabricated parts 10; each of the first side wall prefabricated parts 10 is provided with a second side wall prefabricated part 19. The first side wall prefabricated part 10 is connected to the corresponding second side wall prefabricated part 19 through grooves; the two ends of the second layer board are respectively supported on the two second side wall prefabricated parts. The open-cut composite assembled underground structure and its construction method provided by the present invention have a wide range of applications, and the first side wall prefabricated part 10 and the second side wall prefabricated part 19 are connected by grooves to improve the integrity of the assembled structure.

进一步地,所述第一侧墙预制件10与对应的所述围护结构1之间设有第一侧墙现浇层12,所述第二侧墙预制件19与对应的所述围护结构1之间设有第二侧墙现浇层。本实施例在侧墙预制件与围护结构1之间吊装有侧墙钢筋骨架,侧墙钢筋骨架与对应的侧墙预制件上预留的钢筋进行拼接定位,然后通过在侧墙预制件与围护结构1之间浇筑混凝土形成侧墙现浇层,侧墙现浇层与侧墙预制件形成叠合结构,提高装配式地下结构的防水性能以及整体受力性能。本实施例可先在围护结构1上对应侧墙的位置先施工防水层,再吊装侧墙钢筋骨架以及浇筑混凝土,提高侧墙的防水性能。Further, a first side wall cast-in-place layer 12 is provided between the first side wall prefabricated part 10 and the corresponding enclosure structure 1, and the second side wall prefabricated part 19 is connected to the corresponding enclosure structure 1. A second cast-in-place layer of side walls is provided between the structures 1 . In this embodiment, a side wall reinforcement skeleton is hoisted between the side wall prefabricated part and the enclosure structure 1, and the side wall reinforcement skeleton is spliced and positioned with the steel bars reserved on the corresponding side wall prefabricated part, and then through the side wall prefabricated part and the Concrete is poured between the enclosure structures 1 to form the cast-in-place layer of the side wall, and the cast-in-place layer of the side wall and the prefabricated part of the side wall form a superimposed structure to improve the waterproof performance and overall mechanical performance of the assembled underground structure. In this embodiment, a waterproof layer can be constructed first at the position corresponding to the side wall on the enclosure structure 1, and then the steel skeleton of the side wall is hoisted and concrete is poured to improve the waterproof performance of the side wall.

进一步地,如图8-图12所示,所述第一侧墙预制件10的上设有牛腿11,所述第一层板的两端分别支撑于两个第一侧墙预制件10的牛腿11上,且所述第一侧墙预制件10的顶部于所述第一层板的上方与对应的所述第二侧墙预制件19通过企口定位连接。本实施例通过将第一侧墙预制件10与第二侧墙预制件19的连接节点设置在第一层板的上方,可以进一步提高相邻两层之间的整体性。Further, as shown in FIGS. 8-12 , corbels 11 are provided on the first side wall prefabricated part 10 , and the two ends of the first layer board are respectively supported by two first side wall prefabricated parts 10 on the corbel 11 of the first side wall prefabricated part 10, and the top of the first side wall prefabricated part 10 is connected to the corresponding second side wall prefabricated part 19 through groove-and-groove positioning above the first layer. In this embodiment, by arranging the connection node between the first side wall prefabricated part 10 and the second side wall prefabricated part 19 above the first layer board, the integrity between two adjacent layers can be further improved.

作为一种实施方式,如图4-图12所示,所述底层板包括底纵梁预制件8以及用于分别支撑两个第一侧墙预制件10的两个底层板预制件7;所述底纵梁预制件8和所述底层板预制件7均设置于混凝土换撑板5上,所述底纵梁预制件8设置于两个底层板预制件7之间,所述底纵梁预制件8与所述底层板预制件7之间浇筑有底层板现浇连接段9。本实施例的底层板通过多段预制件进行拼装连接,减小单个预制件的尺寸以及重量,便于预制件的运输、吊装和拼装;且相邻的预制件之间通过浇筑混凝土现浇连接,预制件与混凝土换撑板5上形成叠合结构,提高结构的整体性以及防水性。本实施例的第一侧墙预制件10的底部与底层板预制件7的顶部可通过企口结构定位连接。As an embodiment, as shown in Fig. 4-Fig. 12, the bottom slab includes a bottom stringer prefabricated part 8 and two prefabricated bottom slab parts 7 for respectively supporting two first side wall prefabricated parts 10; Both the bottom longitudinal beam prefabricated part 8 and the bottom slab prefabricated part 7 are arranged on the concrete support plate 5, the bottom longitudinal beam prefabricated part 8 is arranged between two bottom slab prefabricated parts 7, and the bottom longitudinal beam Between the prefabricated part 8 and the prefabricated part 7 of the bottom slab, there is a cast-in-place connection section 9 for the bottom slab. The bottom plate of this embodiment is assembled and connected by multi-section prefabricated parts, which reduces the size and weight of a single prefabricated part, and facilitates the transportation, hoisting and assembly of prefabricated parts; A superimposed structure is formed on the parts and the concrete replacement brace 5, which improves the integrity and waterproofness of the structure. The bottom of the first side wall prefabricated part 10 and the top of the bottom plate prefabricated part 7 in this embodiment can be positioned and connected through a groove-and-groove structure.

更进一步地,混凝土换撑板5的下方还设有混凝土垫层4,混凝土垫层4与混凝土换撑板5之间施工有防水层,提高底层板的防水性能。Furthermore, a concrete cushion 4 is provided below the concrete brace 5, and a waterproof layer is constructed between the concrete cushion 4 and the concrete brace 5 to improve the waterproof performance of the bottom plate.

更进一步地,所述底层板预制件7背离所述围护结构1的一侧设有第一凹槽71,所述底纵梁预制件8上与所述第一凹槽71相对的一侧设有第二凹槽81,所述底层板现浇连接段9位于所述第一凹槽71与所述第二凹槽81之间。本实施例的第一凹槽71与第二凹槽81相对设置,使得底层板现浇连接段9中间宽,上下两端窄,进一步提高装配式地下结构的整体性以及防水性能。此外,底层板预制件7上预留的钢筋从第一凹槽71中伸出,底纵梁预制件8上预留的钢筋从第二凹槽81中伸出,两预制件的钢筋在底层板现浇连接段9中部分重叠,提高底层板现浇连接段9的连接强度,本实施例的其他的两个预制件之间的连接也可以采用这种凹槽与钢筋的布置形式,如用于第一层板预制件16与第一层板预制件16之间的连接等。Furthermore, a first groove 71 is provided on the side of the prefabricated bottom plate 7 facing away from the enclosure structure 1 , and a side of the prefabricated bottom stringer 8 opposite to the first groove 71 A second groove 81 is provided, and the cast-in-place connection section 9 of the bottom plate is located between the first groove 71 and the second groove 81 . In this embodiment, the first groove 71 and the second groove 81 are arranged opposite to each other, so that the cast-in-place connection section 9 of the bottom slab is wide in the middle and narrow at the upper and lower ends, which further improves the integrity and waterproof performance of the assembled underground structure. In addition, the steel bars reserved on the bottom slab prefabricated part 7 protrude from the first groove 71, and the steel bars reserved on the bottom longitudinal beam prefabricated part 8 protrude from the second groove 81, and the steel bars of the two prefabricated parts are on the ground floor. Parts of the cast-in-place connection section 9 of the slab overlap to improve the connection strength of the cast-in-place connection section 9 of the bottom slab. The connection between other two prefabricated parts of this embodiment can also adopt this arrangement of grooves and reinforcing bars, such as It is used for the connection between the first ply prefabricated part 16 and the first ply prefabricated part 16 and the like.

作为另一种实施方式,本实施例的底层板还可以为现浇混凝土结构,在施工完混凝土垫层4以及防水层后,在防水层之上通过在施工现场进行钢筋骨架绑扎后浇筑混凝土形成混凝土现浇底层板,并在混凝土现浇底层板的两端预留钢筋以便于与第一侧墙预制件10的底部进行定位连接,此时混凝土现浇底层板与第一侧墙预制件10之间通过现浇连接,可与第一侧墙现浇层12一起浇筑。As another embodiment, the bottom slab of this embodiment can also be a cast-in-situ concrete structure. After the concrete cushion 4 and the waterproof layer are constructed, the concrete is formed by binding the steel frame on the construction site and then pouring concrete on the waterproof layer. The concrete cast-in-place bottom slab, and steel bars are reserved at both ends of the concrete cast-in-place bottom slab so as to be positioned and connected to the bottom of the first side wall prefabricated part 10. At this time, the concrete cast-in-place bottom slab and the first side wall prefabricated part 10 They are connected by cast-in-place, and can be poured together with the first side wall cast-in-place layer 12.

进一步地,所述底纵梁预制件8上设有第一中立柱13,所述第一中立柱13与所述底纵梁预制件8之间浇筑有第一中立柱现浇连接段14;所述上设有第一中纵梁15,所述第一层板的中部支撑于所述第一中纵梁15上,通过第一中立柱13和第一中纵梁15对第一层板的中部进行支撑。本实施例的第一中立柱13和第一中立柱13可以采用现浇形式,也可以采用预制形式,当采用预制件形式时,可利用在等待第一侧墙现浇层12的混凝土龄期时,完成预制件的拼装及固定,预制件与预制件之间可通过浇筑混凝土形成现浇连接段将两个预制件连成整体。Further, the bottom longitudinal beam prefabricated part 8 is provided with a first central column 13, and a first central column cast-in-place connection section 14 is cast between the first central column 13 and the bottom longitudinal beam prefabricated part 8; The first middle longitudinal beam 15 is arranged on the top, and the middle part of the first layer board is supported on the first middle longitudinal beam 15, and the first middle board is supported by the first middle column 13 and the first middle longitudinal beam 15. support in the middle. The first central column 13 and the first central column 13 of this embodiment can be cast-in-place or prefabricated. When prefabricated, the age of concrete waiting for the cast-in-place layer 12 of the first side wall can be utilized. When the assembly and fixation of the prefabricated parts are completed, the two prefabricated parts can be connected into a whole by pouring concrete to form a cast-in-place connecting section between the prefabricated parts.

作为一种实施方式,所述第一层板包括两个第一层板预制件16,各所述第一层板预制件16的一端支撑于第一中纵梁15上,另一端支撑于第一侧墙预制件10上,两个第一层板预制件16上浇筑有第一层板现浇层17。如图12所示,两个第一层板预制件16上、两个第一层板预制件16之间以及第一层板预制件16与对应的第一侧墙预制件10之间均浇筑有混凝土,使得第一层板预制件16、第一侧墙预制件10以及第一中纵梁15形成整体,增强装配式地下结构整体性。作为另一种实施方式,第一层板包括两个第一层板预制件16,各所述第一层板预制件16的一端支撑于第一中纵梁15上,另一端支撑于第一侧墙预制件10上;两个第一层板预制件16之间以及第一层板预制件16与对应的第一侧墙预制件10之间浇筑有第一层板现浇连接段。此外,本实施例中第一层板还可以采用全现浇的形式,通过在第一侧墙预制件10与第一中纵梁15之间搭建底模,在施工现场进行绑扎钢筋骨架后浇筑混凝土形成现浇第一层板。As an embodiment, the first layer board includes two first layer board prefabricated parts 16, one end of each first layer board prefabricated part 16 is supported on the first middle longitudinal beam 15, and the other end is supported on the first middle longitudinal beam 15. On the side wall prefabricated part 10, the first layer slab cast-in-place layer 17 is poured on the two first layer slab prefabricated parts 16. As shown in FIG. 12 , pouring There is concrete, so that the first floor slab prefabricated part 16, the first side wall prefabricated part 10 and the first middle longitudinal beam 15 are integrated to enhance the integrity of the prefabricated underground structure. As another embodiment, the first layer includes two first layer prefabricated parts 16, one end of each first layer prefabricated part 16 is supported on the first middle longitudinal beam 15, and the other end is supported on the first On the side wall prefabricated part 10 ; between the two first ply prefabricated parts 16 and between the first ply prefabricated part 16 and the corresponding first side wall prefabricated part 10 , a first ply cast-in-place connection section is poured. In addition, in this embodiment, the first floor slab can also be in the form of full cast-in-place, by building a base form between the first side wall prefabricated part 10 and the first middle longitudinal beam 15, and then pouring after binding the steel skeleton on the construction site The concrete forms the cast-in-place first slab.

进一步地,所述第一层板上设有第二中立柱21,所述第二中立柱21上设有第二中纵梁22,所述第二层板的中部支撑于所述第二中纵梁22上。通过第二中立柱21和第二中纵梁22对第二层板的中部进行支撑;本实施例的第二中立柱21和第二中立柱21可以采用现浇形式,也可以采用预制形式,当采用预制件形式时,可利用在等待第二侧墙现浇层的混凝土龄期时,完成预制件的拼装及固定,预制件与预制件之间可通过浇筑混凝土形成现浇连接段将两个预制件连成整体。Further, the first layer is provided with a second central column 21, and the second central column 21 is provided with a second middle longitudinal beam 22, and the middle part of the second layer is supported by the second middle On the stringer 22. The middle part of the second laminate is supported by the second center column 21 and the second center longitudinal beam 22; the second center column 21 and the second center column 21 of this embodiment can be cast-in-place or prefabricated. When the form of prefabricated parts is adopted, the assembly and fixing of the prefabricated parts can be completed while waiting for the age of the concrete of the cast-in-place layer of the second side wall. The prefabricated parts are connected into a whole.

作为一种实施方式,所述第二层板包括两个第二层板预制件23,各所述第二层板预制件23的一端支撑于第二中纵梁22上,另一端支撑于第二侧墙预制件19上,两个第二层板预制件23上浇筑有第二层板现浇层24。如图12所示,两个第二层板预制件23上、两个第二层板预制件23之间以及第二层板预制件23与对应的第二侧墙现浇层之间均浇筑有混凝土,使得第二层板预制件23、第二侧墙预制件19、第二侧墙现浇层以及第二中纵梁22形成整体,增强装配式地下结构整体性。作为另一种实施方式,第二层板包括两个第二层板预制件23,各所述第二层板预制件23的一端支撑于第二中纵梁22上,另一端支撑于第二侧墙预制件19上;两个第二层板预制件23之间以及第二层板预制件23与对应的第二侧墙现浇层之间浇筑有第二层板现浇连接段。此外,本实施例中第二层板还可以采用全现浇的形式,通过在第二侧墙预制件19与第二中纵梁22之间搭建底模,在施工现场进行绑扎钢筋骨架后浇筑混凝土形成现浇第二层板。As an embodiment, the second layer board includes two second layer board prefabricated parts 23, one end of each second layer board prefabricated part 23 is supported on the second middle longitudinal beam 22, and the other end is supported on the second middle longitudinal beam 22. On the two side wall prefabricated parts 19, the second layer slab cast-in-place layer 24 is poured on the two second layer slab prefabricated parts 23. As shown in Figure 12, on the two second layer slab prefabricated parts 23, between the two second layer slab prefabricated parts 23 and between the second layer slab prefabricated parts 23 and the corresponding second side wall cast-in-place layer. There is concrete, so that the second floor slab prefabricated part 23, the second side wall prefabricated part 19, the second side wall cast-in-place layer and the second middle longitudinal beam 22 are integrated to enhance the integrity of the prefabricated underground structure. As another embodiment, the second layer board includes two second layer board prefabricated parts 23, one end of each second layer board prefabricated part 23 is supported on the second middle longitudinal beam 22, and the other end is supported on the second middle longitudinal beam 22. On the side wall prefabricated part 19 ; between the two second layer slab prefabricated parts 23 and between the second layer slab prefabricated part 23 and the corresponding second side wall cast-in-place layer, a second layer slab cast-in-place connection section is poured. In addition, the second floor slab in this embodiment can also be cast in place, by building a base form between the second side wall prefabricated part 19 and the second middle longitudinal beam 22, and then pouring after binding the steel skeleton on the construction site Concrete forms the cast-in-place second slab.

实施例二Embodiment two

本发明实施例提供一种明挖法复合装配式地下结构的施工方法,以地下两层单柱双跨结构设三道内支撑3为例进行说明,该施工方法包括如下步骤:The embodiment of the present invention provides a construction method of an open-cut composite assembled underground structure. The construction method of an underground two-story single-column double-span structure with three inner supports 3 is used as an example. The construction method includes the following steps:

1)完成两个围护结构1施工后,施工冠梁2,采用明挖法施工,在两个围护结构1之间边开挖边架设三道内支撑3,开挖到基坑底,如图1所示;1) After the construction of the two enclosure structures 1 is completed, the crown beam 2 is constructed, and the open cut method is used for construction. Three internal supports 3 are erected between the two enclosure structures 1 while excavating, and excavated to the bottom of the foundation pit, such as As shown in Figure 1;

2)在基坑底先施工混凝土垫层4,再在混凝土垫层4上施工防水层,提高装配式地下结构的防水性能,然后在防水层上吊装钢筋骨架完成拼装后,浇筑混凝土,形成混凝土换撑板5,待混凝土换撑板5强度达到设计要求后,拆除最下面的一道内支撑3,如图2所示;2) Concrete cushion 4 is first constructed at the bottom of the foundation pit, and then a waterproof layer is constructed on the concrete cushion 4 to improve the waterproof performance of the fabricated underground structure. After the steel skeleton is hoisted on the waterproof layer and assembled, concrete is poured to form concrete Replace the brace 5, after the strength of the concrete brace 5 meets the design requirements, remove the bottom inner support 3, as shown in Figure 2;

3)施工围护结构1找平层施工防水层,吊装第一侧墙钢筋骨架6,第一侧墙钢筋骨架6的底部与混凝土换撑板5上预留的钢筋进行搭接,顶部与围护结构1定位连接,防止倒塌,如图3所示;3) Construction enclosure structure 1 leveling layer construction waterproof layer, hoisting the first side wall steel skeleton 6, the bottom of the first side wall steel skeleton 6 is lapped with the reserved steel bars on the concrete replacement slab 5, and the top is connected to the enclosure Structure 1 is positioned and connected to prevent collapse, as shown in Figure 3;

4)完成底层板的施工;4) Complete the construction of the bottom slab;

5)吊装第一侧墙预制件10,第一侧墙预制件10的底部与底层板预制件7定位连接,每块第一侧墙预制件10之间均需要进行张拉,第一侧墙预制件10安装完成后利用斜撑固定第一侧墙预制件10,防止其倾倒;两侧的第一侧墙预制件10均完成施工后,施工2-3段后,利用第一侧墙预制件10作为侧墙内模,围护结构1作为外模,混凝土浇筑围护结构1与第一侧墙预制件10之间的空隙,与先前吊装的第一侧墙钢筋骨架6形成第一侧墙现浇层12,第一侧墙现浇层12与第一侧墙预制件10形成叠合墙,如图5-图6所示;5) Hoist the first side wall prefabricated part 10, the bottom of the first side wall prefabricated part 10 is positioned and connected with the ground floor prefabricated part 7, each first side wall prefabricated part 10 needs to be stretched, the first side wall After the prefabricated part 10 is installed, fix the first side wall prefabricated part 10 with diagonal braces to prevent it from toppling over; after the construction of the first side wall prefabricated parts 10 on both sides is completed, after 2-3 stages of construction, use the first side wall prefabricated Part 10 is used as the inner formwork of the side wall, and the enclosure structure 1 is used as the outer formwork. The gap between the concrete pouring enclosure structure 1 and the first side wall prefabricated part 10 forms the first side wall with the previously hoisted steel skeleton 6 of the first side wall. The wall cast-in-place layer 12, the first side wall cast-in-place layer 12 and the first side wall prefabricated part 10 form a laminated wall, as shown in Figures 5-6;

6)完成第一中立柱13、第一中纵梁15的施工;6) Complete the construction of the first center column 13 and the first center longitudinal beam 15;

7)完成第一层板的施工,然后拆除中间的一道内支撑3;7) Complete the construction of the first floor, and then remove the inner support 3 in the middle;

8)施工围护结构1找平层施工防水层,吊装第二侧墙钢筋骨架18,第二侧墙钢筋骨架18的底部与第一侧墙现浇层12上预留的钢筋进行搭接,顶部与围护结构1定位连接,防止倒塌;吊装第二侧墙预制件19,第二侧墙预制件19的底部通过企口与第一侧墙预制件10的顶部定位连接,对第二侧墙预制件19进行张拉,然后采用斜撑固定第二侧墙预制件19,防止其倾倒;两侧的第二侧墙预制件19均完成施工后,施工2-3段后,利用第二侧墙预制件19作为侧墙内模,围护结构1作为外模,混凝土浇筑围护结构1与第二侧墙预制件19之间的空隙,与先前吊装的第二侧墙钢筋骨架18形成第二侧墙现浇层,第二侧墙现浇层与第二侧墙预制件19形成叠合墙,如图8-图9所示;8) Construction enclosure structure 1 leveling layer construction waterproof layer, lifting the second side wall reinforcement skeleton 18, the bottom of the second side wall reinforcement skeleton 18 is lapped with the reserved reinforcement on the first side wall cast-in-place layer 12, and the top Position and connect with the enclosure structure 1 to prevent collapse; hoist the second side wall prefabricated part 19, the bottom of the second side wall prefabricated part 19 is positioned and connected with the top of the first side wall prefabricated part 10 through a groove, and the second side wall The prefabricated part 19 is stretched, and then the second side wall prefabricated part 19 is fixed by diagonal braces to prevent it from toppling over; after the construction of the second side wall prefabricated part 19 on both sides is completed, after 2-3 stages of construction, the second side wall prefabricated part 19 is used to The wall prefabricated part 19 is used as the inner formwork of the side wall, and the enclosure structure 1 is used as the outer formwork. The gap between the concrete pouring enclosure structure 1 and the second side wall prefabricated part 19 forms the second side wall reinforcement skeleton 18 previously hoisted. The cast-in-place layer of the two side walls, the cast-in-place layer of the second side wall and the prefabricated part 19 of the second side wall form a laminated wall, as shown in Figures 8-9;

9)完成第二中立柱21、第二中纵梁22的施工;9) Complete the construction of the second center column 21 and the second center longitudinal beam 22;

10)完成第二层板的施工,然后拆除最上面的一道内支撑3;完成管线回迁、顶板覆土回填等工作。10) Complete the construction of the second floor, and then remove the top inner support 3; complete the pipeline relocation, roof backfilling and other work.

本发明提供的装配式平顶有柱地下结构的明挖施工方法较好地实现了装配式地下结构,适用范围广,通过预制件与现浇层形成叠合结构,可以免去部分现场支模、架设脚手架等临时设施,节省工期,并能有效地提高装配式地下结构的防水性能以及整体受力性能;采用合理的构件分块方案,可以减小单个预制件的尺寸以及重量,便于运输、吊装和拼装。The open-cut construction method of the assembled flat-roofed underground structure with columns provided by the present invention better realizes the assembled underground structure and has a wide range of applications. The superimposed structure formed by the prefabricated parts and the cast-in-place layer can eliminate part of the on-site formwork , Erection of temporary facilities such as scaffolding, saving the construction period, and can effectively improve the waterproof performance and overall mechanical performance of the fabricated underground structure; adopting a reasonable component block scheme can reduce the size and weight of a single prefabricated part, which is convenient for transportation, Hoisting and assembly.

进一步地,如图4所示,步骤4)中的底层板的具体施工步骤如下:在混凝土换撑板5上吊装底纵梁预制件8和底层板预制件7,通过机械设备调整各预制构件至相应位置,张拉固定完成后,将纵梁预制件两端预留的钢筋分别与两侧的底层板预制件7上预留的钢筋绑扎搭接,在底纵梁预制件8与底层板预制件7之间浇筑混凝土形成底层板现浇连接段9,完成底层板施工。更进一步地,底层板预制件7和底纵梁预制件8预制时,底层板预制件7的其中一侧加工第一凹槽71,在底纵梁预制件8的两侧均加工第二凹槽81;拼装时,底纵梁预制件8的两个第二凹槽81分别与两侧的底层板预制件7上的第一凹槽71相对,在第一凹槽71与第二凹槽81之间浇筑混凝土形成底层板现浇连接段9。本实施例的第一凹槽71与第二凹槽81相对设置,使得底层板现浇连接段9中间宽,上下两端窄,进一步提高装配式地下结构的整体性以及防水性能;此外,底层板预制件7上预留钢筋从第一凹槽71中伸出,底纵梁预制件8上预留钢筋从第二凹槽81中伸出,两预制件的钢筋在底层板现浇连接段9中部分重叠,提高底层板现浇连接段9的连接强度,本实施例的其他的两个预制件之间的连接也可以采用这种凹槽与钢筋的布置形式,如用于第一层板预制件16与第一层板预制件16之间等。本实施例的步骤4)中混凝土换撑板5上预留的钢筋伸入至底纵梁预制件8和底层板预制件7之间并与底纵梁预制件8和底层板预制件7上预留的钢筋绑扎搭接,使底纵梁预制件8和底层板预制件7与混凝土换撑板5形成复合结构。Further, as shown in Figure 4, the specific construction steps of the bottom slab in step 4) are as follows: hoist the bottom longitudinal beam prefabricated part 8 and the bottom slab prefabricated part 7 on the concrete replacement slab 5, and adjust the prefabricated components through mechanical equipment To the corresponding position, after the tensioning and fixing are completed, the steel bars reserved at both ends of the longitudinal beam prefabricated part are bound and lapped with the reserved steel bars on the bottom slab prefabricated part 7 on both sides, and the bottom longitudinal beam prefabricated part 8 and the bottom slab Concrete is poured between the prefabricated parts 7 to form the cast-in-place connecting section 9 of the bottom slab, and the construction of the bottom slab is completed. Furthermore, when the prefabricated bottom plate prefabricated part 7 and the bottom stringer prefabricated part 8 are prefabricated, the first groove 71 is processed on one side of the bottom plate prefabricated part 7, and the second concave groove 71 is processed on both sides of the bottom stringer prefabricated part 8. Slots 81; when assembled, the two second grooves 81 of the bottom longitudinal beam preform 8 are respectively opposite to the first grooves 71 on the bottom plate preforms 7 on both sides, and the first groove 71 and the second groove Concrete is poured between 81 to form the cast-in-place connecting section 9 of the bottom slab. In this embodiment, the first groove 71 and the second groove 81 are arranged opposite to each other, so that the middle of the cast-in-place connection section 9 of the bottom plate is wide, and the upper and lower ends are narrow, which further improves the integrity and waterproof performance of the fabricated underground structure; in addition, the bottom layer The reserved steel bars on the slab prefabricated part 7 protrude from the first groove 71, and the reserved steel bars on the bottom longitudinal beam prefabricated part 8 protrude from the second groove 81. 9 partially overlaps to improve the connection strength of the cast-in-place connection section 9 of the bottom slab. The connection between the other two prefabricated parts of this embodiment can also adopt this arrangement of grooves and steel bars, such as for the first layer Between the slab preform 16 and the first layer slab preform 16 and so on. In step 4) of this embodiment, the steel bars reserved on the concrete support plate 5 extend between the bottom longitudinal beam prefabricated part 8 and the bottom slab prefabricated part 7 and connect with the bottom longitudinal beam prefabricated part 8 and the bottom slab prefabricated part 7 The reserved steel bars are bound and lapped so that the prefabricated part 8 of the bottom longitudinal beam, the prefabricated part 7 of the bottom slab and the concrete support plate 5 form a composite structure.

进一步地,如图9所示,所述第一侧墙预制件10的上设有牛腿11,所述第一层板的两端分别支撑于两个第一侧墙预制件10的牛腿11上,且所述第一侧墙预制件10的顶部于所述第一层板的上方与对应的所述第二侧墙预制件19通过企口定位连接。本实施例通过将第一侧墙预制件10与第二侧墙预制件19的连接节点设置在第一层板的上方,可以进一步提高相邻两层之间的整体性。Further, as shown in FIG. 9 , corbels 11 are provided on the first side wall prefabricated part 10 , and the two ends of the first laminate are respectively supported on the corbels of the two first side wall prefabricated parts 10 11, and the top of the first side wall prefabricated part 10 is connected to the corresponding second side wall prefabricated part 19 through groove and groove positioning above the first layer. In this embodiment, by arranging the connection node between the first side wall prefabricated part 10 and the second side wall prefabricated part 19 above the first layer board, the integrity between two adjacent layers can be further improved.

作为一种实施方式,如图7所示,步骤7)中的第一层板的具体施工步骤如下:吊装第一层板预制件16,第一层板预制件16的一端支撑于第一中纵梁15上,另一端支撑于第一侧墙预制件10上;每块第一层板预制件16均完成张拉后,利用第一层板预制件16为底模,拼装钢筋网完成后,在第一层板预制件16上浇筑混凝土形成第一层板现浇层17,同时完成梁与板、墙与板节点连接及接缝浇筑,第一层板现浇层17与第一层板预制件16形成叠合结构板承担后期中板上的全部载荷;待第一层板现浇层17的混凝土强度达到设计要求后,拆除中间的一道内支撑3。作为另一种实施方式,步骤7)中的第一层板的具体施工步骤如下:吊装第一层板预制件16,第一层板预制件16的一端支撑于第一中纵梁15上,另一端支撑于第一侧墙预制件10上;以第一中纵梁15为底模,在两个第一层板预制件16之间以及第一层板预制件16与第一侧墙预制件10之间浇筑混凝土形成第一层板现浇连接段,提高装配式地下结构的整体性。此外,本实施例的第一层板还可以直接采用全现浇的形式,通过在第一侧墙预制件10与第一中纵梁15之间搭建底模,在施工现场进行绑扎钢筋骨架后浇筑混凝土形成第一现浇层板。待第一层板的现浇强度达到设计要求后,再拆除中间的一道内支撑33。As an implementation, as shown in Figure 7, the specific construction steps of the first layer in step 7) are as follows: hoisting the first layer prefabricated part 16, one end of the first layer prefabricated part 16 is supported in the first On the longitudinal beam 15, the other end is supported on the first side wall prefabricated part 10; after each first layer prefabricated part 16 is stretched, the first layer prefabricated part 16 is used as the bottom mold, and the assembled steel mesh is completed Concrete is poured on the first floor slab prefabricated part 16 to form the first floor slab cast-in-place layer 17, and at the same time, the joint connection and joint pouring of beams and slabs, walls and slabs are completed, and the first floor slab cast-in-place layer 17 is connected with the first floor The prefabricated slab 16 forms a composite structural slab to bear all the loads on the middle slab in the later stage; after the concrete strength of the cast-in-place layer 17 of the first slab meets the design requirements, the middle inner support 3 is removed. As another implementation, the specific construction steps of the first layer in step 7) are as follows: hoisting the first layer prefabricated part 16, one end of the first layer prefabricated part 16 is supported on the first middle longitudinal beam 15, The other end is supported on the first side wall prefabricated part 10; with the first middle longitudinal beam 15 as the bottom mold, between the two first layer prefabricated parts 16 and between the first layer prefabricated part 16 and the first side wall prefabricated Concrete is poured between the pieces 10 to form the first floor slab cast-in-place connecting section, so as to improve the integrity of the fabricated underground structure. In addition, the first layer slab of this embodiment can also directly adopt the form of full cast-in-place, by building a base form between the first side wall prefabricated part 10 and the first middle longitudinal beam 15, after binding the steel skeleton at the construction site Pour concrete to form the first cast-in-place deck. After the cast-in-place strength of the first layer board meets the design requirements, the inner support 33 in the middle is removed.

作为一种实施方式,如图11所示,步骤10)中的第二层板的具体施工步骤如下:吊装第二层板预制件23,第二层板预制件23的一端支撑于第二中纵梁22上,另一端支撑于第二侧墙预制件19上;每块第二层板预制件23均完成张拉后,利用第二层板预制件23为底模,拼装钢筋网完成后,在第二层板预制件23上浇筑混凝土形成第二层板现浇层24,第二层板现浇层24与第二层板预制件23形成叠合结构板承担后期全部载荷;待第二层板现浇层24的混凝土强度达到设计要求后,拆除最上面的一道内支撑3。作为另一种实施方式,本实施例的第二层板的具体施工步骤如下:吊装第二层板预制件23,第二层板预制件23的一端支撑于第二中纵梁22上,另一端支撑于第二侧墙预制件19上;以第二中纵梁22为底模,在两个第二层板预制件23之间浇筑混凝土形成第一层板现浇连接段,提高装配式地下结构的整体性。此外,本实施例的第一层板还可以直接采用全现浇的形式,通过在第二侧墙预制件19与第二中纵梁22之间搭建底模,在施工现场进行绑扎钢筋骨架后浇筑混凝土形成第二现浇层板。待第二层板的现浇强度达到设计要求后,拆除最上面的一道内支撑3。As an implementation, as shown in Figure 11, the specific construction steps of the second layer slab in step 10) are as follows: hoisting the second layer slab prefabricated part 23, one end of the second layer slab prefabricated part 23 is supported in the second On the longitudinal beam 22, the other end is supported on the second side wall prefabricated part 19; after each second layer prefabricated part 23 is stretched, the second layer prefabricated part 23 is used as the bottom mold, and the assembled steel mesh is completed Concrete is poured on the second slab prefabricated part 23 to form the second slab cast-in-place layer 24, and the second slab cast-in-place layer 24 and the second slab prefabricated part 23 form a laminated structural slab to bear all the loads in the later stage; After the concrete strength of the cast-in-place layer 24 of the second-floor slab meets the design requirements, the top inner support 3 is removed. As another embodiment, the specific construction steps of the second layer slab in this embodiment are as follows: hoisting the second layer slab prefabricated part 23, one end of the second layer slab prefabricated part 23 is supported on the second middle longitudinal beam 22, and the other One end is supported on the second side wall prefabricated part 19; the second middle longitudinal beam 22 is used as the bottom formwork, and concrete is poured between the two second layer slab prefabricated parts 23 to form the first floor slab cast-in-place connection section, which improves the assembly style. The integrity of the underground structure. In addition, the first layer slab of this embodiment can also directly adopt the form of full cast-in-place, by building a base form between the second side wall prefabricated part 19 and the second middle longitudinal beam 22, after binding the steel skeleton at the construction site Pour concrete to form the second cast-in-place slab. After the cast-in-place strength of the second layer slab meets the design requirements, remove the top inner support 3 .

进一步地,如图6所示,步骤6)中当第一中立柱13和第一中纵梁15均采用预制件的形式时,在等待第一侧墙现浇层12的混凝土龄期时,吊装第一中立柱13,第一中立柱13底部预留的钢筋与底纵梁预制件8上预留的钢筋进行绑扎搭接,搭建侧模板后在第一中立柱13底部与底纵梁预制件8顶部之间浇筑混凝土形成第一中立柱现浇连接段14;吊装第一中纵梁15,第一中立柱13的顶部与第一中立柱13的底部之间通过现浇连接。Further, as shown in FIG. 6 , in step 6), when both the first central column 13 and the first central longitudinal beam 15 are in the form of prefabricated parts, while waiting for the concrete age of the cast-in-place layer 12 of the first side wall, The first central column 13 is hoisted, and the steel bars reserved at the bottom of the first central column 13 are bound and overlapped with the steel bars reserved on the prefabricated bottom longitudinal beam 8. After the side formwork is built, the bottom of the first central column 13 and the bottom longitudinal beam are prefabricated Concrete is poured between the tops of parts 8 to form the first central column cast-in-place connection section 14; the first central longitudinal beam 15 is hoisted, and the top of the first central column 13 is connected by cast-in-place between the bottom of the first central column 13.

进一步地,如图10所示,步骤9)中当第二中立柱21和第二中纵梁22均采用预制件的形式时,在等待第二侧墙现浇层的混凝土龄期时,吊装第二中立柱21和第二中纵梁22,并完成预制件的拼装及固定,预制件与预制件之间通过现浇将两个预制件连成整体。Further, as shown in Fig. 10, in step 9), when the second center column 21 and the second center longitudinal beam 22 are both in the form of prefabricated parts, while waiting for the concrete age of the cast-in-place layer of the second side wall, hoisting The second central pillar 21 and the second central longitudinal beam 22 complete the assembly and fixing of the prefabricated parts, and the prefabricated parts are connected into a whole by cast-in-place between the prefabricated parts.

本发明实施例一提供的明挖法复合装配式地下结构以及实施例二提供的明挖法复合装配式地下结构的施工方法中的的侧墙预制件与层板预制件的连接处以及层板预制件与中纵梁的连接处均采用现浇“湿节点”,装配式地下结构的防水性、整体性好。The connection between the side wall prefabricated part and the laminate prefabricated part and the laminate in the open-cut composite prefabricated underground structure provided by the first embodiment of the present invention and the construction method of the open-cut composite prefabricated underground structure provided by the second embodiment The joints between the prefabricated parts and the longitudinal beams are all cast-in-place "wet joints", and the waterproof and integrity of the fabricated underground structure are good.

本实施例提供的明挖法复合装配式地下结构以及明挖法复合装配式地下结构的施工方法均还可以用于其它N层M跨的地下结构,其最顶层与最底层可分别采用本实施例的地下一层和地下二层的结构形式,其余层的侧墙以及层板也可以采用本实施例的其他层板和侧墙的结构形式,加宽部分的结构可以与本实施例相同,在此不再详述;本实施例采用合理的构件分块方案和预先施工换撑板方案建成的地下结构,不受地质条件、内支撑等限制,解决了明挖基坑带内支撑体系施工预制件吊装和拼装困难的问题以及装配式结构防水差、整体性差等问题;以优化的预制构件尺寸及构件重量,适应有内支撑基坑的现场吊装和拼装要求,并能较好实现产业化推广应用。本实施例提供的地下结构通过在侧墙预制件外侧浇筑现浇层形成叠合结构,提高装配式地下结构的防水性能以及结构整体性,适用于城市轨道交通地下车站、地下室、综合管廊等主体结构工程。The construction method of the open-cut composite assembled underground structure provided by this embodiment and the open-cut composite assembled underground structure can also be used for other underground structures with N floors and M spans, and the topmost and bottommost floors can respectively adopt this implementation. The structural forms of the first basement and the second basement of the example, the side walls and laminates of the remaining floors can also adopt the structural forms of other laminates and side walls of this embodiment, and the structure of the widened part can be the same as that of this embodiment. I won’t go into details here; this embodiment uses a reasonable component block plan and pre-constructed plan to replace the support plate to build the underground structure, which is not limited by geological conditions and internal supports, and solves the problem of the construction of the internal support system in the open excavation pit belt. Difficult hoisting and assembly of prefabricated parts, poor waterproofing and poor integrity of prefabricated structures; with optimized size and weight of prefabricated components, it can meet the requirements of on-site hoisting and assembling of foundation pits with internal support, and can better realize industrialization Promote apps. The underground structure provided in this embodiment forms a superimposed structure by pouring cast-in-place layers on the outside of the side wall prefabricated parts to improve the waterproof performance and structural integrity of the assembled underground structure, and is suitable for urban rail transit underground stations, basements, comprehensive pipe corridors, etc. Main structural engineering.

以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention shall be included in the scope of the present invention. within the scope of protection.

Claims (12)

1.一种明挖法复合装配式地下结构,其特征在于:包括底层板、第一层板、第二层板、第一侧墙预制件、第二侧墙预制件和两个围护结构,两个围护结构之间从下往上依次设有底层板、第一层板和第二层板;所述底层板上设置有两个第一侧墙预制件,所述第一层板的两端分别支撑于两个第一侧墙预制件上;各所述第一侧墙预制件上均设有第二侧墙预制件,所述第一侧墙预制件通过企口与对应的所述第二侧墙预制件连接;所述第二层板的两端分别支撑于两个第二侧墙预制上。1. An open-cut composite assembled underground structure is characterized in that: it comprises a base plate, a first layer plate, a second layer plate, a first side wall prefabricated part, a second side wall prefabricated part and two enclosure structures , between the two enclosure structures, there are a ground floor, a first floor and a second floor in sequence from bottom to top; two first side wall prefabricated parts are arranged on the bottom floor, and the first floor The two ends of the two first side wall prefabricated parts are respectively supported on the two first side wall prefabricated parts; each of the first side wall prefabricated parts is provided with a second side wall prefabricated part, and the first side wall prefabricated part is connected with the corresponding The second side wall prefabricated parts are connected; the two ends of the second layer board are respectively supported on the two second side wall prefabricated parts. 2.如权利要求1所述的一种明挖法复合装配式地下结构,其特征在于:所述第一侧墙预制件与对应的所述围护结构之间设有第一侧墙现浇层,所述第二侧墙预制件与对应的所述围护结构之间设有第二侧墙现浇层。2. The open-cut composite assembled underground structure according to claim 1, characterized in that: a first side wall cast-in-place is provided between the first side wall prefabricated part and the corresponding enclosure structure layer, and a second cast-in-place layer of the side wall is provided between the second side wall prefabricated part and the corresponding enclosure structure. 3.如权利要求1所述的一种明挖法复合装配式地下结构,其特征在于:所述底层板包括底纵梁预制件以及用于分别支撑两个第一侧墙预制件的两个底层板预制件;所述底纵梁预制件和所述底层板预制件均设置于混凝土换撑板上,所述底纵梁预制件设置于两个底层板预制件之间,所述底纵梁预制件与所述底层板预制件之间浇筑有底层板现浇连接段。3. The open-cut composite prefabricated underground structure according to claim 1, characterized in that: the bottom slab comprises a prefabricated bottom longitudinal beam and two prefabricated parts for respectively supporting two first side walls. The prefabricated part of the bottom slab; the prefabricated part of the bottom longitudinal beam and the prefabricated part of the bottom slab are both arranged on the concrete support plate, the prefabricated part of the bottom longitudinal beam is arranged between the two prefabricated parts of the bottom slab, and the prefabricated part of the bottom longitudinal beam A cast-in-place connection section of the bottom slab is poured between the beam prefabricated part and the bottom slab prefabricated part. 4.如权利要求3所述的一种明挖法复合装配式地下结构,其特征在于:所述底层板预制件背离所述围护结构的一侧设有第一凹槽,所述底纵梁预制件上与所述第一凹槽相对的一侧设有第二凹槽,所述底层板现浇连接段位于所述第一凹槽与所述第二凹槽之间。4. The open excavation method composite assembled underground structure according to claim 3, characterized in that: the side of the base plate prefabricated part away from the enclosure structure is provided with a first groove, and the bottom longitudinal A second groove is provided on the side of the beam prefabricated part opposite to the first groove, and the cast-in-place connection section of the bottom plate is located between the first groove and the second groove. 5.如权利要求3所述的一种明挖法复合装配式地下结构,其特征在于:所述底纵梁预制件上设有第一中立柱,所述第一中立柱与所述底纵梁预制件之间浇筑有第一中立柱现浇连接段;所述上设有第一中纵梁,所述第一层板的中部支撑于所述第一中纵梁上。5. The open-cut composite assembled underground structure according to claim 3, characterized in that: said bottom longitudinal beam prefabricated part is provided with a first central column, said first central column is connected to said bottom longitudinal beam The first central column cast-in-place connecting section is poured between the beam prefabricated parts; the first central longitudinal beam is arranged on the upper part, and the middle part of the first floor plate is supported on the first central longitudinal beam. 6.如权利要求5所述的一种明挖法复合装配式地下结构,其特征在于:所述第一层板包括两个第一层板预制件,各所述第一层板预制件的一端支撑于第一中纵梁上,另一端支撑于第一侧墙预制件上,两个第一层板预制件上浇筑有第一层板现浇层。6. A kind of open-cut method composite assembled underground structure as claimed in claim 5, characterized in that: said first layer comprises two first layer prefabricated parts, each of said first layer prefabricated parts One end is supported on the first middle longitudinal beam, the other end is supported on the first side wall prefabricated part, and the first layer slab cast-in-place layer is poured on the two first layer slab prefabricated parts. 7.如权利要求1所述的一种明挖法复合装配式地下结构,其特征在于:所述第一层板上设有第二中立柱,所述第二中立柱上设有第二中纵梁,所述第二层板的中部支撑于所述第二中纵梁上。7. The open excavation method composite assembled underground structure according to claim 1, characterized in that: the first layer is provided with a second central column, and the second central column is provided with a second central column. For the longitudinal beam, the middle part of the second layer board is supported on the second middle longitudinal beam. 8.如权利要求7所述的一种明挖法复合装配式地下结构,其特征在于:所述第二层板包括两个第二层板预制件,各所述第二层板预制件的一端支撑于第二中纵梁上,另一端支撑于第二侧墙预制件上,两个第二层板预制件上浇筑有第二层板现浇层。8. A kind of open-cut method composite assembled underground structure as claimed in claim 7, it is characterized in that: said second layer comprises two second layer prefabricated parts, each of said second layer prefabricated parts One end is supported on the second middle longitudinal beam, the other end is supported on the second side wall prefabricated part, and the second layer slab cast-in-place layer is poured on the two second layer slab prefabricated parts. 9.一种明挖法复合装配式地下结构的施工方法,其特征在于,包括如下步骤:9. A construction method for an open-cut composite assembled underground structure, characterized in that it comprises the following steps: 1)完成两个围护结构施工后,施工冠梁,采用明挖法施工,在两个围护结构之间边开挖边架设三道内支撑,开挖到基坑底;1) After the construction of the two enclosure structures is completed, the crown beam will be constructed using the open cut method, and three internal supports will be erected between the two enclosure structures while excavating, and excavated to the bottom of the foundation pit; 2)在基坑底先施工混凝土垫层,再在混凝土垫层上施工防水层,然后在防水层上施工混凝土换撑板,拆除最下面的一道内支撑;2) Construct a concrete cushion at the bottom of the foundation pit first, then construct a waterproof layer on the concrete cushion, then construct a concrete replacement support plate on the waterproof layer, and remove the bottom inner support; 3)吊装第一侧墙钢筋骨架,第一侧墙钢筋骨架的底部与混凝土换撑板上预留的钢筋进行搭接,顶部与围护结构定位连接;3) Hoisting the reinforcement skeleton of the first side wall, the bottom of the reinforcement skeleton of the first side wall is overlapped with the steel bars reserved on the concrete support plate, and the top is positioned and connected with the enclosure structure; 4)完成底层板的施工;4) Complete the construction of the bottom slab; 5)吊装第一侧墙预制件,第一侧墙预制件的底部与底层板定位连接,利用第一侧墙预制件、围护结构作为侧模板,在第一侧墙预制件与围护结构之间浇筑混凝土,与先前吊装的第一侧墙钢筋骨架形成第一侧墙现浇层;5) Hoist the prefabricated part of the first side wall, the bottom of the prefabricated part of the first side wall is positioned and connected with the bottom plate, and the prefabricated part of the first side wall and the enclosure structure are used as the side formwork, and the prefabricated part of the first side wall and the enclosure structure Concrete is poured in between to form the cast-in-situ layer of the first side wall with the steel skeleton of the first side wall hoisted previously; 6)完成第一中立柱、第一中纵梁的施工;6) Complete the construction of the first center column and the first center longitudinal beam; 7)完成第一层板的施工,然后拆除中间的一道内支撑;7) Complete the construction of the first floor, and then remove the inner support in the middle; 8)吊装第二侧墙钢筋骨架,第二侧墙钢筋骨架的底部与第一侧墙现浇层上预留的钢筋进行搭接,顶部与围护结构定位连接;吊装第二侧墙预制件,第二侧墙预制件的底部通过企口与第一侧墙预制件的顶部定位连接,利用第二侧墙预制件、围护结构作为侧模板,在第二侧墙预制件与围护结构之间浇筑混凝土,与先前吊装的第二侧墙钢筋骨架形成第二侧墙现浇层;8) Hoist the second side wall reinforcement skeleton, the bottom of the second side wall reinforcement skeleton is overlapped with the reserved steel bars on the first side wall cast-in-place layer, and the top is positioned and connected with the enclosure structure; hoist the second side wall prefabricated parts , the bottom of the second side wall prefabricated part is positioned and connected with the top of the first side wall prefabricated part through a groove, and the second side wall prefabricated part and the enclosure structure are used as side templates, and the second side wall prefabricated part and the enclosure structure Concrete is poured in between to form the cast-in-situ layer of the second side wall with the previously hoisted steel skeleton of the second side wall; 9)完成第二中立柱、第二中纵梁的施工;9) Complete the construction of the second center column and the second center longitudinal beam; 10)完成第二层板的施工,然后拆除最上面的一道内支撑。10) Complete the construction of the second layer, and then remove the top inner support. 10.如权利要求9所述的一种明挖法复合装配式地下结构的施工方法,其特征在于,步骤4)中的底层板的具体施工步骤如下:在混凝土换撑板上吊装底纵梁预制件和底层板预制件,纵梁预制件两端预留的钢筋分别与两侧的底层板预制件上预留的钢筋绑扎搭接,在底纵梁预制件与底层板预制件之间浇筑混凝土形成底层板现浇连接段。10. The construction method of an open excavation composite assembly type underground structure according to claim 9, characterized in that the specific construction steps of the bottom plate in step 4) are as follows: hoisting the bottom longitudinal beam on the concrete support plate For the prefabricated part and the prefabricated part of the bottom slab, the steel bars reserved at both ends of the prefabricated longitudinal beam are respectively bound and overlapped with the steel bars reserved on the prefabricated bottom slab on both sides, and poured between the prefabricated bottom longitudinal beam and the prefabricated bottom slab The concrete forms the cast-in-place connection sections of the ground floor slab. 11.如权利要求9所述的一种明挖法复合装配式地下结构的施工方法,其特征在于,步骤7)中的第一层板的具体施工步骤如下:吊装第一层板预制件,第一层板预制件的一端支撑于第一中纵梁上,另一端支撑于第一侧墙预制件上;在第一层板预制件上浇筑混凝土形成第一层板现浇层。11. The construction method of an open excavation composite assembly type underground structure as claimed in claim 9, characterized in that the specific construction steps of the first layer in step 7) are as follows: hoisting the first layer prefabricated parts, One end of the first slab prefabricated part is supported on the first middle longitudinal beam, and the other end is supported on the first side wall prefabricated part; concrete is poured on the first slab prefabricated part to form the first slab cast-in-situ layer. 12.如权利要求9所述的一种明挖法复合装配式地下结构的施工方法,其特征在于,步骤10)中的第二层板的具体施工步骤如下:吊装第二层板预制件,第二层板预制件的一端支撑于第二中纵梁上,另一端支撑于第二侧墙预制件上;在第二层板预制件上浇筑混凝土形成第二层板现浇层。12. The construction method of an open-cut composite prefabricated underground structure according to claim 9, wherein the specific construction steps of the second layer slab in step 10) are as follows: hoisting the prefabricated part of the second layer slab, One end of the second slab prefabricated part is supported on the second middle longitudinal beam, and the other end is supported on the second side wall prefabricated part; concrete is poured on the second slab prefabricated part to form the second slab cast-in-situ layer.
CN201910624049.7A 2019-07-11 2019-07-11 A kind of combined assembled underground structure of cut and cover method and its construction method Pending CN110258642A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910624049.7A CN110258642A (en) 2019-07-11 2019-07-11 A kind of combined assembled underground structure of cut and cover method and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910624049.7A CN110258642A (en) 2019-07-11 2019-07-11 A kind of combined assembled underground structure of cut and cover method and its construction method

Publications (1)

Publication Number Publication Date
CN110258642A true CN110258642A (en) 2019-09-20

Family

ID=67925641

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910624049.7A Pending CN110258642A (en) 2019-07-11 2019-07-11 A kind of combined assembled underground structure of cut and cover method and its construction method

Country Status (1)

Country Link
CN (1) CN110258642A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114908794A (en) * 2022-04-12 2022-08-16 中铁二院工程集团有限责任公司 Assembly type construction method of subway station
CN116950126A (en) * 2023-07-13 2023-10-27 广州地铁设计研究院股份有限公司 A construction method for a station structure

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105178357A (en) * 2015-07-16 2015-12-23 中国建筑股份有限公司 Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition
CN205894281U (en) * 2016-08-12 2017-01-18 长沙远大住宅工业集团股份有限公司 Integral basement of coincide assembly of arch without beam system
CN106869172A (en) * 2017-04-01 2017-06-20 中交第二航务工程局有限公司 In-situ deposited prefabricated split-mounting type subway underground station construction method
CN107476341A (en) * 2017-08-21 2017-12-15 中铁六局集团有限公司 Using cast in place and precast construction subway station prefabricated board assembling method
WO2018028043A1 (en) * 2016-08-12 2018-02-15 长沙远大住宅工业集团股份有限公司 Composite assembly integral basement combining beam-column system and flat-slab floor system
CN108487252A (en) * 2018-03-13 2018-09-04 中铁第四勘察设计院集团有限公司 A kind of deep foundation pit open cutting is suitable to make construction method
WO2019056717A1 (en) * 2017-09-21 2019-03-28 中国建筑股份有限公司 Post-tensioned prestressed assembly-style system of concrete framework and shock-resistant and energy-dissipating components, and construction method
CN210658451U (en) * 2019-07-11 2020-06-02 中铁第四勘察设计院集团有限公司 Open cut method composite assembly formula underground structure

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105178357A (en) * 2015-07-16 2015-12-23 中国建筑股份有限公司 Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition
CN205894281U (en) * 2016-08-12 2017-01-18 长沙远大住宅工业集团股份有限公司 Integral basement of coincide assembly of arch without beam system
WO2018028043A1 (en) * 2016-08-12 2018-02-15 长沙远大住宅工业集团股份有限公司 Composite assembly integral basement combining beam-column system and flat-slab floor system
CN106869172A (en) * 2017-04-01 2017-06-20 中交第二航务工程局有限公司 In-situ deposited prefabricated split-mounting type subway underground station construction method
CN107476341A (en) * 2017-08-21 2017-12-15 中铁六局集团有限公司 Using cast in place and precast construction subway station prefabricated board assembling method
WO2019056717A1 (en) * 2017-09-21 2019-03-28 中国建筑股份有限公司 Post-tensioned prestressed assembly-style system of concrete framework and shock-resistant and energy-dissipating components, and construction method
CN108487252A (en) * 2018-03-13 2018-09-04 中铁第四勘察设计院集团有限公司 A kind of deep foundation pit open cutting is suitable to make construction method
CN210658451U (en) * 2019-07-11 2020-06-02 中铁第四勘察设计院集团有限公司 Open cut method composite assembly formula underground structure

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
上海市城市建设工程学校: "《装配式混凝土建筑结构施工》", 31 December 2016, 同济大学出版社, pages: 127 - 130 *
中国建材工业出版社: "《大型工程技术风险控制要点》", 31 August 2018, 中国建材工业出版社, pages: 35 *
辽宁省住房和城乡建设厅: "《装配式混凝土结构设计规程(DB21/T 2572-2019)》", 30 January 2019, /, pages: 29 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114908794A (en) * 2022-04-12 2022-08-16 中铁二院工程集团有限责任公司 Assembly type construction method of subway station
CN116950126A (en) * 2023-07-13 2023-10-27 广州地铁设计研究院股份有限公司 A construction method for a station structure

Similar Documents

Publication Publication Date Title
CN113513041B (en) Assembled multi-layer flat-top large-span pillar-free underground structure and open excavation construction method thereof
CN207498985U (en) A kind of partial precast assembly steel concrete combination underground pipe gallery for exempting from template
CN110409492A (en) A multi-structure combined assembled pipe gallery with superimposed components and its construction method
CN103741812A (en) Connection joint of steel reinforced concrete superposed beams and middle column
CN113136891B (en) Open cut integral assembly column-free underground structure construction method
CN215406163U (en) Assembled multilayer flat-top large-span pillar-free underground structure
CN110258642A (en) A kind of combined assembled underground structure of cut and cover method and its construction method
CN210066817U (en) Assembly integral vault is striden no post underground structure greatly
CN207647033U (en) A kind of precast reinforced basket structure
CN212336090U (en) An underground stacked box structure
CN107514012A (en) A kind of partial precast assembly steel concrete combination underground pipe gallery for exempting from template
CN110080291A (en) A kind of assembled flat-top is greatly across no column underground structure
CN211228597U (en) Enclosure component of assembled underground structure and connection structure of enclosure component and arch plate
CN110080292A (en) A kind of assembled integral vault is greatly across no column underground structure
CN210658451U (en) Open cut method composite assembly formula underground structure
CN117822648A (en) Permanent-face combined integral assembly type subway station structure and construction method
CN210482368U (en) Assembled flat-top large-span pillar-free underground structure
CN108755938B (en) Steel core area node of assembled concrete frame
CN210066816U (en) Assembled vault is striden no post underground structure greatly
CN110359488A (en) A kind of fender member of assembled underground structure and its connecting structure with arch sheet
CN210066818U (en) Assembled flat top has post underground structure
CN215483097U (en) Integrally-assembled pillarless underground structure
CN213417893U (en) Assembled utility tunnel
CN115217121A (en) Cooperative stress system and method for assembly type steel-concrete enclosure support and main body structure
CN211714016U (en) Assembled underground pipe gallery

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination