- CN109518973A CN109518973A CN201811416202.9A CN201811416202A CN109518973A CN 109518973 A CN109518973 A CN 109518973A CN 201811416202 A CN201811416202 A CN 201811416202A CN 109518973 A CN109518973 A CN 109518973A
- Authority
- CN
- China
- Prior art keywords
- pump line
- clip
- bracket
- concreting
- square frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 37
- 239000010959 steel Substances 0.000 claims abstract description 37
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims abstract description 20
- 230000000087 stabilizing effect Effects 0.000 claims abstract description 16
- 239000007787 solid Substances 0.000 claims description 7
- 238000003466 welding Methods 0.000 claims description 5
- 230000000149 penetrating effect Effects 0.000 claims description 2
- 239000004567 concrete Substances 0.000 abstract description 23
- 238000010276 construction Methods 0.000 abstract description 8
- 238000005266 casting Methods 0.000 abstract description 3
- 230000002708 enhancing effect Effects 0.000 abstract 1
- 238000010586 diagram Methods 0.000 description 8
- 238000000034 method Methods 0.000 description 4
- 238000005086 pumping Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 3
- 238000009408 flooring Methods 0.000 description 3
- 230000003139 buffering effect Effects 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 238000005336 cracking Methods 0.000 description 1
- 238000005520 cutting process Methods 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/02—Conveying or working-up concrete or similar masses able to be heaped or cast
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)
Abstract
A kind of concreting pump line bracket, including righting seat and bumper bracket, it is characterized by: the righting seat includes pedestal, four the 1st hounds, the 1st clip, the bumper bracket includes square frame, four the 1st upright bars, the 2nd clip, underwater pipeline stabilizing hole, wherein: bumper bracket is fixed on rectangle square steel flat base, and the backing plate of four the 1st upright bar bottom ends of bumper bracket is welded and fixed with square steel flat base.Concreting pump line bracket of the invention has concreting pump line holder device structure simple, easy to make, concreting pump line supporting structure is stablized, engineering suitable for various concrete pump pipe casting concretes, effectively reduce impact force when concrete pump pipe delivering concrete, avoid concrete impact force excessive the advantages of causing pump line booster, enhancing construction safety and reduction engineering cost.
Description
Technical field
The present invention relates to a kind of brackets that construction site uses, specifically, being a kind of concreting pump line branch
Frame.
Background technique
With the continuous development of domestic construction industry, residential housing competition is more and more fierce, and investor is in order to win real estate
The status in field preferably shows the brand of oneself, higher and higher to the building height design of the house, commercial building of investment,
Therefore, it is increase accordingly to the technical difficulty in construction process, especially engineering entity concreting difficulty is increasing.
201 meters high of frame+core wall structure mode commercial residential building building, floor is more, cubic amount of concrete is larger, and main structure is
The great node of entire project gives great support for follow-up work.
Structurally upper 53 layers of project subject, 201 meters of total building height belongs to super high-rise building.Super High engineering mostly uses greatly
Concrete Pumping Technology carries out structural concrete and pours, by concrete pumping, into flooring casting process, pump line is usually adopted
It promoted with tower crane, move and pour, but cushion effect is larger after concrete pumping to flooring, the stability of pump line is poor, pump line
Cracking, booster are easily caused in joint, bring hidden trouble to construction safety, quality.
After solving concrete pumping to flooring, reduce the cushion effect that concrete impact passes to pump line, this project is adopted
Weakened with conveying impact force of a kind of method of concreting pump line bracket to concrete, concrete conveyance is avoided to rush
Hit that power is excessive to cause pump line booster.
Summary of the invention
The purpose of the present invention is to propose a kind of concreting pump line bracket for reducing concrete impact force.
To achieve the above object, the technical solution of the invention is as follows:
A kind of concreting pump line bracket, including righting seat and bumper bracket, it is characterised in that:
The righting seat includes pedestal, four the 1st hounds, the 1st clip, and the pedestal is rectangle square steel flat base, and four
One end of 1st hound is welded in the quadrangle of pedestal admittedly respectively, and the other end is gathered and the 1st clip outside to pedestal upper center is oblique
Gu weldering, the 1st clip makes by steel plate, steel plate thickness 4mm, width 100mm, and the 1st clip is equipped with a fastening end, the long 50mm in fastening end, tightly
The both sides steel plate center of fixed end is equipped with bolt hole, to use bolt fastening;It is equipped with rubber pad on the inside of 1st clip and is used for fastening steel plate
Gap between button and pump line;
The bumper bracket includes square frame, four the 1st upright bars, the 2nd clip, underwater pipeline stabilizing hole, and the square frame is side length
1000mm, diameter 20mm reinforced frame;The middle part of four the 1st upright bars is solid with the welding of four angles end of square frame respectively
It is fixed, keep the 1st upright bar vertical with square frame plane;Two the 2nd hounds are respectively set on the top of four the 1st upright bars, make two
One end of the 2nd hound of root is welded and fixed to form triangle knot with from the nearly angle end on adjacent both sides respectively from the top of the 1st upright bar
Structure, to support square frame;2nd clip is equipped with four the 3rd hounds, and one end of four the 3rd hounds is welded admittedly respectively
In one side of square frame, the other end is gathered and weldering solid on the outside of the 2nd clip, the 2nd card to square frame upper center is oblique
The structure type of hoop is the same as the 1st clip;Cross bar is arranged between the top by adjacent two the 1st upright bars in the underwater pipeline stabilizing hole, cross bar with
Two the second parallel upright bars are set between one side of square frame, underwater pipeline stabilizing hole, underwater pipeline stabilizing are arranged between two second upright bars
Hole is for penetrating concreting pump line;
Wherein: bumper bracket is fixed on rectangle square steel flat base, the backing plate and square steel plate of four the 1st upright bar bottom ends of bumper bracket
Tube chamber welds with base is fixed.
Concreting pump line bracket of the invention can also be further achieved by the following technical measures.
Concreting pump line bracket above-mentioned, wherein the size of the square steel flat base is 1300 × 1000mm.
Concreting pump line bracket above-mentioned, wherein the square steel specification is width 50mm, long 120mm, thickness 5mm.
Concreting pump line bracket above-mentioned, wherein the tight loop diameter is greater than pump line outer diameter 4mm.
Concreting pump line bracket above-mentioned, wherein the bolt specification is M12*70mm.
Concreting pump line bracket above-mentioned, wherein the diameter of first upright bar is 25mm.
Concreting pump line bracket above-mentioned, wherein underwater pipeline stabilizing hole width is 150mm.
After adopting the above technical scheme, concreting pump line bracket of the invention has the advantage that
1, concreting pump line holder device structure is simple, easy to make;
2, concreting pump line supporting structure is stablized, and suitable for the engineering of various concrete pump pipe casting concretes, effectively subtracts
Impact force when weak concrete pump pipe delivering concrete;
3, it avoids concrete impact force is excessive from causing pump line booster, enhances construction safety, reduce engineering cost.
Detailed description of the invention
Fig. 1 is the righting holder structure schematic diagram of the embodiment of the present invention;
Fig. 2 is the 1st yoke configurations schematic diagram of the embodiment of the present invention;
Fig. 3 is the bumper bracket structural schematic diagram of the embodiment of the present invention;
Fig. 4 is the concreting pump line supporting structure and use state diagram of the embodiment of the present invention.
In figure: 1 pedestal, 2 the 1st hounds, 3 first clips, 4 bolts hole, 5 square steel bar frameworks, 6 first upright bars, 7 the
2 hounds, 8 backing plates, 9 the 3rd hounds, 10 second clips, 11 underwater pipeline stabilizing holes, 12 second upright bars, 13 cross bars, 14 concretings pump
Pipe.
Specific embodiment
With reference to embodiments and its attached drawing further explains the present invention.
Embodiment 1
Concreting pump line bracket of the invention, including righting seat and bumper bracket.Concreting pump line bracket of the invention
Construction process are as follows: determine pump line bend pipe diameter and flow development length → production pump line bracket rectangular square tube pedestal → positioning buffering
Frame leg location → cutting simultaneously welds branch hamstring and skeleton muscle → bumper bracket is fixed in pedestal square tube → and makes pump line pipe collar
→ positioning bumper bracket pump line pipe collar position → welding pipe collar positioning bar → location centralizing frame pump line pipe collar position → welding centralizing bracket
Pump line pipe collar positioning bar → penetrate pump line → fastening pump line pipe collar → comes into operation.
It is the righting holder structure schematic diagram of the embodiment of the present invention referring now to Fig. 1, Fig. 1.As shown, the righting seat packet
Including pedestal 1, four the 1st hound 2, the 1st clip 3, the pedestal is rectangle square steel flat base, the one of four the 1st hounds
End is welded in the quadrangle of pedestal admittedly respectively, and the other end is gathered and weldering solid on the outside of the 1st clip to pedestal upper center is oblique.Fig. 2 is this
1st yoke configurations schematic diagram of inventive embodiments.1st clip is made by steel plate, and steel plate thickness 4mm, width 100mm, the 1st clip are equipped with
The both sides steel plate center of one fastening end, the long 50mm in fastening end, fastening end is equipped with bolt hole 4, to use bolt fastening;1st clip
Inside is equipped with rubber pad and buckles the gap between pump line for fastening steel plate.
Fig. 3 is the bumper bracket structural schematic diagram of the embodiment of the present invention, and the bumper bracket includes square frame 5, four the 1st
Upright bar 6, the 2nd clip 10, underwater pipeline stabilizing hole 11, the square frame are side length 1000mm, diameter 20mm reinforced frame;Described four
The middle part of 1 upright bar is welded and fixed with four angles end of square frame respectively, keeps the 1st upright bar vertical with square frame plane;
Two the 2nd hounds 7 are respectively set on the top of four the 1st upright bars, make one end of two the 2nd hounds from the top of the 1st upright bar
It is welded and fixed to form three-legged structure at the nearly angle end on adjacent both sides respectively, to support square frame, the bottom end of the 1st upright bar
Gu weld pad plate 8;2nd clip is equipped with four the 3rd hounds 9, and one end of four the 3rd hounds is welded in square-shaped frame admittedly respectively
One side of frame, the other end are gathered and weldering solid on the outside of the 2nd clip, the structure shape of the 2nd clip to square frame upper center is oblique
Formula is the same as the 1st clip;The underwater pipeline stabilizing hole is by being arranged cross bar 13 between the top of adjacent two the 1st upright bars, in cross bar and square-shaped frame
Two the second parallel upright bars 12 are set between one side of frame, underwater pipeline stabilizing hole are arranged between two second upright bars, underwater pipeline stabilizing hole is used for
Penetrate concreting pump line.
Fig. 4 is the concreting pump line supporting structure and use state diagram of the embodiment of the present invention.The of righting seat
1 clip center is overlapped with the pump line bend pipe upper end center position that bumper bracket positions, and height and position hangs down in pump line bend pipe upper end
At straight 500mm upwards;Bumper bracket is fixed on rectangle square steel flat base, and bumper bracket width is overlapped with base width center, buffering
The backing plate of four the 1st upright bar bottom ends of frame is welded and fixed with square steel flat base.When righting seat is fixed on square according to making step
When on shape square steel flat base, such as four the 1st hounds are collided with bumper bracket, make the welding position of the 1st hound and pedestal square steel
Set range appropriate adjustment, it is ensured that righting seat is reliably welded with pedestal square steel.
Concreting pump line bracket of the invention production with use when it should be noted that
(1) concrete pump pipe bend pipe positioning requirements: the upper end tube nozzle center of concrete pump pipe bend pipe must with bumper bracket it is rectangular in
Heart point is overlapped, and impact force can be made to be uniformly distributed on entire bumper bracket, pass to pedestal.
(2) positioning of fastening steel plate button, fastening requirements: the fastening steel plate button of bumper bracket is the steel as bend pipe angle is formed
Plate face and tube walls parallel, surrounding is tightly attached to tube wall simultaneously when fastening steel plate fastening is solid, it is ensured that stability.
(3) the fastening steel plate button of righting seat is to be vertically arranged, and steel plate surface is also and pump line tube walls parallel, it is ensured that is close to and steady
It is qualitative.
The present invention has substantive distinguishing features and significant technological progress, concreting pump line holder device knot of the invention
Structure is simple, easy to make, by righting seat by the pump line righting of vertical direction, hold, reduced by bumper bracket on pedestal every
The impact force of secondary pump concrete safeguards the safety and stability of entire transportation system to weaken the impact force of pump line entirety.
Concreting pump line bracket of the invention is applied in foreign exchange commercial square main structure concreting,
Significant effect is used in surface of high building, has obtained the approval of supervisor, construction unit and quality surveillance unit, it is well received.
Above embodiments are used for illustrative purposes only, rather than limitation of the present invention, the technology people in relation to technical field
Member, without departing from the spirit and scope of the present invention, can also make various transformation or variation.Therefore, all equivalent
Technical solution also should belong to scope of the invention, should be limited by each claim.
Claims (7)
1. a kind of concreting pump line bracket, including righting seat and bumper bracket, it is characterised in that:
The righting seat includes pedestal, four the 1st hounds, the 1st clip, and the pedestal is rectangle square steel flat base, and four
One end of 1st hound is welded in the quadrangle of pedestal admittedly respectively, and the other end is gathered and the 1st clip outside to pedestal upper center is oblique
Gu weldering, the 1st clip makes by steel plate, steel plate thickness 4mm, width 100mm, and the 1st clip is equipped with a fastening end, the long 50mm in fastening end, tightly
The both sides steel plate center of fixed end is equipped with bolt hole, to use bolt fastening;It is equipped with rubber pad on the inside of 1st clip and is used for fastening steel plate
Gap between button and pump line;
The bumper bracket includes square frame, four the 1st upright bars, the 2nd clip, underwater pipeline stabilizing hole, and the square frame is side length
1000mm, diameter 20mm reinforced frame;The middle part of four the 1st upright bars is solid with the welding of four angles end of square frame respectively
It is fixed, keep the 1st upright bar vertical with square frame plane;Two the 2nd hounds are respectively set on the top of four the 1st upright bars, make two
One end of the 2nd hound of root is welded and fixed to form triangle knot with from the nearly angle end on adjacent both sides respectively from the top of the 1st upright bar
Structure, to support square frame;2nd clip is equipped with four the 3rd hounds, and one end of four the 3rd hounds is welded admittedly respectively
In one side of square frame, the other end is gathered and weldering solid on the outside of the 2nd clip, the 2nd card to square frame upper center is oblique
The structure type of hoop is the same as the 1st clip;Cross bar is arranged between the top by adjacent two the 1st upright bars in the underwater pipeline stabilizing hole, cross bar with
Two the second parallel upright bars are set between one side of square frame, underwater pipeline stabilizing hole, underwater pipeline stabilizing are arranged between two second upright bars
Hole is for penetrating concreting pump line;
Wherein: bumper bracket is fixed on rectangle square steel flat base, the backing plate and square steel plate of four the 1st upright bar bottom ends of bumper bracket
Tube chamber welds with base is fixed.
2. concreting pump line bracket as described in claim 1, which is characterized in that the size of the square steel flat base is
1300×1000mm。
3. concreting pump line bracket as described in claim 1, which is characterized in that the square steel specification is width 50mm, length
120mm, thickness 5mm.
4. concreting pump line bracket as described in claim 1, which is characterized in that the fastening loop diameter is greater than outside pump line
Diameter 4mm.
5. concreting pump line bracket as described in claim 1, which is characterized in that the bolt specification is M12*70mm.
6. concreting pump line bracket as described in claim 1, which is characterized in that the diameter of first upright bar is
25mm。
7. concreting pump line bracket as described in claim 1, which is characterized in that underwater pipeline stabilizing hole width is 150mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811416202.9A CN109518973A (en) | 2018-11-26 | 2018-11-26 | A kind of concreting pump line bracket |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811416202.9A CN109518973A (en) | 2018-11-26 | 2018-11-26 | A kind of concreting pump line bracket |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109518973A true CN109518973A (en) | 2019-03-26 |
Family
ID=65793547
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811416202.9A Pending CN109518973A (en) | 2018-11-26 | 2018-11-26 | A kind of concreting pump line bracket |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109518973A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111364768A (en) * | 2020-03-06 | 2020-07-03 | 南宁腾宁商品混凝土有限公司 | Concrete pumping anti-blocking method and device |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104213711A (en) * | 2014-10-08 | 2014-12-17 | 广西建工集团第三建筑工程有限责任公司 | Pit pump long-distance-suspended pump pipe swinging concreting construction technology for high-rise buildings |
CN204062152U (en) * | 2014-08-29 | 2014-12-31 | 中国建筑第八工程局有限公司 | High-pressure service pump pipe fixing device |
CN206267528U (en) * | 2016-12-01 | 2017-06-20 | 中建四局第五建筑工程有限公司 | A kind of turnover type pump pipe bracket |
CN207830714U (en) * | 2018-02-08 | 2018-09-07 | 河南科建建设工程有限公司 | A kind of vertical pump line damping fixing device of concrete |
-
2018
- 2018-11-26 CN CN201811416202.9A patent/CN109518973A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN204062152U (en) * | 2014-08-29 | 2014-12-31 | 中国建筑第八工程局有限公司 | High-pressure service pump pipe fixing device |
CN104213711A (en) * | 2014-10-08 | 2014-12-17 | 广西建工集团第三建筑工程有限责任公司 | Pit pump long-distance-suspended pump pipe swinging concreting construction technology for high-rise buildings |
CN206267528U (en) * | 2016-12-01 | 2017-06-20 | 中建四局第五建筑工程有限公司 | A kind of turnover type pump pipe bracket |
CN207830714U (en) * | 2018-02-08 | 2018-09-07 | 河南科建建设工程有限公司 | A kind of vertical pump line damping fixing device of concrete |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111364768A (en) * | 2020-03-06 | 2020-07-03 | 南宁腾宁商品混凝土有限公司 | Concrete pumping anti-blocking method and device |
CN111364768B (en) * | 2020-03-06 | 2022-03-04 | 南宁腾宁商品混凝土有限公司 | Concrete pumping anti-blocking method and device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101265748B (en) | Tools type section steel fastener steel tube outer scaffold | |
CN102888979A (en) | Joint processing and constructing method of overhanging scaffold at large cantilever balcony | |
CN107419893A (en) | A kind of elevator steel platform and preparation method thereof | |
CN103603494B (en) | A kind of ultra-thin steel truss sloping core construction method and formwork structure | |
CN109518973A (en) | A kind of concreting pump line bracket | |
CN201738597U (en) | Sectional steel and steel pipe combined type support system of beam with high and large cross section | |
CN103866692A (en) | Novel assembling method for bent cap bearing frame | |
CN204747914U (en) | Supporting bearing roller frame with adjustable major diameter cleaning tube group butt weld is used | |
CN204456810U (en) | A kind of gaily decorated basket pull bar suspension scaffold | |
CN207893257U (en) | A kind of combined type pipeline for construction site is arranged holder temporarily | |
CN110344577A (en) | A kind of plug-in tripod of socket joint type disk button steel pipe scaffold | |
CN103291080A (en) | Movable sizing runway for floor slab concrete pouring | |
CN204940863U (en) | External wall construction outside large form bracket | |
CN202039606U (en) | Concrete pump pipe fixing structure of super high rise building construction | |
CN202766974U (en) | Bent cap bearing frame without full framing | |
CN214995278U (en) | Large-volume concrete combined raft support | |
CN214568556U (en) | Multi-pipeline transportation device in narrow space | |
CN111267064B (en) | Large-inclination hydroelectric penstock assembling and welding trolley | |
CN115522720A (en) | A portal-type mobile scaffold suitable for complex working conditions and its erection method | |
CN106270310B (en) | The preparation method and its manufacture stand of a kind of shield duct piece steel reinforcement cage | |
CN202248819U (en) | Lightweight wooden structure construction scaffolding | |
CN208023608U (en) | A kind of post-cast strip can have enough to meet the need steel channel formwork system | |
CN204299011U (en) | The supporting construction of high-low bay floor support plate | |
CN207048326U (en) | A kind of suspension type platform for equipment interlayer | |
CN217711368U (en) | Plate buckle beam bottom joist system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |