CN109681248B - A kind of advance support method of grouting anchor cable - Google Patents
A kind of advance support method of grouting anchor cable Download PDFInfo
- Publication number
- CN109681248B CN109681248B CN201811583423.5A CN201811583423A CN109681248B CN 109681248 B CN109681248 B CN 109681248B CN 201811583423 A CN201811583423 A CN 201811583423A CN 109681248 B CN109681248 B CN 109681248B
- Authority
- CN
- China
- Prior art keywords
- grouting
- support
- anchor cable
- anchor
- grouting anchor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
- E21D20/02—Setting anchoring-bolts with provisions for grouting
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/15—Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
- E21D11/152—Laggings made of grids or nettings
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/18—Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D20/00—Setting anchoring-bolts
- E21D20/003—Machines for drilling anchor holes and setting anchor bolts
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D21/00—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
- E21D21/0026—Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)
- Piles And Underground Anchors (AREA)
Abstract
本发明涉及一种注浆锚索超前支护方法,属于超前支护领域,解决了现有技术中支护强度不足、支护速度慢,反复支护造成顶板破碎和工人劳动强度大的问题。本发明的超前支护方法包括以下步骤:步骤一,在当前回采工作面(3)确定待支护的回采巷道(1);步骤二,根据回采巷道(1)的超前支撑压力分布规律以及工程地质条件,确定超前支护距离L;步骤三,对回采巷道(1)的顶板加装注浆锚索超前支护,形成顶板支护结构;采煤时,回采工作面(3)向前推进的同时,沿推进方向不断加装注浆锚索超前支护,使所述超前支护距离维持在安全范围内。本发明的注浆锚索超前支护方法,保证安全回采的同时,提高了支护强度和支护效率,降低了人工劳动强度。
The invention relates to a grouting anchor cable advance support method, belongs to the advance support field, and solves the problems of insufficient support strength, slow support speed, broken roof and high labor intensity of workers caused by repeated support in the prior art. The advance support method of the present invention comprises the following steps: step 1, determining the mining roadway (1) to be supported in the current mining working face (3); step 2, according to the advance support pressure distribution law of the mining roadway (1) and the engineering According to the geological conditions, determine the advance support distance L; step 3, install grouting anchor cable advance support on the roof of the mining roadway (1) to form a roof support structure; during coal mining, the mining face (3) moves forward At the same time, the advance support of the grouting anchor cable is continuously added along the advancing direction, so that the advance support distance is maintained within a safe range. The advanced support method of the grouting anchor cable of the invention improves the support strength and support efficiency and reduces the manual labor intensity while ensuring safe mining.
Description
技术领域technical field
本发明涉及超前支护技术领域,尤其涉及一种注浆锚索超前支护方法。The invention relates to the technical field of advance support, in particular to a method for advance support of grouting anchor cables.
背景技术Background technique
巷道围岩稳定性对矿山安全生产有着重要影响,巷道围岩失稳造成大量的人员伤亡和财产损失,因此加强巷道围岩控制对矿山安全生产意义重大。巷道超前支护主要是为了防止工作面因超前支承压力和沿倾斜方向支承压力的叠加作用而出现巷道围岩变形、移动、破坏等现象。现阶段使用综合机械化设备进行煤炭资源开采,如此产生的普遍压力较大,若无法采用积极有效的支护方式,将会对综采工作面的开采效率造成一定的影响,同时还可能会带来一定的安全风险,给后续的煤炭开采工作埋下一定的安全隐患。The stability of the surrounding rock of the roadway has an important impact on the safe production of the mine. The instability of the surrounding rock of the roadway causes a large number of casualties and property losses. Therefore, strengthening the control of the surrounding rock of the roadway is of great significance to the safe production of the mine. The main purpose of the roadway advanced support is to prevent the deformation, movement and damage of the surrounding rock of the roadway due to the superposition of the advanced support pressure and the support pressure along the inclined direction in the working face. At this stage, the use of comprehensive mechanized equipment for coal resource mining will cause a lot of pressure. If active and effective support methods cannot be adopted, it will have a certain impact on the mining efficiency of the fully mechanized mining face, and may also bring about Certain safety risks will bury certain safety hazards for the follow-up coal mining work.
传统超前支护方式为单体液压支柱配合π型钢(大板)棚支护超前支护,在使用过程中存在一定的局限性,存在如下问题:1)支护强度不足,若顶板受到较大的煤层压力时,传统超前支护达不到应有的强度,此时综采工作面出口处的顶板极有可能出现下沉,同时单体支柱使用的钻底较多,对其进行回撤处理难度较大,特别是在综采工作面后部切顶密集的区域,存在安全隐患的可能性较大;2)支护速度较慢,传统超前支护产生支护效果较慢,支柱回撤速度也较慢,将对工作面的整体推进速度造成影响,降低煤炭开采效率和产量;3)劳动强度较大,在进行传统超前支护过程中,需频繁地进行支设和回撤,大大增加了劳动强度。另外,超前支护液压支架存在如下缺陷:1)在移架过程中会反复支撑顶板,造成顶板的破碎,不利于对顶板的安全管理和维护,对井下巷道工作人员生命及设备造成威胁;2)在前行时顶板与顶梁之间会产生剧烈的滑动摩擦,对巷道顶板造成一定的破坏,影响其寿命,同时也降低其工作的稳定性和可靠性,威胁工作人员的安全;3)安装、维护、拆卸这种支架时工作人员劳动强度非常大。The traditional advanced support method is a single hydraulic prop combined with a π-shaped steel (large slab) shed to support the advance support, which has certain limitations in the use process. When the coal seam pressure is high, the traditional advanced support cannot reach the required strength, and the roof at the exit of the fully mechanized mining face is very likely to sink. It is more difficult to deal with, especially in the area with intensive roof cutting at the rear of the fully mechanized mining face, there is a greater possibility of potential safety hazards; 2) The support speed is slow, the traditional advanced support produces a slow support effect, and the pillar returns. The speed of retraction is also slow, which will affect the overall advancement speed of the working face and reduce the efficiency and output of coal mining; 3) The labor intensity is high, and in the process of traditional advanced support, frequent support and retraction are required. Greatly increased labor intensity. In addition, the advance support hydraulic support has the following defects: 1) The roof will be repeatedly supported in the process of moving the frame, causing the roof to be broken, which is not conducive to the safe management and maintenance of the roof, and poses a threat to the life and equipment of underground tunnel workers; 2 ) When moving forward, there will be severe sliding friction between the roof and the roof beam, causing certain damage to the roadway roof, affecting its life, reducing the stability and reliability of its work, and threatening the safety of workers; 3) When installing, maintaining and dismantling such a bracket, the labor intensity of the staff is very high.
发明内容SUMMARY OF THE INVENTION
鉴于上述的分析,本发明旨在提供一种注浆锚索超前支护方法,用以解决现有技术中超前支护支护强度不足、支护速度慢,反复支护造成顶板破碎影响顶板强度且工人劳动强度大的问题。In view of the above analysis, the present invention aims to provide a method for advance support of grouting anchor cables, which is used to solve the problem of insufficient support strength of advance support in the prior art, slow support speed, and roof broken due to repeated support, which affects the strength of the roof. And the problem of high labor intensity of workers.
本发明的目的主要是通过以下技术方案实现的:The object of the present invention is mainly achieved through the following technical solutions:
一种注浆锚索超前支护方法,包括以下步骤:步骤一,在当前回采工作面确定待支护的回采巷道;步骤二,根据回采巷道的超前支撑压力分布规律以及工程地质条件,确定超前支护距离L;步骤三,对回采巷道的顶板加装注浆锚索超前支护,形成顶板支护结构;采煤时,回采工作面向前推进的同时,沿推进方向不断加装注浆锚索超前支护,使超前支护距离L维持在安全范围内。A grouting anchor cable advance support method, comprising the following steps:
进一步地,步骤三中,加装注浆锚索超前支护步骤包括:S1.在回采巷道的顶板上打锚索孔;S2.将注浆锚索送入锚索孔,待注浆锚索送入至锚索孔孔底后,依次安装止浆塞、托盘和锚具;S3.通过注浆管对注浆锚索注浆,浆料沿注浆管注入,从出浆口流入注浆锚固段;S4.待注浆锚固段注浆完成并且完全凝固后,通过锚具对注浆锚索进行张拉预紧。Further, in
进一步地,超前支护距离L为,Further, the advance support distance L is,
L=L1+L2,L=L 1 +L 2 ,
式中,L为超前支护距离,m;L1为最短安全支护距离,m;L2为保险支护距离,m。In the formula, L is the advance support distance, m; L 1 is the shortest safe support distance, m; L 2 is the insurance support distance, m.
进一步地,采煤时,回采工作面向前推进时,超前支护的有效支护距离L3大于等于最短安全支护距离L1。Further, during coal mining, when the mining working face advances forward, the effective support distance L 3 of the advanced support is greater than or equal to the shortest safe support distance L 1 .
进一步地,顶板支护结构为组合拱结构,组合拱结构包括钢筋网、钢带、锚杆和注浆锚索;组合拱结构由顶板向围岩依次分为锚网组合拱区、锚杆压缩组合拱区及浆液扩散加固拱区。Further, the roof support structure is a combined arch structure, and the combined arch structure includes steel mesh, steel strips, anchor rods and grouting anchor cables; the combined arch structure is divided into an anchor mesh combined arch area, an anchor rod compression area from the roof to the surrounding rock in turn. Combined arch area and slurry diffusion reinforcement arch area.
进一步地,钢筋网紧贴巷道顶板,钢带设置于钢筋网的外侧。Further, the reinforced mesh is close to the roof of the roadway, and the steel strip is arranged on the outside of the reinforced mesh.
进一步地,锚杆的数量为多根,注浆锚索与锚杆交替布置,相邻两排锚杆之间设置至少一排注浆锚索。Further, the number of anchor rods is multiple, the grouting anchor cables and the anchor rods are alternately arranged, and at least one row of grouting anchor cables is arranged between two adjacent rows of anchor rods.
进一步地,每排注浆锚索的数量至少为三根。Further, the number of each row of grouting anchor cables is at least three.
进一步地,锚杆垂直穿过钢带和钢筋网,锚固端连接于巷道顶板中。Further, the anchor rod vertically passes through the steel belt and the steel mesh, and the anchoring end is connected to the roof of the roadway.
进一步地,注浆锚索穿入锚索孔,锚固端连接于巷道顶板上部的稳定岩层中。Further, the grouting anchor cable is inserted into the anchor cable hole, and the anchoring end is connected to the stable rock formation on the upper part of the roof of the roadway.
进一步地,注浆锚索包括:丝堵、锚具、外置式止浆塞、钢绞丝、注浆管和出浆口。Further, the grouting anchor cable includes: a wire plug, an anchor, an external grouting stopper, a steel strand, a grouting pipe and a grouting outlet.
与现有技术相比,本发明至少具有以下有益效果之一:Compared with the prior art, the present invention has at least one of the following beneficial effects:
a)本发明提供的注浆锚索超前支护方法,采用注浆锚索超前支护,显著提高了支护速度,克服了反复支护造成顶板破碎进而影响顶板强度的缺陷,超前支护与采煤的回采工作面3的推进同步进行,只需要在已有的超前支护距离范围的前方进行支护补充即可,操作方便,在保证安全回采的同时提高了超前支护的工作效率,降低了工人劳动强度。a) The grouting anchor cable advance support method provided by the present invention adopts the grouting anchor cable advance support, which significantly improves the support speed and overcomes the defect that the roof is broken due to repeated support and thus affects the strength of the roof. The advancement of the
b)本发明提供的注浆锚索超前支护方法,采用注浆锚索配合锚网支护,可以形成一个多层有效的厚度加大的组合拱结构,即锚网组合拱区、锚杆压缩区组合拱区及浆液扩散加固拱区,避免了破坏巷道顶板、有效维持巷道整体稳定性,从而扩大了支护结构的有效承载范围,提高了支护结构的承载能力和支护强度,进而提高了回采工作面安全性。b) The grouting anchor cable advanced support method provided by the present invention adopts the grouting anchor cable and the anchor net support to form a multi-layer effective composite arch structure with increased thickness, that is, the anchor net composite arch area, the anchor rod Combining the arch area in the compression area and the slurry diffusion reinforcement arch area avoids damage to the roadway roof and effectively maintains the overall stability of the roadway, thereby expanding the effective bearing range of the support structure, and improving the bearing capacity and support strength of the support structure. Improve the safety of the mining face.
本发明中,上述各技术方案之间还可以相互组合,以实现更多的优选组合方案。本发明的其他特征和优点将在随后的说明书中阐述,并且,部分优点可从说明书中变得显而易见,或者通过实施本发明而了解。本发明的目的和其他优点可通过说明书、权利要求书以及附图中所特别指出的内容中来实现和获得。In the present invention, the above technical solutions can also be combined with each other to achieve more preferred combination solutions. Additional features and advantages of the invention will be set forth in the description which follows, and some of the advantages may become apparent from the description, or may be learned by practice of the invention. The objectives and other advantages of the invention may be realized and attained by the things particularly pointed out in the description, claims and drawings.
附图说明Description of drawings
附图仅用于示出具体实施例的目的,而并不认为是对本发明的限制,在整个附图中,相同的参考符号表示相同的部件。The drawings are for the purpose of illustrating specific embodiments only and are not to be considered limiting of the invention, and like reference numerals refer to like parts throughout the drawings.
图1为本发明实施中回采工作面示意图;Fig. 1 is the schematic diagram of the mining face in the implementation of the present invention;
图2为注浆锚索结构示意图;Figure 2 is a schematic diagram of the grouting anchor cable structure;
图3为本发明实施中回采巷道支护平面图;Fig. 3 is the plan view of mining roadway support in the implementation of the present invention;
图4为回采巷道注浆锚索超前支护断面图。Figure 4 is a sectional view of the advance support of the grouting anchor cable in the mining roadway.
附图标记:Reference number:
1-回采巷道;2-煤岩体;3-回采工作面;4-采空区;5-锚杆;6-注浆锚索;7-钢带;8-托盘;9-丝堵;10-锚具;11-外置式止浆塞;12-钢绞丝;13-注浆管;14-出浆口。1- mining roadway; 2- coal and rock mass; 3- mining face; 4- goaf; 5- bolt; 6- grouting anchor cable; 7- steel belt; 8- pallet; 9- wire plug; 10 -Anchor; 11-External grouting stopper; 12-Steel strand; 13-Grouting pipe; 14-Grout outlet.
具体实施方式Detailed ways
下面结合附图来具体描述本发明的优选实施例,其中,附图构成本申请一部分,并与本发明的实施例一起用于阐释本发明的原理,并非用于限定本发明的范围。The preferred embodiments of the present invention are specifically described below with reference to the accompanying drawings, wherein the accompanying drawings constitute a part of the present application, and together with the embodiments of the present invention, are used to explain the principles of the present invention, but are not used to limit the scope of the present invention.
本发明的一个具体实施例,公开了一种注浆锚索超前支护方法,包括以下步骤:A specific embodiment of the present invention discloses a grouting anchor cable advance support method, comprising the following steps:
步骤一,在当前回采工作面3确定待支护的回采巷道1。回采巷道1的确定,依据地质条件以及工程生产条件,选择符合上述条件的回采巷道1进行超前支护。Step 1: Determine the
步骤二,选取单条或多条回采巷道1;根据回采巷道1的超前支撑压力分布规律以及工程地质条件,确定超前支护距离L。Step 2, select a single or
步骤三,在原有永久支护的基础上,对回采巷道1的顶板加装注浆锚索超前支护,形成顶板支护结构。采煤时,回采工作面3向前推进的同时,沿推进方向不断加装注浆锚索6超前支护,使超前支护距离维持在安全范围内。Step 3: On the basis of the original permanent support, add grouting anchor cable advance support to the roof of the
本实施例中,由于回采巷道在采煤之前已提前掘好,在掘进的同时进行了永久支护(锚网支护),步骤三是在原有永久支护的基础上进行的。具体的,在采煤工作面回采的同时,在回采巷道1顶板上沿前进方向,每隔一排锚杆5施工锚索孔。施工锚索孔的同时,在锚索孔中安装注浆锚索6和托盘8;注浆锚索6封孔后利用高压泵对顶板裂隙进行注浆,把破碎顶板的缝隙和孔体充实,回采巷道顶板胶结成整体,加注注浆锚索超前支护的具体步骤如下:In this embodiment, since the mining roadway has been dug in advance before coal mining, permanent support (anchor mesh support) is carried out during the excavation, and
S1.在回采巷道1的顶板上打锚索孔;S1. Drill anchor cable holes on the roof of
S2.将注浆锚索6送入锚索孔,待注浆锚索6送入至锚索孔孔底后,依次安装外置式止浆塞11、托盘8和锚具10;S2. Send the grouting anchor cable 6 into the anchor cable hole. After the grouting anchor cable 6 is sent to the bottom of the anchor cable hole, install the
S3.通过注浆管13对注浆锚索6注浆,浆料沿注浆管13注入,从出浆口14流入注浆锚固段;完成注浆后,用丝堵9堵住注浆管13,防止浆液外流。S3. The grouting anchor cable 6 is grouted through the
S4.待注浆锚固段注浆完成并且完全凝固后,通过锚具10对注浆锚索6进行张拉预紧。S4. After the grouting of the grouting anchoring section is completed and completely solidified, the grouting anchor cable 6 is tensioned and pre-tightened by the
图1示出了采空区4、回采工作面3、煤岩体2及回采巷道1之间的位置关系,在回采工作面3进行采煤作业的同时,对回采工作面3前方煤岩体2两侧需要进行超前支护的支护距离范围内的回采巷道1的顶板进行注浆锚索超前支护。随着回采工作面3在煤岩体2的回采方向的向前推移,同步进行对回采巷道1的超前支护范围沿回采方向的向前推移,始终保持回采工作面3前方的超前支护距离维持在安全范围内。Fig. 1 shows the positional relationship among the
本实施例中,超前支护的有效支护距离L3是指采煤过程中保证采煤安全的支护距离;最短安全支护距离L1是指保证采煤安全的最短有效支护距离;保险支护距离L2是指为了在回采工作面3向前推进的同时进行超前支护,保证超前支护的有效支护距离L3始终大于等于最短安全支护距离L1而人为设定的支护距离,保险支护距离L2与回采工作面推进速度、支护速度及注浆凝固时间有关;超前支护距离L等于最短安全支护距离L1与保险支护距离L2之和,即L=L1+L2,式中,L为超前支护距离,m;L1为最短安全支护距离,m;L2为保险支护距离,m。In this embodiment, the effective support distance L 3 of the advance support refers to the support distance to ensure the safety of coal mining during the coal mining process; the shortest safe support distance L 1 refers to the shortest effective support distance to ensure the safety of coal mining; The insurance support distance L 2 refers to the artificially set
为了提高超前支护的支护强度保证支护效果,本发明的注浆锚索超前支护方法构建的顶板支护结构为组合拱结构,组合拱结构包括钢筋网、钢带7、锚杆5和注浆锚索6,组合拱结构由顶板向围岩依次分为锚网组合拱区、锚杆压缩区组合拱区及浆液扩散加固拱区。采用注浆锚索配合锚网支护,能够形成一个多层有效的厚度加大的组合拱结构,即锚网组合拱区、锚杆压缩区组合拱区及浆液扩散加固拱区,从而扩大了支护结构的有效承载范围,提高了支护结构的整体性和承载能力。钢筋网紧贴巷道顶板,钢带7设置于钢筋网的外侧,注浆锚索起到了锚索在挤压加固、多层组合拱结构以及注浆等方面的多重作用,提高了岩体强度,使顶板二次加固,围岩本身和作为支护结构的一部分,且与原岩形成一个整体,使回采巷道保持稳定而不易产生破坏。In order to improve the support strength of the advance support and ensure the support effect, the roof support structure constructed by the grouting anchor cable advance support method of the present invention is a combined arch structure, and the combined arch structure includes a steel mesh, a
本实施例的一个优选实施方式中,锚杆5的数量为多根,注浆锚索6与锚杆5交替布置,相邻两排锚杆5之间设置至少一排注浆锚索6,每排锚杆5的数量、间距根据实际地质条件确定,保证锚杆5受力均匀,进而保证对顶板的支护强度,提高了支护的稳定性和安全性。In a preferred implementation of this embodiment, the number of
为了进一步保证支护强度,注浆锚索6与锚杆5交替布置,在相邻两排锚杆5之间设置一排或多排注浆锚索6,每排注浆锚索6的数量至少为三根,注浆锚索6的数量根据所需超前支护的强度和工程地质条件确定,如图4所示,锚杆5垂直穿过钢带7和钢筋网,锚杆5的锚固端连接于巷道顶板中。注浆锚索6穿过钢筋网,穿入锚索孔;注浆锚索6的锚固端连接于巷道顶板上部的稳定岩层中。锚杆5和注浆锚索6的外锚固段均设置有托盘8,如图3和图4所示。注浆锚索6封孔后,用高压泵对顶板裂隙进行注浆,注完浆之后,用丝堵9堵住注浆管13,防止浆液外流,将破碎顶板的缝隙和孔体充实,回采巷道1的顶板胶结成整体。采用注浆锚索配合锚网支护,可以形成一个多层有效的厚度加大的组合拱结构,即锚网组合拱区、锚杆压缩区组合拱区及浆液扩散加固拱区,从而扩大了支护结构的有效承载范围,提高了支护结构的整体性和承载能力。In order to further ensure the support strength, the grouting anchor cables 6 and the
如图2所示,本发明实施例提供的注浆锚索6结构,包括丝堵9、锚具10、外置式止浆塞11、钢绞丝12、注浆管13、出浆口14组成。注浆锚索6依次可分为外锚固段、注浆锚固段和树脂锚固段。注浆锚索6外部为钢绞线12,注浆锚索内设置有注浆管13,注浆管中后部有出浆口14。通过注浆管13对围岩注浆,浆液由出浆口14流出,把破碎顶板的缝隙和孔体充实,回采巷道顶板胶结成整体。注浆后使得作用在顶板上的垂直载荷能有效地传递到两帮,通过对帮的加固能够把荷载传递到底板,同时由于组合拱结构厚度的加大,克服了作用在底板上的荷载集中度的缺陷,底板更加稳定,减轻底臌现象的发生。此外,底板稳定有助于两帮的稳定,底板及两帮稳定又能保持了顶板的稳定。本实施例提供的超前支护方法,在裂隙发育带、顶板破碎带受回采扰动的巷道围岩控制和支护及维护效果明显。As shown in FIG. 2 , the structure of the grouting anchor cable 6 provided by the embodiment of the present invention includes a
本实施例中,注浆锚索6通过外置式止浆塞11密封固定于煤岩壁上的注浆口处,注浆锚索6上依次设置有锚具10、托盘8,托盘8挤压外置式注浆塞11的大头端,同时利用锚具10预紧,提高了锚索的承载能力和支护效果。In this embodiment, the grouting anchor cable 6 is sealed and fixed to the grouting port on the coal rock wall through an
与现有技术相比,本实施例的注浆锚索超前支护方法,创新性的提出了利用注浆锚索进行超前支护的方式,超前支护与采煤的回采工作面3的推进同步进行,只需要在已有的超前支护距离范围的前方进行支护补充即可,操作方便,在保证安全回采的同时提高了超前支护的工作效率,降低了工人的劳动强度。Compared with the prior art, the advanced support method of grouting anchor cable in this embodiment innovatively proposes a method of using grouting anchor cable for advanced support, and the advance support and the advancement of coal
以上所述,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,可轻易想到的变化或替换,都应涵盖在本发明的保护范围之内。The above description is only a preferred embodiment of the present invention, but the protection scope of the present invention is not limited to this. Substitutions should be covered within the protection scope of the present invention.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201811583423.5A CN109681248B (en) | 2018-12-24 | 2018-12-24 | A kind of advance support method of grouting anchor cable |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201811583423.5A CN109681248B (en) | 2018-12-24 | 2018-12-24 | A kind of advance support method of grouting anchor cable |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN109681248A CN109681248A (en) | 2019-04-26 |
| CN109681248B true CN109681248B (en) | 2020-01-17 |
Family
ID=66189008
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201811583423.5A Active CN109681248B (en) | 2018-12-24 | 2018-12-24 | A kind of advance support method of grouting anchor cable |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN109681248B (en) |
Families Citing this family (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110593924B (en) * | 2019-09-26 | 2020-07-03 | 中国矿业大学 | Support method based on full life cycle of mining roadway |
| CN110529144B (en) * | 2019-09-26 | 2020-08-28 | 中国矿业大学 | A hybrid advance support method for small section mining roadway |
| CN110566238A (en) * | 2019-09-26 | 2019-12-13 | 中国矿业大学 | Mud rock roof small coal pillar gob-side roadway supporting structure and method thereof |
| CN110552731A (en) * | 2019-09-26 | 2019-12-10 | 中国矿业大学 | top coal caving stoping roadway grouting anchor cable supporting structure and advanced supporting method thereof |
| CN110792450B (en) * | 2019-09-26 | 2020-10-27 | 中国矿业大学 | A method for determining the advance support of grouting anchor cable |
| CN110566254B (en) * | 2019-10-09 | 2020-10-20 | 中国矿业大学 | Grouting anchor cable hole sealing device and grouting anchor cable |
| CN111287778B (en) * | 2020-03-09 | 2021-09-17 | 新能矿业有限公司 | Large-span cantilever beam anchor cable supporting method and roadway roof combined supporting method |
| CN112081602A (en) * | 2020-07-27 | 2020-12-15 | 枣庄矿业(集团)付村煤业有限公司 | Advanced support technology for fully mechanized mining face of thick coal seam |
| CN112610258A (en) * | 2020-12-09 | 2021-04-06 | 中国矿业大学 | Impact mine stoping roadway advanced support method applied to smart mine |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101457651A (en) * | 2008-11-19 | 2009-06-17 | 淮南矿业(集团)有限责任公司 | Filling stack advanced support method along empty tunnel in coal-gas co-milling Y-shaped ventilating system |
| CN201507318U (en) * | 2009-09-15 | 2010-06-16 | 济南澳科矿山工程技术有限公司 | Anchored and grouted anchor cable |
| CN104405423A (en) * | 2014-10-23 | 2015-03-11 | 山西晋城无烟煤矿业集团有限责任公司 | Mining grouting anchor rope |
| CN105484760A (en) * | 2016-02-01 | 2016-04-13 | 四川川煤华荣能源股份有限公司花山煤矿 | Forepoling structure of large-dip-angle coal face |
| CN106761813A (en) * | 2017-01-23 | 2017-05-31 | 山东科技大学 | Gob side entry driving unbalanced support method for designing under the unstable overlying strata in deep |
-
2018
- 2018-12-24 CN CN201811583423.5A patent/CN109681248B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN101457651A (en) * | 2008-11-19 | 2009-06-17 | 淮南矿业(集团)有限责任公司 | Filling stack advanced support method along empty tunnel in coal-gas co-milling Y-shaped ventilating system |
| CN201507318U (en) * | 2009-09-15 | 2010-06-16 | 济南澳科矿山工程技术有限公司 | Anchored and grouted anchor cable |
| CN104405423A (en) * | 2014-10-23 | 2015-03-11 | 山西晋城无烟煤矿业集团有限责任公司 | Mining grouting anchor rope |
| CN105484760A (en) * | 2016-02-01 | 2016-04-13 | 四川川煤华荣能源股份有限公司花山煤矿 | Forepoling structure of large-dip-angle coal face |
| CN106761813A (en) * | 2017-01-23 | 2017-05-31 | 山东科技大学 | Gob side entry driving unbalanced support method for designing under the unstable overlying strata in deep |
Non-Patent Citations (2)
| Title |
|---|
| 开采扰动下软岩巷道超前支护对围岩稳定性影响研究;龙武文;《中国优秀硕士学位论文全文数据库》;20170315(第3期);B021-176 * |
| 采动影响下厚坚硬顶板巷道围岩控制技术研究;孟军凯;《中国优秀硕士学位论文全文数据库》;20170315(第3期);B021-61 * |
Also Published As
| Publication number | Publication date |
|---|---|
| CN109681248A (en) | 2019-04-26 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN109681248B (en) | A kind of advance support method of grouting anchor cable | |
| CN112855223B (en) | An integrated grouting method for coal roadway passing through the back wall and front curtain space of goaf | |
| CN103195426B (en) | A kind of large-inclination-angle coal bed long-wall working face coal pillar-free mining method | |
| CN103410515B (en) | It is a kind of that three-soft seam is reciprocating combines mining method without coal column | |
| CN105971606B (en) | A kind of thick sandstone coal wall recovery method | |
| Xie et al. | Stability analysis of integral load-bearing structure of surrounding rock of gob-side entry retention with flexible concrete formwork | |
| CN110529144B (en) | A hybrid advance support method for small section mining roadway | |
| CN111535817A (en) | Working face double-lane tunneling small coal pillar reinforcement construction method | |
| CN108316941B (en) | Broken surrounding rock and soft rock roadway U-shaped steel canopy supporting method | |
| CN102877858B (en) | Reinforcing method for crushed top plate of coal face | |
| CN103244122B (en) | Trinity coupling support stability control method for gob-side entry-driving coal pillar | |
| AU2013354613A1 (en) | Method of local filling to control surface subsidence in worked-out area | |
| CN109026024B (en) | Roadway roof deformation control method under high-level stress action | |
| CN109209490A (en) | It adopts bank face and withdraws method in a kind of waste filling auxiliary end | |
| CN107882566A (en) | A kind of gob-side entry retaining method for not influenceing coal mining process | |
| CN108590723A (en) | Gob side entry driving fender erosion control release is to drawing anchoring integral structure and construction method | |
| CN112610258A (en) | Impact mine stoping roadway advanced support method applied to smart mine | |
| CN107143338A (en) | A kind of coal mine roadway driving and method for protecting support | |
| CN115929308A (en) | Pre-control roof small-section filling mining method | |
| CN103485795A (en) | Method for quickly tunneling mine roadway and consecutively timbering mine roadway | |
| CN105937400B (en) | It is a kind of once to tunnel Liu Sheshuan lanes digging operation production line | |
| CN108049899A (en) | A kind of gob side entry driving thin coal pillar breaking surrounding rock reinforcement means | |
| CN113356850A (en) | Method and system for pre-digging and withdrawing channel of fully mechanized mining face with large mining height | |
| CN114673527B (en) | Progressive roadway and tunnel broken surrounding rock reinforcing method | |
| CN110552731A (en) | top coal caving stoping roadway grouting anchor cable supporting structure and advanced supporting method thereof |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant |
