CN109537456A - The construction method of plank road structure waterborne - Google Patents

The construction method of plank road structure waterborne Download PDF

Info

Publication number
CN109537456A
CN109537456A CN201811377817.5A CN201811377817A CN109537456A CN 109537456 A CN109537456 A CN 109537456A CN 201811377817 A CN201811377817 A CN 201811377817A CN 109537456 A CN109537456 A CN 109537456A
Authority
CN
China
Prior art keywords
concrete
cylinder
pile
girder steel
railing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811377817.5A
Other languages
Chinese (zh)
Other versions
CN109537456B (en
Inventor
李涛
毛子成
熊玎玮
张丽骏
王可东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 5 Group Co Ltd
Original Assignee
Shanghai Construction No 5 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 5 Group Co Ltd filed Critical Shanghai Construction No 5 Group Co Ltd
Priority to CN201811377817.5A priority Critical patent/CN109537456B/en
Publication of CN109537456A publication Critical patent/CN109537456A/en
Application granted granted Critical
Publication of CN109537456B publication Critical patent/CN109537456B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/12Portable or sectional bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/005Piers, trestles, bearings, expansion joints or parapets specially adapted for portable or sectional bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

It needs to set cofferdam for plank road structure construction waterborne in the prior art, it is long in time limit, the problem of environmental pollution is serious, the present invention provides a kind of construction methods of plank road structure waterborne, including several prefabricated piles, distribution beam is combined in length and breadth, corrugated plating, concrete slab and railing, combination distribution beam is set to the top of prefabricated pile in length and breadth, corrugated plating is set to the top for combining distribution beam in length and breadth, concrete slab is set to the top of corrugated plating, railing is set to the two sides of the concrete slab, combination distribution beam includes several lateral girder steels and several longitudinal girder steels in length and breadth, the transverse direction girder steel is respectively arranged at least two prefabricated piles, and several lateral girder steels are arranged in parallel, the both ends of adjacent lateral girder steel pass through corresponding longitudinal girder steel connection respectively, and longitudinal girder steel is flushed with the upper surface of the lateral girder steel.The construction method of plank road structure waterborne provided by the invention, can accelerate construction progress, while can pollution to avoid cofferdam construction to river.

Description

The construction method of plank road structure waterborne
Technical field
The present invention relates to the realm of building construction more particularly to a kind of construction methods of plank road structure waterborne.
Background technique
Existing plank road structure waterborne uses integral cast-in-situ structure, as shown in Figure 1,11 top casting concrete base of friction pile Concrete column 13 is set on plinth plate 12, concrete base slab 12, is arranged on concrete column 13 and combines distribution beam in length and breadth, it is described in length and breadth Combining distribution beam is to combine beams of concrete 2 ' in length and breadth, combines concrete slab is arranged on beams of concrete 2 ' in length and breadth.
On the one hand, since concrete column is arranged on construction concrete base slab, concrete base slab, a large amount of reinforcing bars is needed to tie up The processes such as bundle, template installation, concreting, need a large amount of human and material resources, and concrete base slab and concrete column need to carry out It conserves within 28 days, the duration is very long.
On the other hand, since concrete base slab and concrete column are located at river surface hereinafter, therefore, concrete foundation of constructing The cofferdam 600m long need to be set when plate and concrete column, dredging of drawing water, time-consuming takes a lot of work, is seriously polluted, and cofferdam has one in water Fixed risk.If cost is high, long construction period using steel sheet-pile cofferdam is used.If doing cofferdam using double-row steel pipe stake, Although low cost, bankets and be easy to pollute river.The safety for paying attention to cofferdam at any time is needed during cofferdam construction simultaneously, is kept away Exempt from cofferdam leak, and need to preventing cofferdam collapsing from doing emergency measure, safety is poor.Construction cofferdam about 12 days, work is elongated Phase.
Therefore, how providing one kind can accelerate construction progress, moderate cost, while can be to avoid cofferdam construction to river Pollution plank road structure waterborne construction method, it has also become construction circle need further improvement and optimization the technical issues of.
Summary of the invention
The purpose of the present invention is to provide a kind of construction methods of plank road structure waterborne, can accelerate construction progress, simultaneously It can pollution to avoid cofferdam construction to river.
In order to solve the above technical problems, the invention provides the following technical scheme:
The invention discloses a kind of construction methods of plank road structure waterborne, include the following steps:
Step 1, construction lofting after test pile, carry out the piling construction of prefabricated pile;
Step 2, in the leveling steel plate of the top surface of prefabricated pile setting required thickness, so that the leveling at the top of each prefabricated pile The upper surface of steel plate is located at same level;
Lateral girder steel is fixedly installed in step 3, the top of the leveling steel plate of prefabricated pile, and the lower section of every lateral girder steel is at least It is supported by two prefabricated piles, the transverse direction girder steel is located at river surface or more;
Step 4, the same side of adjacent transverse girder steel pass through a pair of longitudinal girder steel connection respectively, form combination distribution in length and breadth Beam, and longitudinal girder steel is vertical with the lateral girder steel, the longitudinal direction girder steel is flushed with the upper surface of the lateral girder steel;
Corrugated plating is arranged in the top for combining distribution beam in length and breadth in step 5, and the corrugated plating is fixed on described by rivet On longitudinal girder steel;
Step 6, the casting concrete plate on corrugated plating are prefabricated for planting the railing of the bottom of railing on concrete slab Preformed groove;
The bottom fixation of railing is inserted in the railing preformed groove by step 7;
Step 8 is laid with marble slab by adhesive layer in the upper surface of concrete slab and two sides.
Preferably, in the construction method of above-mentioned plank road structure waterborne, the piling construction of prefabricated pile in the step 1 Include:
(1) pitching pile is carried out by the positioning of stake;
(2) it after stake has been inserted, checks correction stake position, should lift if any deviation and insert again, until it is accurate in place, then by pile monkey pressure To stake top, stake is made gently to sink to korneforos, while checking whether the center of pile monkey and pile cover is consistent with stake axis, and check stake Orientation whether there is or not movement, check it is errorless after, open hammer injection;
(3) stake machine uses guide rod type diesel pile driver, when starting piling, should beat tap slowly, the impact energy of pile monkey should not be too Greatly, as squeezing into for stake can be gradually increased the impact energy of pile monkey, when piling, with two theodolites stake just, side two sides is at 90 It spends angle and monitors pile body verticality, if it find that pile deflection, is corrected immediately, row injection again after fixing;
(4) when 1m above to the natural water surface is beaten in stake, using steel pile follower pipe, stake is sent to designed elevation.
Preferably, in the construction method of above-mentioned plank road structure waterborne, in the step 5, corrugated plating is from a side to another The installation of side drop-over, every installation one are stepped into position correction of row, deviation such as occur, rectified a deviation using jack.
Preferably, in the construction method of above-mentioned plank road structure waterborne, the longitudinal direction girder steel, lateral girder steel and ripple Plate palpus derusting by sandblasting, derusting by sandblasting includes three paints: priming paint uses epoxy zinc-rich paint with antirust, and intermediate coat also uses epoxy zinc-rich For paint with further antirust, finishing coat uses polyurethane paint with not eclipsed.
Preferably, it in the construction method of above-mentioned plank road structure waterborne, opens up on the concrete slab for planting column The railing preformed groove of the bottom of bar.
It preferably, further include steel plate bolt in the construction method of above-mentioned plank road structure waterborne, the steel plate bolt packet Level board and vertical plate are included, the level board is fixed on corrugated plating, and the vertical plate is perpendicularly fixed in the level board Portion, the vertical groove that the bottom of the railing is protruded into for the vertical plate of steel plate bolt.
Preferably, in the construction method of above-mentioned plank road structure waterborne, in the step 6, casting concrete plate is specific Include the following steps:
(1) it is wet that template watering is coped with before casting concrete, cleanout should be re-closed after removing sundries and ponding;
(2) casting method should be promoted by one end with " catching up with slurry processes ", and the virtual resurfacing thickness that plate pours should be slightly bigger than plate thickness, be used Immersion vibrator vibrates, and immersion vibrator should be inserted fastly and be pulled out slowly, and slotting point wants evenly distributed, point-by-point mobile, carries out in order, no Must omit, accomplish uniform jolt ramming, mobile spacing is not more than 1.5 times of vibrating head operating radius, vibrate upper one layer when should be inserted into down Layer concrete face 50mm to eliminate the seam of two interlayers pays attention to that Mobile sign or inserted link inspection is constantly used to control concrete plate thickness Degree, vibrates and finishes, with floating rule or planker smooth out surface;
(3) when demoulding, the intensity of concrete must reach the 70% of design grade, surface temperature of concrete and environment temperature Difference, must not exceed 25 DEG C, to prevent concrete surface generate crack;
(4) after concreting, Ying is covered within 12 hours, and water seasoning;Concrete water seasoning Date mixes retarding additive or has the concrete of seepage resistance demand to cannot be less than 14 days, reaches 1.2MPa in concrete strength Before, it must not trample on it or Construction Vibration, daily irrigation times should be able to keep concrete to be in enough wetting states.
Preferably, in the construction method of above-mentioned plank road structure waterborne, it should be carried out continuously when concrete slab pours, such as must Sublevel concreting must should intermittently be finished before front layer concrete initial set, the maximum duration of interval should be by cement type And concrete initial set condition determines, it should be by treatment of construction joints more than 2 hours.
Preferably, in the construction method of above-mentioned plank road structure waterborne, in the step 6, when concrete slab pours, Special messenger should be sent to observe template reinforcing bar, reserving hole, built-in fitting, joint bar etc. whether there is or not displacement deformation or stopping state, find the problem and answer Stop pouring immediately, and modifies and finish before the concrete initial set that pours of Ying Yi.
By techniques disclosed above scheme it is found that compared with prior art, beneficial effects of the present invention are as follows:
The construction method of plank road structure waterborne provided by the invention, compared with prior art, since distribution beam will be combined in length and breadth It is changed to longitudinal girder steel and lateral girder steel from original vertical concrete beam and lateral beams of concrete, before bearing capacity is basically unchanged It puts, greatly reduces self weight, therefore it may only be necessary to which prefabricated pile can carry combines distribution beam, concrete slab and column in length and breadth The components such as bar are supported without having to as the prior art using river surface base plate below and concrete column is located at Square component, on the one hand, when can save the maintenance of base plate, concrete column and vertical concrete beam and lateral beams of concrete Between, it can effectively save the duration;On the other hand it avoids the need to pour underwater foundation plate and concrete column and 600m long need to be set Cofferdam, had both saved the duration of cofferdam construction, moreover, danger source is effectively prevented, because needing to infuse at any time during cofferdam construction The safety in meaning cofferdam, avoids cofferdam leakage accident, moreover, avoid according to the height of cost caused by steel sheet-pile cofferdam, construction week The problem of phase length, and avoid to do to banket caused by cofferdam according to double-row steel pipe stake and be easy to ask what river polluted Topic.It is combined in another aspect, combining distribution beam in length and breadth and being changed to the i.e. longitudinal girder steel of steel member with lateral girder steel, it can be in the construction process The processes such as a large amount of reinforcing bar bindings, template installation, concreting are reduced, a large amount of human and material resources are saved.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of existing plank road structure waterborne;
Fig. 2 is the structural schematic diagram of the plank road structure waterborne of one embodiment of the invention;
Fig. 3 is the portion the A enlarged drawing of Fig. 2;
Fig. 4 is the distribution schematic diagram for combining distribution beam in one embodiment of the invention in length and breadth.
In figure: 1- prefabricated pile, 2- combine distribution beam, 2 '-in length and breadth to combine beams of concrete, 21- transverse direction girder steel, 22- in length and breadth vertical It is viscous to girder steel, 3- corrugated plating, 4- concrete slab, 41- railing preformed groove, 5- railing, the first cylinder of 51-, the second cylinder of 52-, 6- Knot layer, 7- marble slab, 8- steel plate bolt, 81- level board, 82- vertical plate, 9- river surface, the river bed 10-, 11- friction pile, 12- are mixed Solidifying earth foundation plate, 13- concrete column.
Specific embodiment
The present invention is described in further detail below in conjunction with the drawings and specific embodiments.It below will be by cited implementation Example is in conjunction with attached drawing, the technology contents and feature that the present invention will be described in detail.Need in addition it illustrate, attached drawing is all made of very simplified Form and use non-accurate ratio, only for the purpose of facilitating and clarifying the purpose of the embodiments of the invention.For narration side Just, "upper" described below, "lower" are consistent with the upper and lower direction of attached drawing, but this can't be technical solution of the present invention Limitation.
Please see Fig. 2 to Fig. 4, the invention discloses a kind of construction method of plank road structure waterborne, include the following steps:
Step 1, construction lofting after test pile, carry out the piling construction of prefabricated pile 1, and prefabricated pile protrudes into river bed 10;
Step 2, in the leveling steel plate (not indicating) of the top surface of prefabricated pile 1 setting required thickness, so that each prefabricated pile 1 The upper surface of the leveling steel plate at top is located at same level;
Lateral girder steel 21, the lower section of every lateral girder steel 21 is fixedly installed in step 3, the top of the leveling steel plate of prefabricated pile 1 It is at least supported by two prefabricated piles 1, the transverse direction girder steel 21 is located at 9 or more river surface;
Step 4, the same side of adjacent transverse girder steel 21 pass through a pair of longitudinal girder steel 22 respectively and connect, and formation is combined in length and breadth Distribution beam 2, and longitudinal girder steel 22 is vertical with the lateral girder steel 21, the longitudinal direction girder steel 22 and the lateral girder steel 21 Upper surface flushes;
Corrugated plating 3 is arranged in the top for combining distribution beam 2 in length and breadth in step 5, and the corrugated plating 3 is fixed on institute by rivet It states on longitudinal girder steel 22;
Step 6, the casting concrete plate 4 on corrugated plating 3 are prefabricated for planting the bottom of railing 5 on concrete slab 4 Railing preformed groove;
The bottom fixation of railing 5 is inserted in the railing preformed groove by step 7;
Step 8 is laid with marble slab 7 by adhesive layer 6 in the upper surface of concrete slab 4 and two sides.
The construction method of plank road structure waterborne provided by the invention, compared with prior art, since distribution beam 2 will be combined in length and breadth It is changed to longitudinal girder steel 22 and lateral girder steel 21 from original vertical concrete beam and lateral beams of concrete, is basically unchanged in bearing capacity Under the premise of, self weight is greatly reduced, therefore it may only be necessary to which prefabricated pile 1 can carry combination distribution beam 2, concrete slab 4 in length and breadth And the equal components of railing 5, without having to as the prior art using positioned at the base plate below of river surface 9 and concrete column To support top component, on the one hand, base plate, concrete column and vertical concrete beam and lateral beams of concrete can be saved Curing time estimates the saving duration 40 days;On the other hand it avoids the need to pour underwater foundation plate and concrete column and need to set The cofferdam 600m long, had both saved the duration of cofferdam construction, moreover, danger source is effectively prevented, because needing during cofferdam construction The safety for paying attention to cofferdam at any time, avoids cofferdam leakage accident, moreover, avoid according to the height of cost caused by steel sheet-pile cofferdam, The problem of long construction period, and avoid to do to banket caused by cofferdam according to double-row steel pipe stake and be easy to cause dirt to river The problem of dye.It, can be in another aspect, combination distribution beam 2 is changed to the i.e. longitudinal girder steel 22 of steel member and combines with transverse direction girder steel 21 in length and breadth The processes such as a large amount of reinforcing bar bindings, template installation, concreting are reduced in the construction process, save a large amount of human and material resources.
Preferably, in the construction method of above-mentioned plank road structure waterborne, the piling construction of prefabricated pile 1 in the step 1 Include:
(1) pitching pile is carried out by the positioning of stake;
(2) it after stake has been inserted, checks correction stake position, should lift if any deviation and insert again, until it is accurate in place, then by pile monkey pressure To stake top, stake is made gently to sink to korneforos, while checking whether the center of pile monkey and pile cover is consistent with stake axis, and check stake Orientation whether there is or not movement, check it is errorless after, open hammer injection;
(3) stake machine uses guide rod type diesel pile driver, when starting piling, should beat tap slowly, the impact energy of pile monkey should not be too Greatly, as squeezing into for stake can be gradually increased the impact energy of pile monkey, when piling, with two theodolites stake just, side two sides is at 90 It spends angle and monitors pile body verticality, if it find that pile deflection, is corrected immediately, row injection again after fixing;
(4) when 1m above to the natural water surface is beaten in stake, using steel pile follower pipe, stake is sent to designed elevation.
It using above-mentioned pile sinking construction method, can not only guarantee the verticality of prefabricated pile 1, and can protect prefabricated pile 1 It is damaged during the pile driving process.
Preferably, in the construction method of above-mentioned plank road structure waterborne, in the step 5, corrugated plating 3 from a side to The installation of other side drop-over, every installation one are stepped into position correction of row, deviation such as occur, rectified a deviation using jack, thus Guarantee that corrugated plating 3 is correct in place.
Preferably, in the construction method of above-mentioned plank road structure waterborne, the longitudinal direction girder steel 22, lateral girder steel 21 and 3 palpus derusting by sandblasting of corrugated plating, derusting by sandblasting includes three paints: priming paint uses epoxy zinc-rich paint with antirust, and intermediate coat also uses ring For oxygen zinc rich paint with further antirust, finishing coat uses polyurethane paint with not eclipsed.It so can effectively prevent longitudinal girder steel 22, transverse direction Girder steel 21 and corrugated plating 3 get rusty with it is eclipsed, prolong its service life.
In order to enable railing 5 is reliably connected with concrete slab 4, it is preferred that in the construction party of above-mentioned plank road structure waterborne In method, the railing preformed groove of the bottom for planting railing 5 is opened up on the concrete slab 4.
It preferably, further include steel plate bolt 8 in the construction method of above-mentioned plank road structure waterborne, the steel plate bolt 8 Including level board 81 and vertical plate 82, the level board 81 is fixed on corrugated plating 3, and the vertical plate 82 is perpendicularly fixed at described The middle part of level board 81, the lower part of the railing 5 are a step body, and the step body includes the first cylinder 51 and the second cylinder 52, first cylinder 51 and the second cylinder 52 are coaxially disposed, and the first cylinder 51 is set to the lower section of the second cylinder 52, and described the The outer diameter of one cylinder 51 is greater than second cylinder 52, and the railing preformed groove is cylindrical type groove, the outer diameter of the first cylinder 51 Match with the internal diameter of the railing preformed groove, first cylinder 51 is inserted in the railing preformed groove, first circle The depth that the thickness of column 51 is equal to railing preformed groove subtracts the thickness of the level board 81 of steel plate bolt 8,51, first cylinder Bottom open up the vertical groove of the insertion of vertical plate 82 for steel plate bolt 8, adhesive layer 6 above concrete slab 4 and Marble slab 7 covers the step surface between the first cylinder 51 and the second cylinder 52.
On the one hand, by the way that steel plate bolt 8 is arranged, the level board 81 of steel plate bolt 8 is fixedly connected with corrugated plating 3, and steel plate is inserted In the vertical groove that the bottom that the vertical plate 82 of pin 8 is inserted in 51, the first cylinder of the lower part of railing 5 opens up, column can be made Bar 5 and corrugated plating 3 form reliable connection, improve safety.On the other hand, the step body of the lower part of the railing 5 is using the One cylinder 51 and the second cylinder 52, the first cylinder 51 are set to the lower section of the second cylinder 52, and the outer diameter of first cylinder 51 is big In second cylinder 52, first cylinder 51 is inserted in the railing preformed groove, the outer diameter of the first cylinder 51 with it is described The internal diameter of railing preformed groove matches, and the depth that the thickness of first cylinder 51 is equal to railing preformed groove subtracts steel plate bolt 8 Level board 81 thickness, adhesive layer 6 above concrete slab 4 and marble slab 7 cover the first cylinder 51 and second Step surface between cylinder 52, that is, the adhesive layer 6 and marble slab 7 for being located at 4 top of concrete slab cover the upper of the first cylinder 51 Surface, concrete slab 4, which can play, prevents 51 double swerve of the first cylinder, and marble slab 7 can prevent the first cylinder 51 upwards It is mobile, the withdrawal resistance and stability of the first cylinder 51 are improved, to improve the safety of railing 5.
Preferably, in the construction method of above-mentioned plank road structure waterborne, in the step 6, casting concrete plate 4 has Body includes the following steps:
(1) it is wet that template watering is coped with before casting concrete, cleanout should be re-closed after removing sundries and ponding;
(2) casting method should be promoted by one end with " catching up with slurry processes ", and the virtual resurfacing thickness that plate pours should be slightly bigger than plate thickness, be used Immersion vibrator vibrates, and immersion vibrator should be inserted fastly and be pulled out slowly, and slotting point wants evenly distributed, point-by-point mobile, carries out in order, no It must omit, accomplish uniform jolt ramming, to guarantee that the compactness of concrete slab 4, mobile spacing are not more than the 1.5 of vibrating head operating radius Times, vibrate upper one layer when should be inserted into lower-layer concrete face 50mm, to eliminate the seam of two interlayers, pay attention to constantly using Mobile sign or Inserted link inspection controls 4 thickness of concrete slab, vibrates and finishes, with floating rule or planker smooth out surface;
(3) when demoulding, the intensity of concrete must reach the 70% of design grade, surface temperature of concrete and environment temperature Difference, must not exceed 25 DEG C, to prevent concrete surface generate crack;
(4) after concreting, Ying is covered within 12 hours, and water seasoning;Concrete water seasoning Date mixes retarding additive or has the concrete of seepage resistance demand to cannot be less than 14 days, reaches 1.2MPa in concrete strength Before, it must not trample on it or Construction Vibration, daily irrigation times should be able to keep concrete to be in enough wetting states.
In the present embodiment, casting concrete plate 4 uses the above method, it is ensured that the compactness of concrete slab 4, and can prevent Only concrete surface generates crack, improves the pouring quality of casting concrete plate 4.
In order to improve the pouring quality of casting concrete plate 4, it is preferred that in the construction method of above-mentioned plank road structure waterborne In, it should be carried out continuously when concrete slab 4 pours, should intermittently must such as pour secondary layer concrete before front layer concrete initial set It builds and finishes, the maximum duration of interval should be determined by cement type and concrete initial set condition, should be pressed at construction joint more than 2 hours Reason.
Occur template reinforcing bar, reserving hole, built-in fitting, joint bar displacement deformation or stopping state in order to prevent, it is preferred that In the construction method of above-mentioned plank road structure waterborne, in the step 6, when concrete slab 4 pours, special messenger should be sent to observe template Whether there is or not displacement deformation or stopping state, finding the problem should stop pouring immediately, and answer for reinforcing bar, reserving hole, built-in fitting, joint bar etc. It modifies and finishes before the concrete initial set poured.
Please see Fig. 2 to Fig. 4, present embodiment discloses a kind of plank road structure waterborne, including several prefabricated piles 1, group in length and breadth Distribution beam 2, corrugated plating 3, concrete slab 4 and railing 5 are closed, the distribution beam 2 of combination in length and breadth is set to the upper of the prefabricated pile 1 Side, the corrugated plating 3 are set to the top for combining distribution beam 2 in length and breadth, and the concrete slab 4 is set to the corrugated plating 3 Top, the railing 5 is set to the two sides of the concrete slab 4, and the distribution beam 2 of combination in length and breadth includes several lateral girder steels 21 with several longitudinal girder steels 22, the transverse direction girder steel 21 is respectively arranged at least two prefabricated piles 1, and several cross It is arranged in parallel to girder steel 21, the both ends of adjacent lateral girder steel 21 pass through corresponding longitudinal girder steel 22 respectively and connect, and described vertical It is flushed to girder steel 22 with the upper surface of the lateral girder steel 21.
Plank road structure waterborne provided by the invention, compared with prior art, due to indulging combination distribution beam 2 in length and breadth from original It is changed to longitudinal girder steel 22 and lateral girder steel 21 to beams of concrete and lateral beams of concrete, under the premise of bearing capacity is basically unchanged, Self weight is greatly reduced, therefore it may only be necessary to which prefabricated pile 1 can carry combines distribution beam 2, concrete slab 4 and railing 5 in length and breadth Equal components are supported without having to as the prior art using the base plate below of river surface 9 and concrete column is located at Square component, on the one hand, when can save the maintenance of base plate, concrete column and vertical concrete beam and lateral beams of concrete Between, estimate the saving duration 40 days;On the other hand it avoids the need to pour underwater foundation plate and concrete column and 600m long need to be set Cofferdam, had both saved the duration of cofferdam construction, moreover, danger source is effectively prevented, because needing to infuse at any time during cofferdam construction The safety in meaning cofferdam, avoids cofferdam leakage accident, moreover, avoid according to the height of cost caused by steel sheet-pile cofferdam, construction week The problem of phase length, and avoid to do to banket caused by cofferdam according to double-row steel pipe stake and be easy to ask what river polluted Topic.It combines, can be being constructed with lateral girder steel 21 in another aspect, combining distribution beam 2 in length and breadth and being changed to the i.e. longitudinal girder steel 22 of steel member The processes such as a large amount of reinforcing bar bindings, template installation, concreting are reduced in the process, save a large amount of human and material resources.
In order to guarantee that lateral girder steel 21 keeps horizontally disposed, guarantee the safety of entire plank road structure waterborne, it is preferred that upper In the plank road structure waterborne stated, the leveling steel plate (not indicating) of the top surface setting required thickness of the prefabricated pile 1, so that each pre- The upper surface of the leveling steel plate of 1 top surface of stake processed is located at same level, and the transverse direction girder steel 21 connects with leveling steel plate welding It connects.
Preferably, in above-mentioned plank road structure waterborne, the concrete slab 4 with a thickness of 100-150mm.It is vertical due to having Distribution beam 2 is combined in length and breadth with bearing capacity with what lateral girder steel 21 formed to girder steel 22, and therefore, concrete slab 4 only needs 100- 150mm, the thickness of 200-250mm, has been decreased by almost a half thickness than in the prior art.
Preferably, in above-mentioned plank road structure waterborne, the upper surface and two sides of the concrete slab 4 pass through respectively Adhesive layer 6 is provided with marble slab 7, not only can be with effective protection concrete slab 4 using marble slab 7, and can beautify stack Road structure.
In order to improve the mounting stability of railing 5, it is preferred that in above-mentioned plank road structure waterborne, the concrete slab 4 On open up railing preformed groove (not indicating) for planting 5 lower part of railing.
It preferably, further include steel plate bolt 8 in above-mentioned plank road structure waterborne, the steel plate bolt 8 includes level board 81 and vertical plate 82, the level board 81 be fixed on corrugated plating 3, the vertical plate 82 is perpendicularly fixed at the level board 81 Middle part, the lower part of the railing 5 are a step body, and the step body includes the first cylinder 51 and the second cylinder 52, described first Cylinder 51 and the second cylinder 52 are coaxially disposed, and the first cylinder 51 is set to the lower section of the second cylinder 52, first cylinder 51 Outer diameter is greater than second cylinder 52, and the railing preformed groove is cylindrical type groove, the outer diameter and the railing of the first cylinder 51 The internal diameter of preformed groove matches, and first cylinder 51 is inserted in the railing preformed groove, the thickness of first cylinder 51 Equal to railing preformed groove depth subtract steel plate bolt 8 level board 81 thickness, the bottom of 51, first cylinder opens up For the vertical groove that the vertical plate 82 of steel plate bolt 8 is inserted into, adhesive layer 6 and marble slab 7 above concrete slab 4 cover Step surface between lid the first cylinder 51 and the second cylinder 52.
On the one hand, by the way that steel plate bolt 8 is arranged, the level board 81 of steel plate bolt 8 is fixedly connected with corrugated plating 3, and steel plate is inserted In the vertical groove that the bottom that the vertical plate 82 of pin 8 is inserted in 51, the first cylinder of the lower part of railing 5 opens up, column can be made Bar 5 and corrugated plating 3 form reliable connection, improve safety.On the other hand, the step body of the lower part of the railing 5 is using the One cylinder 51 and the second cylinder 52, the first cylinder 51 are set to the lower section of the second cylinder 52, and the outer diameter of first cylinder 51 is big In second cylinder 52, first cylinder 51 is inserted in the railing preformed groove, the outer diameter of the first cylinder 51 with it is described The internal diameter of railing preformed groove matches, and the depth that the thickness of first cylinder 51 is equal to railing preformed groove subtracts steel plate bolt 8 Level board 81 thickness, adhesive layer 6 above concrete slab 4 and the first cylinder of marble slab covering 51 are justified with second Step surface between column 52, that is, the adhesive layer 6 and marble slab that are located at 4 top of concrete slab cover the upper table of the first cylinder 51 Face, concrete slab 4, which can play, prevents 51 double swerve of the first cylinder, and marble slab can prevent the first cylinder 51 to moving up It is dynamic, the withdrawal resistance and stability of the first cylinder 51 are improved, to improve the safety of railing 5.
Preferably, in above-mentioned plank road structure waterborne, the longitudinal direction girder steel 22, lateral girder steel 21 and corrugated plating 3 Surface sand-blasting derusting.Specifically, in plank road structure waterborne in embodiment, the longitudinal direction girder steel 22, lateral girder steel 21 and The surface of corrugated plating 3 sets gradually three paints: priming paint uses the epoxy zinc-rich paint for antirust, and intermediate coat also uses epoxy zinc-rich For paint with further antirust, finishing coat uses polyurethane paint to guarantee the surface of longitudinal girder steel 22, lateral girder steel 21 and corrugated plating 3 not It is eclipsed.
Preferably, in above-mentioned plank road structure waterborne, beam is located at 9 or more river surface in length and breadth for the combination.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this hair Any change, the modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims Range.

Claims (9)

1. a kind of construction method of plank road structure waterborne, which comprises the steps of:
Step 1, construction lofting after test pile, carry out the piling construction of prefabricated pile;
Step 2, in the leveling steel plate of the top surface of prefabricated pile setting required thickness, so that the leveling steel plate at the top of each prefabricated pile Upper surface be located at same level;
Lateral girder steel is fixedly installed in step 3, the top of the leveling steel plate of prefabricated pile, and the lower section of every lateral girder steel is at least by two The support of root prefabricated pile, the transverse direction girder steel are located at river surface or more;
Step 4, the same side of adjacent transverse girder steel pass through a pair of longitudinal girder steel connection respectively, and distribution beam is combined in formation in length and breadth, and The longitudinal direction girder steel is vertical with the lateral girder steel, and the longitudinal direction girder steel is flushed with the upper surface of the lateral girder steel;
Corrugated plating is arranged in the top for combining distribution beam in length and breadth in step 5, and the corrugated plating is fixed on the longitudinal direction by rivet On girder steel;
Step 6, the casting concrete plate on corrugated plating, the prefabricated railing for planting the bottom of railing is reserved on concrete slab Slot;
The bottom fixation of railing is inserted in the railing preformed groove by step 7;
Step 8 is laid with marble slab by adhesive layer in the upper surface of concrete slab and two sides.
2. the construction method of plank road structure waterborne as described in claim 1, which is characterized in that prefabricated pile in the step 1 Piling construction includes:
(1) pitching pile is carried out by the positioning of stake;
(2) it after stake has been inserted, checks correction stake position, should lift if any deviation and insert again, until it is accurate in place, pile monkey is then pressed into stake Top, makes stake gently sink to korneforos, while checking whether the center of pile monkey and pile cover is consistent with stake axis, and check the side of stake Position whether there is or not movement, check it is errorless after, open hammer injection;
(3) stake machine uses guide rod type diesel pile driver, when starting piling, should beat tap slowly, and the impact energy of pile monkey should not be too big, with Stake squeeze into the impact energy that can be gradually increased pile monkey, when piling, with two theodolites stake just, side two sides is at 90 degree of angles Pile body verticality is monitored, if it find that pile deflection, is corrected immediately, row injection again after fixing;
(4) when 1m above to the natural water surface is beaten in stake, using steel pile follower pipe, stake is sent to designed elevation.
3. the construction method of plank road structure waterborne as described in claim 1, which is characterized in that in the step 5, corrugated plating It is installed from a side to other side drop-over, every installation one steps into position correction of row, deviation such as occurs, is entangled using jack Partially.
4. the construction method of plank road structure waterborne as described in claim 1, which is characterized in that the longitudinal direction girder steel, lateral steel Beam and corrugated plating palpus derusting by sandblasting, derusting by sandblasting includes three paints: priming paint uses epoxy zinc-rich paint with antirust, and intermediate coat is also adopted With epoxy zinc-rich paint with further antirust, finishing coat uses polyurethane paint with not eclipsed.
5. the construction method of plank road structure waterborne as described in claim 1, which is characterized in that open up use on the concrete slab Railing preformed groove in the bottom for planting railing.
6. the construction method of plank road structure waterborne as claimed in claim 5, which is characterized in that it further include steel plate bolt, it is described Steel plate bolt includes level board and vertical plate, and the level board is fixed on corrugated plating, and the vertical plate is perpendicularly fixed at described The middle part of level board, the lower part of the railing are a step body, and the step body includes the first cylinder and the second cylinder, described the One cylinder and the second cylinder are coaxially disposed, and the first cylinder is set to the lower section of the second cylinder, and the outer diameter of first cylinder is greater than Second cylinder, the railing preformed groove are cylindrical type groove, the internal diameter of the outer diameter of the first cylinder and the railing preformed groove Match, first cylinder is inserted in the railing preformed groove, and the thickness of first cylinder is equal to railing preformed groove Depth subtracts the thickness of the level board of steel plate bolt, and the bottom of first cylindrical portion opens up the vertical plate insertion for steel plate bolt Vertical groove, adhesive layer above concrete slab and marble slab cover the step between the first cylinder and the second cylinder Face.
7. the construction method of plank road structure waterborne as described in claim 1, which is characterized in that in the step 6, pour mixed Concrete board specifically comprises the following steps:
(1) it is wet that template watering is coped with before casting concrete, cleanout should be re-closed after removing sundries and ponding;
(2) casting method should be promoted by one end with " catching up with slurry processes ", and the virtual resurfacing thickness that plate pours should be slightly bigger than plate thickness, with insertion Formula vibrator vibrates, and immersion vibrator should be inserted fastly and be pulled out slowly, and slotting point wants evenly distributed, point-by-point mobile, carries out, must not lose in order Leakage, accomplishes uniform jolt ramming, and mobile spacing is not more than 1.5 times of vibrating head operating radius, vibrate upper one layer when should to be inserted into lower layer mixed Solidifying soil face 50mm to eliminate the seam of two interlayers pays attention to that Mobile sign or inserted link inspection is constantly used to control concrete slab thickness, vibration It smashes and finishes, with floating rule or planker smooth out surface;
(3) when demoulding, the intensity of concrete must reach the 70% of design grade, surface temperature of concrete and environment temperature it Difference must not exceed 25 DEG C, generate crack to prevent concrete surface;
(4) after concreting, Ying is covered within 12 hours, and water seasoning;The concrete water seasoning date, It mixes retarding additive or there is the concrete of seepage resistance demand to cannot be less than 14 days, before concrete strength reaches 1.2MPa, It must not trample on it or Construction Vibration, daily irrigation times should be able to keep concrete to be in enough wetting states.
8. the construction method of plank road structure waterborne as claimed in claim 7, which is characterized in that Ying Lianxu when concrete slab pours It carries out, should intermittently must such as finish sublevel concreting before front layer concrete initial set, the maximum duration of interval is answered It is determined by cement type and concrete initial set condition, it should be by treatment of construction joints more than 2 hours.
9. the construction method of plank road structure waterborne as claimed in claim 7, which is characterized in that in the step 6, concrete When plate pours, special messenger should be sent to observe template reinforcing bar, reserving hole, built-in fitting, joint bar etc., and whether there is or not displacement deformation or stopping state, hairs Existing problem should stop pouring immediately, and modify and finish before the concrete initial set that pours of Ying Yi.
CN201811377817.5A 2018-11-19 2018-11-19 Construction method of water plank road structure Active CN109537456B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811377817.5A CN109537456B (en) 2018-11-19 2018-11-19 Construction method of water plank road structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811377817.5A CN109537456B (en) 2018-11-19 2018-11-19 Construction method of water plank road structure

Publications (2)

Publication Number Publication Date
CN109537456A true CN109537456A (en) 2019-03-29
CN109537456B CN109537456B (en) 2020-09-08

Family

ID=65848268

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811377817.5A Active CN109537456B (en) 2018-11-19 2018-11-19 Construction method of water plank road structure

Country Status (1)

Country Link
CN (1) CN109537456B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112523059A (en) * 2020-12-11 2021-03-19 上海市水利工程设计研究院有限公司 Novel assembly type water plank road structure and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08326018A (en) * 1995-05-31 1996-12-10 Mitsubishi Heavy Ind Ltd Method of pier preparation construction by method of all casing construction
CN202273169U (en) * 2011-10-25 2012-06-13 中建七局第三建筑有限公司 Trestle
CN202466338U (en) * 2012-02-24 2012-10-03 中铁十二局集团第二工程有限公司 Construction device for rapidly recovering metro station road
CN104532813A (en) * 2014-12-16 2015-04-22 江西省城建建设集团有限公司 Overwater building construction platform and erecting method and use method thereof
CN204530464U (en) * 2015-01-15 2015-08-05 中国建筑第八工程局有限公司 Trestle guardrail
CN204850515U (en) * 2015-07-23 2015-12-09 中国建筑第八工程局有限公司 Steel construction faces limit protector
CN206408639U (en) * 2017-01-10 2017-08-15 杭州市交通规划设计研究院 Assembled steel reinforced concrete composite bridge

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08326018A (en) * 1995-05-31 1996-12-10 Mitsubishi Heavy Ind Ltd Method of pier preparation construction by method of all casing construction
CN202273169U (en) * 2011-10-25 2012-06-13 中建七局第三建筑有限公司 Trestle
CN202466338U (en) * 2012-02-24 2012-10-03 中铁十二局集团第二工程有限公司 Construction device for rapidly recovering metro station road
CN104532813A (en) * 2014-12-16 2015-04-22 江西省城建建设集团有限公司 Overwater building construction platform and erecting method and use method thereof
CN204530464U (en) * 2015-01-15 2015-08-05 中国建筑第八工程局有限公司 Trestle guardrail
CN204850515U (en) * 2015-07-23 2015-12-09 中国建筑第八工程局有限公司 Steel construction faces limit protector
CN206408639U (en) * 2017-01-10 2017-08-15 杭州市交通规划设计研究院 Assembled steel reinforced concrete composite bridge

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
中国水利水电第七工程局有限公司: "《高速铁路核心技术汇展 京沪高速铁路无砟轨道系统建造》", 31 January 2011 *
全国高校建筑施工研究会: "《土木工程施工手册 上》", 31 August 2009 *
汪岩等: "输煤栈桥压型钢板混凝土组合桥面板计算问题", 《华夏地理》 *
陈文建: "《建筑施工技术 第2版》", 30 June 2018 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112523059A (en) * 2020-12-11 2021-03-19 上海市水利工程设计研究院有限公司 Novel assembly type water plank road structure and construction method thereof

Also Published As

Publication number Publication date
CN109537456B (en) 2020-09-08

Similar Documents

Publication Publication Date Title
CN106284080B (en) Continuous rigid frame aqueduct closes up section constructing method
CN111648228A (en) Assembled pier and construction process thereof
CN104060629B (en) The superimposed wall construction method in covered back-digging subway station and portable side wall formwork jumbo
CN108166397B (en) Railway Frame Bridge construction method
CN208996025U (en) A kind of double casing pile foundation construction structures of thick silt layer
CN108755738A (en) A kind of sea high-rise pile cap blower foundation and its construction method
CN110952456A (en) Pile type bridge construction process
CN109853381B (en) Transitional structure for preventing bridge head from jumping and construction method thereof
CN106759439B (en) Tower crane foundation for foundation pit and construction method thereof
CN211395327U (en) Variable cross-section hollow pier construction device
CN111676824B (en) Bridge construction method
CN106930194A (en) Inter-tie and pier stud global formation construction method and template used support
CN209538008U (en) Plank road structure waterborne
CN106088120B (en) A kind of cofferdam decentralization construction method
CN109537431A (en) Plank road structure and method waterborne
CN110184948A (en) A kind of Bridge beam construction method
CN116516845A (en) Maintenance and reinforcement method for underwater pier of bridge in tidal zone
CN209538034U (en) The efficient constructing structure of plank road waterborne
CN109537456A (en) The construction method of plank road structure waterborne
CN111705664A (en) Hoisting process of prefabricated pier stud of assembled bridge
CN216515097U (en) Bridge pier column system
CN114837088A (en) A kind of construction method of bearing platform on highway
CN1851150A (en) Concrete combined cushion wedge for supporting waist beam for pile anchoring system, and its constrection method
CN212506314U (en) A kind of pile-anchor support foundation pit deepening reinforcement support structure
CN115432552A (en) A hanger and a construction method for a prefabricated high-pile wharf using the hanger

Legal Events

Date Code Title Description