CN109736585A - Shear wall, floor total-prefabricated construction safety protecting method - Google Patents

Shear wall, floor total-prefabricated construction safety protecting method Download PDF

Info

Publication number
CN109736585A
CN109736585A CN201910162878.8A CN201910162878A CN109736585A CN 109736585 A CN109736585 A CN 109736585A CN 201910162878 A CN201910162878 A CN 201910162878A CN 109736585 A CN109736585 A CN 109736585A
Authority
CN
China
Prior art keywords
wallboard
layer
railing
floor
superimposed sheet
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910162878.8A
Other languages
Chinese (zh)
Inventor
陈光中
王磊
杨素娜
王军勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201910162878.8A priority Critical patent/CN109736585A/en
Publication of CN109736585A publication Critical patent/CN109736585A/en
Pending legal-status Critical Current

Links

Landscapes

  • Working Measures On Existing Buildindgs (AREA)

Abstract

The present invention relates to the realm of building construction, especially a kind of shear wall, floor total-prefabricated construction safety protecting method carry out: prefabricated panel, the pre-buried railing fixed link of panel tops as follows;Railing is made, railing is mounted on panel tops, wallboard and railing are lifted into installation site and block-by-block is installed;Superimposed sheet is installed, superimposed sheet carries out tying up the pre-buried pipeline laying of muscle, floor after being installed, and pours in-situ layer after the installation of first layer wallboard;It pours completion maintenance and reaches and second layer wallboard is installed after intensity, remove the railing that first layer wallboard correspond to installation site, installation personnel safety belt is fixed near installation site on floor or the guard rail neighbouring with installation site;Second layer wallboard installs second layer superimposed sheet after being installed, superimposed sheet is tied up the pre-buried pipeline of muscle, floor and is laid with after being installed, pour in-situ layer, and maintenance reaches intensity after the completion of pouring;It repeats the above steps and each outer wall of floor plate is installed.The present invention is convenient for disassembly and assembly, and securely and reliably, construction cost is low.

Description

Shear wall, floor total-prefabricated construction safety protecting method
Technical field
The present invention relates to the realm of building construction, especially a kind of shear wall, floor total-prefabricated construction safety protecting method.
Background technique
Assembled architecture is the new industry in building industry, and related construction technology is new technology mostly, with tradition The form of construction work of complete cast-in-place building be very different.Within for outer shear wall, floor total-prefabricated construction, scene exists Minimal amount of concrete cast-in-situ construction, Side fascia, lining, superimposed sheet, stair, balcony slab etc. are all that batch production is prefabricated, scene Lifting installation is merely possible to the security protection when components such as work team's installation Side fascia, superimposed sheet when using external scaffolding.When When scaffold is only used as safety prevention measure, cost input is too high, and current assembled architecture has outside using Side fascia when constructing Side install protective fence way, but such way need on Side fascia reserving hole to install protective fence;The drawbacks of such method It is that the reserving hole water-proofing treatment on Side fascia is difficult, it is easy to cause external wall leak, post-processing difficulty and cost It puts into huge.
Summary of the invention
In order to solve the above technical problems, the present invention proposes that convenient for disassembly and assembly, the safe and reliable shear wall of one kind, floor assemble entirely Formula building safety means of defence.
The present invention adopts the following technical scheme:
A kind of shear wall, floor total-prefabricated construction safety protecting method carry out as follows:
1) prefabricated panel, in the pre-buried railing fixed link in the top of wallboard;
2) railing is made, railing is mounted on to the top of wallboard, the length of railing is consistent with the length of wallboard plane, passes through tower crane Wallboard and railing are lifted into specified installation site together, block-by-block is installed, after the installation of first layer wallboard is in place, wallboard top The railing in portion forms enclosed protective fence;
3) superimposed sheet is installed, superimposed sheet is carried out tying up the pre-buried pipeline laying of muscle, floor after being installed, be poured after the installation of first layer wallboard In-situ layer is built, maintenance reaches floor decoration intensity after the completion of pouring;
4) maintenance installs second layer wallboard after reaching intensity, when installing second layer wallboard, by the corresponding first layer wall of installation site Guard rail disassembly on plate, installation personnel safety belt are fixed on installation site nearby floor or the protection neighbouring with installation site On railing;
5) second layer superimposed sheet is installed, superimposed sheet carries out tying up muscle, floor pre-buried after being installed after second layer wallboard is installed Pipeline is laid with, and pours in-situ layer, and maintenance reaches intensity after the completion of pouring;
6) it repeats the above steps and each outer wall of floor plate is installed.
Compared with prior art, the beneficial effects of the present invention are:
The present invention can be avoided the through-hole for remaining for fixed protection column in advance on wallboard, keep wallboard whole without waterproof weak spot;Wall Dismountable railing at the top of plate replaces outer protective scaffold, convenient for disassembly and assembly, saves cost.
Detailed description of the invention
Fig. 1 is the structural diagram of the present invention;
Fig. 2 is the structural schematic diagram of wallboard;
Fig. 3 is the top view of Fig. 2;
Fig. 4 is the scheme of installation of wallboard;
In figure: wallboard 1;Railing fixed link 2;Railing 3;Upright bar 301.
Specific embodiment
Below in conjunction with the drawings and specific embodiments, the present invention is further described.
Referring to attached drawing: a kind of shear wall, floor total-prefabricated construction safety protecting method carry out as follows:
1) prefabricated panel, in the pre-buried railing fixed link in the top of wallboard.
2) railing is made, the upright bar of railing is made by steel pipe, and vertical rod sleeve is fixed in the railing for being embedded in panel tops On bar, the length of railing is consistent with the length of wallboard plane, and wallboard and railing are lifted into specified installation together by tower crane Position, block-by-block are installed, and after the installation of first layer wallboard is in place, wallboard formed enclosed anti-encirclement along architectural plane one week Column plays the role of security protection when installing superimposed sheet.
3) superimposed sheet is installed after the installation of first layer wallboard, superimposed sheet carries out tying up the pre-buried pipeline paving of muscle, floor after being installed If pouring in-situ layer, maintenance reaches floor decoration intensity after the completion of pouring.
4) maintenance installs second layer wallboard after reaching intensity, when installing second layer wallboard, by installation site corresponding first Guard rail disassembly on layer wallboard, installation personnel safety belt are fixed on installation site floor or neighbouring with installation site nearby On guard rail;Sequence installation the second layer wallboard when, be installed to where, the protective fence on the first layer wallboard of corresponding position Bar is removed, and non-installation position is not removed, and is always maintained at integrally closed protection state.
5) second layer superimposed sheet is installed, superimposed sheet carries out tying up muscle, floor after being installed after second layer wallboard is installed Pre-buried pipeline is laid with, and pours in-situ layer, and maintenance reaches intensity after the completion of pouring.
6) it repeats the above steps and each outer wall of floor plate is installed, security protection is constantly in closed state.
The above is only a specific embodiment of the invention, but are not limited thereto to protection of the invention, all this technologies Field technical staff it is thinkable to the technical program technical characteristic propose equivalent change or replacement, all cover in this hair Within bright protection scope.

Claims (1)

1. a kind of shear wall, floor total-prefabricated construction safety protecting method, which is characterized in that carry out as follows:
1) prefabricated panel, in the pre-buried railing fixed link in the top of wallboard;
2) railing is made, railing is mounted on to the top of wallboard, the length of railing is consistent with the length of wallboard plane, passes through tower crane Wallboard and railing are lifted into installation site together, block-by-block is installed, after the installation of first layer wallboard is in place, the column of panel tops Bar forms enclosed protective fence;
3) superimposed sheet is installed, superimposed sheet is carried out tying up the pre-buried pipeline laying of muscle, floor after being installed, be poured after the installation of first layer wallboard In-situ layer is built, maintenance reaches floor decoration intensity after the completion of pouring;
4) maintenance installs second layer wallboard after reaching intensity, when installing second layer wallboard, by the corresponding first layer wall of installation site Guard rail disassembly on plate, installation personnel safety belt are fixed on installation site nearby floor or the protection neighbouring with installation site On railing;
5) second layer superimposed sheet is installed, superimposed sheet carries out tying up muscle, floor pre-buried after being installed after second layer wallboard is installed Pipeline is laid with, and pours in-situ layer, and maintenance reaches intensity after the completion of pouring;
6) it repeats the above steps and each outer wall of floor plate is installed.
CN201910162878.8A 2019-03-05 2019-03-05 Shear wall, floor total-prefabricated construction safety protecting method Pending CN109736585A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910162878.8A CN109736585A (en) 2019-03-05 2019-03-05 Shear wall, floor total-prefabricated construction safety protecting method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910162878.8A CN109736585A (en) 2019-03-05 2019-03-05 Shear wall, floor total-prefabricated construction safety protecting method

Publications (1)

Publication Number Publication Date
CN109736585A true CN109736585A (en) 2019-05-10

Family

ID=66369366

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910162878.8A Pending CN109736585A (en) 2019-03-05 2019-03-05 Shear wall, floor total-prefabricated construction safety protecting method

Country Status (1)

Country Link
CN (1) CN109736585A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE20001948U1 (en) * 2000-02-03 2000-03-23 Baumann Verwertungsgesellschaft Gmbh, 88471 Laupheim Protective scaffold to be used in construction
US20060180390A1 (en) * 2005-02-01 2006-08-17 Ken Thaler Roof edge fall protection apparatus
CN204370825U (en) * 2014-11-21 2015-06-03 长沙远大住宅工业集团有限公司 Assembled architecture faces frontier defense protection unit
CN105113851A (en) * 2015-09-14 2015-12-02 上海建工二建集团有限公司 Multifunctional prefabricated assembled building construction fence and construction method thereof
CN106968381A (en) * 2017-04-28 2017-07-21 广东省建科建筑设计院有限公司 With the prefabricated shear wall and overlapping plate node of Combined grouting sleeve connection

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE20001948U1 (en) * 2000-02-03 2000-03-23 Baumann Verwertungsgesellschaft Gmbh, 88471 Laupheim Protective scaffold to be used in construction
US20060180390A1 (en) * 2005-02-01 2006-08-17 Ken Thaler Roof edge fall protection apparatus
CN204370825U (en) * 2014-11-21 2015-06-03 长沙远大住宅工业集团有限公司 Assembled architecture faces frontier defense protection unit
CN105113851A (en) * 2015-09-14 2015-12-02 上海建工二建集团有限公司 Multifunctional prefabricated assembled building construction fence and construction method thereof
CN106968381A (en) * 2017-04-28 2017-07-21 广东省建科建筑设计院有限公司 With the prefabricated shear wall and overlapping plate node of Combined grouting sleeve connection

Similar Documents

Publication Publication Date Title
US11655641B2 (en) Construction building equipment and construction method thereof
CN106703416B (en) Steel roof truss dead man hanging method in small space
ITFI20100096A1 (en) "A COMPLEX OF PREFABRICATED ELEMENTS TO FORM A PREFABRICATED BUILDING AT AT LEAST TWO PLANS AND RELATED BUILDING AND INSTALLATION PROCEDURE"
CN110512719B (en) Construction method of large-span interval corridor high-altitude formwork steel platform for high-rise residence
CN102561690A (en) Construction method for supporting structures on two sides of post-cast strip by use of brick column
CN209194697U (en) A kind of prefabricated balcony of assembled architecture
CN104131688B (en) The special external hanging type job platform of assembled architecture and method of operating thereof
CN203625942U (en) Basement outer wall post-cast strip ahead water stopping structure
CN108798059A (en) A kind of old masonry seismic reinforcing structure and construction method
CN104234447B (en) Deep foundation ditch tool-type hangs stair
KR100579440B1 (en) Formwork-reinforced PC panels and assembly structures thereof
CN206352388U (en) A kind of special scaffold of dual operation platform elevator
CN103061508A (en) Triangular slip form device and construction method for the same triangular slip form
CN102733608A (en) Construction method for spray head layer of granulation tower
CN205976167U (en) Based on cast -in -place floor structures of detachable positioning control spare
TWI673418B (en) External wall cantilever construction platform and its assembly method
CN204645093U (en) Basement outer wall post-cast strip advanced treatment structure
CN114837088A (en) A kind of construction method of bearing platform on highway
CN109736585A (en) Shear wall, floor total-prefabricated construction safety protecting method
KR100934376B1 (en) Elevating and lowering platform and method of movement
CN106193621A (en) Fabricated construction superimposed sheet string hangs construction method
KR100901016B1 (en) Exterior Wall Scaffolding Safety Bracket of Building
KR20210141194A (en) Construction Method and Device of Wall and Floor Structure in Elevator's Machine Room in Apartment Building and Office Using Hanging Structural Method by Steel and Deck Plate in Top-down Structure
KR20040076245A (en) Wall structure with method of R.C steel reinforcing ground assembly(assembly plant) the method of estalishment with pulling up
CN204384738U (en) Poured band of outer wall of basement cement concrete draw-in groove construction hoisting equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190510