CN109850744A - A kind of parallel boom hoisting of disk making cutter - Google Patents
A kind of parallel boom hoisting of disk making cutter Download PDFInfo
- Publication number
- CN109850744A CN109850744A CN201910037547.1A CN201910037547A CN109850744A CN 109850744 A CN109850744 A CN 109850744A CN 201910037547 A CN201910037547 A CN 201910037547A CN 109850744 A CN109850744 A CN 109850744A
- Authority
- CN
- China
- Prior art keywords
- arm
- disk
- boom
- grip block
- steel wire
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 55
- 239000010959 steel Substances 0.000 claims abstract description 55
- 238000004519 manufacturing process Methods 0.000 claims abstract description 27
- 238000005520 cutting process Methods 0.000 claims abstract description 15
- 239000007787 solid Substances 0.000 claims description 5
- 125000004122 cyclic group Chemical group 0.000 claims description 3
- 238000000034 method Methods 0.000 abstract description 14
- 238000010008 shearing Methods 0.000 abstract description 9
- 238000010586 diagram Methods 0.000 description 6
- 238000005452 bending Methods 0.000 description 3
- 238000005299 abrasion Methods 0.000 description 2
- 238000005303 weighing Methods 0.000 description 2
- 235000008331 Pinus X rigitaeda Nutrition 0.000 description 1
- 235000011613 Pinus brutia Nutrition 0.000 description 1
- 241000018646 Pinus brutia Species 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 235000013399 edible fruits Nutrition 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
Abstract
A kind of parallel boom hoisting of disk making cutter provided by the invention includes: grip block, boom and steel wire.Two booms are hinged, and the grip block is arranged in one end of the boom, and the steel wire is arranged in the other end of the boom.By the pulling force on the steel wire by providing shearing force to the arm of cutting on the boom top when lifting, so that the linking arm of the bottom of the boom squeezes in opposite directions, so that the grip block on the linking arm is by the groove of disk by the discs clamp, after disk places, the steel wire is unclamped, the offer of shearing force is provided, so that the grip block of the boom other end is removed from groove, easy to operate time and labour saving, the process for using the parallel boom hoisting of disk of the production cutter to reduce tilting disk also make operating process safer.
Description
Technical field
The present invention relates to transporting equipment field more particularly to a kind of parallel boom hoistings of disk for making cutter.
Background technique
During making particular tool, generally require centre to be arranged circular hole, the heavy duty disc that groove is arranged in side wall carries out
Processing, unprocessed disk usually weigh about 1 ton or so, 1 ton or so of disk are moved to the station of 1.5 meters or so height
On, it is then processed further, this process generally requires that first disk is lifted on lifting machine.
In real process, when lifting the disk, often then wirerope is formed a circle directly through intermediate circular hole
It is hanging connected on lifting machine or holds up the disk using pallet, the lifting machine will by way of steel wire hangs and connects the pallet
The disk is moved on station, however there are following problems for above two mode: when disk is placed on the station
Afterwards, need to withdraw from pallet or steel wire below the disk, need to prop the disk using lever, by steel wire or
Pallet takes out, and troublesome in poeration, laborious and risk is big.
Summary of the invention
In order to solve the above technical problems, the disk that the present invention provides a kind of production cutter easy to disassemble plays lifting in parallel
It sets.
A kind of parallel boom hoisting of disk making cutter, comprising: two booms for intersecting hinged and solid respectively
Due to the grip block of described boom one end, wherein
Two booms are hinged by articulated shaft, and the other end of the boom is fixedly connected with steel wire, and the steel wire is hung
It is connected to lifting machine.
Preferably, the boom, which is divided into, cuts arm, loading arm and linking arm, and the top of the boom is to cut arm, the boom
Middle part be loading arm, the bottom of the boom is linking arm, described to cut arm and the linking arm is set to the load-bearing arm axle
The two sides of line, the loading arm are greater than the angle of the loading arm and linking arm with the angle for cutting arm.
Preferably, cut the top setting lifting lug of arm described in two, the steel wire pass through the lifting lug be fixed on it is described cut arm,
The top of the steel wire connects hanging ring.
Preferably, each described to cut junction setting through-hole of the arm with the loading arm, load-bearing is fixed in the through-hole
Bearing, the articulated shaft pass through and are fixedly connected on the load-bearing bearing on two booms.
Preferably, raised there are two the hanging ring inside tops, there is groove between two protrusions, the lifting machine
It is mounted in the groove.
Preferably, the main body of the hanging ring is in the cyclic structure of dislocation, is horizontal fixation between the end of the main body
Bar, the fixation with steel wire is in the fixed link.
Preferably, rib, length of the rib along the loading arm are fixed in the opposite side of two loading arms respectively
Spend direction setting.
Preferably, one end of the linking arm is perpendicularly fixed at the middle part of the grip block, it is described hang linking arm with it is described
Grip block is vertically arranged, and the angle of the grip block and the linking arm is fixed with the dowel of triangle.
Preferably, the grip block includes straight panel and the grip block for being fixed on the straight panel both ends, and the grip block is used for
Be plugged in the circular groove of disk side wall, four grip blocks of two grip blocks are oppositely arranged, the grip block with it is described
Straight panel is mutually perpendicular to, the trapezoidal structure of grip block, and the arc-shaped structure in one end end face of the grip block far from straight panel,
The curved end of four grip blocks is on same circular arc, is fixed on the linking arm in the middle part of the straight panel.
Compared with the relevant technologies, the parallel boom hoisting of disk of production cutter provided by the invention has following beneficial to effect
Fruit:
The parallel boom hoisting of disk of production cutter provided by the invention, when lifting, are passed through by the pulling force on the steel wire
Shearing force is provided to the arm of cutting on the boom top, so that the linking arm of the bottom of the boom squeezes in opposite directions, so that institute
The grip block on linking arm is stated by the groove of disk by the discs clamp, after disk places, by the steel wire pine
It opens, the offer of shearing force is provided, so that the grip block of the boom other end is removed from groove, compare pallet or steel
Cord directly hangs the mode connect around circular hole and no longer needs to mobile disk and can take the parallel boom hoisting of disk of the production cutter
Under, easy to operate time and labour saving is also made using the process that the parallel boom hoisting of disk of the production cutter reduces tilting disk
It is safer to obtain operating process.
In parallel boom hoisting provided by the embodiments of the present application, it is short to cut the arm steel wire, when lifting, so that two institutes
It states steel wire substantially along the vertical direction, separates the biggish situation of angle compared to longer two steel wires of arm are cut, lift by crane phase homogenous quantities
Disk, the bearing steel wires are bigger by pulling force, increase the steel wire load ability;The setting of the load-bearing bearing is hung described in reducing
Abrasion between arm and articulated shaft guarantees the service life of the parallel boom hoisting of disk of the production cutter, increases the system
Make the safety of the parallel boom hoisting of disk of cutter;The setting of the hanging ring facilitates the extension that the steel wire is hung on to lifting machine
Hook, the other raised channel of the hanging ring inside top, so that the hanging ring and the hook angle are opposite stable, the hanging ring
On fixed link on the steel wire between distance be adjusted according to the misalignment of the boom, avoid the steel wire spacing
When with the boom misalignment disunity, bending force is generated on the articulated shaft.
Detailed description of the invention
Fig. 1 is that the parallel boom hoisting of disk of production cutter provided by the invention cooperates the structural schematic diagram of disk;
Fig. 2 is the structural schematic diagram of the parallel boom hoisting of disk of production cutter shown in FIG. 1;
Fig. 3 is the structural schematic diagram of the articulated shaft and load-bearing bearing shown in FIG. 1;
Fig. 4 is the structure top view of the parallel boom hoisting of disk of production cutter shown in Fig. 3.
Figure label: 1, grip block, 2, dowel, 3, rib, 4, load-bearing bearing, 5, boom, 51, lifting lug, 6, steel wire, 7,
Hanging ring, 8, articulated shaft.
Specific embodiment
The invention will be further described with embodiment with reference to the accompanying drawing.
Fig. 1, Fig. 2, Fig. 3 and Fig. 4 are please referred to, wherein Fig. 1 is that the disk of production cutter provided by the invention is parallel
The structural schematic diagram of boom hoisting cooperation disk;Fig. 2 is the structure of the parallel boom hoisting of disk of production cutter shown in FIG. 1
Schematic diagram;Fig. 3 is the structural schematic diagram of the articulated shaft and load-bearing bearing shown in FIG. 1;Fig. 4 is production cutter shown in Fig. 3
The parallel boom hoisting of disk structure top view.
As shown in fig.1, a kind of parallel boom hoisting of disk for making cutter provided by the invention includes: grip block 1, hangs
Arm 5 and steel wire 6.Two booms 5 are hinged, and one end of the boom 5 is arranged the grip block 1, the boom 5 it is another
The steel wire 6 is arranged in one end.In specific implementation process, the specific connection embodiment of above structure is as follows:
Embodiment one
A kind of parallel boom hoisting of disk making cutter, comprising: two booms 5 for intersecting hinged and solid respectively
Due to the grip block 1 of described 5 one end of boom, wherein the boom 5 divides to cut arm, loading arm and linking arm, the boom 5
Top is to cut arm, described to cut that the arm lengths steel wire 6 is short, the top setting lifting lug 51 of arm is cut described in two, the steel wire 6 is worn
Cross the lifting lug 51 be fixed on it is described cut arm, the top of the steel wire 6 connects hanging ring 7, and there are two convex for 7 inside top of hanging ring
It rises, has groove between two protrusions, the hook of the lifting machine is mounted in the groove, and the middle part of the boom 5 connects
Connecing the part for cutting arm is loading arm, each junction setting through-hole for cutting arm and the loading arm, in the through-hole
It is respectively fixed with load-bearing bearing 4, the load-bearing bearing 4 that the articulated shaft 8 is passed through and is fixedly connected on two booms 5
Interior, the load-bearing bearing 4 is cylinder roller bearing, so that the load-bearing capacity of the load-bearing bearing 4 is larger, two loading arms
Rib 3 is fixed in opposite side respectively, and the rib 3 is arranged along the length direction of the loading arm, and the rib 3 makes described
Loading arm is able to bear bigger power, and the part that the bottom of the boom 5 connects the loading arm is linking arm, the linking arm
One end be perpendicularly fixed at the middle part of the grip block 1, the linking arm that hangs is vertically arranged with the grip block 1, and the folder
The angle for holding plate 1 and the linking arm is fixed with the dowel 2 of triangle.
Specifically, the grip block 1 includes straight panel and the grip block for being fixed on the straight panel both ends, the grip block is used for
Be plugged in the circular groove of disk side wall, four grip blocks of two grip blocks 1 are oppositely arranged, the grip block with it is described
Straight panel is mutually perpendicular to, the trapezoidal structure of grip block, and the arc-shaped structure in one end end face of the grip block far from straight panel,
The curved end of four grip blocks is on same circular arc, is fixed on the linking arm in the middle part of the straight panel.It is described
It cuts arm and the linking arm is set to the two sides of the loading arm axis, the loading arm is greater than the load-bearing with the angle for cutting arm
The angle of arm and linking arm.
Embodiment two
A kind of parallel boom hoisting of disk making cutter, comprising: two booms 5 for intersecting hinged and solid respectively
Due to the grip block 1 of described 5 one end of boom, the boom 5 is plate-like, wherein the boom 5 divides to cut arm, loading arm and company
Connecing arm, the top of the boom 5 is to cut arm, it is described to cut that arm lengths are short, the top setting lifting lug 51 of arm, the steel are cut described in two
Silk 6 pass through the lifting lug 51 be fixed on it is described cut arm, the top of the steel wire 6 connects hanging ring 7, and 7 inside top of hanging ring has
Two protrusions, two it is described protrusion between have groove, the hook of the lifting machine is mounted in the groove, the boom 5
Cutting arm described in the connection of middle part is loading arm, each junction setting through-hole for cutting arm and the loading arm, the through-hole
Inside it is respectively fixed with load-bearing bearing 4, the load-bearing axle that the articulated shaft 8 is passed through and is fixedly connected on two booms 5
It holds in 4, the load-bearing bearing 4 is that cylinder roller bearing is held described in two so that the load-bearing capacity of the load-bearing bearing 4 is larger
Rib 3 is fixed in the opposite side of weighing arm respectively, and the rib 3 is arranged along the length direction of the loading arm, and the rib 3 makes
The loading arm is able to bear bigger power, and it is linking arm that the bottom of the boom 5, which connects the loading arm, the linking arm
One end be perpendicularly fixed at the middle part of the grip block 1, the linking arm that hangs is vertically arranged with the grip block 1, and the folder
The angle for holding plate 1 and the linking arm is fixed with the dowel 2 of triangle.
Specifically, the grip block 1 includes straight panel and the grip block for being fixed on the straight panel both ends, the grip block is used for
Be plugged in the circular groove of disk side wall, four grip blocks of two grip blocks 1 are oppositely arranged, the grip block with it is described
Straight panel is mutually perpendicular to, the trapezoidal structure of grip block, and the arc-shaped structure in one end end face of the grip block far from straight panel,
The curved end of four grip blocks matches the circular arc of the disk groove, is fixed on the linking arm in the middle part of the straight panel
On.
It is described to cut arm and the linking arm is set to the two sides of the loading arm axis in specific implementation process, it is described to hold
Weighing arm with cut 155 ° -170 ° of angle, 135 ° -150 ° of angle of the loading arm and linking arm of arm.Above-mentioned angled relationships make
When two linking arms are vertical, cutting described in two has lesser angle between arm, so that the steel wire 6 begins during lifting
Shearing force, which is provided, to the boom 5 eventually guarantees that the disk will not fall off so that the grip block 1 clamps the disk always,
The angle when angle of the loading arm and the linking arm makes two linking arms vertical, between two loading arms
Between 60 ° -90 °, the smaller load-bearing capacity of angle between the loading arm is larger, and the loading arm is not too long, the hinge
It is little that spindle withstands forces square.
Embodiment three
A kind of parallel boom hoisting of disk making cutter, comprising: two booms 5 for intersecting hinged and solid respectively
Due to the grip block 1 of described 5 one end of boom, the boom 5 is plate-like, wherein the boom 5 divides to cut arm, loading arm and company
Connect arm, the top of the boom 5 is to cut arm, and described to cut that the arm lengths steel wire 6 is short, the top setting that arm is cut described in two is hung
Ear 51, the steel wire 6 pass through the lifting lug 51 be fixed on it is described cut arm, the top of the steel wire 6 connects hanging ring 7, the hanging ring 7
It is raised that there are two inside tops, has groove between two protrusions, the hook of the lifting machine is mounted in the groove, institute
The main body for stating hanging ring 7 is in the cyclic structure of dislocation, is horizontal fixed link between the end of the main body, the steel wire 6 is socketed
In in the fixed link, cutting arm described in the middle part connection of the boom 5 is loading arm, each described to cut arm and the load-bearing
Through-hole is arranged in the junction of arm, is respectively fixed with load-bearing bearing 4 in the through-hole, the articulated shaft 8 is passed through and is fixedly connected on
In the load-bearing bearing 4 on two booms 5, the load-bearing bearing 4 is cylinder roller bearing, so that the load-bearing bearing
4 load-bearing capacity is larger, and rib 3 is fixed in the opposite side of two loading arms respectively, and the rib 3 is along the loading arm
Length direction setting, the rib 3 make the loading arm be able to bear bigger power, described in the bottom connection of the boom 5
Loading arm is linking arm, and one end of the linking arm is perpendicularly fixed at the middle part of the grip block 1, described to hang linking arm and institute
It states grip block 1 to be vertically arranged, and the angle of the grip block 1 and the linking arm is fixed with the dowel 2 of triangle.
Specifically, the grip block 1 includes straight panel and the grip block for being fixed on the straight panel both ends, the grip block is used for
Be plugged in the circular groove of disk side wall, four grip blocks of two grip blocks 1 are oppositely arranged, the grip block with it is described
Straight panel is mutually perpendicular to, the trapezoidal structure of grip block, and the arc-shaped structure in one end end face of the grip block far from straight panel,
The curved end of four grip blocks matches the circular arc of the disk groove, is fixed on the linking arm in the middle part of the straight panel
On.It is described to cut arm and the linking arm is set to the two sides of the loading arm axis, the loading arm and 155 ° of the angle-for cutting arm
170 °, 135 ° -150 ° of angle of the loading arm and linking arm.
In specific implementation process, the distance between described steel wire 6 of two be set in the fixed link is hung according to described
Misalignment between arm 5 is adjusted, and prevents the steel wire 6 from generating the plate face perpendicular to the boom 5 to the boom 5
Pulling force, and then prevent the boom 5 from generating contrary bending force to 8 both ends of articulated shaft, increasing the load-bearing bearing 4
Load-bearing.
The use principle of the parallel boom hoisting of disk of production cutter provided by the invention is as follows:
The disk parallel boom hoisting of production cutter provided by the invention is logical by the pulling force on the steel wire 6 when lifting
Crossing makes to the arm offer shearing force of cutting on 5 top of boom so that the linking arm of the bottom of the boom 5 squeezes in opposite directions
The grip block 1 on the linking arm is obtained by the groove of disk by the discs clamp, after disk places, by the steel
Silk 6 unclamps, and cancels the offer of shearing force, so that the grip block 1 of 5 other end of the boom is removed from groove, operation side
Just time and labour saving, the process for using the parallel boom hoisting of disk of the production cutter to reduce tilting disk also make operating process
It is safer.
The disk parallel boom hoisting of production cutter provided by the invention is logical by the pulling force on the steel wire 6 when lifting
Crossing makes to the arm offer shearing force of cutting on 5 top of boom so that the linking arm of the bottom of the boom 5 squeezes in opposite directions
The grip block 1 on the linking arm is obtained by the groove of disk by the discs clamp, after disk places, by the steel
Silk 6 unclamps, and cancels the offer of shearing force, so that the grip block 1 of 5 other end of the boom is removed from groove, compared to support
Disk or wirerope directly hang the mode connect around circular hole and no longer need to mobile disk and can play in parallel the disk of the production cutter
Device for hoisting is removed, easy to operate time and labour saving, is reduced using the parallel boom hoisting of disk of the production cutter and is tilted disk
Process also makes operating process safer.
The arm of cutting is shorter, when lifting, so that two steel wires 6 are substantially along the vertical direction, it is two longer compared to arm is cut
The steel wire 6 separates the biggish situation of angle, lifts by crane the disk of phase homogenous quantities, the receiving of steel wire 6 pulling force is bigger, described in increase
6 load ability of steel wire;The setting of the load-bearing bearing 4 reduces the abrasion between the boom 5 and articulated shaft 8, guarantees the system
Make the service life of the parallel boom hoisting of disk of cutter, increases the safety of the parallel boom hoisting of disk of the production cutter
Property;The setting of the hanging ring 7 facilitates the hook that the steel wire 6 is hung on to lifting machine, and in addition 7 inside top of the hanging ring is convex
Play groove so that the hanging ring 7 and the hook angle are opposite stable, the steel wire 6 in fixed link on the hanging ring 7 it
Between distance be adjusted according to the misalignment of the boom 5, avoid 6 spacing of steel wire and 5 misalignment of boom not
When unified, bending force is generated on the articulated shaft 8.
The above description is only an embodiment of the present invention, is not intended to limit the scope of the invention, all to utilize this hair
Equivalent structure or equivalent flow shift made by bright specification and accompanying drawing content is applied directly or indirectly in other relevant skills
Art field, is included within the scope of the present invention.
Claims (8)
1. a kind of parallel boom hoisting of disk for making cutter characterized by comprising two hinged booms that intersect
(5) and it is individually fixed in the grip block (1) of the boom (5) one end, wherein
Hingedly by articulated shaft (8), the other end of the boom (5) is fixedly connected with steel wire (6), institute to two booms (5)
It states steel wire (6) and is hung on lifting machine;
The grip block (1) includes straight panel and the grip block for being fixed on the straight panel both ends, and the grip block is for being plugged in circle
Four grip blocks of the circular groove of disk side wall, two grip blocks (1) are oppositely arranged, the grip block and the straight panel phase
It is mutually vertical, the trapezoidal structure of grip block, and the arc-shaped structure in one end end face of the grip block far from straight panel, four institutes
The curved end for stating grip block is on same circular arc, is fixed on the boom (5) in the middle part of the straight panel.
2. the parallel boom hoisting of disk of production cutter according to claim 1, which is characterized in that the boom (5) point
To cut arm, loading arm and linking arm, the top of the boom (5) is to cut arm, and the middle part of the boom (5) is loading arm, described
Cut that the arm lengths steel wire (6) is short, the bottom of the boom (5) is linking arm, described to cut arm and the linking arm is set to
The two sides of the loading arm axis, the loading arm are greater than the angle of the loading arm and linking arm with the angle for cutting arm.
3. the parallel boom hoisting of disk of production cutter according to claim 2, which is characterized in that cut arm described in two
Lifting lug (51) are arranged in top, and the steel wire (6), which passes through the lifting lug (51), is fixed on and described cuts arm, the top of the steel wire (6)
It connects hanging ring (7).
4. the parallel boom hoisting of disk of production cutter according to claim 2, which is characterized in that it is each described cut arm with
Through-hole is arranged in the junction of the loading arm, is fixed with load-bearing bearing (4) in the through-hole, and the articulated shaft (8) passes through and consolidates
Surely it is connected to the load-bearing bearing (4) on two booms (5) Nei.
5. the parallel boom hoisting of disk of production cutter according to claim 3, which is characterized in that hanging ring (7) top
It is raised there are two on the inside of portion, there is groove between two protrusions, the hook of the lifting machine is mounted in the groove.
6. the parallel boom hoisting of disk of production cutter according to claim 5, which is characterized in that the hanging ring (7)
Main body is in the cyclic structure of dislocation, is horizontal fixed link between the end of the main body, the steel wire (6) is fixed on described solid
In fixed pole.
7. the parallel boom hoisting of disk of production cutter according to claim 2, which is characterized in that two loading arms
Rib (3) are fixed respectively in opposite side, and the rib (3) is arranged along the length direction of the loading arm.
8. the parallel boom hoisting of disk of production cutter according to claim 2, which is characterized in that the one of the linking arm
End is perpendicularly fixed at the middle part of the grip block (1), and the linking arm is vertically arranged with the grip block (1), and the clamping
The angle of plate (1) and the linking arm is fixed with the dowel (2) of triangle.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910037547.1A CN109850744A (en) | 2019-01-15 | 2019-01-15 | A kind of parallel boom hoisting of disk making cutter |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910037547.1A CN109850744A (en) | 2019-01-15 | 2019-01-15 | A kind of parallel boom hoisting of disk making cutter |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109850744A true CN109850744A (en) | 2019-06-07 |
Family
ID=66894789
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910037547.1A Pending CN109850744A (en) | 2019-01-15 | 2019-01-15 | A kind of parallel boom hoisting of disk making cutter |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109850744A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114524184A (en) * | 2022-02-21 | 2022-05-24 | 东风汽车集团股份有限公司 | Rotor lamination supports transfer device |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201284187Y (en) * | 2008-06-07 | 2009-08-05 | 者中林 | Self-hanging self-tipping type hanging scissor |
CN201907916U (en) * | 2010-12-28 | 2011-07-27 | 邵阳维克液压股份有限公司 | Hoisting device |
CN205257768U (en) * | 2015-12-30 | 2016-05-25 | 浙江晶星齿轮电机有限公司 | Stator transport anchor clamps |
CN206680075U (en) * | 2016-12-30 | 2017-11-28 | 葫芦岛力天重工机械有限公司 | Development machine hobboing cutter cutter ring hanging apparatus |
CN207943781U (en) * | 2018-02-10 | 2018-10-09 | 西继迅达(许昌)电梯有限公司 | A kind of cable disc suspender |
-
2019
- 2019-01-15 CN CN201910037547.1A patent/CN109850744A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201284187Y (en) * | 2008-06-07 | 2009-08-05 | 者中林 | Self-hanging self-tipping type hanging scissor |
CN201907916U (en) * | 2010-12-28 | 2011-07-27 | 邵阳维克液压股份有限公司 | Hoisting device |
CN205257768U (en) * | 2015-12-30 | 2016-05-25 | 浙江晶星齿轮电机有限公司 | Stator transport anchor clamps |
CN206680075U (en) * | 2016-12-30 | 2017-11-28 | 葫芦岛力天重工机械有限公司 | Development machine hobboing cutter cutter ring hanging apparatus |
CN207943781U (en) * | 2018-02-10 | 2018-10-09 | 西继迅达(许昌)电梯有限公司 | A kind of cable disc suspender |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114524184A (en) * | 2022-02-21 | 2022-05-24 | 东风汽车集团股份有限公司 | Rotor lamination supports transfer device |
CN114524184B (en) * | 2022-02-21 | 2023-12-19 | 东风汽车集团股份有限公司 | Rotor lamination supports transfer device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109850744A (en) | A kind of parallel boom hoisting of disk making cutter | |
CN108975157B (en) | Hoisting clamp special for spool | |
CN212503588U (en) | Sleeper lifting appliance | |
CN102381623B (en) | Special lifting tool for circuit breaker | |
CN212769429U (en) | Fast assembling and disassembling clamp for concrete electric pole | |
CN211226002U (en) | Steel sheet hoist and mount frock | |
CN211004168U (en) | Trolley lifting appliance | |
CN215666592U (en) | Spool lifting appliance | |
CN217972205U (en) | Balanced hoist that case roof beam was used | |
CN201161868Y (en) | Multifunctional lifted crane | |
CN202414964U (en) | Travelling crane hoisting auxiliary device | |
CN220131679U (en) | Large-scale titanium ingot hoisting device | |
CN213203830U (en) | Suspension bridge steel beam lifting device using temporary cable clamp as support | |
CN210193166U (en) | Hoisting balancing device | |
CN220223266U (en) | Large-scale major axis class forging hoist and mount anchor clamps | |
CN212334355U (en) | Hoisting clamp for cylindrical steel ingot | |
CN204369421U (en) | A kind of freight container suspension hook | |
CN217376980U (en) | double-T-beam self-balancing hoisting sling | |
CN208648544U (en) | A kind of horizontal hoisting fixture of H profile steel | |
CN214828330U (en) | Vertical lifting appliance | |
CN215479151U (en) | Lifting hook | |
CN219526010U (en) | Arm hoisting clamp for crane manufacturing | |
CN214456170U (en) | Auxiliary hoisting device for crane | |
CN215439275U (en) | Short rail recovery balancing device for railway special line | |
CN210012494U (en) | Calcium carbide cold breaking crown block single-holding clamp self-locking device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190607 |