CN110258584A - 基坑边坡土钉管墙围护结构与施工方法 - Google Patents
基坑边坡土钉管墙围护结构与施工方法 Download PDFInfo
- Publication number
- CN110258584A CN110258584A CN201910541024.0A CN201910541024A CN110258584A CN 110258584 A CN110258584 A CN 110258584A CN 201910541024 A CN201910541024 A CN 201910541024A CN 110258584 A CN110258584 A CN 110258584A
- Authority
- CN
- China
- Prior art keywords
- soil nailing
- pipe
- soil
- nailing pipe
- excavation slope
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 239000002689 soil Substances 0.000 title claims abstract description 245
- 238000009412 basement excavation Methods 0.000 title claims abstract description 63
- 238000010276 construction Methods 0.000 title claims abstract description 25
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 49
- 238000003780 insertion Methods 0.000 claims abstract description 32
- 230000037431 insertion Effects 0.000 claims abstract description 32
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 17
- 238000007789 sealing Methods 0.000 claims abstract description 17
- 239000010959 steel Substances 0.000 claims abstract description 17
- 238000001556 precipitation Methods 0.000 claims abstract description 16
- 239000004744 fabric Substances 0.000 claims abstract description 13
- 230000029142 excretion Effects 0.000 claims abstract description 8
- 238000005086 pumping Methods 0.000 claims abstract description 5
- 238000002347 injection Methods 0.000 claims description 10
- 239000007924 injection Substances 0.000 claims description 10
- 238000009825 accumulation Methods 0.000 claims description 7
- 239000003673 groundwater Substances 0.000 abstract description 4
- 230000015572 biosynthetic process Effects 0.000 abstract description 2
- 230000000694 effects Effects 0.000 description 11
- 238000007569 slipcasting Methods 0.000 description 9
- 239000004568 cement Substances 0.000 description 7
- 238000005516 engineering process Methods 0.000 description 6
- 238000000034 method Methods 0.000 description 6
- 230000008859 change Effects 0.000 description 4
- 238000010586 diagram Methods 0.000 description 4
- 230000004048 modification Effects 0.000 description 4
- 238000012986 modification Methods 0.000 description 4
- 230000003014 reinforcing effect Effects 0.000 description 4
- 239000002002 slurry Substances 0.000 description 4
- 238000004873 anchoring Methods 0.000 description 3
- 238000007596 consolidation process Methods 0.000 description 3
- 239000011148 porous material Substances 0.000 description 3
- 239000000243 solution Substances 0.000 description 3
- 230000007547 defect Effects 0.000 description 2
- 239000003657 drainage water Substances 0.000 description 2
- 238000005553 drilling Methods 0.000 description 2
- 239000011440 grout Substances 0.000 description 2
- 230000008595 infiltration Effects 0.000 description 2
- 238000001764 infiltration Methods 0.000 description 2
- 230000002787 reinforcement Effects 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 239000007787 solid Substances 0.000 description 2
- 239000007921 spray Substances 0.000 description 2
- 230000006641 stabilisation Effects 0.000 description 2
- 238000011105 stabilization Methods 0.000 description 2
- 230000004075 alteration Effects 0.000 description 1
- 230000000903 blocking effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 239000011083 cement mortar Substances 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 238000005034 decoration Methods 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000004992 fission Effects 0.000 description 1
- 229920002457 flexible plastic Polymers 0.000 description 1
- 238000002156 mixing Methods 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 230000010355 oscillation Effects 0.000 description 1
- 229920003023 plastic Polymers 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 230000009467 reduction Effects 0.000 description 1
- 230000008439 repair process Effects 0.000 description 1
- 239000004576 sand Substances 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
- E02D17/207—Securing of slopes or inclines with means incorporating sheet piles or piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/10—Restraining of underground water by lowering level of ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
- E02D5/76—Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Hydrology & Water Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
Description
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910541024.0A CN110258584B (zh) | 2019-06-20 | 2019-06-20 | 基坑边坡土钉管墙围护结构与施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910541024.0A CN110258584B (zh) | 2019-06-20 | 2019-06-20 | 基坑边坡土钉管墙围护结构与施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110258584A true CN110258584A (zh) | 2019-09-20 |
CN110258584B CN110258584B (zh) | 2024-01-30 |
Family
ID=67920144
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910541024.0A Active CN110258584B (zh) | 2019-06-20 | 2019-06-20 | 基坑边坡土钉管墙围护结构与施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110258584B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114855813A (zh) * | 2022-04-25 | 2022-08-05 | 唐山学院 | 一种基坑上层滞水降水坡面支护装置及施工方法 |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104213564A (zh) * | 2014-09-04 | 2014-12-17 | 中建四局第六建筑工程有限公司 | 一种基坑边坡支护结构及施工方法 |
CN204080822U (zh) * | 2014-09-04 | 2015-01-07 | 中建四局第六建筑工程有限公司 | 一种基坑边坡支护结构 |
CN206220103U (zh) * | 2016-11-29 | 2017-06-06 | 常熟理工学院 | 一种带柱状冻土锚固头的复合土钉墙 |
CN206220104U (zh) * | 2016-11-29 | 2017-06-06 | 常熟理工学院 | 一种冻土帷幕复合土钉墙支护结构体系 |
CN109137928A (zh) * | 2018-08-22 | 2019-01-04 | 中国冶集团有限公司 | 一种基坑挡土板支护、止水结构及其施工方法 |
CN109610486A (zh) * | 2018-12-17 | 2019-04-12 | 中冶天工集团有限公司 | 一种高边坡透水夹层疏水方法 |
CN109736334A (zh) * | 2019-01-05 | 2019-05-10 | 中国建筑第二工程局有限公司 | 一种湿陷性黄土边坡支护施工装置及方法 |
CN109881694A (zh) * | 2019-04-04 | 2019-06-14 | 中铁十一局集团城市轨道工程有限公司 | 一种针对基坑基底涌水涌砂进行封堵的施工结构及方法 |
CN210395369U (zh) * | 2019-06-20 | 2020-04-24 | 中国建筑第八工程局有限公司 | 基坑边坡土钉管墙围护结构 |
-
2019
- 2019-06-20 CN CN201910541024.0A patent/CN110258584B/zh active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104213564A (zh) * | 2014-09-04 | 2014-12-17 | 中建四局第六建筑工程有限公司 | 一种基坑边坡支护结构及施工方法 |
CN204080822U (zh) * | 2014-09-04 | 2015-01-07 | 中建四局第六建筑工程有限公司 | 一种基坑边坡支护结构 |
CN206220103U (zh) * | 2016-11-29 | 2017-06-06 | 常熟理工学院 | 一种带柱状冻土锚固头的复合土钉墙 |
CN206220104U (zh) * | 2016-11-29 | 2017-06-06 | 常熟理工学院 | 一种冻土帷幕复合土钉墙支护结构体系 |
CN109137928A (zh) * | 2018-08-22 | 2019-01-04 | 中国冶集团有限公司 | 一种基坑挡土板支护、止水结构及其施工方法 |
CN109610486A (zh) * | 2018-12-17 | 2019-04-12 | 中冶天工集团有限公司 | 一种高边坡透水夹层疏水方法 |
CN109736334A (zh) * | 2019-01-05 | 2019-05-10 | 中国建筑第二工程局有限公司 | 一种湿陷性黄土边坡支护施工装置及方法 |
CN109881694A (zh) * | 2019-04-04 | 2019-06-14 | 中铁十一局集团城市轨道工程有限公司 | 一种针对基坑基底涌水涌砂进行封堵的施工结构及方法 |
CN210395369U (zh) * | 2019-06-20 | 2020-04-24 | 中国建筑第八工程局有限公司 | 基坑边坡土钉管墙围护结构 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114855813A (zh) * | 2022-04-25 | 2022-08-05 | 唐山学院 | 一种基坑上层滞水降水坡面支护装置及施工方法 |
Also Published As
Publication number | Publication date |
---|---|
CN110258584B (zh) | 2024-01-30 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108035335A (zh) | 一种冻结法施工井筒式地下停车库方法 | |
CN105862887A (zh) | 一种离子型稀土矿山生态护坡结构 | |
CN105672348A (zh) | 一种深水区砂卵石地层截除桥梁桩基的施工方法 | |
CN107503257A (zh) | 一种傍山高填路堤稳定与变形控制结构及施工方法 | |
CN205999903U (zh) | 环保型植草混凝土公路护坡结构 | |
CN110847197B (zh) | 黄土隧道进洞口段穿越滑坡体综合治理方法 | |
CN108755716A (zh) | 一种含水易风化岩质顺层边坡的综合防护治理方法 | |
CN207109475U (zh) | 傍山高填路堤稳定与变形控制结构 | |
CN106703044B (zh) | 一种流塑状冲填土软弱地层放坡组合支护方法 | |
CN107700511A (zh) | 一种高地下水位条件下沉井及其施工方法 | |
CN110528523A (zh) | 一种强透水地层建筑基坑水平注浆封底施工方法 | |
CN110778328B (zh) | 穿越滑坡体的黄土隧道进洞口段施工方法 | |
CN110318410A (zh) | 一种深基坑遇承压水突涌减压控水处理施工方法 | |
CN109736334A (zh) | 一种湿陷性黄土边坡支护施工装置及方法 | |
CN108678781A (zh) | 一种临近河道盾构始发端头地层加固方法 | |
CN107090837A (zh) | 一种坑中坑钢筋砼挡墙复合支护结构及其施工方法 | |
CN110080248A (zh) | 近水深基坑支护结构 | |
CN114575355B (zh) | 一种土护降施工方法 | |
CN114164846B (zh) | 一种永久边坡防水加固施工方法 | |
CN107245989A (zh) | 承受高内外水压力的隧洞结构及其施工工艺 | |
CN105113513B (zh) | 一种防渗水基坑支护结构及施工方法 | |
CN110258584A (zh) | 基坑边坡土钉管墙围护结构与施工方法 | |
CN110821512B (zh) | 穿越滑坡体的黄土隧道进洞口段预加固及开挖施工方法 | |
CN207331699U (zh) | 一种坑中坑钢筋砼挡墙复合支护结构 | |
CN208167783U (zh) | 挡泥墙组合结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20200603 Address after: 201306 building C, No. 888, Huanhu West 2nd Road, Lingang New Area, China (Shanghai) pilot Free Trade Zone, Pudong New Area, Shanghai Applicant after: China Construction Eighth Engineering Bureau Technology Construction Co.,Ltd. Address before: 200122 Shanghai, China (Shanghai) free trade zone, Century Avenue, No. 27, layer 1568, layer Applicant before: CHINA CONSTRUCTION EIGHTH ENGINEERING DIVISION Co.,Ltd. |
|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20240725 Address after: T-75, 1st Floor, Building 2, No. 88 Qin'an Street, Xiaokunshan Town, Songjiang District, Shanghai, 201614 Patentee after: China Construction Future Intelligent Manufacturing Technology (Shanghai) Co.,Ltd. Country or region after: China Address before: 201306 building C, No. 888, Huanhu West 2nd Road, Lingang New District, China (Shanghai) pilot Free Trade Zone, Pudong New Area, Shanghai Patentee before: China Construction Eighth Engineering Bureau Technology Construction Co.,Ltd. Country or region before: China |