Perimeter security protects screen component Download PDF

Info

Publication number
CN109689995A
CN109689995A CN201780040991.8A CN201780040991A CN109689995A CN 109689995 A CN109689995 A CN 109689995A CN 201780040991 A CN201780040991 A CN 201780040991A CN 109689995 A CN109689995 A CN 109689995A
Authority
CN
China
Prior art keywords
screen component
protection screen
perimeter security
suspension
protection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201780040991.8A
Other languages
Chinese (zh)
Inventor
埃米利奥·罗萨蒂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Form 700 Pty Ltd
Original Assignee
Form 700 Pty Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority to AU2016901878A priority Critical patent/AU2016901878A0/en
Priority to AU2016901878 priority
Priority to AU2016904047A priority patent/AU2016904047A0/en
Priority to AU2016904047 priority
Application filed by Form 700 Pty Ltd filed Critical Form 700 Pty Ltd
Priority to PCT/AU2017/000117 priority patent/WO2017197440A1/en
Publication of CN109689995A publication Critical patent/CN109689995A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/32Safety or protective measures for persons during the construction of buildings
    • E04G21/3204Safety or protective measures for persons during the construction of buildings against falling down
    • E04G21/3247Storey high safety barrier hung from the facade and sliding up from level to level as work progresses

Abstract

This disclosure relates to which the perimeter security for building protects screen component.In one aspect, the perimeter security protection screen component includes upper protection screen component and screen component is protected in suspension that is additional from upper protection screen component and extending below upper protection screen component.In one form, upper protection screen component or suspension protection at least one of screen component are adapted so as to protect screen component that can be attached on upper protection screen component and from upper protective net assembly removal in just suspension while using on building of upper protection screen component.

Description

Perimeter security protects screen component
Priority document
This application claims priority below:
The Australia of entitled " suspension protective net (HANGING SCREEN) " submitted on May 19th, 2016 is interim special Benefit application No.2016901878;
Entitled " perimeter security protection screen component (the A PERIMETER SAFETY submitted on October 5th, 2016 SCREEN ASSEMBLY) " Australian Provisional Patent Application No.2016904047;
The content of every patent application is fully incorporated herein by reference.
It is incorporated by reference into
Following publication is cited in this application, and its content is fully incorporated herein by reference:
Entitled with the name of Formula One Self Driving Screens Pty Ltd " uses reciprocating thousand The promotion on jin top or transport device (A LIFTING OR TRANSPORTING MEANS USING A RECIPROCATING JACK international patent application No.PCT/AU2003/001112) ".
Technical field
This disclosure relates to which the perimeter security for building protects screen component.
Background technique
Perimeter security protective net is commonly used in providing protective net in the edge of the floor for the building built (screen) or barrier.
It is desirable that safety guard net extends above uppermost completion floor, to protect worker as the new of building More high-storey prepares template, and extends downwardly into lower floor, waits the final fixation of window or exterior wall.However, protective net ruler A very little critical limitation is the fact that they are usually transported and then hung in place by semitrailer.This is to protective net and/or prevents The physical size of protective net sub-component is applied with limitation.
Exactly in this background and in the case where problems associated and difficulty, the present invention is developed.
From the following description taken in conjunction with the accompanying drawings, certain objects and advantages of the invention will become obvious, wherein pass through Illustrate and exemplary mode, discloses the embodiment of the present invention.
Summary of the invention
According in a first aspect, providing a kind of perimeter security protection screen component for building, perimeter security protection Screen component includes upper protection screen component, and suspension that is additional from upper protection screen component and extending below upper protection screen component is anti- Protecting net component.
In one form, at least one of upper protection screen component or suspension protection screen component are adapted so that in upper protection Just suspension protection screen component can be attached on upper protection screen component and from upper protection screen component while using on building Screen component removes.
In one form, upper protection screen component is adapted so that suspension protection screen component can protect screen component attached from this Add.
In one form, suspension protection screen component is suitable for additional from upper protection screen component.
In one form, suspension protection screen component is fixed against protection screen component.
In one form, suspension protection screen component extends from upper protection screen component.
In one form, upper protection screen component is climbing protection screen component.That is, with building work into Exhibition, it is adapted to building raising.
In one form, as an alternative, upper protection screen component is not climbing protection screen component, and is had to be by The component that its external device (such as crane or capstan system) relocates.
In one form, upper protection screen component includes for relative to the fixed perimeter security protection screen component of building Pedestal by frame on the base, and relies on the protective net on frame.
In one form, upper protection screen component includes at least one extended inside the protective net and towards building Platform.
In one form, upper protection screen component includes multiple platforms being vertically spaced apart.
In one form, suspension protection screen component includes frame and relies on the protective net on frame.
In one form, each protective net includes multiple protective net panels.
In one form, each protective net panel includes frame and filling panel.
In one form, the filling panel or each filling panel include net.As an alternative, fill surface Plate includes solid panels.
In one form, suspension protection screen component further includes being located inside protective net and extending at least towards building One platform.
In one form, suspension protection screen component includes multiple platforms being vertically spaced apart.
In one form, each platform is dismountable, or can be moved between extended position and retracted position, with Suspension protection screen component is sling in help.
In one form, suspension protection screen component is in the outside of the protective net of upper protection screen component (relative to building) It relies on protection screen component.
In one form, as an alternative, suspension protection screen component is in the inside of the protective net of upper protection screen component (relative to building) is fixed against on upper protection screen component.
In one form, as an alternative, suspension protection screen component relies on the protective net of protection screen component On lower edge.
In one form, the protective net of suspension protection screen component forms the continuation of the protective net of protection screen component Point.
In one form, upper protection screen component includes at least one installation part, and suspension protection screen component can be suspended on On the installation part.
In one form, upper protection screen component includes multiple installation parts.
In one form, upper protection screen component includes multiple installation parts being vertically spaced apart.
In one form, the installation part or each installation part are located at the outer of the protective net of upper protection screen component Side.
In one form, each installation part in these installation parts includes for can nestedly receive suspension protective net group The saddle of a part of part.
In one form, the part or each part are the transverse beam assemblies for hanging protection screen component.? In this case, transverse beam assembly is cross-member, and which increase the supports to frame.
In one form, as an alternative, the part or each part are the cross for hanging protection screen component Beam.In this case, crossbeam is lateral member, and which increase the supports to frame.
In one form, each installation part includes (or hook-shaped) installation guide outwardly extending, angled up, For one in crossbeam to be directed in saddle.
In one form, the transverse beam assembly or each transverse beam assembly include length adjustment device.
In one form, the transverse beam assembly or each transverse beam assembly include that center portion and a pair are adjustable End.
In one form, each end can be moved between retracted position and extended position relative to center portion It is dynamic.
In one form, the protective net for each of upper protection screen component and suspension protection screen component includes more A protective net panel assembly.
In one form, each protective net panel assembly includes width adjusting device.
In one form, the protective net panel assembly or each protective net panel assembly include center portion and a pair Adjustable side.
In one form, each side can be moved between retracted position and extended position relative to center portion It is dynamic.
In one form, as an alternative, the arrangement of installation part and transverse beam assembly can in upper protection screen component and It is inverted on suspension protection screen component.
A kind of suspension protective net group of perimeter security protection screen component for building is provided according to another aspect, Part, perimeter security protection screen component includes upper protection screen component and suspension protection screen component, wherein suspension protection screen component is suitable In additional from upper protection screen component and extend below upper protection screen component.
A kind of upper protection screen component of perimeter security protection screen component for building is provided according to another aspect, Perimeter security protection screen component includes upper protection screen component and suspension protection screen component, wherein upper protection screen component is adapted so that Suspension protection screen component can add from upper protection screen component and extend below upper protection screen component.
A kind of perimeter security protection screen component for building, perimeter security protection are provided according to another aspect, Screen component includes the first protection screen component and protects screen component from the first protection screen component additional second, wherein the first protective net At least one of component or the second protection screen component are adapted so that just using on building in the first protection screen component same When the second protection screen component can be attached on the first protection screen component and from the first protective net assembly removal.
For ease of description, implement perimeter security of the invention below with usually assembled position description as shown in drawings to prevent Protecting net component, and it is possible to use the terms such as front, rear, top, and bottom, level, longitudinal direction with reference to the usual position.However, periphery Security protection screen component can be to be different from the orientation for being described herein as and showing manufacture, transport or sale.
The detailed description of one or more embodiments of the invention is provided with reference to the accompanying drawing, and attached drawing is by way of example Show the principle of the present invention.Although describing the present invention in conjunction with these embodiments, it is to be understood that the present invention is not limited to any Embodiment.On the contrary, the scope of the present invention is limited only by the appended claims, and the present invention include many replacements, modification and Equivalent.For exemplary purposes, numerous specific details are set forth in the following description in order to provide to thorough reason of the invention Solution.
The present invention can be practiced according to claim in the case where some or all of these no details. For the sake of clarity, it is not described in known technologic material in technical field related to the present invention, thus will not need not The fuzzy present invention in strategic point.
Detailed description of the invention
The embodiment of the present invention is discussed below with reference to accompanying drawings, in the accompanying drawings:
Fig. 1 is the schematic side elevation of perimeter security protection screen component according to first embodiment;
Fig. 2 is the schematic side elevation of perimeter security protection screen component according to the second embodiment;
Fig. 3 is the front view of the perimeter security protection screen component of Fig. 2;
Fig. 4 is the plan view of the perimeter security protection screen component of Fig. 2;
Fig. 5 is the schematic side elevation of perimeter security protection screen component according to the third embodiment;
Fig. 6 is the decomposition side view of the perimeter security protection screen component of Fig. 5;
Fig. 7 is the front view of the perimeter security protection screen component of Fig. 5;
Fig. 8 is the plan view of the perimeter security protection screen component of Fig. 5, and which further illustrate lift frame components;
Fig. 9 is the detail view intercepted at " details 1 " in Fig. 5;
Figure 10 is the front view of lift frame component shown in Fig. 8 and Fig. 9;
Figure 11 is the plan view of the lift frame component of Figure 10;
Figure 12 is the front view of the center portion of the lift frame component of Figure 10;
Figure 13 is the plan view of the center portion of Figure 12;
Figure 14 is the front view of the end of the lift frame component of Figure 10;
Figure 15 is the plan view of the end of Figure 14;And
Figure 16 is the detailed view of the end plate since the end of Figure 14.
In the following description, run through attached drawing, identical appended drawing reference indicates identical or corresponding part.
Specific embodiment
Referring now to fig. 1, perimeter security protection screen component 1 is shown, multi-story structure just under construction is relied on Completion floor 2 on.
Perimeter security protect screen component 1 include upper protection screen component 50, surround in use the periphery of building and Extend above uppermost completion floor, primarily to protection prepares the worker of the template of the new more high-storey of building.
Upper protection screen component 50 includes the protective net 52 being made of multiple protective net panels 54, wherein each protective net panel 54 include plate framework and filling panel (being in this case net), and wherein each protective net panel 54 relies on frame 60 On.In this embodiment, frame 60 includes the space frame structure of approximately cuboid shape, and including multiple frames spaced apart Trestle 62, frame column 62 are bridged by multiple beams 64 and hound 66.
Frame 60 further includes at least a pair of of vertical support frame column 70.As shown in figure 3, each stent strut 70 is by along stent strut 70 and the evenly-spaced multiple connectors 68 of length of frame column 62 be connected to frame column 62 but be spaced apart with frame column 62.It connects Clutch 68 is narrower than stent strut 70.The result is that forming a series of elongated slots between stent strut 70, frame column 62 and connector 68.This The function of a little elongated slots will be further described below.
Each stent strut 70 is carried on bracket (also referred to as shoe) 80, which relies on horizontal shore (also referred to as Needle or pedestal) on 90, which fixes relative to 2 plate of floor again.
Each bracket 80 includes a pair of side plates, and each side plate has flange on its leading edge, is located to flange portion every Before a stent strut 70.One or each side plate can be hinged or can be separated so that bracket 80 is fixed to stent strut 70 On.
Each bracket 80 includes locking devicen, which is designed so that stent strut 70 can be only with respect to each Frame 80 moves in one direction.Locking devicen (not shown) includes the bar for being hinged to the top edge of a side plate.Bar is across branch Frame 80 extends, so that it is shelved on the upper surface of opposite side plate.Bar is positioned to extend through by bracket 80, protection net post 62 and connector 68 interval formed elongated hole.
Frame 60 is inserted into protective net 52 and stent strut 70, so that the plate of the protective net 52 of upper protection screen component 50 and completion 2 edge is horizontally spaced apart.In this way, the beam 64 of frame 60 can be the one or more formed by the plank for bridging these beams 64 Platform (or aisle) provides support.In this way it is possible to nearly form the edge of the plate 2 of floor.
Perimeter security protection screen component 1 further includes suspension protection screen component 150, and suspension protects screen component 150 from upper protection Screen component 50 is additional, and extends to lower floor below upper protection screen component 50 around the periphery of building, waiting window and/or The final fixation of exterior wall.
Suspension protection screen component 150 includes frame 60 and the protective net 152 being made of multiple protective net panels 154.
In order to accommodate suspension protection screen component 150, upper protection screen component 50 includes for hanging the multiple of protective net 150 Installation part 100.Each of these installation parts 100 include the crossbeam 160 for can nestedly receive suspension protective net 150 Saddle 102 and outwardly extending installation guide 104, the installation guide (or hook-shaped) angled up is to be used for a cross Beam is directed in saddle 102.
In order to accommodate installation part 100, each beam 64 of frame 60 includes one section of square hollow steel part.Each installation part 100 are similarly included one section of square hollow steel part, are sized to be inserted into from the outside (relative to building) of protective net 52 In one beam 64 of frame 60.Each of beam 64 and installation part 100 include pin hole array, for receive pin (or bolt) with Installation part 100 is fixed to the beam 64 of frame 60.
In use, suspension protection screen component 150 is lifted (using crane lifting point) in place, and when suspension protection When screen component 150 is reduced by crane, guidance suspension protective net 150 is entered its saddle on installation part 100 by installation guide 104 In seat 102.Then, suspension protection screen component 150 by it is upper protection screen component 50 lower end its (relative to building) towards Outer side and upper protection screen component 150 are partly be overlapped.
Perimeter security protection screen component 1 further includes the device for promoting it relative to building.One reality of the device The detailed description for applying example can be found in PCT/AU2003/001112, and be incorporated herein at least through the mode of reference.So And, it should be understood that it can be using the hoisting mechanism of substitution, or can be promoted using the external of such as crane or capstan winch Device.
In one embodiment, lifting device includes two hydraulic cylinders (although these cylinders can use power screw or machinery Jack replacement), wherein each hydraulic cylinder extends at end on it from the bracket 80 of the mounting rail 90 in its lower end not to be had Another bracket 80 of mounting rail 90.Notwithstanding two hydraulic cylinders, but three or more hydraulic cylinders also can be used.? In the case where two or more hydraulic cylinders, important requirement is to realize the reasonable equal expansion rate of each cylinder.This can be by Hydraulic technique personnel easily realize.Furthermore it is possible to provide the system using single hydraulic cylinder.In this case, additional Supporting beam 90 can be in same level in the side of hydraulic cylinder with hydraulic cylinder or spaced above or below in hydraulic cylinder It opens.
In operation, when hydraulic cylinder expands, the locking devicen on the bracket 80 of hydraulic cylinder upper end will be engaged against Device and therefore lifting bracket column 70.It will not pass through remaining bracket 80 and prevent moving up for frame.Bar will be hinged up with Allow connector as desired by.
In use, when stent strut 70 is moving up, connector will be finally against the lower surface of locking bar.Stent strut 70 continue upward it is mobile will lead to bar and be hinged up and connector is allowed to pass through, therefore bar will be again downwards hingedly to be shelved on On the upper surface of adjacent side plates.When connector is against the upper surface of bar, bar will prevent stent strut 70 from moving down.
In the maximum swelling degree of hydraulic cylinder, connector 68 be spaced apart so that connector 68 just passed through it is hydraulic Locking devicen and remaining bracket on the bracket 80 of cylinder lower end.Therefore, the contraction of hydraulic cylinder will lead to stent strut 70 and be kept, Because connector is resisted against on the upper surface of the bar on the bracket 80 on hydraulic cylinder lower end.On the bracket 80 of hydraulic cylinder upper end Locking devicen will operate to allow bracket 80 to move down relative to stent strut 70, until it reaches its extreme lower position.In addition, This can be designed to make it easily to place relative to connector, so that when the expansion of hydraulic cylinder starts, on hydraulic cylinder upper end Bracket 80 on bar will re-engage with connector to restore lifting bracket column 70.
In this way, stent strut 70 is easily elevated relative to supporting beam 90.Obviously, relatively short stroke hydraulic cylinder It can be efficiently used for lift frame.
Once the lower edge of protective net reaches its extreme higher position relative to supporting beam 90, then hydraulic cylinder is repositioned onto Layer is a simple process.As shown in Fig. 2, hydraulic cylinder can be disconnected from the bracket 80 of its lower end.Upper bracket 80 and stent strut 70 disconnect.Lower bracket 80 continues braced frame while hydraulic cylinder disconnects.
In order to provide additional support, other beam 90 and bracket 80 can be fixed on above the position of hydraulic cylinder or under At the floor of side.
In use, suspension protection screen component 150 will hang and be hung below from upper protection screen component 50, and work as Worker provides protection when completing facade (and except other) of building in lower floor.When upper protection screen component 50 increases When, the suspension protective net 150 hung on it will rise therewith.
Suspension protection screen component 150 may also include one or more platforms or aisle 170, from frame 152 towards building Object extends, substantially to bridge the gap between these.
For the ease of aisle 170, suspension protection screen component 150 includes multiple aisle installation parts 180.Each aisle installation part 180 include the bracket fixed relative to the frame 152 of suspension protection screen component 150, wherein each bracket includes for cantilever Mode receives the one end in the aisle of supporting beam 174.Bolt hole array extends along each aisle supporting beam 174, and is using In, bolt can pass through this some holes releasedly to fix aisle supporting beam 174 relative to installation part 180.
Bracket 180 arranges (is laterally extended across suspension protection screen component 150) that in groups every group is protected screen component along suspension 150 152 longitudinal gap of frame is opened.In this way, aisle 170 may be positioned to the floor levels of match.
The additional stability in aisle 170 can be provided by diagonal struts.One example of diagonal struts 176 is anti-in suspension Extend between the frame 152 and aisle supporting beam 174 of protecting net component 150, and another example of diagonal struts 178 is in vertical phase Extend between the aisle supporting beam 174 in adjacent aisle 170.
It pivots, and exists between the open and closed positions if desired, aisle 170 or aisle 170 can be removed Space between protective net 152 and the edge of floor 2 can be used for transmitting object between floor 2.In one example may be used The object of such as window or cladding boards etc to be reduced to the pre-determined bit of side of buildings using minor crane from upper floor Set, but in the inside of protective net 152, crane supports the weight of window or coating plate, at the same be positioned and fixed in this way to Position.
Referring now to Fig. 2 to Fig. 4, perimeter security protection screen component 1a according to another embodiment is shown.Periphery Security protection screen component 1a's is identical (or almost the same) as corresponding component shown in the perimeter security of Fig. 1 protection screen component 1 Those of component will be indicated by the same numbers, and will not be described in detail further.
In perimeter security protection screen component 1a, the outermost of the frame 60 of the protective net 52 for upper protection screen component 50 Frame column 62 extends high than most inner side frame column 62, and protective net 52 is allowed to extend get Geng Gao, to increase as building The amount for the protection that worker at the top of object provides.
Referring now to Fig. 5 to Fig. 9, perimeter security protection screen component 1000 according to another embodiment is shown.Week (or the almost phase identical as corresponding component shown in the perimeter security of Fig. 1 protection screen component 1 of side security protection screen component 1000 Component will be indicated by the same numbers those of together), and will not be described in detail further.
It includes upper protection screen component 1050 that perimeter security, which protects screen component 1000, comprising by multiple protective net panel assemblies The protective net 1052 of 1054 compositions.
Referring to each of Fig. 7, Fig. 8 and Fig. 9, it can be seen that each protective net panel assembly 1054 includes center portion 1054a and a pair of adjustable side 1054b.Each side 1054b in retracted position and can be stretched relative to center portion 1054a It is moved between setting exhibition position.In retracted position, side 1054b is Chong Die with the top center portion 1054a or lower part is overlapped, and is stretching Exhibition position is set, and each side 1054b extends from the side edge of center portion 1054a.Moreover, in this embodiment, each side 1054b is relative to center portion 1054a intussusception.That is, each side 1054b is slidably received in center portion In slot in the side edge of 1054a.In this way, each protective net panel assembly 1054 can prolonging by side 1054b It stretches and broadens, or narrowed by their fold-back.By widening protective net panel assembly 1054, adjacent periphery can be bridged Gap between security protection screen component 1000.Narrowing during transport and processing for protective net panel assembly 1054 is useful , especially lift up into using position and by them by them from when position being used to reduce.
Perimeter security protection screen component 1000 further includes suspension protection screen component 1150, and suspension protection screen component 1150 is from upper It protects screen component 1050 additional, and extend to lower floor below upper protection screen component 1050 around the periphery of building, waits The final fixation of window and/or exterior wall.
Suspension protection screen component 1150 includes frame 1160 and relies on multiple protective net panel assemblies on frame 1160 1054.That is, each protective net panel assembly 1054 includes center portion 1054a and a pair of adjustable side 1054b. As described above, each side 1054b can be moved between retracted position and extended position relative to center portion 1054a.
Frame 1160 for hanging protection screen component 1150 includes a pair of slender strutting piece 1161, Suo Youfang spaced apart Protective net panel assembly 1054 depends on the slender strutting piece 1161.
Referring now to fig. 10 to 16, transverse beam assembly 2000 is shown.Transverse beam assembly 2000 includes center portion 2000a With a pair of adjustable end 2000b.Each end 2000b can be relative to center portion 2000a in retracted position and extending position It is moved between setting.
Center portion 2000a includes the beam 2002 of one section of square hollow sections (SHS) form.Each end 2000b includes The sleeve 2004 of SHS is sized to one end slideably received within center portion 2000a (although this sequentially can be anti- Turn).Each end 2000b includes the promotion lug 2006 extended from sleeve 2004, and sleeve 2004 terminates at mounting plate 2008。
In each of which end or towards each of which end, center portion 2000a includes the array in hole 2010 spaced apart; Similarly, the sleeve 2004 of each end 2000b includes the array in hole 2012 spaced apart.In use, each end 2000b Position relative to central part 2000a is adjustable, then by passing through suitably pin or bolt respectively in center portion Alignment hole 2010 and 2012 in each of 2000a and end 2000b is arranged.
In use, one or more transverse beam assemblies 2000 extend simultaneously (logical between slender strutting piece 1161 spaced apart Cross and be bolted and/or weld) it is fixed.In use, transverse beam assembly 2000 can be used for by attached relative to lug 2006 is promoted Crane hook is connect, to promote suspension protection screen component 1150.In addition, a part of transverse beam assembly 2000 may be received in installation In part 100, it is suspended on upper protection screen component 1050 to hang protection screen component 1150.
Transverse beam assembly 2000 be designed to can with suspension protection screen component 1150 separate so that the quantity of transverse beam assembly 2000 and Position can be adjusted as needed and be arranged, to adapt to the structural requirement of weight and balance and specific installation.
Transverse beam assembly 2000 is designed to adjustable length to assist installing and remove, and makes it also possible to adapt to different rulers Screen component is protected in the suspension of very little (especially width).
Referring now to Fig. 5 and details 1, the capstan winch track 1800 relied on protection screen component 1050 is shown. Capstan winch bracket 1820 relies on capstan winch track, and capstan winch 1840 relies on capstan winch bracket 1820 again.
Capstan winch track 1800 includes I-beam 1802, extends laterally across the lower edge of protection screen component 1050.Work Word beam 1802 is bolted to the frame of protection screen component 1050 by its upper flange 1804.
Capstan winch bracket 1820 includes roller yoke device, which includes having substantially parallel flange cross-sectional Main body 1822.The parallel flanges cross section includes bottom plate 1824 and a pair of of parallel flanges 1826 for upwardly extending from bottom plate 1824. The roller 1828 being directed inwardly toward is fixed relative to each flange 1826.Any of I-beam 1802 is arranged in these rollers 1826 Side, to extend along the lower flange 1806 of I-beam 1802.
Lifting bolt 1830 extends through the bottom plate 1824 of parallel flanges cross section.Capstan winch 1840 is suspended on the lifting bolt On 1830.
Capstan winch 1840 is used to promote panel from lower floor.By stacked horizontally on lower floor, each panel is connected to panel Capstan winch line and vertical-lift.Capstan winch 1840 can along 1800 transverse shifting of capstan winch track with positioning panel to be fixed.
Suspension protection screen component 1150 may also include one or more platforms or aisle 170 towards building extension.It can Selection of land, one or more of these platforms or aisle 170 may include fin 190, and fin 190 is far from protective net panel assembly 1054, and be suitable for moving between the closed position and the open position, fin bridges (and covering) platform 170 in closed position Gap between building, gap is uncovered in the open position.When each fin is opened, exterior window or covering can make It is lowered from above in place with capstan winch 1840, and the worker on the platform 170 by standing inside safety guard net fixes.
It protects screen component to provide the protection in bigger region or range according to the perimeter security of the disclosure, while overcoming and moving The dynamic and bigger associated difficulty of protective net of assembling.
In the whole instruction and subsequent claims, unless the context otherwise requires, otherwise word " comprising " and "comprising" and its variant will be understood as implying comprising the element or element group, but be not excluded for any other element or element Group.
In this specification to the reference of any prior art be not be also not construed as recognizing that such prior art is formed it is public Any form suggestion of a part of common sense.
It will be understood by those skilled in the art that the present invention is unrestricted when it is used for described specific application.The present invention In its preferred embodiment for the particular element and/or feature that are described herein or describe also there is no limit.It should be understood that The present invention is not limited to disclosed one or more embodiments, but be able to carry out many rearrange, modify and replace without It is detached from the scope of the present invention for illustrating and limiting such as following the claims.

Claims (23)

1. a kind of perimeter security for building protects screen component, the perimeter security protection screen component includes upper protective net group Screen component is protected in part, and suspension that is additional from upper protection screen component and extending below upper protection screen component.
2. perimeter security according to claim 1 protects screen component, wherein above protect screen component or suspension protection screen component At least one of be adapted so that upper protection screen component just on building use while suspension protection screen component can be attached It is added on protection screen component and from upper protective net assembly removal.
3. perimeter security according to any one of the preceding claims protects screen component, wherein it is suitable for above protecting screen component Screen component is protected in the climbing climbed relative to building.
4. perimeter security according to any one of the preceding claims protects screen component, wherein above protection screen component includes For the pedestal relative to the fixed perimeter security protection screen component of building, by frame on the base, and frame is relied on Protective net on frame.
5. perimeter security according to any one of the preceding claims protects screen component, wherein suspension protection screen component packet It includes frame and relies on the protective net on frame.
6. perimeter security according to any one of the preceding claims protects screen component, wherein suspension protection screen component exists The outside (relative to building) of the protective net of upper protection screen component is fixed against upper protection screen component.
7. perimeter security according to claim 5 or 6 protects screen component, wherein above protecting screen component includes at least one For hanging the installation part of protective net.
8. perimeter security according to claim 7 protects screen component, wherein above protecting screen component includes multiple installation parts.
9. perimeter security according to claim 7 or 8 protects screen component, wherein it includes multiple vertical for above protecting screen component Installation part spaced apart.
10. perimeter security according to any one of claims 7 to 9 protects screen component, wherein the installation part is each The installation part is located at the outside of the protective net of upper protection screen component.
11. perimeter security according to any one of claims 7 to 10 protects screen component, wherein the installation part or this Each installation part in a little installation parts includes the saddle for can nestedly receive a part of suspension protection screen component.
12. perimeter security according to claim 11 protects screen component, wherein the portion of the suspension protection screen component Divide or each of the suspension protection screen component part includes transverse beam assembly.
13. perimeter security according to claim 12 protects screen component, wherein suspension protective net includes multiple perpendicular separations The transverse beam assembly opened.
14. perimeter security according to claim 12 or 13 protects screen component, wherein the transverse beam assembly is each described Transverse beam assembly is located at the inside of the protective net of suspension protection screen component.
15. the perimeter security according to any one of claim 8 to 14 protects screen component, wherein each installation part includes For one at least part in transverse beam assembly to be directed to the installation guide in saddle.
16. according to claim 1 perimeter security described in any one of 2 to 15 protect screen component, wherein the transverse beam assembly or Each transverse beam assembly includes center portion and a pair of adjustable end.
17. perimeter security according to claim 16 protects screen component, wherein each end can be relative to center It is moved between retracted position and extended position part.
18. perimeter security according to any one of the preceding claims protects screen component, wherein be used for upper protection screen component Protective net with each of suspension protection screen component includes multiple protective net panel assemblies.
19. perimeter security according to claim 18 protects screen component, wherein each protective net panel assembly includes center Part and a pair of adjustable side.
20. perimeter security according to claim 19 protects screen component, wherein each side can be relative to center It is moved between retracted position and extended position part.
21. a kind of perimeter security for building protects screen component, the perimeter security protection screen component includes upper protective net Screen component is protected in component and suspension that is additional from upper protection screen component and extending below upper protection screen component, wherein upper protection At least one of screen component or suspension protection screen component are adapted so that just using on building in upper protection screen component same When suspension protection screen component can be attached on protection screen component and from upper protective net assembly removal.
22. screen component, the perimeter security protective net are protected in a kind of suspension of the perimeter security protection screen component for building Component includes upper protection screen component and hangs protection screen component, wherein suspension protection screen component is suitable for adding from upper protection screen component And extend below upper protection screen component.
23. a kind of upper protection screen component of the perimeter security protection screen component for building, the perimeter security protective net group Part includes upper protection screen component and suspension protection screen component, wherein upper protection screen component is adapted so that suspension protection screen component can It adds from upper protection screen component and extends below upper protection screen component.
CN201780040991.8A 2016-05-19 2017-05-19 Perimeter security protects screen component Pending CN109689995A (en)

Priority Applications (5)

Application Number Priority Date Filing Date Title
AU2016901878A AU2016901878A0 (en) 2016-05-19 Hanging screen
AU2016901878 2016-05-19
AU2016904047A AU2016904047A0 (en) 2016-10-05 A perimeter safety screen assembly
AU2016904047 2016-10-05
PCT/AU2017/000117 WO2017197440A1 (en) 2016-05-19 2017-05-19 A perimeter safety screen assembly

Publications (1)

Publication Number Publication Date
CN109689995A true CN109689995A (en) 2019-04-26

Family

ID=60324611

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201780040991.8A Pending CN109689995A (en) 2016-05-19 2017-05-19 Perimeter security protects screen component

Country Status (10)

Country Link
US (1) US20190169865A1 (en)
EP (1) EP3458658A4 (en)
JP (1) JP2019515166A (en)
KR (1) KR20190008918A (en)
CN (1) CN109689995A (en)
AU (1) AU2017268028B2 (en)
CA (1) CA3024483A1 (en)
RU (1) RU2736256C2 (en)
SG (1) SG11201810278XA (en)
WO (1) WO2017197440A1 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SG10201800475RA (en) * 2018-01-18 2019-08-27 Building Modern Pte Ltd Integrated Structural and Architectural Facade Level-by-Level Construction System

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3728661B2 (en) * 2001-05-28 2005-12-21 清水建設株式会社 Peripheral curing device and peripheral curing method for building attached structures
CN201206336Y (en) * 2008-05-20 2009-03-11 竹鹰企业有限公司 Support frame structure for drop-prevention net
CN202248823U (en) * 2011-09-01 2012-05-30 深圳市特辰科技股份有限公司 Attached-type lifting scaffold with net suspended at bottom
WO2012155211A1 (en) * 2011-05-19 2012-11-22 Natform Pty Ltd A lifting apparatus for a safety screen
CN103195233A (en) * 2013-02-06 2013-07-10 江苏江中集团有限公司 Attachable lifting scaffold capable of being translated
GB2510881A (en) * 2013-02-18 2014-08-20 Ischebeck Titan Ltd Safety screen
CN104379853A (en) * 2012-06-26 2015-02-25 福姆700私人有限公司 Improved frame for climbing screen

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR1385321A (en) * 1964-03-17 1965-01-08 Safety and protection device, especially for construction workers
SU557165A2 (en) * 1975-10-13 1977-05-05 Куйбышевский Филиал Всесоюзного Института По Проектированию Организации Энергетического Строительства "Оргэнергострой" Stairs
DE4415827A1 (en) * 1994-05-05 1995-11-09 Baumann Verwertungs Gmbh System for erection of protective wall on outside of building
AU2006100471A4 (en) * 2006-05-31 2006-07-06 Pch Group Limited Guard Panel
DE102007018853A1 (en) * 2007-04-20 2008-10-30 Doka Industrie Gmbh Self-climbing system for use in area of construction engineering, has platform and main platform for carrying out formwork operation, and railing element is fixed below main platform and in position of self-climbing system
KR100944463B1 (en) * 2009-07-02 2010-03-05 송재근 Composite cage for construction
DK2539522T3 (en) * 2010-02-24 2021-01-25 Form 700 Pty Ltd DETACHABLE BARRIER FOR PLACING ON AN UPPER OF A WALL
CN201826542U (en) * 2010-06-09 2011-05-11 北京星河人施工技术有限责任公司 Self-climbing protective screening
GB201414112D0 (en) * 2014-08-08 2014-09-24 Ischebeck Titan Ltd Bendable climbing screen,support and system

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3728661B2 (en) * 2001-05-28 2005-12-21 清水建設株式会社 Peripheral curing device and peripheral curing method for building attached structures
CN201206336Y (en) * 2008-05-20 2009-03-11 竹鹰企业有限公司 Support frame structure for drop-prevention net
WO2012155211A1 (en) * 2011-05-19 2012-11-22 Natform Pty Ltd A lifting apparatus for a safety screen
CN202248823U (en) * 2011-09-01 2012-05-30 深圳市特辰科技股份有限公司 Attached-type lifting scaffold with net suspended at bottom
CN104379853A (en) * 2012-06-26 2015-02-25 福姆700私人有限公司 Improved frame for climbing screen
CN103195233A (en) * 2013-02-06 2013-07-10 江苏江中集团有限公司 Attachable lifting scaffold capable of being translated
GB2510881A (en) * 2013-02-18 2014-08-20 Ischebeck Titan Ltd Safety screen

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨嗣信等: "《建筑业重点推广新技术应用手册》", 30 April 2003, 中国建筑工业出版社 *

Also Published As

Publication number Publication date
US20190169865A1 (en) 2019-06-06
EP3458658A4 (en) 2020-02-05
KR20190008918A (en) 2019-01-25
EP3458658A1 (en) 2019-03-27
CA3024483A1 (en) 2017-11-23
RU2018142825A (en) 2020-06-19
AU2017268028A1 (en) 2018-12-20
RU2018142825A3 (en) 2020-06-22
RU2736256C2 (en) 2020-11-12
AU2017268028B2 (en) 2021-08-19
SG11201810278XA (en) 2018-12-28
JP2019515166A (en) 2019-06-06
WO2017197440A1 (en) 2017-11-23

Similar Documents

Publication Publication Date Title
AU2017221870B2 (en) Improved frame for climbing screen
KR101654483B1 (en) The building is equipped with safety scaffold equipment
CN103953187B (en) A kind of sliding-mode platform system of band center vertical tube structure
CN109689995A (en) Perimeter security protects screen component
EP1691007B1 (en) Detachable cross-piece for supporting platforms in scaffolds
CN209780193U (en) Suspension type scaffold
US20190017282A1 (en) Runback backstructure access system
AU2008323613A1 (en) Perimeter screening system
JP6520533B2 (en) Overhead crane support device and load receiving member
JP5356091B2 (en) Crane girder exchanging method and crane girder exchanging apparatus
CN105649209A (en) Hanging bracket system applied to narrow space of jacking platform
KR20170086352A (en) gang form
US20140332486A1 (en) Jacking tower installation system
EP3423390B1 (en) A foldable platform lift
KR102236750B1 (en) Window Workbench For One man Having Compatible Structure
JP2002129747A (en) Lift-up method and lift-up system
CN213569261U (en) Attached lower hanging turnover plate type operating platform for installing tower crane
CN205348616U (en) Prefabricated formula steel stair
JP2019027145A (en) Installation method for falling object protective device
KR20130099581A (en) Stanchion integrated scaffolding stage bracket
US20130263549A1 (en) Safety screen system for steel erection work
JP2690822B2 (en) Steel construction method for low-rise buildings
GB2465452A (en) Auxiliary platform for scaffolding
JP2015203239A (en) Vertically movable mobile scaffold for assembling temporary overhead landing bridge
CA2810883A1 (en) Safety screen system for steel erection work

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
REG Reference to a national code

Ref country code: HK

Ref legal event code: DE

Ref document number: 40007103