A kind of application method of the Chain Link shaving die for automatic forging
Technical field
The Chain Link technical field that the invention belongs to use on engineering machinery crawler belt, and in particular to one kind is for automating forging
The application method for the Chain Link shaving die made.
Background technique
The Chain Link used on engineering machinery crawler belt is complex-shaped, and forging process is more, generally flattening, blocking, finish-forging, punching
Hole, trimming, correction, the Chain Link after finish forging are cut away extra overlap using trimming process, overlap it is in irregular shape and
For a full circle, excision process mostly uses manual operation trimming and removes whole circle overlap, restricts entire forging process automation
Realization, forge low efficiency, high labor cost.
Summary of the invention
Place in order to overcome the above-mentioned deficiencies of the prior art, the present invention provide a kind of Chain Link for automatic forging and cut
The application method of side mode tool.
The present invention is achieved through the following technical solutions: a kind of Chain Link shaving die for automatic forging makes
With method, shaving die includes punch-pin and cavity plate, the protrusion for having Chain Link shape to match in the middle part of punch-pin, is had in the middle part of cavity plate
The groove that Chain Link shape matches, the raised quadrangle and raised central portion two sides of punch-pin are provided with cutter mounting hole;Chain rail
It is as follows to save specific trimming:
Step 1: the lower die holder for being fixed with punch-pin is fixed on press machine processing platform, cutter is installed in cutter mounting hole,
After whole cutters is installed, the Chain Link after finish-forging is placed on punch-pin, cavity plate is mounted on upper die holder;
Step 2: cavity plate is cut away with overlap is about under press ram, whole circle overlap is fallen on the blade of cutter;
Step 3: after the completion, the Chain Link after removing trimming places into new band trimming Chain Link;
Step 4: whole circle overlap is pressed on first lap overlap after second Chain Link trimming, when sliding block is run to bottom dead centre,
The whole circle overlap cut away for the first time is divided into several pieces thin-sheet to fall along punch-pin inclined-plane by cutter cutting;Repeat step 3 and step
Rapid four, it is recycled with this, realizes automated production.
Further, in step 2 when press ram comes downwards to bottom dead centre, vertical direction distance 1 between cutter and cavity plate
~2mm.
The beneficial effects of the present invention are: whole circle overlap is cut into several pieces simultaneously by the Chain Link shaving die by this method
Automatically it falls, realizes trimming process automation, forging efficiency greatly improves.
Detailed description of the invention
Fig. 1 is punch structure schematic diagram of the present invention;
Fig. 2 is cutter structure schematic diagram of the present invention;
Fig. 3 is cavity die structure schematic diagram of the present invention;
Fig. 4 is inventive die assembling schematic diagram;
In figure, 1, punch-pin, 2, cutter, 3, cavity plate, 4, Chain Link.
Specific embodiment
Below according to drawings and examples, the present invention is further described.
As shown in Figures 1 to 4, a kind of application method of the Chain Link shaving die for automatic forging, shaving die
Including punch-pin 1 and cavity plate 3, there is Chain Link shape at the protrusion that the middle part of punch-pin 1 has Chain Link shape to match, the middle part of cavity plate 3
The groove to match, the raised quadrangle and raised central portion two sides of punch-pin 1 are provided with cutter mounting hole;Chain Link is specifically cut
Side is as follows:
Step 1: the lower die holder for being fixed with punch-pin 1 is fixed on press machine processing platform, cutter is installed in cutter mounting hole
2, after whole cutters 2 is installed, the Chain Link 4 after finish-forging is placed on punch-pin 1, cavity plate 3 is bolted to
In die holder;
Step 2: cavity plate 3 is cut away with overlap is about under press ram, whole circle overlap is fallen on the blade of cutter 2;Work as press machine
When slide block down to bottom dead centre (at the lower limit position of press ram), vertical direction distance 1 between cutter 2 and cavity plate 3~
2mm。
Step 3: after the completion, the Chain Link 4 after removing trimming places into new band trimming Chain Link 4;
Step 4: whole circle overlap is pressed on first lap overlap after second 4 trimming of Chain Link, run in sliding block to bottom dead centre
When, the whole circle overlap cut away for the first time is divided into several pieces thin-sheet to fall along 1 inclined-plane of punch-pin by cutter cutting;Chain to trimming
Rail section 4 can be completed to transmit between process by walking beam clamping jaw or manipulator clamping jaw, repeat step 3 and step 4, followed with this
Ring realizes automated production.
By the Chain Link shaving die, whole circle overlap is cut into several pieces and is fallen automatically, realizes that trimming process is automatic