CN110130648A - A kind of structure and method of steel pipe column side-wall hole casting concrete - Google Patents

A kind of structure and method of steel pipe column side-wall hole casting concrete Download PDF

Info

Publication number
CN110130648A
CN110130648A CN201910482520.3A CN201910482520A CN110130648A CN 110130648 A CN110130648 A CN 110130648A CN 201910482520 A CN201910482520 A CN 201910482520A CN 110130648 A CN110130648 A CN 110130648A
Authority
CN
China
Prior art keywords
steel pipe
pipe column
hole
pouring
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910482520.3A
Other languages
Chinese (zh)
Inventor
潘樱桃
谢景亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fourth Engineering Division Corp Ltd
China Construction Fourth Engineering Division South China Construction Co Ltd
Original Assignee
China Construction Fourth Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fourth Engineering Division Corp Ltd filed Critical China Construction Fourth Engineering Division Corp Ltd
Priority to CN201910482520.3A priority Critical patent/CN110130648A/en
Publication of CN110130648A publication Critical patent/CN110130648A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/02Conveying or working-up concrete or similar masses able to be heaped or cast
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/24Scaffolds essentially supported by building constructions, e.g. adjustable in height specially adapted for particular parts of buildings or for buildings of particular shape, e.g. chimney stacks or pylons
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/14Railings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

本发明公开了一种钢管柱侧壁开孔浇筑混凝土的结构及方法,本发明是在钢管柱(1)侧壁设置浇筑孔(3),并在浇筑孔(3)下方的钢管柱(1)侧壁设置泄水孔(4);将泵管从浇筑孔(3)伸入钢管柱(1)内完成钢管柱内混凝土的浇筑;混凝土浇筑完成后,将浇筑孔(3)和泄水孔(4)封堵。本发明提高了施工安全系数,缩短了施工工期,对节约劳动力和施工成本起到了良好的作用。本发明具有结构简单、施工安全方便、省时省力的特点。The invention discloses a structure and a method for pouring concrete by opening a hole in the side wall of a steel pipe column. The invention provides a pouring hole (3) on the side wall of a steel pipe column (1), and the steel pipe column (1) under the pouring hole (3) ) side wall is provided with a drain hole (4); the pump pipe is extended from the pouring hole (3) into the steel pipe column (1) to complete the concrete pouring in the steel pipe column; after the concrete pouring is completed, the pouring hole (3) and the drain Hole (4) plugged. The invention improves the construction safety factor, shortens the construction period, and plays a good role in saving labor force and construction cost. The invention has the characteristics of simple structure, safe and convenient construction, time-saving and labor-saving.

Description

一种钢管柱侧壁开孔浇筑混凝土的结构及方法A structure and method for pouring concrete with holes in the side wall of a steel pipe column

技术领域technical field

本发明涉及一种钢管柱侧壁开孔浇筑混凝土的结构及方法,属于建筑施工技术领域。The invention relates to a structure and a method for pouring concrete through holes in the side wall of a steel pipe column, and belongs to the technical field of building construction.

背景技术Background technique

钢管混凝土柱—钢筋混凝土核心筒的双重抗侧力体系结构是当前超高层常用的一种结构形式,该种结构形式外框通常设计为水平钢结构+钢管混凝土柱。由于内筒和外框采用不同性能的材料,钢筋混凝土核心筒和外框钢结构施工难以同步,核心筒先行施工,导致钢管柱内混凝土浇筑困难。Concrete-filled steel tube column-reinforced concrete core tube dual lateral force-resistant system structure is a commonly used structural form of super high-rise buildings. The outer frame of this structural form is usually designed as a horizontal steel structure + concrete-filled steel tube column. Since the inner tube and the outer frame are made of materials with different properties, it is difficult to synchronize the construction of the reinforced concrete core tube and the outer frame steel structure.

发明内容Contents of the invention

本发明的目的在于,提供一种钢管柱侧壁开孔浇筑混凝土的结构及方法,以在钢管柱连续安装完成后,在楼层内进行混凝土浇筑,可减少临空作业,并确保工程质量和施工进度,从而克服现有技术的不足。The object of the present invention is to provide a structure and method for pouring concrete through holes in the side walls of steel pipe columns, so that after the continuous installation of steel pipe columns is completed, concrete pouring can be carried out in the floor, which can reduce aerial work and ensure project quality and construction quality. progress, thereby overcoming the deficiencies of the prior art.

为实现上述目的,本发明采用如下技术方案:To achieve the above object, the present invention adopts the following technical solutions:

本发明的一种钢管柱侧壁开孔浇筑混凝土的结构;包括钢管柱,在钢管柱侧壁上设有能伸入泵管的浇筑孔,并在浇筑孔下方的钢管柱侧壁上设有泄水孔。A structure for pouring concrete with openings in the side wall of a steel pipe column according to the present invention; comprising a steel pipe column, a pouring hole capable of extending into a pump pipe is provided on the side wall of the steel pipe column, and a scupper.

上述结构中,所述浇筑孔处的钢管柱内壁设有补强环,补强环设有灌浆孔;补强环的中心线与浇筑孔的中心线重合;补强环外径大于浇筑孔孔径,补强环孔径小于浇筑孔孔径;补强环的接触面与钢管柱的钢管柱内壁的弧度对应;补强环四周与钢管柱内壁焊接。In the above structure, the inner wall of the steel pipe column at the pouring hole is provided with a reinforcing ring, and the reinforcing ring is provided with a grouting hole; the center line of the reinforcing ring coincides with the center line of the pouring hole; the outer diameter of the reinforcing ring is larger than the diameter of the pouring hole , the aperture of the reinforcing ring is smaller than the aperture of the pouring hole; the contact surface of the reinforcing ring corresponds to the curvature of the inner wall of the steel pipe column; the periphery of the reinforcing ring is welded to the inner wall of the steel pipe column.

用于上述结构的本发明的一种钢管柱侧壁开孔浇筑混凝土方法;该方法是在钢管柱侧壁上预先设置浇筑孔,并在浇筑孔下方的钢管柱侧壁上设置泄水孔;将泵管从浇筑孔伸入钢管柱内完成钢管柱内混凝土的浇筑;混凝土浇筑完成后,将浇筑孔和泄水孔封堵。A method for pouring concrete by opening a hole in the side wall of a steel pipe column of the present invention for the above-mentioned structure; the method is to pre-set a pouring hole on the side wall of the steel pipe column, and set a drain hole on the side wall of the steel pipe column below the pouring hole; Extend the pump pipe from the pouring hole into the steel pipe column to complete the concrete pouring in the steel pipe column; after the concrete pouring is completed, seal the pouring hole and the drain hole.

前述方法中,所述浇筑孔的中心线位于楼层钢梁顶面标高以上800mm~1200mm处。In the aforementioned method, the center line of the pouring hole is located at 800 mm to 1200 mm above the level of the top surface of the floor steel beam.

前述方法中,所述浇筑孔处的楼层钢梁上设有操作平台;操作平台周围设有临边护栏。In the aforementioned method, an operation platform is provided on the floor steel beam at the pouring hole; edge guardrails are provided around the operation platform.

前述方法中,所述泵管包括一组首尾连接的竖向泵管;竖向泵管经支架与楼层钢梁连接。In the aforementioned method, the pump pipes include a group of vertical pump pipes connected end to end; the vertical pump pipes are connected to the floor steel beams through brackets.

前述方法中,所述竖向泵管两端设有连接法兰;拆除位于浇筑孔处的一段竖向泵管,将下段竖向泵管顶端与直角弯泵管一端连接;直角弯泵管另一端伸入钢管柱内并经连接法兰与小弯头连接;小弯头的出口端向下弯曲并与钢管柱的中心线重合。In the aforementioned method, the two ends of the vertical pump pipe are provided with connecting flanges; a section of the vertical pump pipe located at the pouring hole is removed, and the top end of the lower section of the vertical pump pipe is connected to one end of the right-angle bend pump pipe; the other end of the right-angle bend pump pipe is One end extends into the steel pipe column and is connected to the small elbow through the connecting flange; the outlet end of the small elbow bends downward and coincides with the centerline of the steel pipe column.

前述方法中,所述直角弯泵管底部设有支撑,支撑与操作平台或临边护栏连接。In the aforementioned method, a support is provided at the bottom of the right-angled pump pipe, and the support is connected to the operation platform or the side guardrail.

前述方法中,所述浇筑孔和泄水孔采用数控切割技术进行切割,切割下来的浇筑孔原钢板用于混凝土浇筑完成后对浇筑孔进行封堵;切割下来的泄水孔原钢板用于混凝土浇筑完成后对泄水孔进行封堵。In the aforementioned method, the pouring hole and the drain hole are cut using numerical control cutting technology, and the cut original steel plate for the pouring hole is used to seal the pouring hole after the concrete pouring is completed; the cut original steel plate for the drain hole is used for concrete After the pouring is completed, the weep hole shall be sealed.

前述方法中,在进行混凝土浇筑时,采用分层振捣,分层高度不大于1米;分层停歇时,采用中频振捣棒自浇筑孔伸进钢管柱内进行振捣;同时钢管柱外配合人工木槌敲击,根据声音判断混凝土是否密实。In the aforementioned method, when pouring concrete, layered vibration is used, and the layered height is not greater than 1 meter; when layering stops, a medium-frequency vibrating rod is used to extend into the steel pipe column from the pouring hole for vibration; With artificial mallet knocking, judge whether the concrete is dense according to the sound.

前述方法中,同一根钢管柱的浇筑应连续进行,中间间隔时间不能超过混凝土的初凝时间;当混凝土不能及时供应时,应采取间歇泵送方式。In the aforementioned method, the pouring of the same steel pipe column should be carried out continuously, and the interval time in between should not exceed the initial setting time of the concrete; when the concrete cannot be supplied in time, the intermittent pumping method should be adopted.

由于采用了上述技术方案,本发明与现有技术相比,本发明提高了施工安全系数,缩短了施工工期,对节约劳动力和施工成本起到了良好的作用。本发明具有结构简单、施工安全方便、省时省力的特点。Due to the adoption of the above technical solution, compared with the prior art, the present invention improves the construction safety factor, shortens the construction period, and plays a good role in saving labor and construction costs. The invention has the characteristics of simple structure, safe and convenient construction, time-saving and labor-saving.

附图说明Description of drawings

图1是本发明的方法示意图;Fig. 1 is a schematic diagram of the method of the present invention;

图2是补强环的结构示意图;Fig. 2 is the structural representation of reinforcing ring;

图3是切割下来备用的浇筑孔原钢板;Fig. 3 is the spare former steel plate of pouring hole that cuts off;

图4是切割下来备用的泄水孔原钢板。Fig. 4 is the original steel plate of the scupper that is cut out for use.

附图中的标记为:1-钢管柱、2-楼层钢梁、3-浇筑孔、4-泄水孔、5-泄水孔原钢板、6-补强环、7-支撑、8-灌浆孔、9-钢管柱内壁、10-浇筑孔原钢板、11-操作平台、12-临边护栏、13-小弯头、14-支架、15-连接法兰、16-直角弯泵管、17-竖向泵管、18-接触面。The marks in the drawings are: 1-steel pipe column, 2-floor steel beam, 3-pouring hole, 4-drainage hole, 5-original steel plate for weeping hole, 6-reinforcing ring, 7-support, 8-grouting Hole, 9-inner wall of steel pipe column, 10-original steel plate for pouring hole, 11-operating platform, 12-edge guardrail, 13-small elbow, 14-bracket, 15-connecting flange, 16-right-angle elbow pump pipe, 17 - vertical pump tube, 18 - contact surface.

具体实施方式Detailed ways

下面结合附图和实施例对本发明作进一步的详细说明。The present invention will be further described in detail below in conjunction with the accompanying drawings and embodiments.

本发明的一种钢管柱侧壁开孔浇筑混凝土的结构,如图1和图2所示,包括钢管柱1,在钢管柱1侧壁上设有能伸入泵管的浇筑孔3,并在浇筑孔3下方的钢管柱1的侧壁上设有泄水孔4。A steel pipe column side wall opening pouring concrete structure of the present invention, as shown in Figure 1 and Figure 2, includes a steel pipe column 1, a pouring hole 3 that can extend into the pump pipe is provided on the side wall of the steel pipe column 1, and A drain hole 4 is provided on the side wall of the steel pipe column 1 below the pouring hole 3 .

在上述结构中,在浇筑孔3处的钢管柱1内壁设有补强环6,补强环6如图2所示,补强环6设有灌浆孔8;补强环6的中心线与浇筑孔3的中心线重合;补强环6外径大于浇筑孔3孔径,补强环6孔径小于浇筑孔3孔径;补强环6的接触面18与钢管柱1的钢管柱内壁9的弧度对应;补强环6四周与钢管柱内壁9焊接,焊缝等级为一级。In the above structure, a reinforcement ring 6 is provided on the inner wall of the steel pipe column 1 at the pouring hole 3, and the reinforcement ring 6 is shown in Figure 2, and the reinforcement ring 6 is provided with a grouting hole 8; the center line of the reinforcement ring 6 and The center line of the pouring hole 3 coincides; the outer diameter of the reinforcing ring 6 is larger than the aperture of the pouring hole 3, and the aperture of the reinforcing ring 6 is smaller than the aperture of the pouring hole 3; the radian of the contact surface 18 of the reinforcing ring 6 and the inner wall 9 of the steel pipe column 1 Corresponding; the reinforcement ring 6 is welded with the inner wall 9 of the steel pipe column, and the grade of the weld is first grade.

用于上述结构的本发明的一种钢管柱侧壁开孔浇筑混凝土的方法;如图1所示,该方法是在钢管柱1侧壁上预先设置浇筑孔3,并在浇筑孔3下方的钢管柱1侧壁上设置泄水孔4;将泵管从浇筑孔3伸入钢管柱1内完成钢管柱内混凝土的浇筑;混凝土浇筑完成后,将浇筑孔3和泄水孔4封堵。A method for pouring concrete by opening a hole in the side wall of a steel pipe column of the present invention for the above-mentioned structure; A drain hole 4 is provided on the side wall of the steel pipe column 1; the pump pipe is extended from the pouring hole 3 into the steel pipe column 1 to complete the concrete pouring in the steel pipe column; after the concrete pouring is completed, the pouring hole 3 and the drain hole 4 are blocked.

浇筑孔3的中心线位于楼层钢梁2顶面标高以上800mm~1200mm处。浇筑孔3处的楼层钢梁2上设有操作平台11;操作平台11周围设有临边护栏12。泵管包括一组首尾连接的竖向泵管17;竖向泵管17经支架14与楼层钢梁2连接。竖向泵管17两端设有连接法兰15;拆除位于浇筑孔3处的一段竖向泵管17,将下段竖向泵管17顶端与直角弯泵管16一端连接;直角弯泵管16另一端伸入钢管柱1内并经连接法兰15与小弯头13连接;小弯头13的出口端向下弯曲并与钢管柱1的中心线重合。直角弯泵管16底部设有支撑7,支撑7与操作平台11或临边护栏12连接。The center line of the pouring hole 3 is located at 800 mm to 1200 mm above the level of the top surface of the floor steel beam 2 . An operation platform 11 is provided on the floor steel beam 2 at the pouring hole 3; a border guardrail 12 is provided around the operation platform 11. The pump pipes include a group of vertical pump pipes 17 connected end to end; the vertical pump pipes 17 are connected to the floor steel beams 2 via brackets 14 . Connecting flanges 15 are provided at both ends of the vertical pump pipe 17; a section of the vertical pump pipe 17 located at the pouring hole 3 is removed, and the top of the lower vertical pump pipe 17 is connected to one end of the right-angle bend pump pipe 16; the right-angle bend pump pipe 16 The other end extends into the steel pipe column 1 and connects with the small elbow 13 through the connecting flange 15; A support 7 is provided at the bottom of the right-angled pump pipe 16, and the support 7 is connected with the operating platform 11 or the side guardrail 12.

浇筑孔3和泄水孔4采用数控切割技术进行切割,切割下来的浇筑孔原钢板10(见图3)用于混凝土浇筑完成后对浇筑孔3进行封堵;切割下来的泄水孔原钢板5(见图4)用于混凝土浇筑完成后对泄水孔4进行封堵。The pouring hole 3 and the drain hole 4 are cut by numerical control cutting technology, and the cut original steel plate 10 for the pouring hole (see Figure 3) is used to seal the pouring hole 3 after the concrete pouring is completed; the cut original steel plate for the drain hole 5 (see Figure 4) is used to block the drain hole 4 after the concrete pouring is completed.

在进行混凝土浇筑时,采用分层振捣,分层高度不大于1米;分层停歇时,采用中频振捣棒自浇筑孔3伸进钢管柱1内进行振捣;同时钢管柱1外配合人工木槌敲击,根据声音判断混凝土是否密实。同一根钢管柱1的浇筑应连续进行,中间间隔时间不能超过混凝土的初凝时间;当混凝土不能及时供应时,应采取间歇泵送方式。When pouring concrete, vibrate in layers, and the height of the layers is not more than 1 meter; when the layers are stopped, use a medium-frequency vibrating rod to extend from the pouring hole 3 into the steel pipe column 1 for vibration; The artificial mallet is struck to judge whether the concrete is dense according to the sound. The pouring of the same steel pipe column 1 should be carried out continuously, and the intermediate interval time should not exceed the initial setting time of the concrete; when the concrete cannot be supplied in time, the intermittent pumping method should be adopted.

实施例Example

如图1所示:包括钢管柱1侧壁开的浇筑孔3,浇筑孔3作为下层钢管柱的混凝土浇筑泵管的伸进孔。浇筑孔3设在楼层钢梁2顶面标高以上800mm~1200mm,浇筑孔3的高度位置应便于浇筑混凝土。距离浇筑孔3中心线往下设置一个泄水孔4,泄水孔4用于排水和控制混凝土浇筑的标高。具体施工时,在浇筑孔3处内的钢管柱内壁9贴一个厚度为25mm的补强环6,补强环6如图2所示,补强环6上设有灌浆孔8,灌浆孔8的轴线与浇筑孔3的轴线一致。浇筑孔3和泄水孔4均采用数控切割技术进行切割,切割下来的浇筑孔原钢板10(见图3)用于混凝土浇筑完成后对浇筑孔3进行封堵;切割下来的泄水孔原钢板5(见图4)用于混凝土浇筑完成后对泄水孔4进行封堵。封堵时,应对浇筑孔3和浇筑孔原钢板10以及泄水孔4和泄水孔原钢板5进行打磨,将浇筑孔原钢板10和泄水孔原钢板5四周打磨出坡口,然后在坡口内完成四周围焊,焊缝应饱满无气泡。焊缝等级为一级焊缝。补强环6外弧应与钢管柱内壁9弧度相同,确保补强环6外弧与钢管柱内弧紧密贴合。贴合采用三角焊缝四周围焊。As shown in Fig. 1 : it includes the pouring hole 3 opened on the side wall of the steel pipe column 1, and the pouring hole 3 is used as the protruding hole of the concrete pouring pump pipe of the steel pipe column on the lower floor. The pouring hole 3 is set at 800mm-1200mm above the level of the top surface of the floor steel beam 2, and the height of the pouring hole 3 should be convenient for pouring concrete. A drain hole 4 is arranged downward from the center line of the pouring hole 3, and the drain hole 4 is used for draining water and controlling the elevation of concrete pouring. During specific construction, a reinforcing ring 6 with a thickness of 25 mm is pasted on the inner wall 9 of the steel pipe column in the pouring hole 3. The reinforcing ring 6 is shown in Figure 2. The reinforcing ring 6 is provided with a grouting hole 8, and the grouting hole 8 The axis is consistent with the axis of pouring hole 3. Both the pouring hole 3 and the drain hole 4 are cut by numerical control cutting technology, and the cut pouring hole original steel plate 10 (see Figure 3) is used to seal the pouring hole 3 after the concrete pouring is completed; the cut drain hole is originally The steel plate 5 (see FIG. 4 ) is used to block the drain hole 4 after the concrete pouring is completed. When plugging, the pouring hole 3 and the original steel plate 10 of the pouring hole and the drain hole 4 and the original steel plate 5 of the drain hole should be ground, and the original steel plate 10 of the pouring hole and the original steel plate 5 of the drain hole should be polished to form a groove, and then The surrounding welding is completed in the groove, and the weld seam should be full without air bubbles. The weld grade is Class I weld. The outer arc of the reinforcement ring 6 should be the same as the 9 arcs of the inner wall of the steel pipe column to ensure that the outer arc of the reinforcement ring 6 fits closely with the inner arc of the steel pipe column. The fit is welded around the triangle weld.

本发明按以下步骤施工:The present invention constructs according to the following steps:

1、在专业化工厂根据图纸完成钢管柱1上浇筑孔3和泄水孔4的切割;切割下来的浇筑孔原钢板10和泄水孔原钢板5保留备用。并在专业化工厂根据图纸完成补强环6的制作,并将补强环6焊接在浇筑孔3对应位置处的钢管柱内壁9上;1. Complete the cutting of the pouring hole 3 and the drain hole 4 on the steel pipe column 1 according to the drawings in a professional chemical factory; the cut original steel plate 10 for the pouring hole and the original steel plate 5 for the drain hole are reserved for future use. And complete the production of the reinforcing ring 6 according to the drawings in the specialized chemical factory, and weld the reinforcing ring 6 on the inner wall 9 of the steel pipe column at the position corresponding to the pouring hole 3;

2、将钢管柱1首尾相接,完成钢管柱1的安装;同时完成钢管柱1与楼层钢梁的连接;2. Connect the steel pipe column 1 end to end to complete the installation of the steel pipe column 1; at the same time, complete the connection between the steel pipe column 1 and the floor steel beam;

3、在钢管柱1的浇筑孔3外搭设操作平台11;并在操作平台11边缘搭设临边护栏12;3. Set up an operation platform 11 outside the pouring hole 3 of the steel pipe column 1; and set up a border guardrail 12 on the edge of the operation platform 11;

4、利用操作平台11布设竖向泵管17,竖向泵管17采用连接法兰15连接,竖向泵管17通过支架14与楼层钢梁2连接;4. Use the operating platform 11 to lay out the vertical pump pipe 17, the vertical pump pipe 17 is connected with the connecting flange 15, and the vertical pump pipe 17 is connected to the floor steel beam 2 through the bracket 14;

5、拆除位于浇筑孔3外的一段竖向泵管17,并在下一段竖向泵管17顶端连接直角弯泵管16,直角弯泵管16另一端伸入钢管柱1内并经连接法兰15与小弯头13连接;小弯头13的出口端向下弯曲并与钢管柱1的中心线重合;5. Remove a section of vertical pump pipe 17 located outside the pouring hole 3, and connect the right-angled pump pipe 16 at the top of the next vertical pump pipe 17, and the other end of the right-angled pump pipe 16 extends into the steel pipe column 1 and passes through the connecting flange 15 is connected with the small elbow 13; the outlet end of the small elbow 13 is bent downward and coincides with the center line of the steel pipe column 1;

6、在直角弯泵管16底部设置支撑7,支撑7与操作平台11或临边护栏12连接。6. A support 7 is provided at the bottom of the right-angled pump pipe 16, and the support 7 is connected to the operating platform 11 or the side guardrail 12.

7、进行混凝土浇筑;混凝土浇筑采用分层振捣,分层高度不大于1米,分层停歇时间,采用中频振捣棒自浇筑孔3伸进钢管柱1内进行振捣。同时钢管柱1外配合人工木槌敲击,根据声音判断混凝土是否密实。浇筑时应控制好泵车的泵送力度,令混凝土在空腔内垂直下落,利用混凝土下落产生的动能来达到混凝土的自密实。并利用泄水孔4进行控制,浇筑至泄水孔4溢出混凝土浆时,即停止浇筑。下节钢管柱1内的混凝土浇筑成型面距泄水孔4距离不能小于500mm。7. Concrete pouring; Concrete pouring adopts layered vibrating, the layering height is not more than 1 meter, and the layering rest time, the medium frequency vibrating rod is used to extend from the pouring hole 3 into the steel pipe column 1 for vibration. At the same time, the outside of the steel pipe column 1 is knocked with an artificial mallet to judge whether the concrete is dense according to the sound. When pouring, the pumping force of the pump truck should be well controlled, so that the concrete falls vertically in the cavity, and the kinetic energy generated by the falling concrete is used to achieve the self-compacting of the concrete. And utilize weep hole 4 to control, when pouring to weep hole 4 and overflow concrete slurry, promptly stop pouring. The distance between the concrete pouring forming surface in the steel pipe column 1 in the lower section and the drain hole 4 should not be less than 500mm.

8、一层混凝土浇筑完成后,在进行上层后混凝土浇筑前进行浇筑孔原钢板10和泄水孔原钢板5封堵焊接,焊缝等级为一级焊缝。焊接时必须严格控制焊接工序,焊接完成后需要进行探伤检测合格,保证质量。8. After the concrete pouring of the first floor is completed, the original steel plate 10 of the pouring hole and the original steel plate 5 of the drain hole are sealed and welded before the concrete pouring of the upper layer, and the weld grade is a first-class weld. The welding process must be strictly controlled during welding. After the welding is completed, a flaw detection test is required to ensure the quality.

在进行浇筑孔原钢板10和泄水孔原钢板5封堵焊接时,应确保钢管柱内1混凝土不能因焊接受损。同一根钢管柱1的浇筑时应连续进行,中间间隔时间不能超过混凝土的初凝时间。当混凝土不能及时供应时,应采取间歇泵送方式。When sealing and welding the original steel plate 10 of the pouring hole and the original steel plate 5 of the drain hole, it should be ensured that the concrete in the steel pipe column 1 cannot be damaged by welding. The pouring of the same steel pipe column 1 should be carried out continuously, and the interval between them should not exceed the initial setting time of the concrete. When concrete cannot be supplied in time, intermittent pumping should be adopted.

混凝土浇筑过程由下至上进行,重复步骤5~8直至完成整根钢管柱1的浇筑。The concrete pouring process is carried out from bottom to top, and steps 5 to 8 are repeated until the pouring of the entire steel pipe column 1 is completed.

本发明提高了施工安全系数,缩短了施工工期,对节约劳动力和施工成本起到了良好的作用。本发明具有结构简单、施工安全方便、省时省力的特点。The invention improves the construction safety factor, shortens the construction period, and plays a good role in saving labor force and construction cost. The invention has the characteristics of simple structure, safe and convenient construction, time-saving and labor-saving.

Claims (10)

1. a kind of structure of steel pipe column side-wall hole casting concrete, including steel pipe column (1), it is characterised in that: in steel pipe column (1) Side wall is equipped with the pouring hole (3) that can protrude into pump line, and drain hole is equipped on steel pipe column (1) side wall below pouring hole (3) (4).
2. the structure of steel pipe column side-wall hole casting concrete according to claim 1, it is characterised in that: the pouring hole (3) steel pipe column (1) inner wall at is equipped with reinforcing ring (6), and reinforcing ring (6) is equipped with grout hole (8);The center line of reinforcing ring (6) with The center line of pouring hole (3) is overlapped;Reinforcing ring (6) outer diameter is greater than pouring hole (3) aperture, and reinforcing ring (6) aperture is less than pouring hole (3) aperture;The contact surface (18) of reinforcing ring (6) and the radian of inner wall of steel pipe column (9) of steel pipe column (1) are corresponding;Reinforcing ring (6) four Week welds with inner wall of steel pipe column (9).
3. a kind of method of steel pipe column side-wall hole casting concrete;It is characterized by: this method is on steel pipe column (1) side wall It presets pouring hole (3), and drain hole (4) is set on steel pipe column (1) side wall below pouring hole (3);By pump line from pouring It builds hole (3) and protrudes into pouring for the interior completion steel pipe column interior concrete of steel pipe column (1);After the completion of concreting, by pouring hole (3) and Drain hole (4) blocks.
4. the method for steel pipe column side-wall hole casting concrete according to claim 3, it is characterised in that: the pouring hole (3) center line is located at the above 800mm~1200mm of absolute altitude of floor girder steel (2) top surface.
5. the method for steel pipe column side-wall hole casting concrete according to claim 3, it is characterised in that: the pouring hole (3) the floor girder steel (2) at is equipped with operating platform (11);It is equipped with around operating platform (11) and faces side guardrail (12).
6. the method for steel pipe column side-wall hole casting concrete according to claim 3, it is characterised in that: the pump line includes The vertical pump line (17) of one group of head and the tail connection;Vertical pump line (17) is connect through bracket (14) with floor girder steel (2).
7. the method for steel pipe column side-wall hole casting concrete according to claim 6, it is characterised in that: the vertical pump line (17) both ends are equipped with connecting flange (15);One section of vertical pump line (17) being located at pouring hole (3) is removed, by the vertical pump line of lower section (17) top is connect with quarter bend pump line (16) one end;Quarter bend pump line (16) other end protrudes into steel pipe column (1) and through connecting Flange (15) is connect with eyesight elbow (13);The outlet end of eyesight elbow (13) is bent downwardly and is overlapped with the center line of steel pipe column (1).
8. the method for steel pipe column side-wall hole casting concrete according to claim 7, it is characterised in that: the quarter bend pump It manages (16) bottom and is equipped with support (7), support (7) and operating platform (11) or face side guardrail (12) and connect.
9. the method for steel pipe column side-wall hole casting concrete according to claim 3, it is characterised in that: the pouring hole (3) it is cut with drain hole (4) using cutting technique, the pouring hole raw steel plate (10) cut down is poured for concrete Pouring hole (3) is blocked after the completion of building;The drain hole raw steel plate (5) cut down for after the completion of concreting to letting out Water hole (4) is blocked.
10. the method for steel pipe column side-wall hole casting concrete according to claim 3, it is characterised in that: carrying out coagulation It when soil pours, is vibrated using layering, layer height is not more than 1 meter;Layering is when resting, using intermediate frequency vibrating spear from pouring hole (3) It puts in steel pipe column (1) and vibrates;The artificial mallet of steel pipe column (1) fit on simultaneously taps, and judges that concrete is according to sound It is no closely knit;Pouring for same root steel pipe column (1) should be carried out continuously, presetting period of the midfeather time no more than concrete; When concrete cannot be in time for that at once, should take intermittent pumping mode.
CN201910482520.3A 2019-06-04 2019-06-04 A kind of structure and method of steel pipe column side-wall hole casting concrete Pending CN110130648A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910482520.3A CN110130648A (en) 2019-06-04 2019-06-04 A kind of structure and method of steel pipe column side-wall hole casting concrete

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910482520.3A CN110130648A (en) 2019-06-04 2019-06-04 A kind of structure and method of steel pipe column side-wall hole casting concrete

Publications (1)

Publication Number Publication Date
CN110130648A true CN110130648A (en) 2019-08-16

Family

ID=67580247

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910482520.3A Pending CN110130648A (en) 2019-06-04 2019-06-04 A kind of structure and method of steel pipe column side-wall hole casting concrete

Country Status (1)

Country Link
CN (1) CN110130648A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115405047A (en) * 2022-10-12 2022-11-29 中建八局第四建设有限公司 Method for pouring concrete in steel pipe

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10110530A (en) * 1996-10-04 1998-04-28 Nkk Corp Method and apparatus for draining water from steel pipe concrete column
CN203066355U (en) * 2012-12-06 2013-07-17 中建钢构有限公司 Concrete-filled steel tube column and subassembly thereof
CN103510702A (en) * 2013-09-29 2014-01-15 广州建筑股份有限公司 Concrete-filled steel tube column needle type concrete pouring construction method
CN104131704A (en) * 2014-05-16 2014-11-05 中国建筑第四工程局有限公司 Steel pipe column concrete lateral pouring method and steel pipe column structure used in method
CN206071063U (en) * 2016-10-13 2017-04-05 中国建筑一局(集团)有限公司 High-pressure pump pipe jacking and pouring system for post-repair construction of super high-rise building
CN210563437U (en) * 2019-06-04 2020-05-19 中建四局华南建设有限公司 Structure for pouring concrete through opening in side wall of steel pipe column

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10110530A (en) * 1996-10-04 1998-04-28 Nkk Corp Method and apparatus for draining water from steel pipe concrete column
CN203066355U (en) * 2012-12-06 2013-07-17 中建钢构有限公司 Concrete-filled steel tube column and subassembly thereof
CN103510702A (en) * 2013-09-29 2014-01-15 广州建筑股份有限公司 Concrete-filled steel tube column needle type concrete pouring construction method
CN104131704A (en) * 2014-05-16 2014-11-05 中国建筑第四工程局有限公司 Steel pipe column concrete lateral pouring method and steel pipe column structure used in method
CN206071063U (en) * 2016-10-13 2017-04-05 中国建筑一局(集团)有限公司 High-pressure pump pipe jacking and pouring system for post-repair construction of super high-rise building
CN210563437U (en) * 2019-06-04 2020-05-19 中建四局华南建设有限公司 Structure for pouring concrete through opening in side wall of steel pipe column

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115405047A (en) * 2022-10-12 2022-11-29 中建八局第四建设有限公司 Method for pouring concrete in steel pipe

Similar Documents

Publication Publication Date Title
CN208167956U (en) A kind of basement inwall using reverse construction
CN103526929A (en) Super high-rise steel pipe column interior concrete pouring construction method
CN103821280A (en) Construction method for steel tube confined concrete composite columns
CN105804395B (en) Stair continuously poured in one molding construction method based on monoblock type typified form
CN104131704A (en) Steel pipe column concrete lateral pouring method and steel pipe column structure used in method
CN106760502A (en) Shear wall end cylinder construction method
CN101487293A (en) Concrete pouring method for beam-column joints with different strength grades
CN210563437U (en) Structure for pouring concrete through opening in side wall of steel pipe column
CN110017023A (en) Collar tie beam construction method based on tool-type regularization concrete collar tie beam formwork erecting structure
CN106284980A (en) A kind of residential building shear wall structure deformation joint wall form manufacture method
CN103206088B (en) Parts of shear wall structure wall, slab integral pouring construction method
CN107191006B (en) Dismantling and repairing method for refractory concrete layer of diversion trench
CN110130648A (en) A kind of structure and method of steel pipe column side-wall hole casting concrete
CN112878462A (en) Construction method of circular inspection well template
CN106193093B (en) Rim of a cup foundation forms is reinforced and hydraulic pressure construction process for removing
CN109025292A (en) A kind of large-sized concrete funnel formwork erection method
CN203834809U (en) Steel pipe column structure for steel pipe column concrete side pouring method
CN206625553U (en) For pouring the formwork bracing system of high-low bay structure simultaneously
CN206397136U (en) Assembled aluminum template masonry shearwalls reinforced concrete structural column
CN110863953A (en) Circular-shaped CFST combined wind turbine tower structure
CN105064500A (en) Balcony beam slab inner side filling wall body and main body structure integral casting construction method
CN104912209B (en) Bars In Poured Concrete Slab reserved holes of pipes plugging device and processing and plugging construction method
CN107859061A (en) A kind of construction method of box culvert primary concreting
CN108331343A (en) The construction method of Cantilever Beams and aluminum alloy mould plate lap-joint
CN207846202U (en) A kind of double steel cylinder temporary supports for precast beam installation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20200116

Address after: 510700 room 702, building a, room 701, building a, No. 18, science Avenue, Huangpu District, Guangzhou City, Guangdong Province

Applicant after: South China Construction Co.,Ltd. of China Construction Fourth Engineering Bureau

Applicant after: CHINA CONSTRUCTION FOURTH ENGINEERING DIVISION CORP.,LTD.

Address before: 510665 Guangzhou, Guangdong, Guangzhou, Tianhe District, 16 Guangzhou Road, B 4 block.

Applicant before: CHINA CONSTRUCTION FOURTH ENGINEERING DIVISION CORP.,LTD.

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190816