CN109577734A CN201910061642.5A CN201910061642A CN109577734A CN 109577734 A CN109577734 A CN 109577734A CN 201910061642 A CN201910061642 A CN 201910061642A CN 109577734 A CN109577734 A CN 109577734A
Authority
CN
China
Prior art keywords
tower body
flange
bracing means
column
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910061642.5A
Other languages
Chinese (zh)
Inventor
李伟
孙健
聂邵华
田成立
才文军
滕立志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Limited By Share Ltd Jilin Jida Communication Design Institute Changchun Branch
Original Assignee
Limited By Share Ltd Jilin Jida Communication Design Institute Changchun Branch
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Limited By Share Ltd Jilin Jida Communication Design Institute Changchun Branch filed Critical Limited By Share Ltd Jilin Jida Communication Design Institute Changchun Branch
Priority to CN201910061642.5A priority Critical patent/CN109577734A/en
Publication of CN109577734A publication Critical patent/CN109577734A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H12/00Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
    • E04H12/02Structures made of specified materials
    • E04H12/08Structures made of specified materials of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0218Increasing or restoring the load-bearing capacity of building construction elements

Abstract

The present invention provides a kind of tower body bracing means and tubular structure towers, it is related to tower body reinforcement technique field, it is big to solve influence of the existing reinforcing mode existing in the prior art to environment, occupied area is increased while reinforcing, and the heavy workload of strengthening construction, technical problem at high cost, the device includes several columns being arranged on the outside of tower body, column is uniformly distributed along the circumferential direction of tower body, and column and tower body pass through flanged joint, flange is connect with tower body by fastener, and the present invention is used to improve the reinforcing mode of tower body.

Description

A kind of tower body bracing means and tubular structure tower
Technical field
The present invention relates to tower body reinforcement technique fields, more particularly, to a kind of tower body bracing means and tubular structure tower.
Background technique
Existing steel tower is not able to satisfy the demand for carrying additionally antenna equipment since the bearing capacity of tower body is poor.Traditional reinforcing In modification scheme, general to improve, tower body bearing capacity is insufficient to be asked by the way of setting external rigidity support arm or external bracing wire Topic.But applicants have discovered that at least there is following technical problem in the prior art: influence of the existing reinforcing mode to environment Greatly, the occupied area of pylon, and the heavy workload of strengthening construction, scene are also increased together while reinforcing to existing tower body Working space is insufficient, and construction cost is high.
Summary of the invention
The purpose of the present invention is to provide a kind of tower body bracing means and tubular structure towers, to solve to exist in the prior art Influence of the existing reinforcing mode to environment it is big, increase occupied area, and the heavy workload of strengthening construction while reinforcing, Technical problem at high cost.Many technologies effect that optimal technical scheme in many technical solutions provided by the invention can be generated Fruit elaboration as detailed below.
To achieve the above object, the present invention provides following technical schemes:
A kind of tower body bracing means provided by the invention, including several columns on the outside of tower body, the column edge is arranged in The circumferential direction of the tower body is uniformly distributed, and the column and the tower body, by flanged joint, the flange and the tower body are logical Cross fastener connection.
Preferably, the fastener is set as anchor ear.
Preferably, the anchor ear is fixedly connected on the inner surface of the flange, the diameter of the anchor ear and its corresponding to The diameter of tower body position is identical.
Preferably, the flange is sheet flange, and the flange includes the first flange structure and second in mirror settings Flange arrangement, the first flange structure and the fan-shaped setting of the second flange structure.
Preferably, the anchor ear includes the first hoop plate and the second hoop plate, and the first hoop plate is welded in the first flange The inner surface of structure, the second hoop plate are welded in the inner surface of the second flange structure.
Preferably, the width of the first hoop plate is greater than the thickness of the first flange structure, the width of the second hoop plate Degree is greater than the thickness of the second flange structure.
Preferably, the flange is equipped with multiple fan-shaped pore structures, and the scallop hole structure setting is in the flange and institute State the junction of anchor ear.
Preferably, the junction of the column and the flange is equipped with ribbed stiffener.
A kind of tubular structure tower, including above-mentioned tower body bracing means.
Preferably, column is set as every three meter Yi Gen along the vertical direction of the tower body, the both ends of the column and One of flange is respectively provided at interval of Yi meter Chu on the column.
Tower body bracing means and tubular structure tower provided by the invention, are uniformly arranged column by the circumferential direction in tower body, stand Column is arranged using radial pattern, from structural theory, the covert design concept for using enlarging section, by being fixed on tower body with flange Waist, improve cantilever member lumbar region bending stiffness, the Lateral resisting ability of structure is improved, to improve local tower body Bending strength, and then its anti-bending strength is improved, and improve displacement of the structure under horizontal wind excitation, to meet structure Applicable performance is connect with tower body by fastener by setting flange, and in-site installation is convenient, is connected by screw bolts installation completely Working measure reduces construction cost, reduces cost and improves local tower body bending strength.
Detailed description of the invention
In order to more clearly explain the embodiment of the invention or the technical proposal in the existing technology, to embodiment or will show below There is attached drawing needed in technical description to be briefly described, it should be apparent that, the accompanying drawings in the following description is only this Some embodiments of invention for those of ordinary skill in the art without creative efforts, can be with It obtains other drawings based on these drawings.
Fig. 1 is the structural schematic diagram of one embodiment of tower body bracing means of the present invention;
Fig. 2 is the overlooking structure diagram of one embodiment of tower body bracing means of the present invention;
Fig. 3 is the left view structural representation of one embodiment of tower body bracing means of the present invention;
Fig. 4 is the structural schematic diagram of tubular structure tower of the present invention;
Fig. 5 is the partial enlarged view of footing in Fig. 4.
In figure: 1, tower body;2, column;3, flange;4, anchor ear;5, ribbed stiffener;6, fan-shaped pore structure;7, bolt;31, first Flange arrangement;32, second flange structure;41, the first hoop plate;42, the second hoop plate.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, technical solution of the present invention will be carried out below Detailed description.Obviously, described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Base Embodiment in the present invention, those of ordinary skill in the art are obtained all without making creative work Other embodiment belongs to the range that the present invention is protected.
The present invention provides a kind of tower body bracing means, Fig. 1 is the structural schematic diagram of the present embodiment, as shown in Figure 1, including Several columns 2 in 1 outside of tower body are set, and column 2 is uniformly distributed along the circumferential direction of tower body 1, and column 2 and tower body 1 pass through flange 3 Connection, flange 3 are connect with tower body 1 by fastener.
By being uniformly arranged column 2 in the circumferential direction of tower body 1, column 2 is arranged using radial pattern, from structural theory, in a disguised form The bending resistance of cantilever member lumbar region is improved by being fixed on the waist of tower body with flange 3 using the design concept of enlarging section Rigidity, improves the Lateral resisting ability of structure, to improve the bending strength of local tower body, and then improves its anti-bending strength, and Improve displacement of the structure under horizontal wind excitation, thus meet the applicable performance of structure, it is logical by setting flange 3 and tower body 1 Fastener connection is crossed, in-site installation is convenient, is connected by screw bolts the working measure of installation completely, reduces construction cost, and reduction is made Valence simultaneously improves local tower body bending strength.
Optionally embodiment, fastener is set as anchor ear 4, while easy to disassemble, can better play tight Solid effect, column 2 and flange 3 are directly fixed on tower body by anchor ear 4 and fastened, does not generate any shadow to environment It rings, avoids the technical issues of existing reinforcing mode takes up a large area, be fastened by bolts, reduce the construction time, And construction cost is low and construction is easy.
Optionally embodiment, anchor ear 4 are fixedly connected on the inner surface of flange 3, the diameter of anchor ear 4 and its corresponding to 1 position of tower body diameter it is identical, by the effect of anchor ear 4, flange 3, column 2 are linked together with what tower body fastened, lead to The waist for being fixed on tower body with flange 3 is crossed, the bending stiffness of cantilever member lumbar region is improved, improves the anti-lateral displacement energy of structure Power to improve the bending strength of local tower body, and then improves its anti-bending strength.
Optionally embodiment, Fig. 2 are the overlooking structure diagrams of the present embodiment, as shown in Fig. 2, flange 3 is piece Shape flange, flange 3 include the first flange structure 31 and second flange structure 32 in mirror settings, first flange structure 31 and the The fan-shaped setting of two flange arrangements 32.
Optionally embodiment, anchor ear 4 include the first hoop plate 41 and the second hoop plate 42, and the first hoop plate 41 is welded in the The inner surface of one flange arrangement 31, the second hoop plate 42 are welded in the inner surface of second flange structure 32, wherein the first hoop 41 He of plate Second hoop plate 42 is including semi-annular shape structure and two engaging lugs being respectively arranged at semi-annular shape structure both ends, Mei Gelian It is equipped with two exhausting holes on lug, every row is arranged two in the present embodiment, and in actual work progress, the number of through-hole can root It is set as one or more according to actual requirement of engineering, is not limited specifically herein.As shown in figure 3, by the way that bolt 7 is inserted Enter in through-hole, the first hoop plate 41 is fixedly connected with the second hoop plate 42.
Optionally embodiment, the width of the first hoop plate 41 are greater than the thickness of first flange structure 31, the second hoop plate 42 width is greater than the thickness of second flange structure 32, in use, by the cooperation of the first hoop plate 41 and the second hoop plate 42, by tower Body 1 is fixed together with column 2, avoids existing tower body bearing capacity insufficient.
Optionally embodiment, flange 3 are equipped with multiple fan-shaped pore structures 6, scallop hole structure setting in flange 3 with The junction of anchor ear 4 mitigates the weight of flange, may pass through antenna feed in fan-shaped pore structure by the way that multiple fan-shaped pore structures are arranged Line and power supply line make this tower body bracing means have carry mounting condition, make to reinforce while can satisfy otherwise application, Overall structure is simple and practical, securely and reliably.
The junction of optionally embodiment, column and the flange is equipped with ribbed stiffener 5, by the way that ribbed stiffener is arranged 5, it avoids the flange 3 due to use excessively thin, generates the problems in stress collection at the column edge of 1 junction of flange 3 and tower body, and Column and tower body are can simultaneously be effectively combined into unified structural body by the cooperative bearing of tunable column and tower body, are established Form stress system, structure body characteristics are as follows: the housing structure of upper and lower variable diameter, upper diameter 300mm, base diameter 600mm;Tower body Receiving antenna horizontal wind excitation at 33.5 meters, 31.0 meters, 28.0 meters of absolute altitudes is respectively 1990 newton, 1940 newton, 1890 Ns ?;It is with the steel column of the Φ 18 of tower body kernel of section radius 600mm radiation arrangement used by reinforcing;Reinforcing scope is tower body 10 meters away from ground~22 meters interval ranges;Front and back is reinforced, targeted housing structure is identical, and Structure Calculation is limited using Midas First software for calculation, as shown in table 1:
Table 1:
Under conditions of identical tower body structure and external load, tower body top structure displacement before reinforcing: 1143mm;Add Gu displacement after is 884mm, by a disguised form using the design concept of enlarging section, reduces the displacement at the top of tower body, improves The service life of tower increases the safety in use process.
A kind of tubular structure tower, including above-mentioned tower body bracing means, Fig. 4 is that the structure of the present embodiment tubular structure tower is shown It is intended to, as shown in figure 4, communication tower, which can play to reinforce well, to be made by using this tower body bracing means to existing lamppost tower With.Specifically, column 2 is set as every three meter Yi Gen along the vertical direction of tower body 1, in order to install, and the both ends of column 2 And it is respectively provided with one of flange 3 at interval of Yi meter Chu on column 2, to guarantee contacting reliably between column 2 and tower body 1.
Fig. 5 is the partial enlarged view of footing in Fig. 4, as shown in figure 5, tower body 1 is every three meters or so upper along the vertical direction Column 2, the both ends of each column 2 and along the vertical direction each meter of left and right settings flange, in actual work progress are set In, the number of flange 3 can be arranged according to actual requirement of engineering, it is ensured that meet and use required intensity, the present embodiment In, 4 flanges are equipped with using each column 2, this tubular structure tower is from structural theory, the covert design for using enlarging section Theory improves the bending stiffness of cantilever member lumbar region, improves the anti-of structure by being fixed on the waist of tower body with flange 3 Sidesway ability to improve the bending strength of local tower body, and then improves its anti-bending strength, and improves structure in horizontal wind lotus Displacement under carrying is connect with tower body 1 by fastener, scene peace to meet the applicable performance of structure by setting flange 3 Dress is convenient, is connected by screw bolts the working measure of installation completely, reduces construction cost, reduces cost and improves local tower body bending resistance Intensity.
The above description is merely a specific embodiment, but scope of protection of the present invention is not limited thereto, any Those familiar with the art in the technical scope disclosed by the present invention, can easily think of the change or the replacement, and should all contain Lid is within protection scope of the present invention.Therefore, protection scope of the present invention should be based on the protection scope of the described claims.

Claims (10)

1. a kind of tower body bracing means, it is characterised in that: including several columns on the outside of tower body are arranged in, the column is described in The circumferential direction of tower body is uniformly distributed, and the column and the tower body are passed through tightly by flanged joint, the flange and the tower body Firmware connection.
2. tower body bracing means according to claim 1, it is characterised in that: the fastener is set as anchor ear.
3. tower body bracing means according to claim 2, it is characterised in that: the anchor ear is fixedly connected on the flange Inner surface, the diameter of the anchor ear with its corresponding to the diameter of tower body position it is identical.
4. tower body bracing means according to claim 2 or 3, it is characterised in that: the flange is sheet flange, the method Orchid includes the first flange structure and second flange structure in mirror settings, the first flange structure and the second flange knot The fan-shaped setting of structure.
5. tower body bracing means according to claim 4, it is characterised in that: the anchor ear includes the first hoop plate and the second hoop Plate, the first hoop plate are welded in the inner surface of the first flange structure, and the second hoop plate is welded in the second flange The inner surface of structure.
6. tower body bracing means according to claim 5, it is characterised in that: the width of the first hoop plate is greater than described the The width of the thickness of one flange arrangement, the second hoop plate is greater than the thickness of the second flange structure.
7. tower body bracing means according to claim 2 or 3, it is characterised in that: the flange is equipped with multiple scallop holes Structure, the scallop hole structure setting is in the junction of the flange and the anchor ear.
8. tower body bracing means according to claim 1, it is characterised in that: the junction of the column and the flange is equal Equipped with ribbed stiffener.
9. a kind of tubular structure tower, it is characterised in that: including any tower body bracing means of claim 1-8.
10. tubular structure tower according to claim 9, it is characterised in that: column is arranged along the vertical direction of the tower body For every three meter Yi Gen, one of flange is respectively provided at interval of Yi meter Chu on the both ends of the column and the column.
CN201910061642.5A 2019-01-22 2019-01-22 A kind of tower body bracing means and tubular structure tower Pending CN109577734A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910061642.5A CN109577734A (en) 2019-01-22 2019-01-22 A kind of tower body bracing means and tubular structure tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910061642.5A CN109577734A (en) 2019-01-22 2019-01-22 A kind of tower body bracing means and tubular structure tower

Publications (1)

Publication Number Publication Date
CN109577734A true CN109577734A (en) 2019-04-05

Family

ID=65917675

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910061642.5A Pending CN109577734A (en) 2019-01-22 2019-01-22 A kind of tower body bracing means and tubular structure tower

Country Status (1)

Country Link
CN (1) CN109577734A (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150013267A1 (en) * 2013-07-09 2015-01-15 Jeffrey Huncovsky Systems and Methods for Repairing Utility Poles
CN104963541A (en) * 2015-07-23 2015-10-07 孙仲齐 Method for manufacturing nano-composite tower capable of resisting strong breeze whose speed is greater than 60 m/s
CN204729241U (en) * 2015-07-07 2015-10-28 新疆天山恒合能源装备有限责任公司 A kind of wind-power tower corrosion prevention operation flange
CN106013832A (en) * 2016-05-27 2016-10-12 山东省邮电规划设计院有限公司 Reinforcement and reconstruction method of communication pipe tower
CN108360907A (en) * 2018-04-13 2018-08-03 国网冀北电力有限公司迁西县供电分公司 A kind of 10kV circuits dual power supply gets in touch with hand in hand structure and its installation and application method
CN207829577U (en) * 2017-12-28 2018-09-07 广州信盛通信科技有限公司 A kind of mounting structure of communication equipment platform
CN108775188A (en) * 2018-06-01 2018-11-09 中国航空规划设计研究总院有限公司 A kind of prestressing force communication king-post and its construction method
US20180347547A1 (en) * 2017-05-30 2018-12-06 General Electric Company Wind turbine tower reinforcement system
CN209523522U (en) * 2019-01-22 2019-10-22 吉林吉大通信设计院股份有限公司长春分院 A kind of tower body bracing means and tubular structure tower

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20150013267A1 (en) * 2013-07-09 2015-01-15 Jeffrey Huncovsky Systems and Methods for Repairing Utility Poles
CN204729241U (en) * 2015-07-07 2015-10-28 新疆天山恒合能源装备有限责任公司 A kind of wind-power tower corrosion prevention operation flange
CN104963541A (en) * 2015-07-23 2015-10-07 孙仲齐 Method for manufacturing nano-composite tower capable of resisting strong breeze whose speed is greater than 60 m/s
CN106013832A (en) * 2016-05-27 2016-10-12 山东省邮电规划设计院有限公司 Reinforcement and reconstruction method of communication pipe tower
US20180347547A1 (en) * 2017-05-30 2018-12-06 General Electric Company Wind turbine tower reinforcement system
CN207829577U (en) * 2017-12-28 2018-09-07 广州信盛通信科技有限公司 A kind of mounting structure of communication equipment platform
CN108360907A (en) * 2018-04-13 2018-08-03 国网冀北电力有限公司迁西县供电分公司 A kind of 10kV circuits dual power supply gets in touch with hand in hand structure and its installation and application method
CN108775188A (en) * 2018-06-01 2018-11-09 中国航空规划设计研究总院有限公司 A kind of prestressing force communication king-post and its construction method
CN209523522U (en) * 2019-01-22 2019-10-22 吉林吉大通信设计院股份有限公司长春分院 A kind of tower body bracing means and tubular structure tower

Similar Documents

Publication Publication Date Title
CN209523522U (en) A kind of tower body bracing means and tubular structure tower
CN111608864A (en) Guyed steel cylinder tower of wind generating set and steel cylinder replacing method
CN109779002A (en) Overall assembled framework house
CN109577734A (en) A kind of tower body bracing means and tubular structure tower
CN104612908A (en) Wind power generation tower cylinder platform and wind power generation tower cylinder
KR100972965B1 (en) A support apparatus for a tower of a wind turbine
CN202072386U (en) Lifting appliance for lifting raft foundation reinforcement cage of containment vessel of nuclear power station
CN203896264U (en) Single column photovoltaic assembly support
CN206149183U (en) Photovoltaic module reinforcing bracket
CN209874624U (en) Standard module suitable for multiple scenes and assembly tower thereof
CN211230712U (en) Transparent type liftable wind power tower
CN203079591U (en) Crane wall-attaching steel-structure switch connection support
CN211257308U (en) Assembled steel structure beam column connected node
CN207377750U (en) A kind of vertical pump necessary electromotor support construction on the basis of three supporting leg
CN111749852A (en) Grillage tower for wind power generator (group) and manufacturing method thereof
CN211524273U (en) Additional steel truss of communication tower synthesizes bill-board structure
CN212563532U (en) Tower drum and wind generating set
CN218324188U (en) Firm in structure single-pipe tower
CN212535934U (en) Guyed steel cylinder tower of wind generating set
CN213269058U (en) Stiff temporary support structure for inclined column
CN215716087U (en) Bracing built-up connection structure for rack
CN218208675U (en) Group's string data dc-to-ac converter mounting structure
CN216198698U (en) Wind generating set cabin top cover supporting assembly
CN210068385U (en) Buried bearing framework for assembling wind power base
CN211851159U (en) Pre-assembled structure for tower piece

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination