CN110056197A - 一种悬挑三维曲面钢罩棚整体吊装施工方法 - Google Patents

一种悬挑三维曲面钢罩棚整体吊装施工方法 Download PDF

Info

Publication number
CN110056197A
CN110056197A CN201910360245.8A CN201910360245A CN110056197A CN 110056197 A CN110056197 A CN 110056197A CN 201910360245 A CN201910360245 A CN 201910360245A CN 110056197 A CN110056197 A CN 110056197A
Authority
CN
China
Prior art keywords
steel cage
canopy
cage canopy
curved surface
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910360245.8A
Other languages
English (en)
Inventor
路希鑫
王申杰
钱浩
孙亚辉
方义军
汝刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201910360245.8A priority Critical patent/CN110056197A/zh
Publication of CN110056197A publication Critical patent/CN110056197A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks

Abstract

本发明公开了一种悬挑三维曲面钢罩棚整体吊装施工方法,属于建设施工技术领域。本发明包括以下步骤:步骤1.应用BIM技术对钢罩棚整体预拼装;步骤2.计算钢罩棚整体重量,选择吊车、吊具、钢丝绳等;步骤3.基于有限元分析软件对吊装过程受力状态分析;步骤4.钢罩棚整体地面拼装,包括支撑网架、檩条、托架、屋面钢板;步骤5.吊车、吊具、钢丝绳安装就位,试吊,起吊;步骤6.钢罩棚整体就位,支撑点安装、焊接、固定,焊缝检测;步骤7.依据受力分析状态及施工模拟进行逐步卸载、完成。本发明基于BIM技术进行吊装全过程施工模拟,有效悬挑曲面钢罩棚整体吊装过程的安全性和效率,取得较好的社会效益和经济效益。

Description

一种悬挑三维曲面钢罩棚整体吊装施工方法
技术领域
本发明涉及建设施工技术领域,更具体地说,涉及一种悬挑三维曲面钢罩棚整体吊装施工方法。
背景技术
工程建设中体育场看台钢罩棚应用越来越广泛。钢罩棚的施工中,有高空拼装、吊装等施工方法。吊装方法由于其施工工艺流程简单方便,仍然是首选方法。但是由于钢罩棚是悬挑结构,又有三维曲面罩棚等多种形式的存在,其结构不规则,吊装施工中又存在一定的难度,因此,需要解决悬挑三维曲面钢罩棚吊装施工中存在的问题。
发明内容
1.发明要解决的技术问题
针对现有技术存在的缺陷与不足,本发明提供了一种悬挑三维曲面钢罩棚整体吊装施工方法,基于有限元分析悬挑三维曲面结构的吊装过程受力状态,选择合适吊点数量和位置;基于BIM技术进行吊装全过程施工模拟,有效悬挑曲面钢罩棚整体吊装过程的安全性和效率,取得较好的社会效益和经济效益。
2.技术方案
为达到上述目的,本发明提供的技术方案为:
本发明的一种悬挑三维曲面钢罩棚整体吊装施工方法,包括以下步骤:
步骤1.应用BIM技术对钢罩棚整体预拼装,包括支撑网架、檩条、托架、屋面钢板;
步骤2.计算钢罩棚整体重量,选择吊车、吊具、钢丝绳等;
步骤3.基于有限元分析软件对吊装过程受力状态分析,并选择合适的吊点数量和吊点位置进行三维动态施工模拟;
步骤4.钢罩棚整体地面拼装,包括支撑网架、檩条、托架、屋面钢板;
步骤5.吊车、吊具、钢丝绳安装就位,试吊,起吊;
步骤6.钢罩棚整体就位,支撑点安装、焊接、固定,焊缝检测;
步骤7.依据受力分析状态及施工模拟进行逐步卸载、完成。
3.有益效果
采用本发明提供的技术方案,与现有技术相比,具有如下有益效果:
本发明采用BIM技术对钢罩棚进行整体预拼装,基于有限元分析悬挑三维曲面结构的吊装过程受力状态,选择合适吊点数量和位置;基于BIM技术进行吊装全过程施工模拟,有效悬挑曲面钢罩棚整体吊装过程的安全性和效率,取得较好的社会效益和经济效益。
附图说明
图1为本发明的施工流程图。
具体实施方式
下面结合附图和实施例对本发明作进一步的描述:
实施例1
从图1可以看出,本实施例的一种悬挑三维曲面钢罩棚整体吊装施工方法,包括以下步骤:
步骤1.应用BIM技术对钢罩棚整体预拼装,包括支撑网架、檩条、托架、屋面钢板;钢罩棚面积为3000m2,支撑点前部悬挑23m,后部悬挑7m;共一排9个支撑点;网架顶面及屋面板顶面曲面弧度为150°;
步骤2.计算钢罩棚整体重量,选择吊车、吊具、钢丝绳等;钢罩棚总重量为90t,选用400t吊车4台,钢丝绳共12条;
步骤3.基于有限元分析软件对吊装过程受力状态分析,并选择合适的吊点数量和吊点位置进行三维动态施工模拟;每台吊车吊点为3个,呈三角状;
步骤4.钢罩棚整体地面拼装,包括支撑网架、檩条、托架、屋面钢板;
步骤5.吊车、吊具、钢丝绳安装就位,试吊,起吊;钢罩棚整体离地20cm,吊车暂停5分钟;起吊中,每升高5m,暂停5分钟进行标高监测;
步骤6.钢罩棚整体就位,支撑点安装、焊接、固定,焊缝检测;
步骤7.依据受力分析状态及施工模拟进行逐步卸载,卸载按20%、40%、60%、80%和100%计算,完成。
以上示意性的对本发明及其实施方式进行了描述,该描述没有限制性,附图中所示的也只是本发明的实施方式之一,实际的方法并不局限于此。所以,如果本领域的普通技术人员受其启示,在不脱离本发明创造宗旨的情况下,不经创造性的设计出与该技术方案相似的结构方式及实施例,均应属于本发明的保护范围。

Claims (1)

1.一种悬挑三维曲面钢罩棚整体吊装施工方法,其特征在于:包括以下步骤:
步骤1.应用BIM技术对钢罩棚整体预拼装,包括支撑网架、檩条、托架、屋面钢板;
步骤2.计算钢罩棚整体重量,选择吊车、吊具、钢丝绳等;
步骤3.基于有限元分析软件对吊装过程受力状态分析,并选择合适的吊点数量和吊点位置进行三维动态施工模拟;
步骤4.钢罩棚整体地面拼装,包括支撑网架、檩条、托架、屋面钢板;
步骤5.吊车、吊具、钢丝绳安装就位,试吊,起吊;
步骤6.钢罩棚整体就位,支撑点安装、焊接、固定,焊缝检测;
步骤7.依据受力分析状态及施工模拟进行逐步卸载、完成。
CN201910360245.8A 2019-04-30 2019-04-30 一种悬挑三维曲面钢罩棚整体吊装施工方法 Pending CN110056197A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910360245.8A CN110056197A (zh) 2019-04-30 2019-04-30 一种悬挑三维曲面钢罩棚整体吊装施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910360245.8A CN110056197A (zh) 2019-04-30 2019-04-30 一种悬挑三维曲面钢罩棚整体吊装施工方法

Publications (1)

Publication Number Publication Date
CN110056197A true CN110056197A (zh) 2019-07-26

Family

ID=67321805

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910360245.8A Pending CN110056197A (zh) 2019-04-30 2019-04-30 一种悬挑三维曲面钢罩棚整体吊装施工方法

Country Status (1)

Country Link
CN (1) CN110056197A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110295755A (zh) * 2019-06-26 2019-10-01 浙江精工钢结构集团有限公司 一种基于bim技术的空间网格结构翻身脱胎施工方法
CN110950267A (zh) * 2019-11-07 2020-04-03 广西电网有限责任公司桂林供电局 一种变压器的起吊方法
CN111428410A (zh) * 2020-03-25 2020-07-17 中国十七冶集团有限公司 一种基于bim的大跨度网架结构施工方法
CN111980419A (zh) * 2020-08-25 2020-11-24 南通大学 一种钢结构运输通道的安装工艺
CN113235946A (zh) * 2021-06-04 2021-08-10 中国建筑第四工程局有限公司 一种大型场馆钢罩棚高空旋转施工方法
CN113882685A (zh) * 2021-03-30 2022-01-04 中建科工集团有限公司 胎架卸载方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104866659A (zh) * 2015-05-13 2015-08-26 江苏新蓝天钢结构有限公司 基于bim的钢结构整体吊装方法
CN107100309A (zh) * 2017-06-26 2017-08-29 福建省闽南建筑工程有限公司 一种用于整体吊装大型多棱角悬挑桁架的施工方法
CN108532953A (zh) * 2018-05-18 2018-09-14 宝业湖北建工集团有限公司 基于bim的悬挑板施工方法及建筑施工方法
CN108643584A (zh) * 2018-04-02 2018-10-12 中国十七冶集团有限公司 一种钢结构超长悬挑大梁无支撑安装的施工方法
CN109441127A (zh) * 2018-12-05 2019-03-08 中铁二局第三工程有限公司 一种大跨悬挑钢结构虚拟仿真现场安装施工方法

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104866659A (zh) * 2015-05-13 2015-08-26 江苏新蓝天钢结构有限公司 基于bim的钢结构整体吊装方法
CN107100309A (zh) * 2017-06-26 2017-08-29 福建省闽南建筑工程有限公司 一种用于整体吊装大型多棱角悬挑桁架的施工方法
CN108643584A (zh) * 2018-04-02 2018-10-12 中国十七冶集团有限公司 一种钢结构超长悬挑大梁无支撑安装的施工方法
CN108532953A (zh) * 2018-05-18 2018-09-14 宝业湖北建工集团有限公司 基于bim的悬挑板施工方法及建筑施工方法
CN109441127A (zh) * 2018-12-05 2019-03-08 中铁二局第三工程有限公司 一种大跨悬挑钢结构虚拟仿真现场安装施工方法

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110295755A (zh) * 2019-06-26 2019-10-01 浙江精工钢结构集团有限公司 一种基于bim技术的空间网格结构翻身脱胎施工方法
CN110950267A (zh) * 2019-11-07 2020-04-03 广西电网有限责任公司桂林供电局 一种变压器的起吊方法
CN111428410A (zh) * 2020-03-25 2020-07-17 中国十七冶集团有限公司 一种基于bim的大跨度网架结构施工方法
CN111428410B (zh) * 2020-03-25 2023-04-25 中国十七冶集团有限公司 一种基于bim的大跨度网架结构施工方法
CN111980419A (zh) * 2020-08-25 2020-11-24 南通大学 一种钢结构运输通道的安装工艺
CN113882685A (zh) * 2021-03-30 2022-01-04 中建科工集团有限公司 胎架卸载方法
CN113235946A (zh) * 2021-06-04 2021-08-10 中国建筑第四工程局有限公司 一种大型场馆钢罩棚高空旋转施工方法

Similar Documents

Publication Publication Date Title
CN110056197A (zh) 一种悬挑三维曲面钢罩棚整体吊装施工方法
CN207582986U (zh) 一种出屋面组合式玻璃幕墙吊装施工系统
CN105645248B (zh) 一种钢筋笼起吊装置及方法
CN104631810B (zh) 高空移动吊篮系统以及施工方法
CN110027987A (zh) 一种弧形悬挑钢梁吊装施工方法
CN205892588U (zh) 一种吊装设备
CN104925680B (zh) 一种稳定塔吊塔身的方法
CN205777428U (zh) 电梯井自爬升平台
CN108946542A (zh) 一种小炮车及其施工方法
CN106012861B (zh) 波形钢腹板的安装定位装置及该波形钢腹板的施工方法
CN207390874U (zh) 一种移动式辅助物料安装施工装置
CN215457726U (zh) 一种幕墙清洗工具系统
CN116044178A (zh) 一种上方有悬挑结构的大倾角端屏的安装方法
CN207277197U (zh) 一种适用于高墩波形钢腹板悬臂安装的操作平台
CN205023698U (zh) 用于堆高机空箱吊具装配的专用起吊装置
CN208777169U (zh) 一种用于桥梁底面作业的吊篮装置
CN205741935U (zh) 波形钢腹板的安装定位装置
CN107060347A (zh) 一种大跨金属悬挑装饰屋面预制及高空滑移拼装结构
CN208716676U (zh) 电除尘阳极模块吊装设备
CN209957241U (zh) 一种钢吊架
CN105978454B (zh) 安装地面光伏支架及光伏组件用悬挂架装置及使用方法
CN205530877U (zh) 一种用于高层石材幕墙的石材悬挂装置
CN105883580A (zh) 一种轨道吊主梁腹板吊装工艺
CN211292365U (zh) 一种石材挂件组合单元挂装强度测试装置
CN111706060A (zh) 一种钢丝绳斜拉式吊篮装置

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190726