CN109695454A - The construction method of preliminary bracing is carried out in the constructing tunnel of high earthquake zone fracture area - Google Patents

The construction method of preliminary bracing is carried out in the constructing tunnel of high earthquake zone fracture area Download PDF

Info

Publication number
CN109695454A
CN109695454A CN201910075700.XA CN201910075700A CN109695454A CN 109695454 A CN109695454 A CN 109695454A CN 201910075700 A CN201910075700 A CN 201910075700A CN 109695454 A CN109695454 A CN 109695454A
Authority
CN
China
Prior art keywords
tunnel
steel
rock
underground water
carried out
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910075700.XA
Other languages
Chinese (zh)
Inventor
孟志强
郝国强
徐立新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Original Assignee
Hebei University of Engineering
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hebei University of Engineering filed Critical Hebei University of Engineering
Priority to CN201910075700.XA priority Critical patent/CN109695454A/en
Publication of CN109695454A publication Critical patent/CN109695454A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/003Arrangement of measuring or indicating devices for use during driving of tunnels, e.g. for guiding machines

Abstract

The invention discloses the construction methods that preliminary bracing is carried out in a kind of high earthquake zone fracture area constructing tunnel, comprising the following steps: one, rock stratum detection, two, underground water detection, three, tunnel excavation, four, top protection, five, integer support.The rubble of tunnel inner wall is first carried out closing protection by protective net by the present invention, it is fixed again by I-steel and arch steel structure, when being fixed using steelframe can the country rock to tunnel inner wall comprehensively closed, therefore, hereafter carry out the case where rubble is fallen from concrete would not occur when gunite concrete step again, not only facilitate carry out constructing tunnel, but also improve the safety of constructing tunnel.

Description

The construction method of preliminary bracing is carried out in the constructing tunnel of high earthquake zone fracture area
Technical field
The present invention relates to technical field of tunnel construction, more particularly to a kind of high earthquake zone fracture area constructing tunnel The middle construction method for carrying out preliminary bracing.
Background technique
When carrying out boring construction using Mining Method, surrounding rock supporting is generally divided into preliminary bracing and secondary lining, secondary lining Usually concrete or reinforced concrete structure.Before secondary lining applies, after just excavating, the support form that carries out immediately Referred to as preliminary bracing.Preliminary bracing increases structure safety to discharge and deforming in right amount for control surrouding rock stress after tunnel excavation It spends and facilitates construction, apply that rigidity is smaller and structure sheaf as permanent bearing structure a part immediately, generally there is injection coagulation Soil, gunite concrete add the forms such as anchor pole, gunite concrete anchor pole and steelframe combined supporting.
But there are some drawbacks in use in traditional preliminary bracing, and such as: traditional preliminary bracing is general only Need to carry out gunite concrete after tunnel excavation, or using anchor pole and steelframe to some biggish rocks loosened into One simple supporting of row, but this method is suitable only for the more stable situation use of rock property, on some highlands When shake band fracture area carries out preliminary bracing, since this area is in earthquake zone, tunnel surrounding medium stone is more, if using Gunite concrete carries out preliminary bracing, is easy the rubble when the concrete of injection does not solidify also and has fallen;If using anchor pole Comprehensive supporting, therefore existing initial stage branch can not also be carried out at this time since cofferdam medium stone is excessive by carrying out supporting with steelframe Maintaining method is not particularly suited for the tunnel surrounding supporting of high earthquake zone fracture area.
Therefore, how to overcome defect in the prior art, a kind of tunnel suitable for high earthquake zone fracture area is provided to enclose Petrous branch shield, the problem of becoming for those skilled in the art's urgent need to resolve.
Summary of the invention
In view of this, the present invention provides the construction parties for carrying out preliminary bracing in a kind of high earthquake zone fracture area constructing tunnel Method.
To achieve the goals above, the present invention adopts the following technical scheme:
The construction method of preliminary bracing is carried out in a kind of high earthquake zone fracture area constructing tunnel, comprising the following steps:
S100, rock stratum detection: drill hole sampling detection is carried out in tunnel surrounding rock to be excavated, and to rock interior rock Layer is made a concrete analysis of;
S200, underground water detection: using water detection appratus to the underground water in rock stratum there are situations to detect, and The area of the underground water source detected, flow direction, spatial position are detected in detail;
S300, tunnel excavation: after the detection and analysis of step S100 and step S200, selection rock property preferably and There is no the region of underground water to excavate tunnel, tunnel excavation method stays core local method or seven step steps using Ring Cutting Method;
S400, top protection: the Ring Cutting used in step S300 stay core local method or seven step benching tunnelling methods be intended to from Tunnel top starts to excavate, and after the completion of excavating tunnel top, Yao Jinhang top shield, steps are as follows for Specific construction:
S401, protective net is laid in tunnel top inner wall;
S402, anchor hole is stamped on the country rock of tunnel top inner wall;
S403, along tunnel direction of travel equidistant laying I-steel parallel to each other;
S404, I-steel is fixed on inside anchor hole using anchor pole;
S500, integer support: core local method or seven step benching tunnelling methods are stayed all to dig entire tunnel cross-section using Ring Cutting After opening, then integer support is carried out, steps are as follows for Specific construction:
S501, anchor hole is stamped on the country rock of tunnel side inner walls;
S502, protective net is laid in tunnel side inner walls;
S503, along tunnel direction of travel equidistant laying I-steel parallel to each other;
S504, I-steel is fixed on inside anchor hole using anchor pole;
S505, it is supported using I-steel of the arch steel structure to all inner walls in tunnel;
S506, all inner walls in tunnel progress gunning concrete is fixed.
The rubble of tunnel inner wall is first carried out closing protection by protective net by the present invention, then by I-steel and arch steel structure into Row fix, when being fixed using steelframe can the country rock to tunnel inner wall comprehensively closed, therefore, hereafter It carries out the case where rubble is fallen from concrete would not occur when gunite concrete step again, has both facilitated carry out constructing tunnel, The safety of constructing tunnel is improved again.
Further, based on the above technical solution, the present invention can also be improved as follows:
Preferably, in the step S100, when carrying out drill hole sampling detection, the spacing that tube sample boring opens up is 2 meters -5 meters, And it is in grid arrangement that tube sample boring, which is 2 meters -5 meters with spacing in tunnel upper to be excavated,;The region overlay of drill hole sampling is opened Region locating for the tunnel of digging enables the rock stratum of tunnel perimeter comprehensively to be sampled, and rock stratum is adequately visited in guarantee It surveys.
It preferably,, need to be by the rock taken out from drilling hole successively when carrying out drill hole sampling detection in the step S100 It removes, and rock is placed into marshalling in a reservoir, keep the rock sample taken out completely continuous.
The utility model has the advantages that being mostly detritus inside rock stratum, only collecting drilling because tunnel is provided with high earthquake zone fracture area The continuity that rock sample is kept when the rock sample of taking-up, just can enable rock sample completely reflect rock interior rock stratum The case where.
Preferably, in the step S200, when carrying out underground water detection, if there are undergrounds in tunnel excavation region for discovery Water then according to the water size of underground water and judges whether the underground water is underground underground river, if the underground water water less and It is not underground underground river, then is solved by way of carrying out extracting discharge to the underground water;If the underground water water is larger or should Underground water is underground underground river, then needs to be modified to avoid underground water at this to the path in tunnel.
The utility model has the advantages that can effectively avoid the groundwater recharge in construction only local into tunnel internal for above-mentioned technical proposal After lower water finder carries out detailed detection to tunnel excavation region, do not find that there are underground water in tunnel excavation region, It can directly be excavated.
Preferably, in the step S300, Ring Cutting stays the tunnel excavation method of core local method are as follows: first to tunnel top Portion is excavated, and is then excavated respectively to the tunnel side Liang Ge, and the rock at last middle part is cleared up by equipment;Seven step platforms The tunnel excavation method of rank method are as follows: tunnel top is excavated first, two successively then are carried out to the tunnel side Liang Ge respectively The rock at middle part is finally divided three layers and cleared up respectively by secondary excavation.
The utility model has the advantages that above two digging mode is all local excavation when excavating, be conducive to when excavating in time to tunnel Road inner wall carries out supporting, and country rock rubble is avoided to collapse.
It preferably,, need to be first using support rod to protection when tunnel top inner wall is laid with protective net in the step S401 Net is supported, and is then carried out anchor hole again and is opened up.
Preferably, the anchor hole in the step S402 and step S501, which needs to throw hole into hard when opening up, encloses Inside rock, guarantee that anchor pole can be fixed in country rock.
Preferably, in the step S403 and step S503, the laying spacing between two I-steel parallel to each other is 40-60 centimetres.
Preferably, in the step S404 and step S504, the tool that is fixed on I-steel using anchor pole inside anchor hole Body step are as follows: first anchor pole is inserted in anchor hole, then is perfused made of quick hardening cement in the gap among anchor pole and anchor hole Anchor pole is finally fixed on inside anchor hole using cement slurry by cement slurry.
Preferably, in the step S403 and step S503, I-steel when being laid with along tunnel direction of travel, by In tunnel be sublevel drive, therefore I-steel be by one section one section respectively splicing be laid with, and need to weld between every section of I-steel Being connected together makes I-steel form an entirety.
Preferably, it in the step S505, is supported, is had using I-steel of the arch steel structure to all inner walls in tunnel Body are as follows: arch steel structure is first divided into several segments, during installation from tunnel top using the mounting means of splicing by arch steel structure Start to install, every section of splicing is mounted on I-steel respectively, finally each section of arch steel structure is welded together, makes arch steel Structure forms an entirety.
By using above-mentioned technical proposal, preliminary bracing is carried out in a kind of high earthquake zone fracture area constructing tunnel of the present invention Construction method has the beneficial effect that
1, the present invention high earthquake zone fracture area carry out constructing tunnel when, first to the lithology of constructing tunnel region rock into Row deep drilling sample detection, while also the underground hydrological situation in constructing tunnel region is explored, final choice rock is strong The broken not serious, rock strength of degree is higher and region of not underground water carries out constructing tunnel, avoids the underground in construction Water is poured into tunnel internal, ensure that the safety of construction in later period.
2, the present invention selects Ring Cutting that core local method or seven step benching tunnelling methods is stayed to construct in construction, can accelerate The construction speed in tunnel and the safety for improving constructing tunnel.
3, the present invention timely uses protective net during tunnel excavation and blocks to tunnel inner wall, while using support Bar is supported protective net, and the rubble that can be avoided in the country rock of tunnel inner wall is fallen, and improves the safety of constructing tunnel.
4, the present invention is then passed through protective net after being supported using protective net and lays anchor hole on the country rock of tunnel inner wall, and I-steel and protective net are also secured to tunnel inner wall using anchor pole, protective net is fixed using I-steel, finally again Jack-up is supported to I-steel using arch steel structure, realizes the closed allround to tunnel inner wall country rock, then in tunnel It is just not in the case where rubble is fallen from concrete that gunite concrete, which is fixed, on wall, substantially increases work progress Convenience and safety.
Specific embodiment
The technical scheme in the embodiments of the invention will be clearly and completely described below, it is clear that described implementation Example is only a part of the embodiment of the present invention, instead of all the embodiments.Based on the embodiments of the present invention, this field is common Technical staff's every other embodiment obtained without making creative work belongs to the model that the present invention protects It encloses.
Embodiment:
The present invention provides the construction method that preliminary bracing is carried out in a kind of high earthquake zone fracture area constructing tunnel, this method Specifically includes the following steps:
S100, rock stratum detection: drill hole sampling detection is carried out in tunnel surrounding rock to be excavated, and to rock interior rock Layer is made a concrete analysis of;
Specifically, in above-mentioned steps S100, firstly, being drilled in tunnel surrounding rock to be excavated using probing method Sampling detection, the drilling depth that when sampling drills need to reach inside the rock stratum at tunnel excavation, and need to be to rock when drill hole sampling The lithology of layer is analyzed;Secondly, the spacing that tube sample boring opens up is 2-5 meters, and tube sample boring when carrying out drill hole sampling detection It with spacing is 2-5 meter in grid arrangement in tunnel upper to be excavated, the region of drill hole sampling will cover excavated tunnel comprehensively Region locating for road;It again, is mostly detritus inside rock stratum, therefore bored collecting since tunnel is provided with high earthquake zone fracture area The continuity that rock sample is kept when the rock sample that hole is taken out, need to successively remove the rock taken out from drilling hole, and The case where rock is placed marshalling in a reservoir, rock sample is enable completely to reflect rock interior rock stratum.
S200, underground water detection: using water detection appratus to the underground water in rock stratum there are situations to detect, and The area of the underground water source detected, flow direction, spatial position are detected in detail;
Specifically, the presence of the underground water in rock stratum is detected using water detection appratus in above-mentioned steps S200, When detecting in tunnel excavation region there are when underground water source, need to area to underground water source, flow direction, spatial position carry out it is detailed Detection, for avoiding in construction groundwater recharge into tunnel internal, when water detection appratus tunnel excavation region is carried out it is detailed That there are underground water in discovery tunnel excavation region after thin detection, then can directly be excavated.More specifically, it carries out When underground water detects, if there are underground water in tunnel excavation region for discovery, according to the water size of underground water and judgement Whether the underground water is underground underground river, if the underground water water is little and is not underground underground river, by carrying out to the underground water The mode for extracting discharge solves;If the underground water water is larger or the underground water is underground underground river, the road to tunnel is needed Diameter is modified to avoid underground water at this.
S300, tunnel excavation: after the detection and analysis of step S100 and step S200, selection rock property preferably and There is no the region of underground water to excavate tunnel, tunnel excavation method stays core local method or seven step steps using Ring Cutting Method;
Specifically, selection exists after to the lithology and the detailed detection of underground water progress and analysis in tunnel excavation region Rock property is preferably and tunnel is not excavated in the region of underground water, select when excavation Ring Cutting stay core local method or Seven step benching tunnelling methods excavate tunnel, and Ring Cutting stays the tunnel excavation method of core local method are as follows: first to tunnel top into Row excavates, and then excavates respectively to the tunnel side Liang Ge, and the rock at last middle part is cleared up by equipment;Seven step benching tunnelling methods Tunnel excavation method are as follows: tunnel top is excavated first, then successively the tunnel side Liang Ge is opened twice respectively It digs, finally divides three layers for the rock at middle part and clear up respectively.Since Ring Cutting stays core local method or seven step benching tunnelling methods to exist All it is local excavation when excavation, is conducive to carry out supporting to tunnel inner wall in time when excavating, country rock rubble is avoided to collapse.
S400, top protection: the Ring Cutting used in step S300 stay core local method or seven step benching tunnelling methods be intended to from Tunnel top starts to excavate, and because the area of constructing tunnel is high earthquake zone fracture area, has excavated by tunnel top Cheng Hou needs to carry out top shield in time, and steps are as follows for Specific construction:
S401, it is laid with chain link fence in tunnel top inner wall, chain link fence is used for the rubble loose to tunnel inner wall It is blocked, when tunnel top inner wall is laid with chain link fence, first chain link fence need to be supported using support rod, so Anchor hole is carried out again afterwards to open up;
S402, anchor hole is stamped on the country rock of tunnel top inner wall, the anchor hole opened up on country rock is used to install anchor pole, Anchor hole needs to throw hole inside Hard Rock Mass into when opening up, and guarantees that anchor pole can be securely held in country rock;
S403, along tunnel direction of travel equidistant laying I-steel parallel to each other, wherein two I-steel parallel to each other Between laying spacing be 50 centimetres;
S404, I-steel is fixed on inside anchor hole using anchor pole, which can not only fix chain link fence In tunnel inner wall, moreover it is possible to which the biggish rubble of tunnel inner wall quality is fixed;
Specifically, I-steel to be fixed on to the specific steps inside anchor hole using anchor pole are as follows: anchor pole is first inserted in anchoring Kong Zhong, then cement slurry made of quick hardening cement is perfused in the gap among anchor pole and anchor hole, finally utilize cement slurry by anchor Bar is fixed on inside anchor hole.
S500, integer support: core local method or seven step benching tunnelling methods are stayed all to dig entire tunnel cross-section using Ring Cutting After opening, integer support is carried out again to tunnel side inner walls, steps are as follows for Specific construction:
S501, anchor hole is stamped on the country rock of tunnel side inner walls, the anchor hole opened up on country rock is used to install anchor pole, Anchor hole needs to throw hole inside Hard Rock Mass into when opening up, and guarantees that anchor pole can be securely held in country rock;
S502, it is laid with chain link fence in tunnel side inner walls, chain link fence is used for the rubble loose to tunnel inner wall It is blocked;
S503, along tunnel direction of travel equidistant laying I-steel parallel to each other, wherein two I-steel parallel to each other Between laying spacing be 50 centimetres;
S504, I-steel is fixed on inside anchor hole using anchor pole, which can not only fix chain link fence In tunnel inner wall, moreover it is possible to which the biggish rubble of tunnel inner wall quality is fixed;
Specifically, I-steel to be fixed on to the specific steps inside anchor hole using anchor pole are as follows: anchor pole is first inserted in anchoring Kong Zhong, then cement slurry made of quick hardening cement is perfused in the gap among anchor pole and anchor hole, finally utilize cement slurry by anchor Bar is fixed on inside anchor hole.
S505, it is supported using I-steel of the arch steel structure to all inner walls in tunnel;
Specifically, arch steel structure and I-steel are fixed using bolt after being installed arch steel structure, Arch steel structure is for further supporting I-steel, wherein arch steel structure agrees with tunnel inner wall;
S506, all inner walls in tunnel progress gunning concrete is fixed, gunning concrete can be by chain link fence and tunnel Road inner wall is fixed, and further the rubble of tunnel inner wall is fixed.
In order to further optimize the above technical scheme, in step S403 and step S503, I-steel is advanced along tunnel When direction is laid with, since tunnel is sublevel drive, I-steel be by one section one section respectively splicing be laid with, therefore it is every It needs to weld together between section I-steel, so that I-steel is formed an entirety, to ensure its stability, fastness.
In order to further optimize the above technical scheme, in step S505, using arch steel structure to all inner walls in tunnel I-steel is supported, specifically: arch steel structure is first divided into several segments using the mounting means of splicing by arch steel structure, It is preferred that 9 sections, it installs since tunnel top, every section of splicing is mounted on I-steel during installation respectively, finally encircle each section Shape welding for steel structure together, makes arch steel structure form an entirety, to ensure its stability, fastness.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest scope of cause.

Claims (10)

1. carrying out the construction method of preliminary bracing in a kind of high earthquake zone fracture area constructing tunnel, which is characterized in that this method packet Include following steps:
S100, rock stratum detection: in tunnel surrounding rock to be excavated carry out drill hole sampling detection, and to rock interior rock stratum into Row concrete analysis;
S200, underground water detection: using water detection appratus to the underground water in rock stratum there are situations to detect, and to spy The area of the underground water source measured, flow direction, spatial position are detected in detail;
S300, tunnel excavation: after the detection and analysis of step S100 and step S200, selection is preferable in rock property and does not have Tunnel is excavated in the region of underground water, and tunnel excavation method stays core local method or seven step benching tunnelling methods using Ring Cutting;
S400, top protection: the Ring Cutting used in step S300 stays core local method or seven step benching tunnelling methods to be intended to from tunnel Top starts to excavate, and after the completion of excavating tunnel top, Yao Jinhang top shield, steps are as follows for Specific construction:
S401, protective net is laid in tunnel top inner wall;
S402, anchor hole is stamped on the country rock of tunnel top inner wall;
S403, along tunnel direction of travel equidistant laying I-steel parallel to each other;
S404, I-steel is fixed on inside anchor hole using anchor pole;
S500, integer support: after staying core local method or seven step benching tunnelling methods all to excavate entire tunnel cross-section using Ring Cutting, Integer support is carried out again, and steps are as follows for Specific construction:
S501, anchor hole is stamped on the country rock of tunnel side inner walls;
S502, protective net is laid in tunnel side inner walls;
S503, along tunnel direction of travel equidistant laying I-steel parallel to each other;
S504, I-steel is fixed on inside anchor hole using anchor pole;
S505, it is supported using I-steel of the arch steel structure to all inner walls in tunnel;
S506, all inner walls in tunnel progress gunning concrete is fixed.
2. the construction method of preliminary bracing is carried out in high earthquake zone fracture area constructing tunnel according to claim 1, it is special Sign is: in the step S100, when carrying out drill hole sampling detection, the spacing that tube sample boring opens up is 2-5 meters, and tube sample boring It with spacing is 2-5 meter in grid arrangement in tunnel upper to be excavated;Locating for the tunnel that the region overlay of drill hole sampling is excavated Region.
3. the construction method of preliminary bracing is carried out in high earthquake zone fracture area constructing tunnel according to claim 1, it is special Sign is: in the step S100, when carrying out drill hole sampling detection, the rock taken out from drilling hole need to successively be removed, and Rock is placed into marshalling in a reservoir, keeps the rock sample taken out completely continuous.
4. the construction method of preliminary bracing is carried out in high earthquake zone fracture area constructing tunnel according to claim 1, it is special Sign is: in the step S200, when carrying out underground water detection, if there are underground water, roots in tunnel excavation region for discovery According to underground water water size and judge whether the underground water is underground underground river, if the underground water water less and be not underground Underground river is then solved by way of carrying out extracting discharge to the underground water;If the underground water water is larger or the underground water is Underground underground river then needs to be modified to avoid underground water at this to the path in tunnel.
5. the construction method of preliminary bracing is carried out in high earthquake zone fracture area constructing tunnel according to claim 1, it is special Sign is: in the step S300, Ring Cutting stays the tunnel excavation method of core local method are as follows: opens first tunnel top It digs, then the tunnel side Liang Ge is excavated respectively, the rock at last middle part is cleared up by equipment;The tunnel of seven step benching tunnelling methods Road digging mode are as follows: tunnel top is excavated first, then successively the tunnel side Liang Ge is excavated twice respectively, most Divide three layers for the rock at middle part afterwards to clear up respectively.
6. the construction method of preliminary bracing is carried out in high earthquake zone fracture area constructing tunnel according to claim 1, it is special Sign is: in the step S401, when tunnel top inner wall is laid with protective net, need to first be propped up using support rod protective net Support, then carries out anchor hole again and opens up.
7. the construction method of preliminary bracing is carried out in high earthquake zone fracture area constructing tunnel according to claim 1, it is special Sign is: in the step S403 and step S503, the laying spacing between two I-steel parallel to each other is 40-60 lis Rice.
8. the construction method of preliminary bracing is carried out in high earthquake zone fracture area constructing tunnel according to claim 1, it is special Sign is: in the step S404 and step S504, the specific steps that are fixed on I-steel using anchor pole inside anchor hole are as follows: First anchor pole is inserted in anchor hole, then cement slurry made of quick hardening cement is perfused in the gap among anchor pole and anchor hole, most Anchor pole is fixed on inside anchor hole using cement slurry eventually.
9. the construction method of preliminary bracing is carried out in high earthquake zone fracture area constructing tunnel according to claim 1, it is special Sign is: in the step S403 and step S503, I-steel along tunnel direction of travel when being laid with, since tunnel is Sublevel drive, therefore I-steel is to be spliced to be laid with respectively by one section one section, and need to weld together between every section of I-steel I-steel is set to form an entirety.
10. the construction method of preliminary bracing is carried out in high earthquake zone fracture area constructing tunnel according to claim 1, it is special Sign is: in the step S505, it is supported using I-steel of the arch steel structure to all inner walls in tunnel, specifically: arch Arch steel structure is first divided into several segments, is pacified since tunnel top during installation by shape steel construction using the mounting means of splicing Every section of splicing, is mounted on I-steel respectively, finally welds together each section of arch steel structure, make arch steel structure shape by dress At an entirety.
CN201910075700.XA 2019-01-25 2019-01-25 The construction method of preliminary bracing is carried out in the constructing tunnel of high earthquake zone fracture area Pending CN109695454A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910075700.XA CN109695454A (en) 2019-01-25 2019-01-25 The construction method of preliminary bracing is carried out in the constructing tunnel of high earthquake zone fracture area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910075700.XA CN109695454A (en) 2019-01-25 2019-01-25 The construction method of preliminary bracing is carried out in the constructing tunnel of high earthquake zone fracture area

Publications (1)

Publication Number Publication Date
CN109695454A true CN109695454A (en) 2019-04-30

Family

ID=66234523

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910075700.XA Pending CN109695454A (en) 2019-01-25 2019-01-25 The construction method of preliminary bracing is carried out in the constructing tunnel of high earthquake zone fracture area

Country Status (1)

Country Link
CN (1) CN109695454A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113588190A (en) * 2021-10-08 2021-11-02 四川藏区高速公路有限责任公司 Vibration response test device for blasting construction to adjacent existing tunnel

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102852533A (en) * 2012-10-18 2013-01-02 山东大学 High-strength three-dimensional support system of yielding type restriction concrete lagging jack
CN103615273A (en) * 2013-12-04 2014-03-05 山东大学 Square steel confined concrete arch center wall back filling bolting-grouting support system and construction method
CN106869969A (en) * 2017-03-14 2017-06-20 中铁五局集团第工程有限责任公司 A kind of excavation supporting construction method of soft rock large section tunnel
CN206972268U (en) * 2017-06-27 2018-02-06 中铁十一局集团第四工程有限公司 A kind of extrusion pressing type weak surrounding rock large section tunnel support system
CN108374663A (en) * 2018-02-01 2018-08-07 中铁十二局集团有限公司 Mould builds construction twice for a kind of sand gravel geology tunnel
CN108825234A (en) * 2018-04-26 2018-11-16 新汶矿业集团有限责任公司 Gob side entry retaining structure and method under the conditions of a kind of pit mining girdle

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102852533A (en) * 2012-10-18 2013-01-02 山东大学 High-strength three-dimensional support system of yielding type restriction concrete lagging jack
CN103615273A (en) * 2013-12-04 2014-03-05 山东大学 Square steel confined concrete arch center wall back filling bolting-grouting support system and construction method
CN106869969A (en) * 2017-03-14 2017-06-20 中铁五局集团第工程有限责任公司 A kind of excavation supporting construction method of soft rock large section tunnel
CN206972268U (en) * 2017-06-27 2018-02-06 中铁十一局集团第四工程有限公司 A kind of extrusion pressing type weak surrounding rock large section tunnel support system
CN108374663A (en) * 2018-02-01 2018-08-07 中铁十二局集团有限公司 Mould builds construction twice for a kind of sand gravel geology tunnel
CN108825234A (en) * 2018-04-26 2018-11-16 新汶矿业集团有限责任公司 Gob side entry retaining structure and method under the conditions of a kind of pit mining girdle

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
仲崇海: "软弱围岩大断面隧道台阶法施工技术参数研究", 《中国优秀硕士学位论文全文数据库 工程科技II辑》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113588190A (en) * 2021-10-08 2021-11-02 四川藏区高速公路有限责任公司 Vibration response test device for blasting construction to adjacent existing tunnel

Similar Documents

Publication Publication Date Title
CN104675403B (en) A kind of underground space construction method and supporting construction
CN101775988B (en) Method for constructing from inclined shaft to main tunnel in weak surrounding rock
CN110219654B (en) Advanced construction method for side pilot tunnel of mud-rock arch tunnel
CN104879144B (en) The excavating construction method of the underground space is built with array push pipe in soft clay area
CN102966108B (en) Construction method of deep foundation pit close to building and adopting underground structure as internal support
CN103469817B (en) Existing subway station main structure broadening construction method
CN102748040B (en) Main structure for metro long-span station and pillar arching construction method thereof
CN103161476B (en) Mechanical shaft-forming method of shield cutterhead maintenance shaft in tunnel and underground construction
CN202707075U (en) Long-span subway station main structure constructed based on column and arch method
CN108035733B (en) A kind of perpendicular support partial excavation method of rock matter large section tunnel steelframe dike combination
CN109208637A (en) Increase the construction method of open-cut station newly on the basis of existing tunnel
CN108130904A (en) A kind of construction method of the composite bushing drill-pouring pilework of neighbouring existing subway
CN106567717A (en) Construction oblique channel structure utilizing subway exit and entrance and construction method
CN106285715B (en) Closely the construction method of first branch bored tunnel is worn in side to balancing earth-pressure shielding machine
CN106437726A (en) Ground fracture crushed zone passing construction method for shallow-buried tunnel excavation
CN108843333A (en) Collapsible Loess District tunneling double-arched tunnel passes through the construction method of existing railway
CN109339080A (en) A kind of open-cut foundation ditch deep slob region vacuum precipitation system and construction method
CN109538246A (en) Ledge method tunneling subway station arch springing ruggedized construction and construction method
CN108677924A (en) Double miniature steel pipe pile slip casting is at wall partition-type structures and method
CN107023300A (en) A kind of use canopy, which is defended the doctrine, builds the construction method of subway station
WO2021088349A1 (en) Method for excavating tunnel shaft
CN110017144A (en) A kind of three step construction method of loess tunnel considering bottom stab ilization processing
CN104675405B (en) Rectangular pipe jacking machine tunnel entering auxiliary structure and construction method
CN109723443A (en) Method for tunnel construction
CN107503755A (en) A kind of construction method for exempting from button arch flat-top cavern-pile method construction subway station

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20190731

Address after: 056038 Guangming South Street, Hebei, Handan, No. 199

Applicant after: Hebei University of Engineering

Applicant after: China Railway 19th Bureau Group 2nd Co., Ltd.

Address before: 056038 Guangming South Street, Hebei, Handan, No. 199

Applicant before: Hebei University of Engineering

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190430