CN109958066A - 钢箱梁顶推施工限位导向装置及限位施工方法 - Google Patents
钢箱梁顶推施工限位导向装置及限位施工方法 Download PDFInfo
- Publication number
- CN109958066A CN109958066A CN201910327037.8A CN201910327037A CN109958066A CN 109958066 A CN109958066 A CN 109958066A CN 201910327037 A CN201910327037 A CN 201910327037A CN 109958066 A CN109958066 A CN 109958066A
- Authority
- CN
- China
- Prior art keywords
- steel box
- box girder
- limit guide
- support frame
- roller
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 73
- 239000010959 steel Substances 0.000 title claims abstract description 73
- 238000010276 construction Methods 0.000 title claims abstract description 46
- 230000007246 mechanism Effects 0.000 claims abstract description 39
- 238000006073 displacement reaction Methods 0.000 claims abstract description 20
- 238000000034 method Methods 0.000 claims description 10
- 238000006243 chemical reaction Methods 0.000 claims description 8
- 230000000712 assembly Effects 0.000 claims description 2
- 238000000429 assembly Methods 0.000 claims description 2
- 238000009434 installation Methods 0.000 description 5
- 239000010720 hydraulic oil Substances 0.000 description 4
- 230000008569 process Effects 0.000 description 3
- 238000005096 rolling process Methods 0.000 description 2
- 230000008602 contraction Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2/00—Bridges characterised by the cross-section of their bearing spanning structure
- E01D2/04—Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/30—Metal
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明提供了一种设计合理且效率高的钢箱梁顶推施工限位导向装置及限位施工方法。一种钢箱梁顶推施工限位导向装置,钢箱梁顶推施工限位导向装置对称设置在钢箱梁两侧,其包括支撑架、横向位移微调机构和一个以上限位导向机构;横向位移微调机构设置在支撑架外侧,用于驱动支撑架沿横梁移动;限位导向机构位于钢箱梁与支撑架支架,每个限位导向机构包括滚筒、滚筒架和两个以上丝杠丝母组件,滚筒设置在滚筒架上,滚筒架通过丝杠丝母组件连接在支撑架上。
Description
技术领域
本发明涉及一种钢箱梁顶推施工限位导向装置及限位施工方法,属于钢结构桥梁施工技术领域。
背景技术
现有钢箱梁安装方法有支架安装、悬臂拼装和顶推安装三种,其中支架安装是指在成桥桥位搭设支架,利用塔吊、汽车吊或浮吊等地面或水上起重设备将钢箱梁逐节吊装就位,此种施工方案简单可靠,钢箱梁就位后无需进行大的调整,适用于桥下场地良好,便于搭设支架的陆地或水上环境,但对于地面条件不允许或跨线有通车需求的工程则不适用;悬臂拼装是指利用可在钢桥面上移动的桥面吊机安装钢箱梁,每节钢箱梁通过运梁车等运输到桥下,由桥面吊机提升就位,焊接加固完毕后桥面吊机前移,安装下一节段,此种施工方案多用于跨度比较大且平曲线较小的的斜拉桥,对于小半径曲线的钢桥施工则不适用;钢箱梁顶推法指的是梁体在桥头逐段拼装,用千斤顶纵向顶推,使梁体通过各墩顶或局部支架的临时滑动支座面就位的施工方法,该方法适用于跨度较大的等截面连续桥,尤其是桥下环境复杂的山谷和有跨线通车需求的工程。
现有技术中顶推施工的限位机构一般采用滑动摩擦形式,增加了钢箱梁纵向的顶推施工阻力,需要配备大推力的顶推油缸,既增加了施工成本有降低的施工效率。
发明内容
本发明要解决的技术问题是提供了一种钢箱梁顶推施工限位导向装置及限位施工方法。
本发明为实现上述目的,通过以下技术方案实现:
一种钢箱梁顶推施工限位导向装置,钢箱梁顶推施工限位导向装置对称设置在钢箱梁两侧,其包括支撑架、横向位移微调机构和一个以上限位导向机构;横向位移微调机构设置在支撑架外侧,用于驱动支撑架沿横梁移动;限位导向机构位于钢箱梁与支撑架支架,每个限位导向机构包括滚筒、滚筒架和两个以上丝杠丝母组件,滚筒设置在滚筒架上,滚筒架通过丝杠丝母组件连接在支撑架上。
所述钢箱梁顶推施工限位导向装置优选方案,横向位移微调机构包括液压油缸和反力座,液压油缸的缸体与反力座连接,液压油缸的缸杆与支撑架连接。
所述钢箱梁顶推施工限位导向装置优选方案,支撑架包括两根斜杆、一根立杆和一根横杆,其中一根斜杆与立杆及横杆构成一个大三角形结构,另外一根斜杆同时连接立杆和横杆将大三角形结构分成两个小三角形结构。
所述钢箱梁顶推施工限位导向装置优选方案,滚筒架包括底板和设置在底板上的两侧板,滚筒通过销轴连接两侧板。
一种利用所述钢箱梁顶推施工限位导向装置进行钢箱梁限位施工的方法,包括以下步骤:
1)安装支架、铺设横梁及纵移轨道;
2)将支撑架组装好并安装限位导向机构后整体安装在横梁上,在横梁上安装横向位移微调机构,通过丝杠丝母组件微调滚筒伸出的距离,以适应不同角度斜腹板的钢箱梁;
3)调节横向位移微调机构,使限位导向机构顺桥向按钢箱梁曲线布置;
4)将预制钢箱梁运输到工地;
5)利用地面起重设备将钢箱梁放置在纵移轨道上;
6)顶推钢箱梁纵移时,滚筒与钢箱梁接触,滚筒转动,从而使钢箱梁始终沿纵移轨道移动,直到将钢箱梁顶推到位。
本发明的优点在于:
1、结构简单、安全可靠:整体为三角架形式,结构简单稳定、安全可靠;
2、施工效率高:限位导向机构导向过程由传统的滑动摩擦改为滚动摩擦,减小了顶推过程的施工阻力,提高了钢箱梁顶推安装的施工效率;
3、经济性好:减轻了支架自重,与传统的限位方案相比节约了经济成本;
4、适应性高:该限位导向装置具备横向位移微调功能,可以适应不同平曲线半径和不同角度斜腹板钢箱梁的顶推施工。
附图说明
附图用来提供对本发明的进一步理解,并且构成说明书的一部分,与本发明的实施例一起用于解释本发明,并不构成对本发明的限制。
图1为本发明横断面图;
图2为本发明局部放大图一;
图3为本发明局部放大图二;
图4为本发明纵向布置图;
其中,1.钢箱梁;2. 支撑架;3.横向位移微调机构;4.限位导向机构;5.纵移轨道;6.底部横梁;7.支架;2-1.斜杆;2-2.立杆;2-3.横杆;2-4.卡槽;3-1.液压油缸;3-2.反力座;4-1.滚筒;4-2.滚筒销轴;4-3.滚筒架;4-4.丝杆;4-5丝杆螺母。
具体实施方式
以下结合附图对本发明的优选实施例进行说明,应当理解,此处所描述的优选实施例仅用于说明和解释本发明,并不用于限定本发明。
参考图1,一种钢箱梁顶推施工限位导向装置,钢箱梁顶推施工限位导向装置对称设置在钢箱梁两侧,其包括支撑架2、横向位移微调机构3和一个以上限位导向机构4。
参考图2,支撑架2包括两根斜杆2-1、一根立杆2-2和一根横杆2-3,其中一根斜杆2-1与立杆2-2及横杆2-3构成一个大三角形结构,另外一根斜杆2-1同时连接立杆2-2和横杆2-3将大三角形结构分成两个小三角形结构。在保持自身结构稳定性的同时提高了侧向刚度,可以有效抵抗钢箱梁1顶推施工中产生的侧向力,在横杆2-3下方设计有卡槽2-4,卡槽2-4可以使支撑架2平稳的沿横梁6滑动。
参考图1及图2,横向位移微调机构3设置在支撑架2外侧,用于驱动支撑架2沿横梁移动;横向位移微调机构3包括液压油缸3-1和反力座3 ,反力座3-2焊接在横梁6上固定不动,液压油缸3-1的缸体与反力座3连接,液压油缸3-1的缸杆与支撑架2连接。通过液压油缸3-1的伸缩带动支撑架2的横向移动,进而起到对支撑架2位移进行微调的作用。
参考图3,限位导向机构4位于钢箱梁与支撑架支架,每个限位导向机构4包括滚筒4-1、滚筒架4-3和两个以上丝杠丝母组件,滚筒架包括底板和设置在底板上的两侧板,滚筒4-1通过销轴4-2连接两侧板,滚筒4-1设置在滚筒架4-3上,滚筒架4-3通过丝杆4-4和丝杆螺母4-5连接在支撑架2上。钢箱梁1向前顶推施工时与滚筒4-1产生滚动摩擦,既减小了顶推过程的阻力又起到了横向限位作用,使钢箱梁始终沿纵移轨道5移动,滚筒销轴4-2安装在滚筒架4-3上,调节丝杆螺母4-5的位置可以微调滚筒4-1的伸出的距离,以适应不同角度斜腹板的钢箱梁1。
一种利用权利要求1至4任一项所述钢箱梁顶推施工限位导向装置进行钢箱梁限位施工的方法,包括以下步骤:
1)安装支架7、铺设横梁6及纵移轨道5;
2)将支撑架2组装好并安装限位导向机构4后整体安装在横梁6上,在横梁6上安装横向位移微调机构3,通过丝杠丝母组件微调滚筒4-1伸出的距离,以适应不同角度斜腹板的钢箱梁1;
3)调节横向位移微调机构3,使限位导向机构顺桥向按钢箱梁1曲线布置;
4)将预制钢箱梁1运输到工地;
5)利用地面起重设备将钢箱梁1放置在纵移轨道5上;
6)顶推钢箱梁1纵移时,滚筒4-1与钢箱梁1接触,滚筒4-1转动,从而使钢箱梁1始终沿纵移轨道5移动,直到将钢箱梁1顶推到位。
最后应说明的是:以上所述仅为本发明的优选实施例而已,并不用于限制本发明,尽管参照前述实施例对本发明进行了详细的说明,对于本领域的技术人员来说,其依然可以对前述各实施例所记载的技术方案进行修改,或者对其中部分技术特征进行等同替换。凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。
Claims (5)
1.一种钢箱梁顶推施工限位导向装置,其特征在于:钢箱梁顶推施工限位导向装置对称设置在钢箱梁两侧,其包括支撑架(2)、横向位移微调机构(3)和一个以上限位导向机构(4);横向位移微调机构(3),设置在支撑架(2)外侧,用于驱动支撑架(2)沿横梁移动;限位导向机构(4)位于钢箱梁与支撑架支架,每个限位导向机构(4)包括滚筒(4-1)、滚筒架(4-3)和两个以上丝杠丝母组件,滚筒(4-1)设置在滚筒架(4-3)上,滚筒架(4-3)通过丝杠丝母组件连接在支撑架(2)上。
2.根据权利要求1所述钢箱梁顶推施工限位导向装置,其特征在于:横向位移微调机构(3)包括液压油缸(3-1)和反力座(3) ,液压油缸(3-1)的缸体与反力座(3)连接,液压油缸(3-1)的缸杆与支撑架(2)连接。
3.根据权利要求1所述钢箱梁顶推施工限位导向装置,其特征在于:支撑架(2)包括两根斜杆(2-1)、一根立杆(2-2)和一根横杆(2-3),其中一根斜杆(2-1)与立杆(2-2)及横杆(2-3)构成一个大三角形结构,另外一根斜杆(2-1)同时连接立杆(2-2)和横杆(2-3)将大三角形结构分成两个小三角形结构。
4.根据权利要求2所述钢箱梁顶推施工限位导向装置,其特征在于:滚筒架包括底板和设置在底板上的两侧板,滚筒(4-1)通过销轴(4-2)连接两侧板。
5.一种利用权利要求1至4任一项所述钢箱梁顶推施工限位导向装置进行钢箱梁顶推施工的方法,其特征在于包括以下步骤:
1)安装支架(7)、铺设横梁(6)及纵移轨道(5);
2)将支撑架(2)组装好并安装限位导向机构(4)后整体安装在横梁(6)上,在横梁(6)上安装横向位移微调机构(3),通过丝杠丝母组件微调滚筒(4-1)伸出的距离,以适应不同角度斜腹板的钢箱梁(1);
3)调节横向位移微调机构(3),使限位导向机构顺桥向按钢箱梁(1)曲线布置;
4)将预制钢箱梁(1)运输到工地;
5)利用地面起重设备将钢箱梁(1)放置在纵移轨道(5)上;
6)顶推钢箱梁(1)纵移时,滚筒(4-1)与钢箱梁(1)接触,滚筒(4-1)转动,从而使钢箱梁(1)始终沿纵移轨道(5)移动,直到将钢箱梁(1)顶推到位。
Priority Applications (2)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910327037.8A CN109958066A (zh) | 2019-04-23 | 2019-04-23 | 钢箱梁顶推施工限位导向装置及限位施工方法 |
| PCT/CN2019/115004 WO2020215651A1 (zh) | 2019-04-23 | 2019-11-01 | 钢箱梁顶推施工限位导向装置及限位施工方法 |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201910327037.8A CN109958066A (zh) | 2019-04-23 | 2019-04-23 | 钢箱梁顶推施工限位导向装置及限位施工方法 |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN109958066A true CN109958066A (zh) | 2019-07-02 |
Family
ID=67026522
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201910327037.8A Pending CN109958066A (zh) | 2019-04-23 | 2019-04-23 | 钢箱梁顶推施工限位导向装置及限位施工方法 |
Country Status (2)
| Country | Link |
|---|---|
| CN (1) | CN109958066A (zh) |
| WO (1) | WO2020215651A1 (zh) |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110424276A (zh) * | 2019-08-30 | 2019-11-08 | 山东省路桥集团有限公司 | 基于bim技术的双曲线钢箱梁双向顶推施工方法 |
| CN111169805A (zh) * | 2019-10-18 | 2020-05-19 | 绍兴市城投建筑工业化制造有限公司 | 一种辅助盖梁堆放的防侧倾装置 |
| WO2020215651A1 (zh) * | 2019-04-23 | 2020-10-29 | 山东省路桥集团有限公司 | 钢箱梁顶推施工限位导向装置及限位施工方法 |
| CN112281671A (zh) * | 2020-11-03 | 2021-01-29 | 龙建路桥股份有限公司 | 一种钢箱梁顶推施工限位导向装置 |
| CN114572829A (zh) * | 2022-03-02 | 2022-06-03 | 振天建设集团有限公司 | 一种钢箱梁吊装与临时墩多点定位辅助装置及辅助方法 |
| CN115506263A (zh) * | 2022-11-02 | 2022-12-23 | 芜湖天达重工有限公司 | 一种钢箱梁顶推施工时导梁的侧向限位装置 |
| CN116163235A (zh) * | 2022-12-21 | 2023-05-26 | 中铁四局集团第五工程有限公司 | 一种大坡度钢箱梁顶推纵向限位装置及限位施工方法 |
Families Citing this family (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN114687292A (zh) * | 2022-04-08 | 2022-07-01 | 中铁大桥局集团第四工程有限公司 | 一种用于陆域桥梁施工的滑移通用支架 |
| CN115821794B (zh) * | 2022-12-12 | 2025-08-05 | 安徽省交通建设股份有限公司 | 一种双钢箱梁交替顶推防偏移施工方法 |
Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE3501075A1 (de) * | 1985-01-15 | 1986-07-17 | Polensky & Zöllner GmbH & Co, 6000 Frankfurt | Verfahren und vorrichtung zum laengsverschieben eines langgestreckten bauwerkes |
| CN201420241Y (zh) * | 2009-05-07 | 2010-03-10 | 中铁四局集团第四工程有限公司 | 钢箱梁动态液压纠偏系统 |
| CN201817775U (zh) * | 2010-10-26 | 2011-05-04 | 湖南中铁五新钢模有限责任公司 | 可纵移式外模组件 |
| CN203498761U (zh) * | 2013-09-16 | 2014-03-26 | 中铁十七局集团第二工程有限公司 | 箱梁顶推用的侧向限位与纠偏装置 |
| CN204418006U (zh) * | 2014-12-31 | 2015-06-24 | 中国铁路总公司 | 限位装置 |
| CN205711778U (zh) * | 2016-06-14 | 2016-11-23 | 郑州铁路工程有限公司 | 一种用于连续梁顶推的侧向限位装置及系统 |
| CN205975376U (zh) * | 2016-08-17 | 2017-02-22 | 广州市第三市政工程有限公司 | 一种箱梁斜腹板组合模板 |
| CN206204799U (zh) * | 2016-08-31 | 2017-05-31 | 中铁十八局集团第五工程有限公司 | 一种用于梁体的顶推纠偏装置 |
| CN207079483U (zh) * | 2017-08-08 | 2018-03-09 | 云南公投建设集团第六工程有限公司 | 可用于大跨度钢箱梁施工的导向及纠偏装置 |
| CN210140772U (zh) * | 2019-04-23 | 2020-03-13 | 山东省路桥集团有限公司 | 钢箱梁顶推施工限位导向装置 |
Family Cites Families (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US7669272B2 (en) * | 2008-01-28 | 2010-03-02 | Powers James M | Method of launching bridge spans in bridge construction |
| CN201428114Y (zh) * | 2009-07-02 | 2010-03-24 | 上海同新机电控制技术有限公司 | 大型钢拱梁、钢箱梁施工用顶推设备 |
| CN207032059U (zh) * | 2017-08-08 | 2018-02-23 | 云南公投建设集团第六工程有限公司 | 可用于大跨度钢箱梁施工的顶推动力装置 |
| CN109958066A (zh) * | 2019-04-23 | 2019-07-02 | 山东省路桥集团有限公司 | 钢箱梁顶推施工限位导向装置及限位施工方法 |
-
2019
- 2019-04-23 CN CN201910327037.8A patent/CN109958066A/zh active Pending
- 2019-11-01 WO PCT/CN2019/115004 patent/WO2020215651A1/zh not_active Ceased
Patent Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE3501075A1 (de) * | 1985-01-15 | 1986-07-17 | Polensky & Zöllner GmbH & Co, 6000 Frankfurt | Verfahren und vorrichtung zum laengsverschieben eines langgestreckten bauwerkes |
| CN201420241Y (zh) * | 2009-05-07 | 2010-03-10 | 中铁四局集团第四工程有限公司 | 钢箱梁动态液压纠偏系统 |
| CN201817775U (zh) * | 2010-10-26 | 2011-05-04 | 湖南中铁五新钢模有限责任公司 | 可纵移式外模组件 |
| CN203498761U (zh) * | 2013-09-16 | 2014-03-26 | 中铁十七局集团第二工程有限公司 | 箱梁顶推用的侧向限位与纠偏装置 |
| CN204418006U (zh) * | 2014-12-31 | 2015-06-24 | 中国铁路总公司 | 限位装置 |
| CN205711778U (zh) * | 2016-06-14 | 2016-11-23 | 郑州铁路工程有限公司 | 一种用于连续梁顶推的侧向限位装置及系统 |
| CN205975376U (zh) * | 2016-08-17 | 2017-02-22 | 广州市第三市政工程有限公司 | 一种箱梁斜腹板组合模板 |
| CN206204799U (zh) * | 2016-08-31 | 2017-05-31 | 中铁十八局集团第五工程有限公司 | 一种用于梁体的顶推纠偏装置 |
| CN207079483U (zh) * | 2017-08-08 | 2018-03-09 | 云南公投建设集团第六工程有限公司 | 可用于大跨度钢箱梁施工的导向及纠偏装置 |
| CN210140772U (zh) * | 2019-04-23 | 2020-03-13 | 山东省路桥集团有限公司 | 钢箱梁顶推施工限位导向装置 |
Cited By (8)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| WO2020215651A1 (zh) * | 2019-04-23 | 2020-10-29 | 山东省路桥集团有限公司 | 钢箱梁顶推施工限位导向装置及限位施工方法 |
| CN110424276A (zh) * | 2019-08-30 | 2019-11-08 | 山东省路桥集团有限公司 | 基于bim技术的双曲线钢箱梁双向顶推施工方法 |
| CN111169805A (zh) * | 2019-10-18 | 2020-05-19 | 绍兴市城投建筑工业化制造有限公司 | 一种辅助盖梁堆放的防侧倾装置 |
| CN112281671A (zh) * | 2020-11-03 | 2021-01-29 | 龙建路桥股份有限公司 | 一种钢箱梁顶推施工限位导向装置 |
| CN114572829A (zh) * | 2022-03-02 | 2022-06-03 | 振天建设集团有限公司 | 一种钢箱梁吊装与临时墩多点定位辅助装置及辅助方法 |
| CN115506263A (zh) * | 2022-11-02 | 2022-12-23 | 芜湖天达重工有限公司 | 一种钢箱梁顶推施工时导梁的侧向限位装置 |
| CN115506263B (zh) * | 2022-11-02 | 2024-06-21 | 芜湖天达重工有限公司 | 一种钢箱梁顶推施工时导梁的侧向限位装置 |
| CN116163235A (zh) * | 2022-12-21 | 2023-05-26 | 中铁四局集团第五工程有限公司 | 一种大坡度钢箱梁顶推纵向限位装置及限位施工方法 |
Also Published As
| Publication number | Publication date |
|---|---|
| WO2020215651A1 (zh) | 2020-10-29 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN109958066A (zh) | 钢箱梁顶推施工限位导向装置及限位施工方法 | |
| JP5179804B2 (ja) | 移動吊支保工 | |
| CN106400701B (zh) | 一种单主梁低位平衡悬臂拼装架桥机 | |
| CN109252452A (zh) | 一种架桥机 | |
| CN106917360A (zh) | 抬腿式架板机及其架板方法 | |
| CN219793684U (zh) | 一种长距离顶推钢箱梁跨越既有公路落梁导向装置 | |
| CN113123238B (zh) | 一种变宽段钢桁梁横移架设方法 | |
| CN218757041U (zh) | 一种钢箱梁顶推施工限位导向装置 | |
| CN113120771A (zh) | 适用于复合截面节段梁桥后装挑臂的双侧同步吊装设备及施工方法 | |
| CN115341482B (zh) | 一种单边变宽不平衡重悬臂箱梁挂篮及其施工方法 | |
| CN210140772U (zh) | 钢箱梁顶推施工限位导向装置 | |
| CN113774813A (zh) | 便于安装大节段钢桁架箱梁的牵引纠偏设备 | |
| CN112144401B (zh) | 一种基于曲线轨迹和大纵坡环境下的架桥机过跨方法 | |
| CN112211112A (zh) | 一种在既有桥梁上采用双导梁架桥机的钢箱梁安装方法 | |
| CN219218724U (zh) | 一种用于组合梁斜拉桥的主梁吊铺一体机 | |
| CN107142850A (zh) | 跨既有铁路大吨位连续梁单点顶推过轨施工方法 | |
| CN115748479A (zh) | 一种双跨型架桥机及其桥梁架设施工方法 | |
| CN215558503U (zh) | 适用于复合截面节段梁桥后装挑臂的双侧同步吊装设备 | |
| CN215801120U (zh) | 中小跨径梁桥施工加固平台 | |
| CN206438420U (zh) | 固定式非对称桥梁悬臂拼装设备 | |
| CN110258359B (zh) | 通过吊推支架施工的变高度钢梁施工方法 | |
| CN115323931A (zh) | 一种递进与退行式拼装钢箱系杆拱桥的施工方法及系统 | |
| CN108677732B (zh) | 适用于变截面梁段的辅助移动模架主梁悬吊后退施工方法 | |
| CN114476962A (zh) | 一种基于桥面吊机的钢混组合梁架设系统 | |
| CN114277688A (zh) | 架桥机 |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190702 |