CN110212536A - A kind of medium voltage distribution network interconnection switch state identification method - Google Patents
A kind of medium voltage distribution network interconnection switch state identification method Download PDFInfo
- Publication number
- CN110212536A CN110212536A CN201910318553.4A CN201910318553A CN110212536A CN 110212536 A CN110212536 A CN 110212536A CN 201910318553 A CN201910318553 A CN 201910318553A CN 110212536 A CN110212536 A CN 110212536A
- Authority
- CN
- China
- Prior art keywords
- voltage
- node
- topology
- state
- tie switch
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06N—COMPUTING ARRANGEMENTS BASED ON SPECIFIC COMPUTATIONAL MODELS
- G06N7/00—Computing arrangements based on specific mathematical models
- G06N7/01—Probabilistic graphical models, e.g. probabilistic networks
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for AC mains or AC distribution networks
- H02J3/04—Circuit arrangements for AC mains or AC distribution networks for connecting networks of the same frequency but supplied from different sources
- H02J3/06—Controlling transfer of power between connected networks; Controlling sharing of load between connected networks
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2203/00—Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
- H02J2203/20—Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Evolutionary Computation (AREA)
- Mathematical Optimization (AREA)
- Computational Mathematics (AREA)
- Data Mining & Analysis (AREA)
- Algebra (AREA)
- Probability & Statistics with Applications (AREA)
- Mathematical Analysis (AREA)
- Artificial Intelligence (AREA)
- Pure & Applied Mathematics (AREA)
- Computing Systems (AREA)
- General Engineering & Computer Science (AREA)
- Mathematical Physics (AREA)
- Software Systems (AREA)
- Power Engineering (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
本发明公开了一种中压配电网联络开关状态识别方法,包括如下步骤:步骤S1,计算可行拓扑,中压配电网中首端电压、各节点的注入负荷有功无功功率已知,节点间线路阻抗已知,分别求联络开关支路上的开关的状态,并得到多种联络开关状态组合,对联络开关状态组合快速进行拓扑分析,剔除形成环路的组合,得到可行联络开关组;步骤S2,对于步骤S1的联络开关组可行状态,或某一种可行拓扑策略,进行基于前推回代的潮流计算;步骤S3,基于潮流计算结果进行基于递归贝叶斯方法的后验概率计算。本发明基于前推后代潮流计算的BRA方法,无论是在迭代次数还是计算时间方面,都要比基于WLS状态估计的BRA方法具有优势。
The invention discloses a method for identifying the state of a tie switch in a medium-voltage distribution network, which includes the following steps: step S1, calculating a feasible topology, the voltage at the head end of the medium-voltage distribution network, and the active and reactive power of each node injected into the load are known, The line impedance between nodes is known, and the state of the switch on the tie switch branch is calculated separately, and a variety of tie switch state combinations are obtained, and the topology analysis is quickly performed on the tie switch state combination, and the combination that forms a loop is eliminated to obtain a feasible tie switch group; Step S2, for the feasible state of the tie switch group in step S1, or a certain feasible topology strategy, carry out the power flow calculation based on the forward-back generation; step S3, carry out the posterior probability calculation based on the recursive Bayesian method based on the power flow calculation result . The BRA method of the present invention based on the calculation of the power flow of the forward and future generations has advantages over the BRA method based on the WLS state estimation in terms of the number of iterations and calculation time.
Description
技术领域technical field
本发明属于中压配电系统技术领域,具体涉及一种在中压配电网中基于负荷量测数据和前推后代潮流计算的配电网联络开关状态识别方法。The invention belongs to the technical field of medium-voltage power distribution systems, and in particular relates to a method for identifying the state of a distribution network tie switch in a medium-voltage distribution network based on load measurement data and forward and subsequent power flow calculations.
背景技术Background technique
电力系统中压是指22/10/6.3kV电压等级;中压配电网,是指从高压变电站(电压等级为220/110/35kV)的中压母线引出的中压等级的线路以及相关开关设备、用户用电设备连接的网络。The medium voltage of the power system refers to the 22/10/6.3kV voltage level; the medium voltage distribution network refers to the medium voltage line and related switches drawn from the medium voltage busbar of the high voltage substation (voltage level is 220/110/35kV) The network connected to the device and the user's electrical equipment.
中压配电网采用闭环设计、开环运行方式,通过按装大量的线路分段开关、分支开关、联络开关或设立开闭所、环网站,使得配电网可以根据检修、故障、经济运行等需求,采用多种开环运行方式,确保供电质量和供电可靠性;配电网合解环操作十分频繁,占了调度日常操作项目的48.1%。The medium-voltage distribution network adopts a closed-loop design and an open-loop operation mode. By installing a large number of line section switches, branch switches, contact switches or setting up switching stations and ring stations, the distribution network can be operated according to maintenance, failure, and economical operation. Various open-loop operation modes are adopted to ensure the quality and reliability of power supply; the closing and unlinking operations of the distribution network are very frequent, accounting for 48.1% of the daily operation items of dispatching.
开闭所、环网站的常开开关也统称联络开关,因此这些联络开关就成为改变中压配电网运行方式最重要的控制对象,联络开关状态成为配电网动态拓扑的决定因数。The normally open switches of switching stations and ring stations are also collectively referred to as tie switches, so these tie switches become the most important control objects to change the operation mode of the medium-voltage distribution network, and the state of the tie switch becomes the determining factor of the dynamic topology of the distribution network.
中压配电网静态拓扑,是指所有联络开关按照设计态处于常开状态下的节点之间的连接关系;动态拓扑,是指所有开关按照真实开关状态所形成的节点之间的连接关系;可行的动态拓扑,是形成的实际连接关系不能形成环路。The static topology of the medium-voltage distribution network refers to the connection relationship between all the nodes in which all the contact switches are in the normally open state according to the design state; the dynamic topology refers to the connection relationship between the nodes formed by all the switches according to the real switch state; A feasible dynamic topology is that the actual connection relationship formed cannot form a loop.
目前中压10kV配电网的负荷节点(也是末梢节点),包括专用配电变压器、公用配电变压器,也包括大用户专线或接入的分布式电源,均安装有包含智能电表在内的采集终端,从而可以提供采集间隔为15分钟的电气和电能数据。但是由于配电自动化的滞后,决定中压配电网动态拓扑的开关状态(包括分段、分支、联络开关或开闭所、环网站内开关位置)在目前乃至很长一段时间内难以全面获取,因此在未来很长一段时间内,中压10kV配电网只能获取所有注入功率及部分开关位置,而这种动态拓扑缺失的状况,使得大量高级应用难以在实际工程中得到应用,因此基于负荷功率量测和不完全网络开关位置等采集数据识别中压配电网动态拓扑,已成为一个急于解决的迫切问题。At present, the load nodes (also terminal nodes) of the medium-voltage 10kV distribution network, including dedicated distribution transformers, public distribution transformers, and distributed power sources connected to large user lines, are all equipped with data collection systems including smart meters. terminal, thereby providing electrical and power data collected at 15-minute intervals. However, due to the lag of distribution automation, it is difficult to fully obtain the switch status (including segment, branch, contact switch or switch station, and switch position in the ring network) that determines the dynamic topology of the medium-voltage distribution network. , so for a long period of time in the future, the medium-voltage 10kV distribution network can only obtain all the injected power and part of the switch position, and the lack of dynamic topology makes it difficult for a large number of advanced applications to be applied in actual engineering, so based on It has become an urgent problem to be solved urgently by collecting data such as load power measurement and incomplete network switch position to identify the dynamic topology of medium voltage distribution network.
发明内容Contents of the invention
本发明所要解决的技术问题就是提供一种基于负荷量测数据和前推后代潮流计算的中压配电网联络开关状态识别方法,来识别无法自动监测的剩余开关的开合状态。The technical problem to be solved by the present invention is to provide a method for identifying the state of tie switches in a medium-voltage distribution network based on load measurement data and calculation of forward and subsequent power flows to identify the opening and closing states of the remaining switches that cannot be automatically monitored.
为解决上述技术问题,本发明采用如下技术方案:一种中压配电网联络开关状态识别方法,包括如下步骤:In order to solve the above technical problems, the present invention adopts the following technical solution: a method for identifying the state of a tie switch in a medium-voltage distribution network, comprising the following steps:
步骤S1,计算可行拓扑,中压配电网中首端电压、各节点的注入负荷有功无功功率已知,节点间线路阻抗已知,分别求联络开关支路上的开关的状态,并得到多种联络开关状态组合,对联络开关状态组合快速进行拓扑分析,剔除形成环路的组合,得到可行联络开关组合,可行联络开关组合其中的某一个拓扑策略表示为ηi;Step S1, calculate the feasible topology, the head-end voltage in the medium-voltage distribution network, the active and reactive power injected into each node are known, the line impedance between nodes is known, and the states of the switches on the tie switch branch are calculated respectively, and multiple A kind of tie switch state combination, quickly carry out topology analysis to the tie switch state combination, eliminate the combination that forms a loop, obtain the feasible tie switch combination, a certain topology strategy in the feasible tie switch combination is expressed as η i ;
步骤S2,对于步骤S1的联络开关组可行状态,或某一种可行拓扑策略ηi,进行基于前推回代的潮流计算,首先作出假设,假设全网电压都为额定电压,根据负荷功率由末端向始端逐段推算,仅计算各元件中的功率损耗而不计算节点电压,求得各支路上的电流和功率损耗,并据此获得始端功率,这是回代过程;再根据给定的始端电压和求得的始端功率,由始端向末端逐段推算电压降落,求得各节点电压,这是前推过程,如此重复上述过程,直至各个节点的功率偏差满足允许条件为止;Step S2, for the feasible state of the tie switch group in step S1, or a certain feasible topology strategy η i , carry out the power flow calculation based on the forward-back generation, first make an assumption, assuming that the voltage of the whole network is the rated voltage, according to the load power by Calculate from the end to the beginning step by step, only calculate the power loss in each component without calculating the node voltage, obtain the current and power loss on each branch, and obtain the power at the start end accordingly, which is a back-substitution process; then according to the given The initial voltage and the obtained initial power are calculated step by step from the initial end to the end voltage drop, and the voltage of each node is obtained. This is the forward process, and the above process is repeated until the power deviation of each node meets the allowable conditions;
步骤S3,基于潮流计算结果进行基于递归贝叶斯方法的后验概率计算。Step S3, performing posterior probability calculation based on the recursive Bayesian method based on the power flow calculation results.
可选的,步骤S2具体过程如下:Optionally, the specific process of step S2 is as follows:
1)首先搜索到各条支路的末梢节点,并以此为起点,根据基尔霍夫电流定律求支路上的电流为:1) First search for the end nodes of each branch, and use this as a starting point to calculate the current on the branch according to Kirchhoff’s current law:
2)找到以末端节点为父节点的各个节点,反向逐次回推各条支路的电流,根据基尔霍夫电流定律可得,其节点的注入电流等于式(2)与该节点流出电流之和,可表示为:2) Find each node with the terminal node as the parent node, reversely push back the current of each branch one by one, according to Kirchhoff’s current law, the injected current of the node is equal to formula (2) and the outgoing current of the node The sum can be expressed as:
3)由式(2)和(3)可以求得所有支路的支路电流,再利用已知的根节点电压,至此,父节点与子节点交换位置,从根节点向前顺次计算各个节点的电压,可表示为:3) The branch currents of all branches can be obtained from equations (2) and (3), and then the known voltage of the root node is used. At this point, the parent node and the child node exchange positions, and each The voltage at the node can be expressed as:
其中,i为新的父节点,j为子节点,Z为i、j间支路的阻抗,至此,完成了一次完整的前推后代过程,Among them, i is the new parent node, j is the child node, and Z is the impedance of the branch between i and j. So far, a complete process of pushing forward and descending is completed.
4)计算各节点每次迭代后的电压差值:4) Calculate the voltage difference of each node after each iteration:
则电压差值的最大值为 Then the maximum value of the voltage difference is
5)判别收敛的条件为:5) The conditions for judging convergence are:
其中,k为迭代次数,当满足式(6)时结束循环并输出电压计算结果,否则重复步骤1)-5)直到达到收敛条件为止。Among them, k is the number of iterations. When formula (6) is satisfied, the cycle ends and the voltage calculation result is output, otherwise, steps 1)-5) are repeated until the convergence condition is reached.
可选的,步骤S3具体如下:Optionally, step S3 is specifically as follows:
其中,Nmodels是策略库中拓扑策略的数量,k是迭代次数,是每个拓扑策略的误差向量的集合,p(ηi丨εk-1)是先验概率,是在给定的ηi拓扑策略是正确的条件下,第i个拓扑策略的误差概率,Among them, N models is the number of topological policies in the policy library, k is the number of iterations, is the set of error vectors for each topological strategy, p(η i丨ε k-1 ) is the prior probability, is the error probability of the i-th topological strategy under the condition that the given η i topological strategy is correct,
将先验概率用分布式高斯的方法可表示为:The prior probability can be expressed as:
其中,Cf,i是一个对角矩阵,它的对角线的元素就是误差向量的各个元素方差的逆,而误差向量可由下式求出:Among them, C f,i is a diagonal matrix, and its diagonal elements are the inverse of the variance of each element of the error vector, and the error vector It can be obtained by the following formula:
其中,zreal是真实的测量向量,是第i个拓扑策略在第k次迭代后的状态估计值,where z real is the real measurement vector, is the state estimate of the i-th topology policy after the k-th iteration,
在求解的算法中,默认地将每个拓扑策略的初始概率平均分配为1/Nmodels,Nmodels为各种可能存在的拓扑策略的总数,该算法通过迭代的方式,利用(8)(9)式,不断地求出新的拓扑策略对应的概率,最终根据概率大小确定为所要求的目标拓扑。In the solution algorithm, by default, the initial probability of each topology strategy is evenly distributed as 1/N models , and N models are the total number of possible topological strategies. The algorithm uses (8)(9 ) formula, constantly find out the probability corresponding to the new topology strategy, and finally determine the required target topology according to the probability.
可选的,规定将概率pi>0.5的拓扑策略确定为所要求的目标拓扑。Optionally, it is stipulated that the topology strategy with probability p i >0.5 is determined as the required target topology.
本发明利用已知静态拓扑,且所有负荷节点具有量测数据、部分开关开合状态可自动监测情况下,来识别无法自动监测的剩余开关的开合状态。The present invention utilizes the known static topology, and all load nodes have measurement data, and the opening and closing states of some switches can be automatically monitored to identify the opening and closing states of the remaining switches that cannot be automatically monitored.
采用基于前推后代潮流计算的BRA方法,无论是在迭代次数还是计算时间方面,基于前推后代潮流计算的BRA方法都要比基于WLS状态估计的BRA方法具有优势。Adopting the BRA method based on the calculation of forward and future power flow, the BRA method based on the calculation of forward and future power flow has advantages over the BRA method based on WLS state estimation in terms of the number of iterations and calculation time.
本发明的具体技术方案及其有益效果将会在下面的具体实施方式中结合附图进行详细的说明。The specific technical solutions and beneficial effects of the present invention will be described in detail in the following specific embodiments with reference to the accompanying drawings.
附图说明Description of drawings
下面结合附图和具体实施方式对本发明作进一步描述:The present invention will be further described below in conjunction with accompanying drawing and specific embodiment:
图1为作为案例的IEEE33节点配电网。Figure 1 is an IEEE33 node distribution network as a case.
具体实施方式Detailed ways
本发明的目的是在利用已知静态拓扑,且所有负荷节点具有量测数据、部分开关开合状态可自动监测情况下,来识别无法自动监测的剩余开关的开合状态。The purpose of the present invention is to identify the opening and closing states of the remaining switches that cannot be automatically monitored when the known static topology is used, all load nodes have measurement data, and the opening and closing states of some switches can be automatically monitored.
一种基于负荷量测数据和前推后代潮流计算的中压配电网联络开关状态识别方法,简称为“基于前推后代潮流计算的BRA方法”。A method for identifying the state of tie switches in medium-voltage distribution networks based on load measurement data and forward-generation power flow calculations, referred to as "BRA method based on forward-generation power flow calculations" for short.
具体步骤如下。Specific steps are as follows.
步骤1.计算可行拓扑Step 1. Calculate Feasible Topology
配电网只允许短暂的环网状态,因此只考虑不存在环网的拓扑组合。The distribution network only allows a short-lived ring state, so only topological combinations without rings are considered.
从图1可以看处,每个联络开关在合闸时均将出现环路,且在其他联络开关均打开的情况下只形成一个惟一的环路,如图中标示的环路L1-L5。实际制定运行方式时,当一个联络开关合上时,必定有一线路分段或分支开关要打开,使得该环路解环,且使得所有节点仍保持带电;假设环路中只有一个与联络开关关联的对偶开关,并假设为S'i(i=1~5),也即:It can be seen from Figure 1 that each tie switch will have a loop when it is closed, and only a unique loop will be formed when the other tie switches are open, the loop L 1 -L marked in the figure 5 . When actually formulating the operation mode, when a tie switch is closed, there must be a line segment or branch switch to be opened, so that the loop is unlooped, and all nodes are still charged; assuming that only one in the loop is associated with the tie switch The dual switch of , and assumed to be S' i (i=1~5), that is:
其中K表示开关的状态,以上表示当K(Si)=1,K(S'i)=0;当K(Si)=0,K(S'i)=1。按此假设,图1存在10个开关,但所有对偶开关的状态是由其相应的联络开关状态决定,因此决定配电网拓扑结构的还是联络开关的状态。Where K represents the state of the switch, the above means that when K(S i )=1, K(S' i )=0; when K(S i )=0, K(S' i )=1. According to this assumption, there are 10 switches in Figure 1, but the state of all dual switches is determined by the state of their corresponding tie switches, so the state of the tie switch determines the topology of the distribution network.
本发明选取图1的IEEE33节点配电网作为案例,其中五个联络开关的线路由虚线标出(S1-S5)。在该中压配电网中,首端电压(节点0处)为10.5kV,各节点的注入负荷有功无功功率已知,节点间线路阻抗已知,分别求五条联络开关支路上的开关的状态。The present invention selects the IEEE33 node distribution network in Fig. 1 as an example, wherein the lines of five tie switches are marked by dotted lines (S1-S5). In this medium-voltage distribution network, the head-end voltage (node 0) is 10.5kV, the active and reactive power injected into each node is known, and the line impedance between nodes is known. state.
图1共有5个联络联络开关,理论上存在25=32种联络开关状态组合;但是,当有2个联络开关合上后,有可能形成新的环路;因此对32个的组合,可快速进行拓扑分析,剔除形成环路的组合,得到如表1的可行联络开关组合。There are 5 tie switches in Fig. 1, theoretically there are 2 5 = 32 kinds of tie switch state combinations; however, when 2 tie switches are closed, a new loop may be formed; therefore, for 32 combinations, it is possible to Quickly carry out topology analysis, eliminate the combinations that form loops, and obtain the feasible tie switch combinations as shown in Table 1.
表1的联络开关组可行状态,称为可行拓扑策略库(model bank),其中的某一个拓扑策略表示为ηi,Nmodels是策略库中拓扑策略的总数量,也即联络开关组可行状态的组数。The feasible state of the tie switch group in Table 1 is called the feasible topological strategy library (model bank), in which a certain topology strategy is expressed as η i , and N models is the total number of topology strategies in the strategy bank, that is, the feasible state of the tie switch group the number of groups.
表1 IEEE33节点配电网不存在环路的联络开关组状态拓扑策略表Table 1 The state topology strategy table of the tie switch group without loops in the IEEE33 node distribution network
步骤2.对于所有可行拓扑进行前推回代潮流计算Step 2. Forward and backward power flow calculations for all feasible topologies
对于以上的联络开关组可行状态,或某一种可行拓扑策略ηi,进行基于前推回代的潮流计算。For the above feasible state of the tie switch group, or a certain feasible topology strategy η i , the power flow calculation based on forward and backward generation is performed.
首先作出假设,假设全网电压都为额定电压,根据负荷功率由末端向始端逐段推算,仅计算各元件中的功率损耗而不计算节点电压,求得各支路上的电流和功率损耗,并据此获得始端功率,这是回代过程;再根据给定的始端电压和求得的始端功率,由始端向末端逐段推算电压降落,求得各节点电压,这是前推过程。如此重复上述过程,直至各个节点的功率偏差满足允许条件为止。First make assumptions, assuming that the voltage of the whole network is the rated voltage, calculate the load power step by step from the end to the beginning, only calculate the power loss in each component without calculating the node voltage, and obtain the current and power loss on each branch, and According to this, the initial power is obtained, which is the back-substitution process; then, according to the given initial voltage and the obtained initial power, the voltage drop is calculated step by step from the initial to the end, and the voltage of each node is obtained, which is the forward process. The above process is repeated until the power deviation of each node satisfies the allowable condition.
具体步骤如下:Specific steps are as follows:
1)首先搜索到各条支路的末梢节点,并以此为起点,根据基尔霍夫电流定律求支路上的电流为:1) First search for the end nodes of each branch, and use this as a starting point to calculate the current on the branch according to Kirchhoff’s current law:
2)找到以末端节点为父节点的各个节点,反向逐次回推各条支路的电流,根据基尔霍夫电流定律可得,其节点的注入电流等于式(2)与该节点流出电流之和,可表示为:2) Find each node with the terminal node as the parent node, reversely push back the current of each branch one by one, according to Kirchhoff’s current law, the injected current of the node is equal to formula (2) and the outgoing current of the node The sum can be expressed as:
3)由式(2)和(3)可以求得所有支路的支路电流,再利用已知的根节点电压,至此,父节点与子节点交换位置,从根节点向前顺次计算各个节点的电压,可表示为:3) The branch currents of all branches can be obtained from equations (2) and (3), and then the known voltage of the root node is used. At this point, the parent node and the child node exchange positions, and each The voltage at the node can be expressed as:
其中,i为新的父节点,j为子节点,Z为i、j间支路的阻抗。至此,完成了一次完整的前推后代过程。Among them, i is the new parent node, j is the child node, and Z is the impedance of the branch between i and j. So far, a complete process of pushing forward to offspring has been completed.
4)计算各节点每次迭代后的电压差值:4) Calculate the voltage difference of each node after each iteration:
则电压差值的最大值为 Then the maximum value of the voltage difference is
5)判别收敛的条件为:5) The conditions for judging convergence are:
其中,k为迭代次数,当满足式(6)时结束循环并输出电压计算结果,否则重复步骤1)-5)直到达到收敛条件为止。Among them, k is the number of iterations. When formula (6) is satisfied, the cycle ends and the voltage calculation result is output, otherwise, steps 1)-5) are repeated until the convergence condition is reached.
步骤3.基于前推回代潮流计算结果的拓扑识别Step 3. Topology identification based on forward-back generation power calculation results
对于表1的联络开关组可行状态,或某一种可行拓扑策略ηi,进行基于潮流计算结果进行基于递归贝叶斯方法(Recursive Bayesian Approach,RBA)的后验概率计算,具体为:For the feasible state of the tie switch group in Table 1, or a certain feasible topology strategy η i , the posterior probability calculation based on the recursive Bayesian method (Recursive Bayesian Approach, RBA) is performed based on the power flow calculation results, specifically:
其中,Nmodels是策略库中拓扑策略的数量,k是迭代次数,是每个拓扑策略的误差向量的集合,p(ηi丨εk-1)是先验概率,是在给定的ηi拓扑策略是正确的条件下,第i个拓扑策略的误差概率。Among them, N models is the number of topological policies in the policy library, k is the number of iterations, is the set of error vectors for each topological strategy, p(η i丨ε k-1 ) is the prior probability, is the error probability of the i-th topological strategy under the condition that the given η i topological strategy is correct.
将先验概率用分布式高斯的方法可表示为:The prior probability can be expressed as:
其中,Cf,i是一个对角矩阵,它的对角线的元素就是误差向量的各个元素方差的逆,而误差向量可由下式求出:Among them, C f,i is a diagonal matrix, and its diagonal elements are the inverse of the variance of each element of the error vector, and the error vector It can be obtained by the following formula:
其中,zreal是真实的测量向量,是第i个拓扑策略在第k次迭代后的状态估计值。在求解的算法中,默认地将每个拓扑策略的初始概率平均分配为1/Nmodels,Nmodels为各种可能存在的拓扑策略的总数。该算法通过迭代的方式,利用(8)(9)式,不断地求出新的拓扑策略对应的概率,最终,规定将超过50%即概率pi>0.5的拓扑策略即为所要求的目标拓扑。where z real is the real measurement vector, is the estimated value of the state of the i-th topology strategy after the k-th iteration. In the solution algorithm, by default, the initial probability of each topological strategy is evenly distributed as 1/N models , and N models are the total number of various possible topological strategies. The algorithm uses equations (8) and (9) in an iterative way to continuously find out the probability corresponding to the new topological strategy. Finally, it is stipulated that the topological strategy that exceeds 50%, that is, the probability p i >0.5, is the required goal topology.
以IEEE33节点配电网作为案例。以表1的可行拓扑组合状态或拓扑策略,分别作为每次试验的正确线路拓扑,利用潮流计算的方法得到每一次迭代估计值,并采用测量值同估计值进行按照公式(9)获取误差,然后按公式(8)计算获得此误差下的先验概率。Take the IEEE33 node distribution network as an example. Take the feasible topology combination state or topology strategy in Table 1 as the correct line topology for each test, use the power flow calculation method to obtain the estimated value of each iteration, and use the measured value and the estimated value to obtain the error according to formula (9). Then calculate the prior probability under this error according to formula (8).
采取本发明技术方案步骤3递归贝叶斯方法的同类方法常见采取基于加权最小二乘法(WLS)状态估计,并以每一步状态估计误差作为公式(9),继而得到类似的判断;方法简称为“基于WLS状态估计的BRA方法”。The similar method that adopts technical solution step 3 of the present invention recursive Bayesian method commonly adopts state estimation based on weighted least squares method (WLS), and uses each step state estimation error as formula (9), and then obtains similar judgment; Method is called for short "BRA method based on WLS state estimation".
以IEEE33节点配电网作为案例。以表1的可行拓扑组合状态或拓扑策略,分别作为每次试验的正确线路拓扑,前几次迭代,所有拓扑组的概率差异还不是很明显,但迭代到后面几次,概率有相较于其他拓扑策略更明显的升高,最终趋近于1,表明该组合为正确的联络开关组合。Take the IEEE33 node distribution network as an example. Taking the feasible topology combination state or topology strategy in Table 1 as the correct line topology for each experiment, the probability difference of all topology groups in the first few iterations is not obvious, but in the next few iterations, the probability is compared with Other topological strategies increase more obviously, and finally tend to 1, indicating that this combination is the correct combination of tie switches.
表2给出了基于前推后代潮流计算的BRA方法。Table 2 gives the BRA method based on the calculation of power flow forward and backward.
表2.基于前推后代潮流计算的RBA和基于WLS状态估计的RBA对比结果Table 2. Comparison results of RBA based on forward power flow calculation and RBA based on WLS state estimation
由表2可以得出,无论是在迭代次数还是计算时间方面,基于前推后代潮流计算的BRA方法都要比基于WLS状态估计的BRA方法具有优势。From Table 2, it can be concluded that the BRA method based on the calculation of forward and future generation power flow has advantages over the BRA method based on WLS state estimation, both in terms of the number of iterations and calculation time.
以上所述,仅为本发明的具体实施方式,但本发明的保护范围并不局限于此,熟悉该本领域的技术人员应该明白本发明包括但不限于上面具体实施方式中描述的内容。任何不偏离本发明的功能和结构原理的修改都将包括在权利要求书的范围中。The above description is only a specific embodiment of the present invention, but the protection scope of the present invention is not limited thereto. Those skilled in the art should understand that the present invention includes but is not limited to the content described in the above specific embodiment. Any modifications that do not depart from the functional and structural principles of the present invention will be included in the scope of the claims.
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910318553.4A CN110212536A (en) | 2019-04-19 | 2019-04-19 | A kind of medium voltage distribution network interconnection switch state identification method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910318553.4A CN110212536A (en) | 2019-04-19 | 2019-04-19 | A kind of medium voltage distribution network interconnection switch state identification method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110212536A true CN110212536A (en) | 2019-09-06 |
Family
ID=67786093
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910318553.4A Pending CN110212536A (en) | 2019-04-19 | 2019-04-19 | A kind of medium voltage distribution network interconnection switch state identification method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110212536A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111262243A (en) * | 2020-03-04 | 2020-06-09 | 国网浙江省电力有限公司 | An intelligent identification and optimization method for the operation mode of the power distribution system in the park |
CN112035988A (en) * | 2020-08-28 | 2020-12-04 | 燕山大学 | Microgrid loop planning based on multiple DGs |
CN113971371A (en) * | 2021-10-29 | 2022-01-25 | 金程科技有限公司 | A method for identification and safety management and control of terminal power grid user equipment |
CN114156850A (en) * | 2021-11-26 | 2022-03-08 | 贵州电网有限责任公司 | Method for self-identifying position state of interconnection switch of power distribution network |
CN114372232A (en) * | 2022-03-23 | 2022-04-19 | 广东电网有限责任公司肇庆供电局 | Transformer area phase sequence topology identification method and system based on voltage sequence similarity transmission |
-
2019
- 2019-04-19 CN CN201910318553.4A patent/CN110212536A/en active Pending
Non-Patent Citations (2)
Title |
---|
BARRY HAYES ET: "Event-triggered Topology Identification for State Estimation in Active Distribution Networks"" * |
BOXIN QIAO ET: "Interconnection Switch On-off State Identification of Distribution Networks Based on Load Measurement" * |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111262243A (en) * | 2020-03-04 | 2020-06-09 | 国网浙江省电力有限公司 | An intelligent identification and optimization method for the operation mode of the power distribution system in the park |
CN111262243B (en) * | 2020-03-04 | 2023-05-12 | 国网浙江省电力有限公司 | Intelligent identification and optimization method for operation mode of park power distribution system |
CN112035988A (en) * | 2020-08-28 | 2020-12-04 | 燕山大学 | Microgrid loop planning based on multiple DGs |
CN112035988B (en) * | 2020-08-28 | 2022-10-25 | 燕山大学 | A Microgrid Loop Planning Method Based on Multiple DGs |
CN113971371A (en) * | 2021-10-29 | 2022-01-25 | 金程科技有限公司 | A method for identification and safety management and control of terminal power grid user equipment |
CN113971371B (en) * | 2021-10-29 | 2023-11-07 | 金程科技有限公司 | A method for terminal power grid user equipment identification and safety management and control |
CN114156850A (en) * | 2021-11-26 | 2022-03-08 | 贵州电网有限责任公司 | Method for self-identifying position state of interconnection switch of power distribution network |
CN114156850B (en) * | 2021-11-26 | 2023-09-26 | 贵州电网有限责任公司 | Method for self-identifying position state of interconnection switch of power distribution network |
CN114372232A (en) * | 2022-03-23 | 2022-04-19 | 广东电网有限责任公司肇庆供电局 | Transformer area phase sequence topology identification method and system based on voltage sequence similarity transmission |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110212536A (en) | A kind of medium voltage distribution network interconnection switch state identification method | |
CN110086168B (en) | A topology identification method for distribution network operation based on multi-source data fusion | |
Amanulla et al. | Reconfiguration of power distribution systems considering reliability and power loss | |
CN107271852B (en) | Fault location method for complex distribution network based on voltage sag information | |
CN104578427B (en) | Fault self-healing method for power distribution network containing microgrid power source | |
CN101958543B (en) | Method for estimating three-phase impedance-free nonlinear multi-source state of transformer substation | |
CN102983594A (en) | Control method of grid closed loop operation impact current | |
CN104158178B (en) | Power partition recovery and global optimization method based on the intelligent power distribution net of reliability | |
CN111030100B (en) | Power distribution network PMU optimal configuration method based on customized inheritance | |
CN103972927B (en) | The grid-connected turn of lonely net integrated control method containing photovoltaic/energy-storing and power-generating system micro-capacitance sensor | |
CN103413044A (en) | Substation measurement information based method for estimating local topology of electric power system | |
CN105738765A (en) | Power distribution network fault positioning method based on feeder line terminals and genetic algorithm | |
CN116826725A (en) | Multi-objective fault power supply recovery method for substation-oriented medium-voltage distribution power supply area (S-SCDN) feeder line group FC | |
CN109687432B (en) | Multi-stage cooperation-based power distribution terminal site selection and sizing method and system | |
CN107895953A (en) | A kind of distribution tidal current computing method of adaptive grid structure | |
Ding et al. | A simple heuristic method for smart distribution system reconfiguration | |
CN103823140B (en) | Power network topology misidentification system and method thereof based on road-loop equation | |
CN115169741A (en) | Multi-stage optimization configuration method and system for voltage sag monitoring device of power distribution network | |
CN110048384A (en) | A kind of distribution high reliability self-healing method and system | |
CN105610156B (en) | A kind of concurrent cyclization method of multi-line | |
Li et al. | A new reconfiguration approach for distribution system with distributed generation | |
Duong et al. | A method for real time voltage stability monitoring in sub-transmission networks | |
CN110797911A (en) | A switch state adjustment method for multi-objective active distribution network based on state splitting | |
CN115133540B (en) | Model-free real-time voltage control method for power distribution network | |
CN116169673A (en) | Elasticity evaluation method and system of power distribution network, electronic equipment and readable storage medium |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190906 |
|
RJ01 | Rejection of invention patent application after publication |