CN109750773A - Assembly concrete external wall integrated dry hanging plate and construction method - Google Patents

Assembly concrete external wall integrated dry hanging plate and construction method Download PDF

Info

Publication number
CN109750773A
CN109750773A CN201910141516.0A CN201910141516A CN109750773A CN 109750773 A CN109750773 A CN 109750773A CN 201910141516 A CN201910141516 A CN 201910141516A CN 109750773 A CN109750773 A CN 109750773A
Authority
CN
China
Prior art keywords
pull rod
dry
fixing piece
external wall
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910141516.0A
Other languages
Chinese (zh)
Inventor
刘俊
刘广建
马文晶
刘亚雄
韩晓龙
李海林
姚喜宁
汪生亮
罗智斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GANSU ANJU CONSTRUCTION ENGINEERING GROUP Co Ltd
Original Assignee
GANSU ANJU CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GANSU ANJU CONSTRUCTION ENGINEERING GROUP Co Ltd filed Critical GANSU ANJU CONSTRUCTION ENGINEERING GROUP Co Ltd
Priority to CN201910141516.0A priority Critical patent/CN109750773A/en
Publication of CN109750773A publication Critical patent/CN109750773A/en
Pending legal-status Critical Current

Links

Landscapes

  • Building Environments (AREA)

Abstract

The invention discloses a kind of assembly concrete external wall integrated dry hanging plate and construction methods, including Side fascia, Side fascia successively includes decorative layer, structure sheaf and insulating layer from outside to inside, Side fascia is fixed by pull rod fixing piece with inner template, the casting space of wall is formed between Side fascia and inner template, inner template is provided with the fixation device for fixing to pull rod fixing piece far from the side of Side fascia.The invention is decoration, heat preservation, template integrated dry hanging plate, reduces construction and product cost, reduces built-loading, and saving steel resource is constructed simple and direct, and stability is good, and difficulty of construction is low, short time limit;Heat insulation effect is good.

Description

Assembly concrete external wall integrated dry hanging plate and construction method
Technical field
The invention belongs to assemble building field, it is related to a kind of assembly concrete external wall integrated dry hanging plate and construction Method.
Background technique
In building trade, thermal insulation material, decorative panel are usually all installed separately construction, usually in reinforced concrete structure Paste heat-preserving material on the alien invasion of wall, and in order to meet fireproof requirement, thermal insulation material can only use A grades of fire proofing materials, example Such as rock wool, foamed cement, foam concrete, foaming, ceramics, so that economy reduces, and this fireproof and heat-insulating material The thermal insulation property of thermal insulation property less fireproof thermal insulation material, such as polystyrene foam plastics etc. is declined.
Decorative panel is typically also the outside for being pasted onto thermal insulation material, with prolonged wind and weather, part decorative panel meeting Removing falls off, and causes security risk for a long time, has violated the original intention of its decoration function.
It needs to build the template for concreting before reinforced concrete structure wall pours, concretings is waited to complete Afterwards, it needs form removable, it is time-consuming and laborious, greatly reduce formation efficiency.
Summary of the invention
In view of this, making the purpose of the present invention is to provide a kind of assembly concrete external wall integrated dry hanging plate It separately constructs when must install without decorative layer, insulating layer, structure sheaf, is not necessarily to keel, at low cost, installation process simply decorates, Heat preservation, template one cladding mounting structure and technique.
In order to achieve the above objectives, the invention provides the following technical scheme:
A kind of assembly concrete external wall integrated dry hanging plate, including Side fascia, Side fascia successively wrap from outside to inside Decorative layer, structure sheaf and insulating layer are included, Side fascia is fixed by pull rod fixing piece with inner template, shape between Side fascia and inner template At the casting space of wall, inner template is provided with far from the side of Side fascia to be consolidated for what is fixed to pull rod fixing piece Determine device.
Further, the first steel bar girder is embedded in structure sheaf, the cross section of the first steel bar girder is V-arrangement, the first steel It is pierced by insulating layer at the top of muscle truss, is pierced by the curved of the top of the first steel bar girder of insulating layer and pull rod fixing piece crotch pull rod Hook portion matches.
Further, it is fixed with embedded sleeve barrel in structure sheaf and insulating layer, embedded sleeve barrel sequentially passes through insulating layer and structure Layer, pull rod fixing piece are end rolled thread pull rod, and end rolled thread pull rod is matched with embedded sleeve barrel, and one end of end rolled thread pull rod is stretched Enter into embedded sleeve barrel, the other end of end rolled thread pull rod is fixed after passing through inner template.
Further, the open end of embedded sleeve barrel is flushed with the lateral surface of insulating layer.
Further, it is fixed between structure sheaf and insulating layer by several equally distributed insulating anchor bolts.
Further, inner template includes template, and the side of template is fixed with the second steel bar girder, template and the second reinforcing bar purlin The through-hole passed through for pull rod fixing piece is provided on frame.
Further, fixed device is that the fixation steel fixed to pull rod fixing piece is matched with pull rod fixing piece Pipe and fixture nut.
A kind of assembly concrete external wall integrated dry Slate hanging construction method, comprising the following steps:
Base course wall is divided typesetting by S1, provides the size of dry-hang board;
S2 produces dry-hang board integration according to required size, and transports to construction site;
S3 installs dry-hang board, and adjusts its flatness and verticality, which replaces exterior sheathing at this time;
S4, installs inner template, and inner template is connect with dry-hang board by pull rod fixing piece;
S5, the casting concrete between dry-hang board and inner template;
S6 removes inner template after concrete setting, cut the steel bar end of pull rod fixing piece and concrete wall surface is in same Plane;
S7 clears up the plate face of dry-hang board and scene and checks and accepts.
Further, the material of the insulating layer of dry-hang board is polymer composite.
Further, the interior decorative coat of dry-hang board is imitation stone lacquer.
The beneficial effects of the present invention are:
The invention is decoration, heat preservation, template integrated dry hanging plate, reduces construction and product cost, reduces building Load, saving steel resource are constructed simple and direct, and stability is good, and difficulty of construction is low, short time limit;Heat insulation effect is good;It is heat insulation decoration integrated Change plate and building body is linked as entirety conscientiously, more ensure that long-term decoration functions and energy-saving heat preserving performance;It is durable, corrosion resistant Erosion, ageing-resistant, Wind-Pressure Resistance, shock resistance;Product external surfaces are using imitation stone lacquer as decorative cover, and color pattern is wide in variety, Ke Yiyi It is wide to carry out tailored range according to the hobby of client;Construction environment not by environment limited can replace exterior sheathing effect, eliminate due to The difference of construction technology and the drawbacks of cause, install very easy;Light-weight, hardness is high, it is not easy to and it is damaged, it carries easily, uses Make exterior-wall heat insulation, will not influence floor decoration power.
Detailed description of the invention
In order to keep the purpose of the present invention, technical scheme and beneficial effects clearer, the present invention provides following attached drawing and carries out Illustrate:
Fig. 1 is the main view that the dry-hang board of the first steel bar girder is embedded with described in the invention embodiment;
Fig. 2 is the longitudinal sectional view that the dry-hang board of the first steel bar girder is embedded with described in the invention embodiment;
Fig. 3 is that dry-hang board described in the invention embodiment is shown with inner template by the structure that crotch pull rod is fixed It is intended to;
Fig. 4 is the main view that the dry-hang board of embedded sleeve barrel is embedded with described in the invention embodiment;
Fig. 5 is the longitudinal sectional view that the dry-hang board of embedded sleeve barrel is embedded with described in the invention embodiment;
Fig. 6 is dry-hang board described in the invention embodiment and the knot that inner template is fixed by end rolled thread pull rod Structure schematic diagram.
Description of symbols:
1, Side fascia;11, decorative layer;12, structure sheaf;13, insulating layer;14, the first steel bar girder;15, embedded sleeve barrel;2, Inner template;21, template;22, the second steel bar girder;3, insulating anchor bolt;4, crotch pull rod;5, end rolled thread pull rod;6, fixed steel Pipe.
Specific embodiment
Below in conjunction with attached drawing, a preferred embodiment of the present invention will be described in detail.
As shown in Figures 1 to 6, a kind of assembly concrete external wall integrated dry hanging plate, including Side fascia 1, Side fascia 1 It from outside to inside successively include decorative layer 11, structure sheaf 12 and insulating layer 13.Incrustation of the layer as plate body is adornd, structure sheaf 12 is Concrete plate body, insulating layer 13 are insulation board.Pass through several equally distributed insulating anchor bolts 3 between structure sheaf 12 and insulating layer 13 It is fixed.Side fascia 1 is fixed by pull rod fixing piece and inner template 2, and the casting that wall is formed between Side fascia 1 and inner template 2 is empty Between.
As shown in Figures 1 to 3, specific embodiment one is embedded with the first steel bar girder 14, the first reinforcing bar purlin in structure sheaf 12 The cross section of frame 14 is V-arrangement, and the top of the first steel bar girder 14 is pierced by insulating layer 13, is pierced by the first steel bar girder of insulating layer 13 14 top is matched with the hook part of pull rod fixing piece crotch pull rod 4.The hook part of crotch pull rod 4 catches on the first steel bar girder 14 top, the other end of crotch pull rod 4 are fixed after passing through inner template 2.
As shown in FIG. 5 and 6, embedded sleeve barrel 15 is fixed in specific embodiment two, structure sheaf 12 and insulating layer 13, it is pre-buried The open end of sleeve 15 is flushed with the lateral surface of insulating layer 13, and embedded sleeve barrel 15 sequentially passes through insulating layer 13 and structure sheaf 12. Pull rod fixing piece is end rolled thread pull rod 5, and end rolled thread pull rod 5 is matched with embedded sleeve barrel 15.One end of end rolled thread pull rod 5 It extend into embedded sleeve barrel 15, the other end of end rolled thread pull rod 5 is fixed after passing through inner template 2.
Inner template 2 includes template 21, and the side of template 21 is fixed with the second steel bar girder 22, template 21 and the second reinforcing bar purlin The through-hole passed through for pull rod fixing piece is provided on frame 22, the second steel bar girder 22 is provided with far from the side of template 21 to be used for The fixation steel pipe 6 and fixture nut fixed to pull rod fixing piece.
As a further improvement of the foregoing solution, decorative layer 11 can use imitation stone lacquer, and insulating layer 13 is multiple using macromolecule Condensation material.
The construction method of the invention:
Base course wall is divided typesetting by the first step, provides the size of dry-hang board;
Second step produces dry-hang board integration according to drawing size, transport to construction site;
Third step installs dry-hang board, and adjusts its flatness and verticality, which replaces exterior sheathing 21 at this time;
4th step, installs inner template 2, and installation inner template 2 is connect with dry-hang board by pull rod fixing piece;
5th step, the casting concrete between dry-hang board and inner template 2;
6th step, removes inner template 2 after concrete setting, the steel bar end of cutting pull rod fixing piece is in concrete wall surface Same plane;
7th step is cleared up the plate face of dry-hang board and scene and is checked and accepted.
The invention the utility model has the advantages that
(1) it separately constructs without decorative layer 11, insulating layer 13, structure sheaf 12 during installation, is not necessarily to keel, at low cost, peace Dress process is simple;Construction and product cost are reduced, built-loading is reduced, saving steel resource is constructed simple and direct;Stability is good, Improve total system stability;
(2) difficulty of construction is low, short time limit, and heat preservation decoration integrative dry-hang board high insulating efficiency is very good, it is possible to reduce energy conservation Loss, therefore, especially in awful weather area such as northeast, northwest etc., energy-saving heat preserving requires often very high, traditional heat preservation It constructs and brings extreme difficulty to construction;
(3) in terms of safety guarantee can anti-scaling, anti-dropout, prevent related, fire prevention lightning protection is shockproof, has decoration functions, prevents Splitting water proof anti-soil dye is always decoration of exterior wall Three Difficult Issues, what the design guarantee of the three proofings system of this dry-hang board integrated board just filled Decorative effect, dry-hang board and building body are linked as entirety conscientiously, more ensure that long-term decoration functions and energy-saving heat preserving performance;
(4) the decoration service life is synchronous with buildings, practical, durable, corrosion-resistant, ageing-resistant, Wind-Pressure Resistance, anti-impact It hits;
(5) due to the protective layer and decorative layer 11 using polymer composite and imitation stone lacquer as thermal insulation material, have Good impact resistance and corrosion resistance, service life are strong;
(6) the available property of external decoration is strong, and for product external surfaces using imitation stone lacquer as decorative cover, color pattern is wide in variety, It is wide can to carry out tailored range according to the hobby of client;
(7) construction environment is not limited the effect that can replace exterior sheathing 21 by environment, is eliminated due to construction technology not The drawbacks of causing together, installation is very easy, and since this product uses the fixed form of pull rod fixing piece connection, there is no need to bases Layer processing, is mounted directly dry-hang board (exterior sheathing 21) and steel bar girder (inner template 2), intermediate after being connected by pull rod fixing piece to pour Concrete is built, is shortened the construction period;
(8) light-weight, hardness is high, it is not easy to and it is damaged, it carries easily, is used as exterior-wall heat insulation, will not influence floor decoration power, Input cost can be reduced.
Finally, it is stated that preferred embodiment above is only used to illustrate the technical scheme of the present invention and not to limit it, although logical It crosses above preferred embodiment the present invention is described in detail, however, those skilled in the art should understand that, can be Various changes are made to it in form and in details, without departing from claims of the present invention limited range.

Claims (10)

1. a kind of assembly concrete external wall integrated dry hanging plate, it is characterised in that: including Side fascia (1), Side fascia (1) From outside to inside successively include decorative layer (11), structure sheaf (12) and insulating layer (13), Side fascia (1) pass through pull rod fixing piece with it is interior Template (2) is fixed, the casting space of wall is formed between Side fascia (1) and inner template (2), inner template (2) is far from Side fascia (1) Side be provided with the fixation device for fixing to pull rod fixing piece.
2. assembly concrete external wall integrated dry hanging plate according to claim 1, it is characterised in that: structure sheaf (12) it is embedded with the first steel bar girder (14) in, the cross section of the first steel bar girder (14) is V-arrangement, the first steel bar girder (14) Top is pierced by insulating layer (13), is pierced by top and the pull rod fixing piece crotch pull rod of the first steel bar girder (14) of insulating layer (13) (4) hook part matches.
3. assembly concrete external wall integrated dry hanging plate according to claim 1, it is characterised in that: structure sheaf (12) and in insulating layer (13) it is fixed with embedded sleeve barrel (15), embedded sleeve barrel (15) sequentially passes through insulating layer (13) and structure sheaf (12), pull rod fixing piece is end rolled thread pull rod (5), and end rolled thread pull rod (5) is matched with embedded sleeve barrel (15), end rolled thread One end of pull rod (5) is extend into embedded sleeve barrel (15), and it is solid afterwards that the other end of end rolled thread pull rod (5) passes through inner template (2) It is fixed.
4. assembly concrete external wall integrated dry hanging plate according to claim 3, it is characterised in that: embedded sleeve barrel (15) open end is flushed with the lateral surface of insulating layer (13).
5. assembly concrete external wall integrated dry hanging plate according to claim 1, it is characterised in that: structure sheaf (12) fixed by several equally distributed insulating anchor bolts (3) between insulating layer (13).
6. assembly concrete external wall integrated dry hanging plate according to claim 1, it is characterised in that: inner template It (2) include template (21), the side of template (21) is fixed with the second steel bar girder (22), template (21) and the second steel bar girder (22) through-hole passed through for pull rod fixing piece is provided on.
7. assembly concrete external wall integrated dry hanging plate according to claim 1, it is characterised in that: fixed device To match the fixation steel pipe (6) fixed to pull rod fixing piece and fixture nut with pull rod fixing piece.
8. a kind of assembly concrete external wall integrated dry Slate hanging construction method, which comprises the following steps:
Base course wall is divided typesetting by S1, provides the size of dry-hang board;
S2 produces dry-hang board integration according to required size, and transports to construction site;
S3 installs dry-hang board, and adjusts its flatness and verticality, which replaces exterior sheathing (21) at this time;
S4, is installed inner template (2), and inner template (2) is connect with dry-hang board by pull rod fixing piece;
S5, the casting concrete between dry-hang board and inner template (2);
S6 removes inner template (2) after concrete setting, and the steel bar end and concrete wall surface for cutting pull rod fixing piece are in same flat Face;
S7 clears up the plate face of dry-hang board and scene and checks and accepts.
9. assembly concrete external wall integrated dry Slate hanging construction method according to claim 8, it is characterised in that: The material of the insulating layer (13) of dry-hang board is polymer composite.
10. assembly concrete external wall integrated dry Slate hanging construction method according to claim 8, feature exist In: decorative layer (11) material of dry-hang board is imitation stone lacquer.
CN201910141516.0A 2019-02-26 2019-02-26 Assembly concrete external wall integrated dry hanging plate and construction method Pending CN109750773A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910141516.0A CN109750773A (en) 2019-02-26 2019-02-26 Assembly concrete external wall integrated dry hanging plate and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910141516.0A CN109750773A (en) 2019-02-26 2019-02-26 Assembly concrete external wall integrated dry hanging plate and construction method

Publications (1)

Publication Number Publication Date
CN109750773A true CN109750773A (en) 2019-05-14

Family

ID=66407699

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910141516.0A Pending CN109750773A (en) 2019-02-26 2019-02-26 Assembly concrete external wall integrated dry hanging plate and construction method

Country Status (1)

Country Link
CN (1) CN109750773A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343190A (en) * 2020-11-13 2021-02-09 山东隆济时节能科技股份有限公司 Assembled architectural decoration integration heated board
CN112360005A (en) * 2020-11-13 2021-02-12 廊坊市勤创建筑材料科技有限公司 Fixed subassembly and wall body

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0374064A1 (en) * 1988-12-16 1990-06-20 Serge Meilleur Insulating formwork for concrete wall
JPH0868143A (en) * 1994-08-26 1996-03-12 Yoshitaka Yoshinari Separator with concrete structure of building and support plate
CN1715580A (en) * 2005-07-04 2006-01-04 田长明 Dismantling-free internal and external wall heat insulation decoration formwork and its construction method
US20090179135A1 (en) * 2008-01-11 2009-07-16 Victor Amend Device having both non-abrading and fire-resistant properties for linking concrete formwork panels
US8266859B1 (en) * 2005-06-28 2012-09-18 James Thomas Harrington Concrete wall forming system
JP2015014111A (en) * 2013-07-04 2015-01-22 株式会社丸高工業 Form structure
CN107143135A (en) * 2017-06-28 2017-09-08 常华北 Structure-integrated insulation and decoration exterior sheathing and its external wall construction method
CN209799087U (en) * 2019-02-26 2019-12-17 甘肃安居建设工程集团有限公司 Assembled concrete building exterior wall integral dry hanging plate

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0374064A1 (en) * 1988-12-16 1990-06-20 Serge Meilleur Insulating formwork for concrete wall
JPH0868143A (en) * 1994-08-26 1996-03-12 Yoshitaka Yoshinari Separator with concrete structure of building and support plate
US8266859B1 (en) * 2005-06-28 2012-09-18 James Thomas Harrington Concrete wall forming system
CN1715580A (en) * 2005-07-04 2006-01-04 田长明 Dismantling-free internal and external wall heat insulation decoration formwork and its construction method
US20090179135A1 (en) * 2008-01-11 2009-07-16 Victor Amend Device having both non-abrading and fire-resistant properties for linking concrete formwork panels
JP2015014111A (en) * 2013-07-04 2015-01-22 株式会社丸高工業 Form structure
CN107143135A (en) * 2017-06-28 2017-09-08 常华北 Structure-integrated insulation and decoration exterior sheathing and its external wall construction method
CN209799087U (en) * 2019-02-26 2019-12-17 甘肃安居建设工程集团有限公司 Assembled concrete building exterior wall integral dry hanging plate

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112343190A (en) * 2020-11-13 2021-02-09 山东隆济时节能科技股份有限公司 Assembled architectural decoration integration heated board
CN112360005A (en) * 2020-11-13 2021-02-12 廊坊市勤创建筑材料科技有限公司 Fixed subassembly and wall body

Similar Documents

Publication Publication Date Title
CN109267677A (en) A kind of GAT external mold plate cast-in-place concrete compound insulation system and its construction technology
CN105544721B (en) Light steel energy-saving assembled house and its construction method
CN106958308A (en) A kind of light steel foam concrete assembled wall of assembled and its application method
WO2015120794A1 (en) Building component replacing plaster layer with prefabricated panel protection layer
CN103104094A (en) Construction method of lattice light-gauge steel house
CN114108889A (en) Prefabricated hollow internal mold metal mesh cement sandwiched heat-insulation external wall panel
CN209837394U (en) External template cast-in-place concrete composite heat insulation system
CN105089149A (en) Side elevation system of aluminum alloy house
CN109750773A (en) Assembly concrete external wall integrated dry hanging plate and construction method
CN105040813B (en) The preceding facade system in aluminium alloy house
CN204590326U (en) A kind of wallboard erects dress syndeton and uses the house of this structure
CN209799087U (en) Assembled concrete building exterior wall integral dry hanging plate
CN204919800U (en) Back facade system in aluminum alloy house
CN204919802U (en) Preceding facade system in aluminum alloy house
CN204940529U (en) The side elevation system in aluminium alloys house
CN204919808U (en) Side direction facade system in aluminum alloy house
CN105040811B (en) The rear facade system in aluminium alloy house
CN210263610U (en) Prefabricated wallboard structure keeps warm
CN108086534A (en) A kind of light steel wall of no heat bridge
CN206599836U (en) Light steel structure house
CN213390730U (en) High strength protection type building curtain
CN210049426U (en) Building thermal insulation wall
CN205502377U (en) Hanging wallboard is partly inlayed to unit -installment light
CN203729464U (en) Decorative thermal insulation composite wall
CN209837398U (en) External template cast-in-place concrete composite heat insulation system for internal and external corner structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190514