CN109782138A - High altitude localities electrical apparatus external insulation characteristic moves experimental provision - Google Patents

High altitude localities electrical apparatus external insulation characteristic moves experimental provision Download PDF

Info

Publication number
CN109782138A
CN109782138A CN201811573485.8A CN201811573485A CN109782138A CN 109782138 A CN109782138 A CN 109782138A CN 201811573485 A CN201811573485 A CN 201811573485A CN 109782138 A CN109782138 A CN 109782138A
Authority
CN
China
Prior art keywords
test
external insulation
electrical apparatus
high altitude
pressure regulator
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811573485.8A
Other languages
Chinese (zh)
Inventor
金海云
刘怀东
王昭
唐红川
高乃奎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian Jiaotong University
Original Assignee
Xian Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian Jiaotong University filed Critical Xian Jiaotong University
Priority to CN201811573485.8A priority Critical patent/CN109782138A/en
Publication of CN109782138A publication Critical patent/CN109782138A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a kind of mobile experimental provisions of high altitude localities electrical apparatus external insulation characteristic, test portion is placed on the middle position of container, test operation part and energy slave part are disposed respectively in container both sides, all it is connected by high-voltage wall bushing with test portion, test operation part is made of observation window and alternating current-direct current hand held console, alternating current connects on pressure regulator, pressure regulator is connected with transformer, protective resistance is connected to after pressure regulator, it is connected with test product, test portion includes one and measures voltage by divider that double capacitors form, divider parallel connection accesses circuit, the leakage current on test product surface is measured by a noninductive resistance or Rogowski coil, noninductive resistance series connection access circuit, oscillograph is in parallel with noninductive resistance.The present invention has concentrated test relevant device, energy auxiliary system, test operation system, while the movement that the device can be convenient, can the relevant issues on the spot to high altitude localities electrical apparatus external insulation further investigate.

Description

High altitude localities electrical apparatus external insulation characteristic moves experimental provision
Technical field
For field research high altitude localities (under low air pressure condition) power transmission and transforming equipment such as insulator, transmission line of electricity, transformation The electrical apparatus external insulations such as device characteristic and discharge mechanism.
Technical background
China's national territorial area is vast, and geographical features are that Xi Gaodong is low for height above sea level, and height above sea level is more than 1000 meters Area account for 60% of national territorial area or more.Simultaneously as the supply of China's energy is at present with coal, water power, wind energy, photovoltaic etc. Based on form, these resources are concentrated mainly on the west area in China, and area that are fairly developed economically has focused largely on the east in China South is coastal, this just creates the energy centre in China in western part, and load center is in the situation of east.China's national territorial area compared with Greatly, farther out, in order to reduce the energy loss in electricity transmission process, super-pressure, UHV transmission are the skills that must be taken to transmission distance Art measure.For this purpose, China's power industry proposes schemes such as " transferring electricity from the west to the east, north and south supply mutually, super grids ".No matter which kind of side Case, transmission line of electricity is all inevitably by high altitude localities.
It is well known that high altitude localities rarefaction of air, air pressure is low, this result in either the discharge voltage of the air gap, Corona inception voltage and pollution flashover voltage can all be reduced with the raising of height above sea level.Meanwhile China's geographical environment is more multiple Miscellaneous, the High aititude transmission line of electricity built inevitably faces filthy and worst case meteorological conditions influences, thus with Developed country compares, and the external insulation problem of the various equipment of China's transmission line of electricity is more prominent.How complex environment is solved to power grid The influence of middle electrical apparatus external insulation characteristic is the technical problem that high pressure, UHV transmission face at this stage.
Up to the present, the world many countries including China have carried out largely electrical apparatus external insulation characteristic Research work, for the external insulation problem of specific electrical equipment, proposes multiple technologies side on the basis of the studies above work Case.But electrical apparatus external insulation problem does not disappear from power grid, in particular with the fast development of China's industry, environment Problem is got worse, and is increasingly taken place frequently so as to cause the fairly large electrical apparatus external insulation accident of China's power grid.
Electrical apparatus external insulation attribute testing generally passes through laboratory or live two ways.At present to electrical equipment outside The research of insulation characterisitic is unfolded in laboratory, and a large number of experiments can be quickly obtained by carrying out correlative study in the lab As a result, the research in terms of capable of preferably carrying out mechanism in laboratory simultaneously.But field test can get and most really electrically set Standby lending analysis condition evaluation results, test result can sufficiently reflect state of the electrical equipment under actual motion condition, Thus obtain the great attention of countries in the world.But, field test is difficult to have due to experimental condition, especially High aititude Area, since the problems such as weather, transport causes test difficulty larger, thus up to the present, the data obtained amount is smaller.
The mobile experimental provision of high altitude localities electrical apparatus external insulation characteristic test relevant device, energy auxiliary system, And test operation system is melted into a whole in the form of container, conveniently moving is quick, solves current field test and needs to consume It can study under different altitude height, different regions, Various Seasonal, varying environment the problem of taking a large amount of human and material resources, financial resources Electrical apparatus external insulation characteristic.Using the experimental provision, experimenter can be quickly obtained great amount of firsthand data, be that China is high Altitude Regions are super, UHV transmission line construction provides technical support.
Summary of the invention
It is an object of the invention to overcome the above-mentioned prior art insufficient, high altitude localities electrical apparatus external insulation characteristic is provided Mobile experimental provision.
The technical scheme of the present invention is realized as follows:
High altitude localities electrical apparatus external insulation characteristic move experimental provision, including test portion, energy slave part with And test operation part, test portion are placed on the middle position of container, test operation part and energy slave part difference Be placed on container both sides, be all connected by high-voltage wall bushing with test portion, test operation part by observation window and Alternating current-direct current hand held console composition, alternating current connect on pressure regulator, and pressure regulator is connected with transformer, and guarantor is connected to after pressure regulator Resistance is protected, is connected with test product, test portion includes one and measures voltage by divider that double capacitors form, and divider is in parallel Circuit is accessed, the leakage current on test product surface, noninductive resistance series connection access are measured by a noninductive resistance or Rogowski coil Circuit, oscillograph are in parallel with noninductive resistance.
Alternating current-direct current hand held console is by overvoltage, overcurrent protection indicator and the rotary pressure regulator four of alternating current and direct current Part forms.
Rectifier is accessed after protective resistance again, alternating current is transformed into direct current.
Energy slave part is made of solar panel, diesel-driven generator, energy storage battery three parts, by casing with Test portion and test operation part are connected.
The present invention has concentrated test relevant device, energy auxiliary system, test operation system, while the device can be convenient Movement, can the relevant issues on the spot to high altitude localities electrical apparatus external insulation further investigate.
Detailed description of the invention
Fig. 1 is schematic diagram of internal structure of the invention;
1 observation window;2 alternating current-direct current hand held consoles;3 energy storage batteries;4 diesel-driven generators;5 solar panels;6 is through walls Casing;7 pressure regulators;8 single-phase transformers;9 rectifiers;10 protective resistances;11 divider;12 ground connection;13 lifting platforms;14 spray dresses It sets;15 oscillographs;16 fire extinguishers;17 atmospheric parameter measuring instruments;18 cameras.
Fig. 2 is alternating current circuit figure of the invention;
T: pressure regulator (20KVA);B: transformer;R0: protective resistance;F: divider (wherein C1、C2It is capacitor);S: tested Test product;R2It is noninductive resistance (or Rogowski coil);J: oscillograph.
Fig. 3 is DC circuit figure of the present invention;
T: pressure regulator (20KVA);B: transformer;R0: protective resistance Z: rectifier;F: divider (wherein C1、C2It is electricity Hold);S: product to be tested;R2It is noninductive resistance (or Rogowski coil);J: oscillograph.
Specific embodiment
Referring to shown in attached drawing, electrical apparatus external insulation characteristic mobile experimental provision in high altitude localities consists of three parts altogether, It is test portion, energy slave part and test operation part respectively.Test portion is placed on the middle position of container, Test operation part and energy slave part are disposed respectively in container both sides, all pass through high-voltage wall bushing and test portion It is connected.
Test operation part is made of observation window and alternating current-direct current hand held console.Alternating current-direct current hand held console by overvoltage, Overcurrent protection indicator and rotary four part of the pressure regulator composition of alternating current and direct current.For guarantee test personnel safety, test Operator observes test process by observation window, passes through alternating current-direct current hand held console Control experiment process.
The alternating current that generator issues connects on the pressure regulator that rated capacity is 20KVA, and pressure regulator is connected with transformer, In order to guarantee circuit safety in the case of decompression, protective resistance is accessed in circuit, is then connected again with test product.Do direct current examination It when testing, needs to access rectifier again after protective resistance, alternating current is transformed into direct current.
The device measures voltage by the divider that double capacitors form by one, and divider parallel connection accesses circuit.Pass through One noninductive resistance (or Rogowski coil) measures the leakage current on test product surface, noninductive resistance series connection access circuit, oscillograph It is in parallel with noninductive resistance.
Energy slave part is made of solar panel, diesel-driven generator, energy storage battery three parts.Solar battery Plate mainly bears daily electricity consumption since electricity is smaller, and extra electric energy is stored in battery.Diesel-driven generator mainly bears examination Test process electricity consumption.They all pass through casing and are connected with test portion and test operation part.
Test portion capital equipment includes the equipment such as transformer, pressure regulator, divider, rectifier, and detail parameters are introduced such as Under:
(1) transformer.Rated capacity 20KVA, voltage rating 100KV, rated current 0.2A.
(2) pressure regulator.Rated capacity 20KVA.
(3) lifting platform.For equipment such as hanging test insulator, conducting wires.In view of transmission facility is in high altitude localities It will appear phenomena such as floaing arc, in order to guarantee the safety of experimenter, and also to can more really reflect local environment to experiment As a result influence, lifting platform should remove container during the test, at least keep safety requirements distance with container.
(4) spray system is humidified.Under dry weather, pollution flashover accident will not generally occur for electrical equipment.Accident generally occurs After electrical equipment is wetted, in order to study the influence to electrical equipment such as mist, dew, rain, experimental box installation humidification spray system System.The system is expired pressure protection, ultrasonic wave fogger, sprinkling equipment and is formed by water tank, water deprivation stress protection, water.
(5) wind regime.Since high altitude localities wind speed changes greatly, the equipment is for studying local wind speed variation pair The influence of electrical apparatus external insulation characteristic.
(6) camera installation.I--speedTR high-speed camera.For shooting the flashover in experimentation, arc phenomenon etc. of floaing.
(7) atmospheric parameter measuring instrument.The PTU2000 general measuring instrument of Vaisala company, Finland production, can measure temperature simultaneously Degree, humidity, air pressure.
(8) divider.SGB-200A power frequency capacitive divider.
(9) leakage current collection system.Noninductive resistance, USB-6215 data collecting card.
(10) salt is close, the close measuring instrument of ash.Using DDS-11A type electric conductivity instrument.
(11) oscillograph.
When carrying out correlation test using the mobile experimental provision of high altitude localities electrical apparatus external insulation characteristic, first power generation The alternating current that machine issues connects on the pressure regulator that rated capacity is 20KVA, and pressure regulator is connected with transformer, in order to guarantee decompression In the case of circuit safety, to access protective resistance in circuit, then be connected again with test product.When doing DC experiment, need Rectifier is accessed after protective resistance again, alternating current is transformed into direct current.
The device measures voltage by the divider that double capacitors form by one, and divider parallel connection accesses circuit.Pass through One noninductive resistance or Rogowski coil measure the leakage current on test product surface, noninductive resistance series connection access circuit, oscillograph with Noninductive resistance is in parallel.
Electrical apparatus external insulation characteristic mobile experimental provision in high altitude localities not only can carry out phase to outdoor electrical equipment Test is closed, the lending analysis that the weather conditions such as mist, rain, dew, filth descend electrical equipment can also be studied with the experimental provision, When doing such test, start supersonic gas day with fog, spray water to electrical equipment, until the leakage current of tested electrical equipment is minimum.
The experimental provision can be used to study exhausted outside electrical equipment under the conditions of Various Seasonal, different altitude height, varying environment Edge characteristic.To be measured in order to distinguish influence of the environment to test result, before test local height above sea level and temperature, humidity, The natural environmental conditions such as filth.
It is close in order to study the influence of the factors External Insulation characteristic such as air pressure, temperature, humidity, wind-force, misty rain, icing The medium-term and long-term weather forecast for paying close attention to local meteorological department's publication, makes experiment routing in advance.
During test, it is contemplated that float arc phenomena such as, testing crew should keep certain safe distance with equipment under test, right Special experimental phenomena is recorded by camera.
Method one: (suitable for measuring the electrical equipment directly removed from power grid.)
Step 1: electrical equipment is unloaded from power grid, in uninstall process, it should be noted that not change electrical equipment surface Filth.
Step 2: the different location on test product surface takes several fractions respectively, for measuring the salt on electrical equipment surface It is close and grey close.In order to not influence the measurement of its flash-over characteristic, the surface re-coating pollution layer that reply was cleaned after measurement gives extensive It is multiple.
Step 3: test product surface is sufficiently soaked with ultrasonic atomizer, and is determined by measuring its leakage current.
Step 4: according to IEC international standard, related discharge attribute testing is carried out to test product.Test process to make test product with Experimental box keeps safe distance.
Method two: (being suitable for man-made chamber)
Step 1: electrical equipment surface clean to be measured is clean, then it is placed on naturally dry on clean cushion.
Step 2: calculating the surface area of electrical equipment to be measured, according to NaCl needed for international standard IEC60507 calculating and not The Specific amounts of soluble substance.Add appropriate amount of purified water to be then evenly stirred until paste, then it is uniformly painted on to insulator to be measured Surface, when brushing, make every effort to uniform.
Step 3: test product surface is sufficiently soaked with ultrasonic atomizer, and is determined by measuring its leakage current.
Step 4: according to IEC international standard, related discharge attribute testing is carried out to test product.Test process to make test product with Experimental box keeps safe distance.
2260 meters of embodiment 1:(height above sea level, Xining, artificial pollution test)
Step 1, selection XP-70 type insulator.Insulator to be measured is carefully cleaned to remove surface filth.It is then hung up liter Naturally dry on platform drops.
Step 2, the PTU2000 general measuring instrument produced using Vaisala company, Finland, measure local temperature, humidity And air pressure.
Step 3 calculates insulator surface product, close, grey close according to insulator surface to be measured product calculating salt, according to international standard The Specific amounts of NaCl and insoluble substance needed for IEC60507 is calculated.Appropriate amount of deionized water is added then to be evenly stirred until paste, it will It is uniformly painted on insulator surface to be measured.Brushing points for attention: make every effort to uniform;It avoids staining substance and fall.
Step 4 is sufficiently soaked with pollution layer of the ultrasonic atomizer to insulator surface, measures its surface conductivity, Stop wetting until surface conductivity is minimum.
Pollution layer conductivity is scaled to 20 DEG C of base temperature as the following formula
K20=Kθ[1-b(6-20)]
Wherein: θ is insulator surface temperature
KθPollution layer conductivity when being θ DEG C of temperature
K20Pollution layer conductivity when being 20 DEG C of temperature
B is coefficient.
Step 5, foundation 60507 international standard of IEC apply voltage to insulator using uniform boosting method, and boost width every time Degree is 0.3KV, is pressurizeed until insulator chain dielectric surface flashover.
Embodiment 2 (1530 meters of height above sea level, Lanzhou, natural pollution test)
Step 1: LXY-70 type insulator being unloaded from transmission line of electricity, is handled with care in uninstall process, not changed The filth of insulator surface.
Step 2: the PTU2000 general measuring instrument produced using Vaisala company, Finland measures local temperature, humidity And air pressure.
Step 3: in the different location of insulator surface, three fractions are taken respectively, for measuring electrical equipment surface Salt is close and grey close.Take the average value of measurement close, grey close as the salt of insulator surface.In order to not influence the survey of its flash-over characteristic Amount is coped with the surface re-coating pollution layer cleaned and is restored after measurement.
Step 4: test product surface sufficiently being soaked with ultrasonic atomizer, and is determined by measuring its leakage current, is leaked Stop wetting when current maxima.Pollution layer conductivity is scaled to 20 DEG C of base temperature as the following formula
K20=Kθ[1-b(θ-20)]
Wherein: θ is insulator surface temperature
KθPollution layer conductivity when being θ DEG C of temperature
K20Pollution layer conductivity when being 20 DEG C of temperature
B is coefficient.
Step 5: according to IEC international standard, after wetting, pressurizeing to insulator, carried out using uniform boosting method immediately Flashover property test, boost 0.3KV every time, pressurizes until generating flashover.

Claims (4)

1. high altitude localities electrical apparatus external insulation characteristic move experimental provision, including test portion, energy slave part and Test operation part, which is characterized in that test portion is placed on the middle position of container, test operation part and energy auxiliary Part be disposed respectively in container both sides, be all connected by high-voltage wall bushing with test portion, test operation part by Observation window and alternating current-direct current hand held console composition, alternating current connect on pressure regulator, and pressure regulator is connected with transformer, in pressure regulator After be connected to protective resistance, be connected with test product, test portion includes one and measures voltage by divider that double capacitors form, point Depressor parallel connection accesses circuit, and the leakage current on test product surface, noninductive resistance are measured by a noninductive resistance or Rogowski coil Series connection access circuit, oscillograph are in parallel with noninductive resistance.
2. the mobile experimental provision of electrical apparatus external insulation characteristic in high altitude localities according to claim 1, which is characterized in that Alternating current-direct current hand held console is made of overvoltage, overcurrent protection indicator and rotary four part of pressure regulator of alternating current and direct current.
3. the mobile experimental provision of electrical apparatus external insulation characteristic in high altitude localities according to claim 1, which is characterized in that Rectifier is accessed after protective resistance again, alternating current is transformed into direct current.
4. the mobile experimental provision of electrical apparatus external insulation characteristic in high altitude localities according to claim 1, which is characterized in that Energy slave part is made of solar panel, diesel-driven generator, energy storage battery three parts, passes through casing and test portion And test operation part is connected.
CN201811573485.8A 2018-12-21 2018-12-21 High altitude localities electrical apparatus external insulation characteristic moves experimental provision Pending CN109782138A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811573485.8A CN109782138A (en) 2018-12-21 2018-12-21 High altitude localities electrical apparatus external insulation characteristic moves experimental provision

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811573485.8A CN109782138A (en) 2018-12-21 2018-12-21 High altitude localities electrical apparatus external insulation characteristic moves experimental provision

Publications (1)

Publication Number Publication Date
CN109782138A true CN109782138A (en) 2019-05-21

Family

ID=66497603

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811573485.8A Pending CN109782138A (en) 2018-12-21 2018-12-21 High altitude localities electrical apparatus external insulation characteristic moves experimental provision

Country Status (1)

Country Link
CN (1) CN109782138A (en)

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1553206A (en) * 2003-12-18 2004-12-08 西安交通大学 Electric power apparatus external insulative leakage current on-line monitoring system in converting station
DE102010017303A1 (en) * 2010-02-05 2011-08-11 Hinow, Georg, Dr. Ing., 01279 Impulse voltage testing system, has high voltage measuring divider installed as intermediate circuit, measurement signal plotting device possessing correction algorithm, and surge voltage generator for producing pulse voltage
CN102590684A (en) * 2012-03-08 2012-07-18 江苏新亚高电压测试设备有限公司 Full-automatic insulated comprehensive testing device
CN204679590U (en) * 2015-04-03 2015-09-30 国网河南省电力公司电力科学研究院 Haze environmental experiment system under a kind of high-tension electricity condition
CN204807663U (en) * 2015-07-15 2015-11-25 广东先达电业股份有限公司 Be applied to alternating current -direct current conversion equipment of withstand voltage test
CN105259488A (en) * 2015-11-26 2016-01-20 云南电网有限责任公司电力科学研究院 500kV high-voltage parallel electric reactor turn-to-turn insulation performance testing platform
CN107271869A (en) * 2017-06-30 2017-10-20 国家电网公司 High altitude localities 750kV shunt reactor partial discharge test methods
CN207730888U (en) * 2018-01-30 2018-08-14 西安热工研究院有限公司 A kind of wind driven generator insulating state is detecting device integrated

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1553206A (en) * 2003-12-18 2004-12-08 西安交通大学 Electric power apparatus external insulative leakage current on-line monitoring system in converting station
DE102010017303A1 (en) * 2010-02-05 2011-08-11 Hinow, Georg, Dr. Ing., 01279 Impulse voltage testing system, has high voltage measuring divider installed as intermediate circuit, measurement signal plotting device possessing correction algorithm, and surge voltage generator for producing pulse voltage
CN102590684A (en) * 2012-03-08 2012-07-18 江苏新亚高电压测试设备有限公司 Full-automatic insulated comprehensive testing device
CN204679590U (en) * 2015-04-03 2015-09-30 国网河南省电力公司电力科学研究院 Haze environmental experiment system under a kind of high-tension electricity condition
CN204807663U (en) * 2015-07-15 2015-11-25 广东先达电业股份有限公司 Be applied to alternating current -direct current conversion equipment of withstand voltage test
CN105259488A (en) * 2015-11-26 2016-01-20 云南电网有限责任公司电力科学研究院 500kV high-voltage parallel electric reactor turn-to-turn insulation performance testing platform
CN107271869A (en) * 2017-06-30 2017-10-20 国家电网公司 High altitude localities 750kV shunt reactor partial discharge test methods
CN207730888U (en) * 2018-01-30 2018-08-14 西安热工研究院有限公司 A kind of wind driven generator insulating state is detecting device integrated

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
廖晓宇等: "高海拔地区变电站外绝缘及空气间隙设计", 《湖南工业大学学报》 *

Similar Documents

Publication Publication Date Title
Hauschild et al. High-voltage test and measuring techniques
Zhang et al. Influence of low atmospheric pressure on AC pollution flashover performance of various types of insulators
CN103001235B (en) Method for evaluating risks of MOV (metal oxide varistor) of series capacitive compensator
CN107248736B (en) Online identification method for positive sequence parameters of power distribution network line
CN106250660A (en) A kind of marine wind electric field harmonic analysis method
Zhao et al. Development of contamination flashover pre-warning system and analysis of operating experience
CN109085527A (en) Capacitance type potential transformer harmonic propagation characteristic measuring system
CN202057762U (en) Device for simulating high-altitude conducting wire electromagnetic environment
CN109782138A (en) High altitude localities electrical apparatus external insulation characteristic moves experimental provision
CN107271871A (en) Submarine cable DC break down voltage test charge accumulation dissipation system and method for testing
CN103267912B (en) A kind of direct current transportation wall bushing risk evaluating system and methods of risk assessment
CN103487702A (en) Small-power movable micro-grid connection detecting system
Quan et al. The real-time digital simulation system for distribution network
CN208172118U (en) A kind of wind power station electric energy quality test device
Xiao et al. Experimental investigation on the minimum approach distance for live working on 1000kV UHV compact transmission line
CN103995201B (en) Wind power generation set islanding test device
CN207380179U (en) Submarine cable DC break down voltage test charge accumulates dissipation system
Huang et al. Flashover prevention on high-altitude HVAC transmission line insulator strings
Yao et al. Experiment Study of 330kV Transmission Line Tower Gaps at 4300m Altitude
Li et al. Remote online monitoring system for suspension insulator strings
Issouribehere et al. Measurements of disturbances produced by power electronic devices on EHV overhead lines using Electric Field Sensors
Limbo Insulator aging tests with HVAC and HVDC excitation using the tracking wheel tester
Xiuyuan et al. Research on Discharge Characteristics and Altitude Correction of Typical Air-gap in 500kV High-Altitude Substation
Liu et al. The effect of the marine environment on the stator insulation system of an offshore wind turbine generator
Hailong et al. Research on detection system for 10kV distribution switcher of both Primary and secondary technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190521