CN109914266A - A kind of Large Steel pipeline overhead lifting vertical shift and promote construction method of installation - Google Patents

A kind of Large Steel pipeline overhead lifting vertical shift and promote construction method of installation Download PDF

Info

Publication number
CN109914266A
CN109914266A CN201910309553.8A CN201910309553A CN109914266A CN 109914266 A CN109914266 A CN 109914266A CN 201910309553 A CN201910309553 A CN 201910309553A CN 109914266 A CN109914266 A CN 109914266A
Authority
CN
China
Prior art keywords
main
vertical shift
arch section
section
main arch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910309553.8A
Other languages
Chinese (zh)
Other versions
CN109914266B (en
Inventor
唐剑
汪泉庆
周彦文
喻明灯
刘杜宏
高佳峰
龚鹏鑫
孙鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and Bridge International Co Ltd
Road and Bridge East China Engineering Co Ltd
Original Assignee
Road and Bridge International Co Ltd
Road and Bridge East China Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Road and Bridge International Co Ltd, Road and Bridge East China Engineering Co Ltd filed Critical Road and Bridge International Co Ltd
Priority to CN201910309553.8A priority Critical patent/CN109914266B/en
Publication of CN109914266A publication Critical patent/CN109914266A/en
Application granted granted Critical
Publication of CN109914266B publication Critical patent/CN109914266B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The present invention provides a kind of Large Steel pipeline overhead lifting entirety vertical shift and lifting construction method, and entire tubular arch is divided into the skewback section of middle part main arch section and both ends, and main arch section weight is limited to the maximum load-carrying capacity no more than main bridge girder steel by when division;The assembly of main arch section is completed on main bridge approach bridge, in the construction of main Surveillance of Continuous Beam, sets up the promotion pylon for promoting main arch section respectively at main bridge both ends, and after the completion of the closure of main Surveillance of Continuous Beam, main arch section vertical shift to main span is designed into stable and continuous lifting position;Two skewback sections are installed at tubular arch design skewback position both ends, then main arch section is promoted to design installation site using promotion pylon, and is connect with two skewback sections, completes tubular arch installation.The present invention not acceptor's bridge girder steel load-bearing capacity and vertical shift section height limitation, greatly expand the scope of application of traditional vertical shift method.

Description

A kind of Large Steel pipeline overhead lifting vertical shift and promote construction method of installation
Technical field
The invention belongs to science of bridge building fields, are related in long-span continuous beam arch bridge " first beam rear arch method " installation steel arch A kind of construction method, specifically synchronize that carry out steel arch in dystopy assembled in Construction of continuous beam, after Construction of continuous beam is completed, Using vertical shift trolley vertical shift steel arch, is then promoted using lifting system and adjusted design installation site is joined the two sections of a bridge, etc.
Background technique
Elder generation's common method of beam rear arch method construction steel pipe arch bridge has following several at present: the first is that bracket is in situ assembled Method, the method heavy workload, operating efficiency is low, and construction speed is slow, is only applicable to construction span and the lesser arch bridge of height;Second Kind is vertical transfer method, its temporary project amount is big, and system transform is complicated, and control difficulty is big, and construction speed is slow, is suitable for construction span With the biggish arch bridge of height;The third is whole vertical shift method, and assembled main arch, has constructed in arch bridge main span beam body on end bay bridge floor Whole vertical shift main arch has Construction control difficulty low to installation site, the method after finishing, and parallel construction is not take up critical circuits, construction The obvious advantage of short time limit, but main arch height and weight are had certain limitations, main arch self weight is no more than vertical shift by beam body Maximum load-carrying capacity, main arch cannot be excessively high, otherwise will cause the excessive reduction lateral stability coefficient of lateral front face area, therefore although Have many advantages, such as, but applicable elements are limited.
Summary of the invention
The purpose of the present invention is improving to above-mentioned whole vertical shift method, using the scheme of " vertical shift+promotion ", entirety is overcome Vertical shift method limits main arch height and self weight, to improve the applicability of this method.
Technical scheme is as follows:
A kind of Large Steel pipeline overhead lifting vertical shift and promote construction method of installation, it is characterised in that:
(1) entire tubular arch is divided into the skewback section of middle part main arch section and both ends, is limited main arch section weight when division For the maximum load-carrying capacity no more than main bridge girder steel;
(2) assembled main arch section: main arch section assembling support is set up on main bridge approach bridge, the vertical shift of main arch section both ends arch springing is installed Trolley utilizes large-scale assembling hoist main arch section;After the completion of main arch section is assembled, the interim prestressing force system at installation connection main arch section both ends Bar forms tie-rod arch structure, then removes steel-pipe assembly bracket;
(3) it sets up promotion pylon: when main Surveillance of Continuous Beam is constructed, is set up respectively at main bridge both ends for promoting main arch section Promotion pylon, tower top install hydraulic synchronization jack lifting system;
(4) after the completion of the closure of main Surveillance of Continuous Beam, installation vertical shift track and debugging vertical shift jack main arch section vertical shift: are laid with Main arch section vertical shift to main span is designed lifting position to stable and continuous by system;
(5) two skewback sections are installed at tubular arch design skewback position both ends, then utilize the hydraulic company for promoting tower top Continuous synchronous jack system promotes main arch section to design installation site, after accurate measurement adjustment, at a temperature of closure with two skewback sections Tubular arch installation is completed in connection.
It is that entire tubular arch is along the bridge moved to master along bridge using track vertical shift trolley that conventional steel pipe, which encircles vertical shift method, Encircle installation site, due to not having adjustment mechanism, tubular arch not can be carried out transversal line adjustment and elevation adjustment after vertical shift in place, in place Required precision is high, and difficulty of construction is big, and tubular arch must cause center of gravity height, lateral windage to design mounting height shift-in row vertical shift Power is big, lateral stability is poor, thus using limited.
The present invention increases on the basis of conventional steel encircles vertical shift method and promotes tower adjustment mechanism, carried out following optimization:
1, increase vertical shift section safety and stability: invention increases after whole lifting means, vertical shift can be reduced The height of section tubular arch reduces lateral wind resistance with the height that lowers the center of gravity, can significantly improve safety during vertical shift and Stability.
2, reduce difficulty of construction: invention increases after whole hoist links, the flexibility that can use lifting means is hung Suo Jinhang longitudinally, laterally with the adjusting of height, can also adjust arching degree using interim stretch tie-bar, it will be apparent that reduce main arch and close Dragon docking difficulty.
3, reduce the limitation of passability: the present invention can flexibly choose vertical shift segment length according to load carrying capacity of bridge, indulge The skewback section for moving section two sides uses bridge floor assembly method matching operation, reduces the limitation to large-scale steel arch bridge vertical shift.
4, shorten the construction period: using the present invention, main arch assembly synchronous can be carried out with beams of concrete construction, in concrete Beam carries out main arch vertical shift construction after reaching intensity, is not take up duration critical circuits, can significantly shorten the construction period.
In a concrete application embodiment of the invention, successfully solves the technology of main bridge 220m Large Steel pipeline overhead lifting installation Problem creates good duration and economic benefit, provides good reference function for the construction of same type large bridge.
Detailed description of the invention
Fig. 1 is the assembled status diagram of main arch section;
Fig. 2 is status diagram when main arch section starts vertical shift;
Fig. 3 is the status diagram in main arch section vertical shift to main bridge;
Fig. 4 be the vertical shift of main arch section in place, the status diagram that is installed of skewback section;
Fig. 5 is the status diagram for promoting the connection of main arch Duan Bingyu skewback section;
Fig. 6 is the status diagram after tubular arch is installed.
Specific embodiment
Below in conjunction with attached drawing, description of specific embodiments of the present invention.
It (1) is the skewback section of middle part main arch section and both ends by entire tubular arch design partition before the present invention starts construction, it is main Encircle section using end of the bridge assembly, the construction method of vertical shift in place.Main arch section weight is limited to when tubular arch divides to be no more than main bridge The maximum load-carrying capacity of girder steel;When in view of vertical shift windage to steel pipe for the influence of section, except being carried according to the maximum of master bridge body Ability determines outside main arch section, and the height of main arch section can be also determined according to lateral wind load.During avoiding excessive height from leading to vertical shift Structural instability.
(2) as shown in Figure 1, setting up main arch section assembling support 2 on main bridge approach bridge 1, installation main arch section both ends arch springing is indulged Moving stage vehicle 3, using large-scale assembling hoist main arch section 4, the assembling method of 4 assembling method of main arch section and common vertical shift method tubular arch It is identical.After the completion of 4 assembly of main arch section, the interim prestressed tie bar 5 at installation connection main arch section both ends forms tie-rod arch structure, so Steel-pipe assembly bracket 2 is removed afterwards.
(3) it sets up promotion pylon: when main Surveillance of Continuous Beam is constructed, is set up respectively at main bridge both ends for promoting main arch section Promotion pylon 6, tower top install hydraulic synchronization jack lifting system;Promote the structure such as institute in Fig. 3, Fig. 4, Fig. 5 of pylon 6 Show.
(4) as shown in Figure 2, Figure 3, Figure 4, it after the completion of main Surveillance of Continuous Beam joins the two sections of a bridge, etc, is laid with installation vertical shift track and debugging is vertical Jack system is moved, 4 vertical shift of main arch section to main span is designed into stable and continuous lifting position;The vertical shift method of main arch section and common The tubular arch vertical shift method of vertical shift method is identical.
(5) as shown in figure 4, two skewback sections 9 are installed in two skewback of tubular arch, 8 position on main bridge 7;As shown in figure 5, skewback section After 9 are installed, main arch section 4 is promoted to design installation using the hydraulic continuous synchronous jack system for promoting 6 top of pylon Position is connect at a temperature of closure with two skewback sections 9 after accurate measurement adjustment, completes the tubular arch installation of arch bridge.
As shown in fig. 6, after tubular arch is installed, removes and promote pylon, continues construction and complete that entire main bridge 7 is subsequent applies Work.

Claims (2)

1. a kind of Large Steel pipeline overhead lifting vertical shift and promotion construction method of installation, it is characterised in that:
(1) entire tubular arch is divided into the skewback section of middle part main arch section and both ends, main arch section weight is limited to not by when division More than the maximum load-carrying capacity of main bridge girder steel;
(2) assembled main arch section: main arch section assembling support is set up on main bridge approach bridge, the vertical shift platform of main arch section both ends arch springing is installed Vehicle utilizes large-scale assembling hoist main arch section;After the completion of main arch section is assembled, the interim prestressing force system at installation connection main arch section both ends Bar forms tie-rod arch structure, then removes steel-pipe assembly bracket;
(3) it sets up promotion pylon: when main Surveillance of Continuous Beam is constructed, is set up respectively at main bridge both ends for promoting mentioning for main arch section Pylon is risen, hydraulic synchronization jack lifting system is installed in tower top;
(4) after the completion of the closure of main Surveillance of Continuous Beam, installation vertical shift track and debugging vertical shift jack system main arch section vertical shift: are laid with Main arch section vertical shift to main span is designed lifting position to stable and continuous by system;
(5) two skewback sections are installed at tubular arch design skewback position both ends, it is then same using the hydraulic continuous for promoting tower top Jack system is walked to connect main arch section promotion to design installation site after accurate measurement adjustment with two skewback sections at a temperature of closure, Complete tubular arch installation.
2. Large Steel pipeline overhead lifting entirety vertical shift according to claim 1 and lifting construction method, it is characterised in that: divide steel pipe When encircleing main arch section, in addition to determining main arch section according to the maximum load-carrying capacity of master bridge body, main arch section is determined also according to lateral wind load Height.
CN201910309553.8A 2019-04-17 2019-04-17 Construction method for longitudinally moving and lifting installation of large steel pipe arch Active CN109914266B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910309553.8A CN109914266B (en) 2019-04-17 2019-04-17 Construction method for longitudinally moving and lifting installation of large steel pipe arch

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910309553.8A CN109914266B (en) 2019-04-17 2019-04-17 Construction method for longitudinally moving and lifting installation of large steel pipe arch

Publications (2)

Publication Number Publication Date
CN109914266A true CN109914266A (en) 2019-06-21
CN109914266B CN109914266B (en) 2020-07-10

Family

ID=66977541

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910309553.8A Active CN109914266B (en) 2019-04-17 2019-04-17 Construction method for longitudinally moving and lifting installation of large steel pipe arch

Country Status (1)

Country Link
CN (1) CN109914266B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110616635A (en) * 2019-08-12 2019-12-27 中交二航局第二工程有限公司 Closure structure and lowering dislocation closure method of hybrid beam rigid frame bridge under strong surge condition
CN110616636A (en) * 2019-08-12 2019-12-27 中交二航局第二工程有限公司 Closure structure of hybrid beam rigid frame bridge under strong surge condition and method for lifting staggered closure
CN110777667A (en) * 2019-11-14 2020-02-11 中铁八局集团有限公司 Hoisting method for preventing deformation of steel pipe arch
CN112281685A (en) * 2020-10-23 2021-01-29 广州文船重工有限公司 Lifting construction method of steel arch structure
CN112359730A (en) * 2020-10-26 2021-02-12 中铁三局集团有限公司 Steel pipe arch installation method
CN114319117A (en) * 2021-12-24 2022-04-12 江苏沪宁钢机股份有限公司 A sliding lift method for bridge steel arches
WO2022099548A1 (en) * 2020-11-12 2022-05-19 China Railway No.3 Engineering Group Co.Ltd Method for installing steel tube arches
CN115613475A (en) * 2022-12-05 2023-01-17 安徽省公路桥梁工程有限公司 A construction method for hoisting arch ribs of integral long-span steel arch bridges in expressway engineering

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100138121A (en) * 2009-06-24 2010-12-31 (주)청석엔지니어링 Mobile temporary facility for construction of composite composite arch structures
CN102367650A (en) * 2011-08-05 2012-03-07 中铁一局集团厦门建设工程有限公司 Construction method of steel pipe arch bridge
CN103255726A (en) * 2013-05-28 2013-08-21 中铁上海设计院集团有限公司 Construction method for continuous beam and arch combination bridge
CN103437296A (en) * 2013-08-28 2013-12-11 山东中宏路桥建设有限公司 Steel tube arch bridge towerless buckling three-section type double-rib folding hoisting construction method
CN104631303A (en) * 2015-02-10 2015-05-20 福建省交通规划设计院 Single-rib-arch reinforced V-shaped supporting rigid-frame-continuous beam bridge and construction method thereof
CN107178042A (en) * 2017-05-31 2017-09-19 中国二十冶集团有限公司 A kind of construction method of large span inverted-triangular CFST Arch Bridge steel arch
CN207919363U (en) * 2017-12-21 2018-09-28 中铁广州工程局集团有限公司 A kind of Filled Steel Tubular Arch Bridge low level assembly lifting system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20100138121A (en) * 2009-06-24 2010-12-31 (주)청석엔지니어링 Mobile temporary facility for construction of composite composite arch structures
CN102367650A (en) * 2011-08-05 2012-03-07 中铁一局集团厦门建设工程有限公司 Construction method of steel pipe arch bridge
CN103255726A (en) * 2013-05-28 2013-08-21 中铁上海设计院集团有限公司 Construction method for continuous beam and arch combination bridge
CN103437296A (en) * 2013-08-28 2013-12-11 山东中宏路桥建设有限公司 Steel tube arch bridge towerless buckling three-section type double-rib folding hoisting construction method
CN104631303A (en) * 2015-02-10 2015-05-20 福建省交通规划设计院 Single-rib-arch reinforced V-shaped supporting rigid-frame-continuous beam bridge and construction method thereof
CN107178042A (en) * 2017-05-31 2017-09-19 中国二十冶集团有限公司 A kind of construction method of large span inverted-triangular CFST Arch Bridge steel arch
CN207919363U (en) * 2017-12-21 2018-09-28 中铁广州工程局集团有限公司 A kind of Filled Steel Tubular Arch Bridge low level assembly lifting system

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110616635A (en) * 2019-08-12 2019-12-27 中交二航局第二工程有限公司 Closure structure and lowering dislocation closure method of hybrid beam rigid frame bridge under strong surge condition
CN110616636A (en) * 2019-08-12 2019-12-27 中交二航局第二工程有限公司 Closure structure of hybrid beam rigid frame bridge under strong surge condition and method for lifting staggered closure
CN110616636B (en) * 2019-08-12 2020-12-25 中交二航局第二工程有限公司 Closure structure of hybrid beam rigid frame bridge under strong surge condition and method for lifting staggered closure
CN110616635B (en) * 2019-08-12 2020-12-25 中交二航局第二工程有限公司 Closure structure and lowering dislocation closure method of hybrid beam rigid frame bridge under strong surge condition
CN110777667A (en) * 2019-11-14 2020-02-11 中铁八局集团有限公司 Hoisting method for preventing deformation of steel pipe arch
CN112281685A (en) * 2020-10-23 2021-01-29 广州文船重工有限公司 Lifting construction method of steel arch structure
CN112359730A (en) * 2020-10-26 2021-02-12 中铁三局集团有限公司 Steel pipe arch installation method
WO2022099548A1 (en) * 2020-11-12 2022-05-19 China Railway No.3 Engineering Group Co.Ltd Method for installing steel tube arches
US11655600B2 (en) 2020-11-12 2023-05-23 China Railway No.3 Engineering Group Co.Ltd Method for installing steel tube arches
CN114319117A (en) * 2021-12-24 2022-04-12 江苏沪宁钢机股份有限公司 A sliding lift method for bridge steel arches
CN115613475A (en) * 2022-12-05 2023-01-17 安徽省公路桥梁工程有限公司 A construction method for hoisting arch ribs of integral long-span steel arch bridges in expressway engineering

Also Published As

Publication number Publication date
CN109914266B (en) 2020-07-10

Similar Documents

Publication Publication Date Title
CN109914266A (en) A kind of Large Steel pipeline overhead lifting vertical shift and promote construction method of installation
CN101831874B (en) Multi-point synchronous jacking construction method for porous long-span continuous steel truss girder
CN208815424U (en) A kind of bridge descending hanging basket
CN103243658B (en) The spelling method of cable stayed bridge dragging suspension basket
CN103774856B (en) A kind of gliding construction method of different shape heavy type girder steel of large span on Super High roofing
CN105421249A (en) Novel dragging- hoisting combined type hanging basket structure and construction method
CN114277673B (en) Large-span large-inclination-angle basket type steel girder and arch segment assembling method
CN104328734A (en) Multi-connection and multi-span continuous steel truss girder bridge and construction method thereof
CN105507165A (en) Hanging basket for corrugated steel web construction and construction process
CN103938552A (en) Self-balancing cantilevering construction method for large-span steel truss arch bridge and main pier limiting supports
CN103882812A (en) Construction method for midspan main beams of cable-stayed bridge
CN109056496A (en) A kind of super-span steel truss continuous bridge having initial curvature and construction method
CN203393639U (en) Diamond self-anchored hanging basket for road and bridge construction
CN110468734B (en) Steel arch rib pushing system and steel arch rib pushing construction method
CN212077660U (en) Large-span wide width bridge girder rhombus hanging basket construction structure
CN201024677Y (en) Super high sliding assembly jig
KR100928063B1 (en) Self-launching movable formwork
LU502338B1 (en) Suspended bridge deck of through type arch bridge reinforced by stiffening longitudinal beam of trussed steel structure and construction method thereof
CN207987749U (en) Ride cable-styled erection crane
CN107761575B (en) Hanging basket and bottom basket system for extra-wide box beam
CN110820566A (en) Corrugated steel web part bearing type hanging basket suspension casting construction method
CN102322024B (en) Construction method of staggered installation of hanging baskets in continuous beam cantilever construction
CN205348008U (en) Basket is hung in construction of wave form rigid web
CN219195679U (en) Single main truss front pivot cradle initial beam section running gear of cable-stayed bridge
CN110820567A (en) Bearing type hanging basket for PC box girder part with corrugated steel web plate

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant