CN109886644A CN201910084997.6A CN201910084997A CN109886644A CN 109886644 A CN109886644 A CN 109886644A CN 201910084997 A CN201910084997 A CN 201910084997A CN 109886644 A CN109886644 A CN 109886644A
Authority
CN
China
Prior art keywords
chart
project
plate
module
bim
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910084997.6A
Other languages
Chinese (zh)
Inventor
施海斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Hope Construction Technology Co Ltd
Original Assignee
Hangzhou Hope Construction Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Hope Construction Technology Co Ltd filed Critical Hangzhou Hope Construction Technology Co Ltd
Priority to CN201910084997.6A priority Critical patent/CN109886644A/en
Publication of CN109886644A publication Critical patent/CN109886644A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of, and the engineering project based on BIM commands managing and control system, including the project drawing board based on BIM, the project drawing board includes project information plate, bid section accounting chart plate, monthly completion chart plate, single payment chart plate, BIM model display plate, quality problems chart plate, personal management chart plate, security risk chart plate, drawing change diagram board block, project Dynamically Announce plate, Project Cost chart plate, trend prediction chart module, vivid progress chart module and overall objective chart module;It further include a data recording module.The present invention carries out classification display and typing by combining project management techniques with BIM technology come Various types of data information such as engineering information, project progress, project quality and BIM models to project, the efficiency of management for increasing substantially engineering project realizes the movable coordinating and unifying of project management and Efficient Operation.

Description

Engineering project based on BIM commands managing and control system
Technical field
The present invention relates to engineering management field, in particular to a kind of engineering project based on BIM commands managing and control system.
Background technique
The management of engineering project is a complexity, arduous system engineering, is related to progress, quality, investment, contract, people Various work such as member, risk, Drawings and documents, numerous participating departments and unit, so that operational difficulties that are common and coordinating, A large amount of information needs effective management, and especially domestic three universal side engineerings increase the difficulty of engineering management.With interconnection The development of network technology and wireless communication technique, modern society stepped into the information age, traditional project management system, Seem more and more painstaking, has needed to find new Method and kit for.The full name in English of architecture information model (BIM) is Building Information Modeling is a complete information model, can be by engineering project in Life cycle In each different phase engineering information, process and resources integration in a model, easily used by each participant of engineering. By real information possessed by 3-dimensional digital technical modelling building, provided for engineering design and construction mutually coordinated, internal Consistent information model makes the model reach the integration of design and construction, and each profession cooperates, to reduce engineering production Cost ensures that engineering presses matter completion on time.BIM technology can be applied to each ranks such as engineering project prospecting, design, construction, O&M Section is realized data sharing of the building each participant of full lifetime on the basis of same multidimensional Building Information Model, is passed through for industrial chain Logical, industrialization is built and booming architectural creation provides technical guarantee;It supports to engineering-environment, economy, quality, safety etc. Analysis checks, provides foundation for the scheme optimization and science decision of project overall process;Each profession is supported to cooperate, project Virtual construction and fine-grained management create conditions for the upgrading synergy of construction industry, energy conservation and environmental protection.At present in the construction of building operation In the process, due to not making full use of information technology, BIM technology, traditional Project design management system is relied solely on, has been shown It is more and more painstaking to obtain, and effective, comprehensively can not carry out typing acquisition to the construction information in construction project.
Summary of the invention
The object of the present invention is to provide a kind of, and the engineering project based on BIM commands managing and control system.The present invention is by by item It is each that mesh administrative skill combines the engineering information to project, project progress, project quality and BIM model etc. with BIM technology Class data information carries out classification display and typing, increases substantially the efficiency of management of engineering project, realizes project management The movable coordinating and unifying and Efficient Operation.
Technical solution of the present invention: a kind of engineering project commander's managing and control system based on BIM, including the project based on BIM Drawing board, the project drawing board include project information plate, bid section accounting chart plate, monthly completion chart plate, Dan Dongzhi Pay chart plate, BIM model display plate, quality problems chart plate, personal management chart plate, security risk diagram board Block, drawing change diagram board block, project Dynamically Announce plate, Project Cost chart plate, trend prediction chart module, image into Spend chart module and overall objective chart module;
The project information plate is for showing project profile information;
The bid section accounting chart plate is for showing the chart containing bid section title, bid section contract price and bid section accounting Information;
The monthly completion chart plate is for showing the figure containing construction time information, planned cost and actual cost Table information;
For showing projects month, this month has paid believes the single payment chart plate with the chart of contract price Breath;
The BIM model display plate is for showing project BIM model;
The quality problems chart plate with display the chart-information containing defective in quality type and quantity;
The personal management chart plate is used to show the figure of the newly-increased number of each bid section, distancing number and current persons count Table information;
The security risk chart plate is for showing security risk type, editing safety hidden danger entry and whole safety Hidden danger changes the chart-information of entry;
The drawing change diagram board block contains relevant unit for display, proposition problem, rectification problem, goes out figure again The practicable chart-information with scene;
The project Dynamically Announce plate is for showing project multidate information;
The Project Cost chart plate is used to show the chart of the title containing projects and operating expenses;
The trend prediction chart plate is used to show the chart-information in construction month and investment amount;
The vivid progress diagram board block is used to show the texts and pictures information of whole bid section progress and each bid section progress;
The overall objective chart is for showing total construction period, overall floorage, overall investment and placement amount chart letter Breath;
It further include a data recording module, data inputting module includes project information module, bid section setup module, monthly Complete module, single payment module, project BIM model module, quality problems module, personal management module, security risk artwork Block, drawing change module, project dynamic module;Project Cost plate, trend prediction module and vivid progress module;
The project information module includes project brief information, is shown in project information plate;
The bid section setup module includes bid section title, bid section contract price and bid section accounting, and bid section accounting is generated and is schemed Sheet form is shown in bid section accounting chart plate;
The monthly completion module includes construction time information, planned cost and actual cost, with construction time information For abscissa, using planned cost and actual cost as ordinate, generate monthly completion chart, be shown in monthly completion chart plate In;
The single payment module includes building, of that month payment and contract price, using Lou Dong as abscissa, to work as monthly expenses It pays and contract price is as ordinate, generate single payment chart, be shown in single month payment diagram board block;
Project BIM model module establishes BIM buildings model based on BIM, and project BIM model module is shown in BIM mould Type is shown in plate;
The quality problems module includes quality problems type, edits issue entry and has rectified and improved issue entry, generates Rectification rate accounting chart, is shown in quality problems chart plate;
The personal management module includes the newly-increased number, distancing number and current persons count of each bid section, generates personnel's pipe Chart is managed, is shown in personal management chart plate;
The security risk module includes security risk type, security risk entry and whole security risk changes entry, Security risk chart and rectification rate percentage chart are generated, is shown in security risk chart plate;
The drawing change module includes relevant unit, proposition problem, rectification problem, figure and scene are implemented out again, It generates drawing and changes chart, be shown in security risk chart plate;
The project dynamic module includes publisher, issuing time and multidate information, is shown in project dynamic display panels In block;
The Project Cost module includes project name and operating expenses, using project name as abscissa, with operating expenses Project cost graph is generated for ordinate, is shown in Project Cost chart plate;
The trend prediction module includes construction month and investment amount, using month of constructing as abscissa, to invest gold Volume is ordinate, generates trend prediction chart, is shown in trend prediction chart plate;
The vivid progress module includes overall progress and each bid section progress, by verbal description and picture presentation come into Row is shown;
The overall objective module includes total construction period, overall floorage, overall investment and placement amount, generates apply respectively Work duration accounting chart is completed construction area accounting chart, has invested accounting chart and has disposed amount accounting chart, total Body index diagram board block is shown.
In above-mentioned engineering project commander's managing and control system based on BIM, the project brief information include project name, Item address, project category, construction unit, general contracting unit, BIM always seek advice from, designing unit, supervisor, audit unit, project The scale of construction, house amount, motor-driven parking stall, plot ratio, site coverage.
Quality problems type described in engineering project commander's managing and control system above-mentioned based on BIM includes that construction quality lacks Sunken, construction quality common fault and accident resulting from poor quality of projects.
In engineering project commander's managing and control system above-mentioned based on BIM, the security risk entry includes tower crane, foot hand The problem of frame, four mouthfuls of Triratna, power supply for construction, hoisting machinery, construction machinery, materials elevator and external elevator entry.
In engineering project commander's managing and control system above-mentioned based on BIM, the multidate information includes disobeying for construction personnel The damage of chapter operation and Work machine.
In engineering project commander's managing and control system above-mentioned based on BIM, the relevant unit includes construction unit, Zong Bao Unit, BIM always seek advice from, designing unit, supervisor and audit unit.
Compared with prior art, the invention has the following advantages:
The present invention combines project management techniques with BIM technology, and the present invention is by by project management techniques and BIM technology Combine that carry out classification come Various types of data information such as engineering information, project progress, project quality and BIM models to project aobvious Show and typing, increase substantially the efficiency of management of engineering project, realizes the movable coordinating and unifying of project management and efficiently Running.Project BIM model module is arranged in the present invention, establishes BIM buildings model based on BIM, and project BIM model module is shown In BIM model display plate, preview is carried out to buildings model.The present invention passes through setting project information board block, bid section accounting Chart plate, monthly completion chart plate, single payment chart plate, project process chart plate, BIM model display plate, Quality problems chart plate, personal management chart plate, security risk chart plate, drawing change diagram board block, project dynamic Show plate, Project Cost chart plate, trend prediction chart module, vivid progress chart module and overall objective chart mould Block;Come various information in the engineering information to project, project progress, project quality and project cost etc. projects into Row is classified into and summarizes, and forms report so that data acquisition becomes directization and facilitation, promotion manage data validity, Authenticity and timeliness carry out depth excavation to data various in project management, flexibly generate various reports, and auxiliary carries out Analysis and prediction, while the business cooperation of engineering construction project is strengthened, communication efficiency is improved, communication cost is reduced, it is real Effective accumulation of project management experience and data is showed, has really realized and brought benefits by advanced management, be conducive to project It is managed and monitors in building course.
Detailed description of the invention
Fig. 1 is system framework schematic diagram of the invention;
Fig. 2 is the display interface figure of project drawing board;
Fig. 3 is the display interface figure of project information chart plate
Fig. 4 is the display interface figure of bid section accounting chart plate;
Fig. 5 is the monthly display interface figure for completing chart plate;
Fig. 6 is the display interface figure of separate payment chart plate;
Fig. 7 is the display interface figure of project dynamic chart plate;
Fig. 8 is the display interface figure of quality problems chart plate;
Fig. 9 is the display interface figure of security risk chart plate;
Figure 10 is the display interface figure of personal management chart plate;
Figure 11 is the display interface figure of drawing change diagram board block;
Figure 12 is the display interface figure of Project Cost chart plate;
Figure 13 is the display interface figure of trend prediction chart plate;
Figure 14 is the display interface figure of vivid progress diagram board block;
Figure 15 is the display interface figure of overall objective chart plate.
Specific embodiment
The present invention is further illustrated with reference to the accompanying drawings and examples, but be not intended as to the present invention limit according to According to.
Embodiment: a kind of engineering project commander's managing and control system based on BIM, as shown in attached drawing 1-15, including based on BIM's Project drawing board, the project drawing board include project information plate, bid section accounting chart plate, monthly completion chart plate, list Payment chart plate, BIM model display plate, quality problems chart plate, personal management chart plate, security risk chart Plate, drawing change diagram board block, project Dynamically Announce plate, Project Cost chart plate, trend prediction chart module, image Progress chart module and overall objective chart module;
As shown in figure 3, the project information plate is for showing project profile information;The project brief packet Project name, item address, project category, construction unit, general contracting unit, BIM is included always to seek advice from, designing unit, supervisor, examine Count unit, the project scale of construction, house amount, motor-driven parking stall, plot ratio, site coverage;
As shown in figure 4, the bid section accounting chart plate contains bid section title, bid section contract price and bid section for showing The chart-information of accounting;
As shown in figure 5, the monthly completion chart plate contains construction time information, planned cost and reality for showing The chart-information of border expense;
As shown in fig. 6, the single payment chart plate is for showing projects month, this month has paid and contract The chart-information of valence;
The BIM model display plate is for showing project BIM model;
As shown in figure 8, the quality problems chart plate is believed with display containing the chart of defective in quality type and quantity Breath;The quality problems type includes engineering quality defects, construction quality common fault and accident resulting from poor quality of projects;
As shown in Figure 10, the personal management chart plate be used to show the newly-increased number of each bid section, distancing number and The chart-information of current persons count;
As shown in figure 9, the security risk chart plate is for showing security risk type, editing safety hidden danger entry Whole security risk changes the chart-information of entry;The security risk entry includes tower crane, scaffold, four mouthfuls of Triratna, applies The problem of work electricity consumption, hoisting machinery, construction machinery, materials elevator and external elevator entry;
As shown in figure 11, drawing change diagram board block is asked for showing containing relevant unit, proposition problem, rectification Topic goes out figure and live practicable chart-information again;The relevant unit includes that construction unit, general contracting unit, BIM are always consulted Inquiry, designing unit, supervisor and audit unit;
As shown in fig. 7, the project Dynamically Announce plate is for showing project multidate information;The multidate information packet Include the operation against rules of construction personnel and the damage of Work machine;
As shown in figure 12, the Project Cost chart plate is for showing title and operating expenses containing projects Chart;
As shown in figure 13, the trend prediction chart plate is used to show the chart letter of construction month and investment amount Breath;
As shown in figure 14, the vivid progress diagram board block is used to show the text of whole bid section progress and each bid section progress Figure information;
As shown in figure 15, the overall objective chart is for showing total construction period, overall floorage, overall investment and placement Amount chart-information;
It further include a data recording module, data inputting module includes project information module, bid section setup module, monthly Complete module, single payment module, project BIM model module, quality problems module, personal management module, security risk artwork Block, drawing change module, project dynamic module;Project Cost plate, trend prediction module and vivid progress module;
The project information module includes project brief information, is shown in project information plate;
The bid section setup module includes bid section title, bid section contract price and bid section accounting, and bid section accounting is generated and is schemed Sheet form is shown in bid section accounting chart plate;
The monthly completion module includes construction time information, planned cost and actual cost, with construction time information For abscissa, using planned cost and actual cost as ordinate, generate monthly completion chart, be shown in monthly completion chart plate In;
The single payment module includes building, of that month payment and contract price, using Lou Dong as abscissa, to work as monthly expenses It pays and contract price is as ordinate, generate single payment chart, be shown in single month payment diagram board block;
The project BIM model module establishes BIM buildings model based on BIM, and project BIM model module is shown In BIM model display plate;
The quality problems module includes quality problems type, edits issue entry and has rectified and improved issue entry, generates Rectification rate accounting chart, is shown in quality problems chart plate;
The personal management module includes the newly-increased number, distancing number and current persons count of each bid section, generates personnel's pipe Chart is managed, is shown in personal management chart plate;
The security risk module includes security risk type, security risk entry and whole security risk changes entry, Security risk chart and rectification rate percentage chart are generated, is shown in security risk chart plate;
The drawing change module includes relevant unit, proposition problem, rectification problem, figure and scene are implemented out again, It generates drawing and changes chart, be shown in security risk chart plate;
The project dynamic module includes publisher, issuing time and multidate information, is shown in project dynamic display panels In block;
The Project Cost module includes project name and operating expenses, using project name as abscissa, with operating expenses Project cost graph is generated for ordinate, is shown in Project Cost chart plate;
The trend prediction module includes construction month and investment amount, using month of constructing as abscissa, to invest gold Volume is ordinate, generates trend prediction chart, is shown in trend prediction chart plate;
The vivid progress module includes overall progress and each bid section progress, by verbal description and picture presentation come into Row is shown;
The overall objective module includes total construction period, overall floorage, overall investment and placement amount, generates apply respectively Work duration accounting chart is completed construction area accounting chart, has invested accounting chart and has disposed amount accounting chart, total Body index diagram board block is shown.
The present invention with BIM technology by combining project management techniques come engineering information, project progress, the item to project The Various types of data such as mesh quality and BIM model information carries out classification display and typing, increases substantially the management effect of engineering project Rate, realizes the movable coordinating and unifying of project management and Efficient Operation, and the present invention is arranged project BIM model module, is based on BIM establishes BIM buildings model, and project BIM model module is shown in BIM model display plate, to buildings model into Row preview.The present invention passes through setting project information board block, bid section accounting chart plate, monthly completion chart plate, single payment Chart plate, project process chart plate, BIM model display plate, quality problems chart plate, personal management chart plate, Security risk chart plate, drawing change diagram board block, project Dynamically Announce plate, Project Cost chart plate, trend prediction Chart module, vivid progress chart module and overall objective chart module;Come the engineering information to project, project progress, project Various information in quality and project cost etc. projects be classified into summarizing, and forms report, so that data obtain Taking becomes directization and facilitation, validity, authenticity and the timeliness of management data is promoted, to various in project management Data carry out depth excavation, flexibly generate various reports, auxiliary is analyzed and predicted, while strengthening engineering construction project Business cooperation improves communication efficiency, reduces communication cost, realizes effective accumulation of project management experience and data, very Positive realize is brought benefits by advanced management, is conducive to be managed and monitor in project building course.

Claims (6)

1. the engineering project based on BIM commands managing and control system, it is characterised in that: including the project drawing board based on BIM, the item Mesh drawing board includes project information plate, bid section accounting chart plate, monthly completion chart plate, single payment chart plate, BIM Model display plate, quality problems chart plate, personal management chart plate, security risk chart plate, drawing change chart Plate, project Dynamically Announce plate, Project Cost chart plate, trend prediction chart module, vivid progress chart module and total Body index chart module;
The project information plate is for showing project profile information;
The bid section accounting chart plate is used to show the chart letter containing bid section title, bid section contract price and bid section accounting Breath;
The monthly completion chart plate is used to show the chart letter containing construction time information, planned cost and actual cost Breath;
The single payment chart plate is for showing that projects month, this month have paid the chart-information with contract price;
The BIM model display plate is for showing project BIM model;
The quality problems chart plate with display the chart-information containing defective in quality type and quantity;
The personal management chart plate is used to show newly-increased number, distancing number and the chart of the current persons count letter of each bid section Breath;
The security risk chart plate is for showing security risk type, editing safety hidden danger entry and whole security risk Change the chart-information of entry;
The described drawing change diagram board block is for showing containing relevant unit, proposing problem, rectification problem, again go out to scheme and existing The practicable chart-information in field;
The project Dynamically Announce plate is for showing project multidate information;
The Project Cost chart plate is used to show the chart of the title containing projects and operating expenses;
The trend prediction chart plate is used to show the chart-information in construction month and investment amount;
The vivid progress diagram board block is used to show the texts and pictures information of whole bid section progress and each bid section progress;
The overall objective chart is for showing total construction period, overall floorage, overall investment and placement amount chart-information;
It further include a data recording module, data inputting module includes project information module, bid section setup module, monthly completion Module, single payment module, project BIM model module, quality problems module, personal management module, security risk module, figure Paper changes module, project dynamic module;Project Cost plate, trend prediction module and vivid progress module;
The project information module includes project brief information, is shown in project information plate;
The bid section setup module includes bid section title, bid section contract price and bid section accounting, and bid section accounting is generated chart shape Formula is shown in bid section accounting chart plate;
The monthly completion module includes construction time information, planned cost and actual cost, is cross with construction time information Coordinate, using planned cost and actual cost as ordinate, generate monthly completion chart, be shown in monthly completion chart plate;
The single payment module includes building, of that month payment and contract price, paid using Lou Dong as abscissa, with of that month and Contract price generates single payment chart, is shown in single month payment diagram board block as ordinate;
The project BIM model module establishes BIM buildings model based on BIM, and project BIM model module is shown in BIM In model display plate;
The quality problems module includes quality problems type, edits issue entry and has rectified and improved issue entry, generates rectification Rate accounting chart is shown in quality problems chart plate;
The personal management module includes the newly-increased number, distancing number and current persons count of each bid section, generates personal management figure Table is shown in personal management chart plate;
The security risk module includes security risk type, security risk entry and whole security risk changes entry, is generated Security risk chart and rectification rate percentage chart, are shown in security risk chart plate;
The drawing change module includes relevant unit, proposition problem, rectification problem, figure and scene are implemented out again, is generated Drawing changes chart, is shown in security risk chart plate;
The project dynamic module includes publisher, issuing time and multidate information, is shown in project Dynamically Announce plate;
The Project Cost module includes project name and operating expenses, is vertical using project name as abscissa, with operating expenses Coordinate generation Project Cost chart is shown in Project Cost chart plate;
The trend prediction module includes construction month and investment amount, is to construct month as abscissa, with investment amount Ordinate generates trend prediction chart, is shown in trend prediction chart plate;
The vivid progress module includes overall progress and each bid section progress, is opened up by verbal description and picture presentation Show;
The overall objective module includes total construction period, overall floorage, overall investment and placement amount, generates construction work respectively Phase accounting chart is completed construction area accounting chart, has invested accounting chart and has disposed amount accounting chart, is referring generally to It marks on a map table panel displays.
2. the engineering project according to claim 1 based on BIM commands managing and control system, it is characterised in that: the item Mesh profile information includes that project name, item address, project category, construction unit, general contracting unit, BIM are always seeked advice from, designed list Position, supervisor, audit unit, the project scale of construction, house amount, motor-driven parking stall, plot ratio, site coverage.
3. the engineering project according to claim 1 based on BIM commands managing and control system, it is characterised in that: the matter Measuring problem types includes engineering quality defects, construction quality common fault and accident resulting from poor quality of projects.
4. the engineering project according to claim 1 based on BIM commands managing and control system, it is characterised in that: the peace Full hidden danger entry includes tower crane, scaffold, four mouthfuls of Triratna, power supply for construction, hoisting machinery, construction machinery, materials elevator and outer With entry the problem of elevator.
5. the engineering project according to claim 1 based on BIM commands managing and control system, it is characterised in that: described is dynamic State information includes the operation against rules of construction personnel and the damage of Work machine.
6. the engineering project according to claim 1 based on BIM commands managing and control system, it is characterised in that: the phase Close unit include construction unit, general contracting unit, BIM always seek advice from, designing unit, supervisor and audit unit.
CN201910084997.6A 2019-01-29 2019-01-29 Engineering project based on BIM commands managing and control system Pending CN109886644A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910084997.6A CN109886644A (en) 2019-01-29 2019-01-29 Engineering project based on BIM commands managing and control system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910084997.6A CN109886644A (en) 2019-01-29 2019-01-29 Engineering project based on BIM commands managing and control system

Publications (1)

Publication Number Publication Date
CN109886644A true CN109886644A (en) 2019-06-14

Family

ID=66927187

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910084997.6A Pending CN109886644A (en) 2019-01-29 2019-01-29 Engineering project based on BIM commands managing and control system

Country Status (1)

Country Link
CN (1) CN109886644A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112070482A (en) * 2020-09-10 2020-12-11 广州市第二装修有限公司 Engineering project integrated management method and device, computer equipment and storage medium
CN113961998A (en) * 2021-10-21 2022-01-21 黑龙江省求索科技信息技术有限公司 Building construction management system and management method for BIM
CN114519626A (en) * 2022-01-10 2022-05-20 湖北国际物流机场有限公司 Salary management method and system based on BIM model

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106408254A (en) * 2016-09-06 2017-02-15 江苏智通交通科技有限公司 Highway engineering project supervision system
US20170336630A1 (en) * 2015-03-31 2017-11-23 Timothy A. Cummings System for virtual display and method of use
CN107622355A (en) * 2017-09-30 2018-01-23 长江勘测规划设计研究有限责任公司 Project cluster work progress digital management system and method
CN108416701A (en) * 2018-03-06 2018-08-17 湖南建工集团有限公司 A kind of processing method of the Engineering Project Construction real data based on BIM

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20170336630A1 (en) * 2015-03-31 2017-11-23 Timothy A. Cummings System for virtual display and method of use
CN106408254A (en) * 2016-09-06 2017-02-15 江苏智通交通科技有限公司 Highway engineering project supervision system
CN107622355A (en) * 2017-09-30 2018-01-23 长江勘测规划设计研究有限责任公司 Project cluster work progress digital management system and method
CN108416701A (en) * 2018-03-06 2018-08-17 湖南建工集团有限公司 A kind of processing method of the Engineering Project Construction real data based on BIM

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112070482A (en) * 2020-09-10 2020-12-11 广州市第二装修有限公司 Engineering project integrated management method and device, computer equipment and storage medium
CN113961998A (en) * 2021-10-21 2022-01-21 黑龙江省求索科技信息技术有限公司 Building construction management system and management method for BIM
CN114519626A (en) * 2022-01-10 2022-05-20 湖北国际物流机场有限公司 Salary management method and system based on BIM model

Similar Documents

Publication Publication Date Title
Naghshbandi BIM for facility management: challenges and research gaps
CN109886644A (en) Engineering project based on BIM commands managing and control system
CN104573892A (en) Whole process visual project management system for engineering construction
CN109035060A (en) A kind of structured processes management system and management method
CN109886563A (en) Wisdom based on BIM builds control platform
CN109726513A (en) Project big data analysis system based on BIM
CN109801040A (en) Multidimensional mould based on BIM examines design collaboration platform
Pena-Mora et al. Information technology planning framework for Japanese general contractors
CN109886645A (en) Multidimensional mould based on BIM examines platform
Li Research on Financial Management Algorithm Based on Machine Learning in Big Data Era
Wu et al. Development trend of green residential buildings in China under the guidance of the low-carbon concept: A policy review and analysis
Wang et al. Promoting additive construction in fast-developing areas: An analysis of policies and stakeholder perspectives
Ya et al. The influence of stakeholders on technology innovation: a case study from China
Ge Exploring the application of BIM engineering in multi-project main body collaborative management platform
RU103014U1 (en) HARDWARE AND SOFTWARE COMPLEX OF THE AUTOMATED SYSTEM FOR THE DEVELOPMENT OF TECHNOLOGICAL PROCESSES
McAuley et al. Advancing the facilities management process in Ireland through the implementation of building information modelling within the public sector
CN110503386A (en) A kind of data processing system for market-oriented project
Wu et al. Research on Design Management Process Based on BIM-Taking the New Phnom Penh Airport Project in Cambodia as an Example
Wang et al. Research on Design Quality Management Based on PDCA Quality Cycle Theory
Yang et al. Smart Construction Engineering and Management
Yu et al. Application of BIM Technology in Construction Project Cost Compilation
Jing Application of Bim Technology in Project Management and Construction Cost Control
Liu et al. Analysis of Budget and Cost Control of New Green Building Projects
Shen et al. Study on the Whole Process Supervision Technology of Digital Intelligent Enabling for Building Safety and Quality Appraisal Institutions
Xianhe Construction Management Characteristics and Quality Control Strategies for Higher Education Infrastructure Projects

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190614