CN109488304B - Conveying method of large drilling grouting equipment - Google Patents
Conveying method of large drilling grouting equipment Download PDFInfo
- Publication number
- CN109488304B CN109488304B CN201811351274.XA CN201811351274A CN109488304B CN 109488304 B CN109488304 B CN 109488304B CN 201811351274 A CN201811351274 A CN 201811351274A CN 109488304 B CN109488304 B CN 109488304B
- Authority
- CN
- China
- Prior art keywords
- equipment
- steel wire
- drilling
- wire rope
- grouting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000005553 drilling Methods 0.000 title claims abstract description 110
- 238000000034 method Methods 0.000 title claims abstract description 62
- 229910000831 Steel Inorganic materials 0.000 claims description 89
- 239000010959 steel Substances 0.000 claims description 89
- 241001023788 Cyttus traversi Species 0.000 claims description 18
- 239000000463 material Substances 0.000 claims description 9
- 238000012546 transfer Methods 0.000 claims description 9
- 230000008569 process Effects 0.000 claims description 8
- 239000002002 slurry Substances 0.000 claims description 7
- 230000005484 gravity Effects 0.000 claims description 6
- 238000009941 weaving Methods 0.000 claims description 3
- 238000003466 welding Methods 0.000 claims description 3
- 238000004804 winding Methods 0.000 claims description 3
- 230000000149 penetrating effect Effects 0.000 claims description 2
- 238000010276 construction Methods 0.000 abstract description 12
- 230000008901 benefit Effects 0.000 abstract description 4
- 238000009434 installation Methods 0.000 abstract description 2
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 7
- JQJCSZOEVBFDKO-UHFFFAOYSA-N lead zinc Chemical compound [Zn].[Pb] JQJCSZOEVBFDKO-UHFFFAOYSA-N 0.000 description 5
- 230000005641 tunneling Effects 0.000 description 5
- 241000269793 Cryothenia peninsulae Species 0.000 description 3
- 230000007547 defect Effects 0.000 description 3
- 238000013461 design Methods 0.000 description 3
- 229910052500 inorganic mineral Inorganic materials 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 3
- 239000011707 mineral Substances 0.000 description 3
- 238000004088 simulation Methods 0.000 description 3
- 238000011161 development Methods 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 238000005065 mining Methods 0.000 description 2
- 238000012986 modification Methods 0.000 description 2
- 230000004048 modification Effects 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 229910052751 metal Inorganic materials 0.000 description 1
- 239000002184 metal Substances 0.000 description 1
- 150000002739 metals Chemical class 0.000 description 1
- 239000011148 porous material Substances 0.000 description 1
- 238000007789 sealing Methods 0.000 description 1
- 238000007569 slipcasting Methods 0.000 description 1
- 238000003860 storage Methods 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D1/00—Sinking shafts
- E21D1/03—Sinking shafts mechanically, e.g. by loading shovels or loading buckets, scraping devices, conveying screws
- E21D1/06—Sinking shafts mechanically, e.g. by loading shovels or loading buckets, scraping devices, conveying screws with shaft-boring cutters
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D5/00—Lining shafts; Linings therefor
- E21D5/04—Lining shafts; Linings therefor with brick, concrete, stone, or similar building materials
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Mechanical Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Earth Drilling (AREA)
Abstract
The invention discloses a conveying method of large drilling grouting equipment, which comprises the following steps: (1) disassembling and classifying drilling grouting equipment; (2) drilling grouting equipment selects different transportation methods according to different classifications; (3) and (4) assembling the drilling grouting equipment. The disassembled drilling grouting equipment is divided into three types of equipment, the first type of equipment is a single piece with large size, the second type of equipment is a single piece with small size and large mass, the third type of equipment is a single piece with an elongated piece, and different methods of transferring, transferring and passing through a ingate are formulated according to different characteristics of the three types of equipment, so that the large drilling grouting equipment can be smoothly put into a well, and the installation is completed. The TSJ-2000 type drilling machine and the 350 pump grouting pump are used for the first time of construction in the well in China. The large-scale equipment adopts the blind vertical shaft to carry out equipment lowering transportation method, has the advantages of high lowering speed, low cost and high stability, and provides important reference significance for lowering similar large-scale equipment into the well.
Description
Technical Field
The invention relates to the technical field of drilling construction. In particular to a method for conveying large-scale drilling grouting equipment.
Background
With the rapid development of national economy in China in recent years, the demand for mineral resources is sharply increased. The supply of nonferrous metals is increasingly tense, while resources with simple shallow and geological conditions are gradually reduced, and the development of resources with complex and deep geological conditions is imperative. The construction amount of the vertical shaft is only less than 10 percent of the total mine construction amount, but the construction period of the vertical shaft is 30 to 40 percent of the total mine, and the vertical shaft is a throat project for mine construction, so that the improvement of the construction speed of the vertical shaft is the key for accelerating the mine construction speed.
In the process of building the shaft of the vertical shaft, the probability of karst cave, large crack, fault fracture zone, fine crack and pore exposed from the shaft of the vertical shaft is high, so that the water inflow quantity often exposed from the shaft of the vertical shaft is high, and once sudden water inflow occurs, the water inflow quantity is larger than the drainage capacity of a water pump, the accident of flooding is caused[5]. Therefore, for the shaft of the deep vertical shaft, the shaft must be pre-grouted to ensure safe and rapid tunneling of the shaft, so that the effects of saving the construction period and reducing the cost are achieved.
The lowest underground mineral exploitation elevation of the lead-zinc mining area of the hair terrace of Yi-Jing-hong mining company Limited is at the middle section of 610 meters, and the mineral reserve with abundant reserves is still found below the middle section of 610 meters. The depth of a shaft of a blind shaft of the 112-line blank plumbum-zincite 112 line of the rough terrace is 960m, the elevation ranges from +910m to-50 m, the shaft is a circular shaft, the diameter of the shaft is 5.7m, the excavation diameter of the shaft is 6.5m, when the shaft of the shaft is excavated to the elevation of +481m, after grouting of a working face and grouting of a wall, the residual water inflow of the shaft is about 50m3H is used as the reference value. The wellbore water inflow is expected to increase substantially in the deep zone. In order to ensure the smooth tunneling of the engineering and eliminate the water trouble of the shaft, the Yi-nations macromining limited company decides to arrange an operation platform at the +670m middle section in the well for shaft pre-grouting.And the pre-grouting engineering needs to convey the equipment to an underground working platform, and the condition that whether large-scale equipment can be smoothly transferred and transported becomes the premise that whether the engineering can be smoothly implemented or not.
Disclosure of Invention
Therefore, the technical problem to be solved by the invention is to provide a conveying method of large drilling grouting equipment.
In order to solve the technical problems, the invention provides the following technical scheme:
the method for conveying the large drilling grouting equipment comprises the following steps:
(1) disassembling and classifying drilling grouting equipment;
(2) drilling grouting equipment selects different transportation methods according to different classifications;
(3) and (4) assembling the drilling grouting equipment.
In the step (1), the drilling grouting equipment comprises a drilling machine, a grouting pump, a slurry pump, a drill rod, a drill collar and a drill tower; the drilling machine can be disassembled into 3 chassis of the drilling machine, a core machine of the drilling machine and a grinding disc of the drilling machine; the grouting pump is disassembled into a grouting pump chassis, a grouting pump motor and a grouting pump body.
In the step (1), the method for conveying the large drilling grouting equipment divides the equipment disassembled into single pieces into three types:
the first type of equipment is a single large-size piece and comprises 3 chassis of a drilling machine and a chassis of a grouting pump;
the second type of equipment is a single piece with small volume and large mass and comprises a mud pump, a core machine of a drilling machine, a grinding disc of the drilling machine, a grouting pump motor and a grouting pump body;
the third type of equipment is a single piece, elongated piece, comprising a drill pipe, a drill collar, and a drill tower.
In the step (2), according to different classification methods, different transportation methods are selected in different transportation sections:
(2-1) transporting from a material yard to a blind shaft well head:
the transfer method of the first equipment comprises the following steps: carrying by shoveling the front end of a loader bucket; one end of the first type of equipment is arranged in a loader bucket, two corners of the other end of the first type of equipment are respectively bound by a steel wire rope, and the other end of the first type of equipment is fixed on the upper part of the bucket by a shackle after the steel wire rope is tensioned; after the loader lifts the bucket, the equipment is directly shoveled and transported to the blind shaft mouth;
the second type of equipment is transported by the following method: carrying by adopting a loader bucket; the second type of equipment is directly bound and fixed by respectively winding two ends of a long steel wire rope for one circle around two ends of the equipment, then the middle part of the steel wire rope is hung on a loader bucket, and after the steel wire rope is adjusted to be horizontal, the equipment is directly hung and transported to a blind shaft well mouth;
the transfer method of the third type of equipment comprises the following steps: hauling with a loader by means of a sledge; firstly, picking and transporting third equipment to the sledge by using a loader, and then firmly binding the third equipment with the sledge by using a steel wire rope, wherein the gravity centers of all the third equipment are slightly in front of the middle part of the sledge in order to ensure the balance and stability in the towing process; then, a long steel wire rope is wound around a third type of equipment from the top, two ends of the long steel wire rope are fixed on special fixing points on two sides of the front end of the sledge, and the middle part of the long steel wire rope is hung on a hook at the tail part of the loader; then the sledge is hauled to the blind shaft well mouth by a loader;
(2-2) lowering the blind shaft to 670 horse head door from the blind shaft mouth:
the lowering method of the first type of equipment comprises the following steps: binding two corners of the short side of the first type of equipment with two ends of a steel wire rope respectively, hanging the middle part of the steel wire rope on a large hook of a lifting system, and directly lowering the steel wire rope to a 670 horsehead door;
the lowering method of the second equipment comprises the following steps: binding and fixing two ends of a long steel wire rope around two ends of the second equipment respectively in a circle, hanging the middle part of the steel wire rope on a large hook of a lifting system, and directly lowering the steel wire rope to the 670 horsehead door;
the lowering method of the third equipment comprises the following steps: weaving 6 steel wire ropes with the length of 11m, wherein the 6 steel wire ropes respectively penetrate through central holes of 6 third-class devices, stringing the 6 steel wire rope ends together by using shackles, then penetrating the other end rope ends of the 6 steel wire ropes by using a thick steel wire rope, hanging the thick steel wire rope on a large hook of a lifting system, lifting the third-class devices to enable the third-class devices to be in an upright stable state after the large hook is lifted, and then directly lowering the third-class devices to 670 horsehead doors;
(2-3) carrying to each operation position by a 670 horsehead door:
the first type of equipment, the second type of equipment and the third type of equipment are conveyed by the following methods: when the device is placed in the 670 ingate, the electric scraper is used for dragging the bottom end of the placed device, signals are sent while dragging, the hook is slowly placed, and when the gravity center of the device is completely positioned in the 670 ingate, the hook steel wire rope is released; after the position of the equipment is adjusted and the steel wire ropes are arranged, the equipment is transported to each operation position by a scraper.
According to the conveying method of the large drilling grouting equipment, the sledge is formed by welding steel pipes, and the manufacturing method comprises the following steps: the two sides of the sledge are large steel pipes, the middle of the sledge is welded and fixed with the small steel pipes, and the pipe orifices at the two ends of the large steel pipes close to the ground are made into upward-warped arcs.
In the step (2-2), the principle of the descending order from the blind shaft mouth to the 670 horsehead door is as follows: the arrangement is carried out according to the assembly sequence of the underground equipment and the space requirement.
The conveying method of the large drilling grouting equipment has the following steps that: firstly, putting down chassis of 3 drilling machines, then putting down a core machine and a millstone of the drilling machine, and finally putting down a drilling tower; the lowering sequence of the grouting pump is as follows: the chassis of the grouting pump is firstly put down, and then the motor and the pump body of the grouting pump are put down.
In the conveying method of the large drilling grouting equipment, in the step (3), the equipment conveyed to each working position is assembled:
slurry pump: the pump body and the motor are assembled after being directly transferred to an operation position by using the electric carry scraper;
grouting pump: directly installing a connecting bolt after a chassis of the grouting pump is directly transferred to an operation position by using an electric scraper; then the pump body of the grouting pump and the motor of the grouting pump are assembled after being directly transferred to the operation position by an electric scraper;
drilling machine: directly installing connecting bolts after 3 chassis of the drilling machine are directly transferred to an operation position by using an electric scraper; the grinding disc of the drilling machine and the core drilling machine of the drilling machine are assembled by using a 16# I-steel lifting beam pre-installed at the top of a drilling pit, a 10t pulley is hung on the lifting beam, an anchor rod is arranged on the edge of the bottom of the drilling pit to fix a winch, a winch steel wire rope penetrates through the pulley and then is connected with a steel wire rope tied on equipment to be lifted, and an electric scraper assists in ensuring the stability and safety of the equipment.
The technical scheme of the invention achieves the following beneficial technical effects:
1. before the large drilling grouting equipment is transported, the drilling grouting equipment is disassembled, so that collision damage in the transportation process of the drilling grouting equipment is reduced.
2. And selecting a descending route, finally selecting 901 a transportation main roadway to be transported to a 112-line blind mixed well according to the characteristics of drilling grouting equipment and the operation capacity of the route, then placing the transportation main roadway to a 670 middle-section ingate from the 112-line blind mixed well, and finally transporting the 670 middle-section ingate to each working position of the grouting chamber and the drilling pit chamber.
3. The disassembled drilling grouting equipment is divided into three types of equipment, the first type of equipment is a single piece with large size, the second type of equipment is a single piece with small size and large mass, the third type of equipment is a single piece with an elongated piece, and different methods of transferring, transferring and passing through a ingate are formulated according to different characteristics of the three types of equipment, so that the large drilling grouting equipment can be smoothly put into a well, and the installation is completed. Safety accidents do not happen in the process of transferring and transporting.
4. In the process of lowering, due to the fact that the space of the underground drill hole chamber is limited, the lowering sequence of the equipment needs to be arranged according to the assembling sequence of the underground equipment and the space requirement.
5. Aiming at the pre-grouting engineering of the 112-line blind shaft of the tarmac lead-zinc ore, the blind shaft is used as a transportation channel, and the problem of well descending of large grouting drilling equipment is solved smoothly. The TSJ-2000 type drilling machine and the 350 pump grouting pump are used for the first time of construction in the well in China. The large-scale equipment adopts the blind shaft to carry out equipment lowering transportation method, has the advantages of high lowering speed, low cost, high stability and the like, and can provide important reference significance for lowering similar large-scale equipment into the well.
Drawings
FIG. 1 is a schematic view of a third type of equipment drill pipe passing through 670 ingate simulation of the transportation method of the large drilling grouting equipment;
fig. 2 is a schematic diagram of a third type of equipment derrick for the transportation method of the large drilling grouting equipment of the invention simulated by a 670 ingate.
Detailed Description
Overview of the engineering
The method comprises the steps that in a high mountain gorge area of a lead-zinc ore place of a rough terrace, a 112-line shaft is a blind shaft, the shaft is a round shaft with the diameter of 5.7m, the designed shaft depth is 960m, the shaft head elevation is plus 910m, the shaft bottom elevation is minus 50m, after the shaft is dug and built to plus 480m, in order to prevent the phenomenon of flooding caused by continuous tunneling, shaft tunneling is suspended, and shaft tunneling operation is resumed after the pre-grouting work is determined to be completed. Due to the limitation of the existing space, finally, an operation platform is arranged in the middle section of +670m underground to perform pre-grouting on the shaft.
The shaft pre-grouting project needs a large amount of equipment, the equipment needs to be conveyed from the ground to the +670m middle section underground, and the equipment mainly comprises a drilling machine, a drill pipe, a slurry pump, a 350 grouting pump and the like. The specific equipment is shown in Table 1.
Table 1 main equipment list
1. Disassembling and classifying drilling grouting equipment;
in order to reduce the collision damage in the transportation process of the equipment, the large drilling grouting equipment is disassembled and classified.
The drilling grouting equipment comprises a drilling machine, a grouting pump, a slurry pump, a drill rod, a drill collar and a drill tower; the drilling machine can be disassembled into 3 chassis of the drilling machine, a core machine of the drilling machine and a grinding disc of the drilling machine; the grouting pump is disassembled into a grouting pump chassis, a grouting pump motor and a grouting pump body.
The equipment disassembled into single pieces is divided into three types:
the first type of equipment is a single large-size piece and comprises 3 chassis of a drilling machine and a chassis of a grouting pump; for example, the length, width and height of the chassis of the grouting pump are 4.8m 2.1m 0.3 m;
the second type of equipment is a single piece with small volume and large mass and comprises a mud pump, a core machine of a drilling machine, a grinding disc of the drilling machine, a grouting pump motor and a grouting pump body; if the weight of a mud pump is 3.1t, the weight of a core machine of a drilling machine reaches 5 t;
the third kind of equipment is a single piece which is an elongated piece and comprises a drill rod, a drill collar and a drill tower; for example, the length of a common drill rod is 9.6 m.
2. The method is characterized in that the existing workprint lead-zinc ore is selected to be at the elevation section of 910m-670m, and four routes are taken as transportation lowering channels:
(1)910 middle section 7# pithead, old shaft, 670 haulage drift, 670 middle section 114 line threading, grouting station and pit drilling position.
The analysis shows that the scheme has the following defects:
① the position of the middle bridgehead of the old shaft 910 and 670 can not satisfy the lowering of the 8m 1.5m derrick;
② 670 middle section transportation drift section is 3m, orbit eccentricity, orbit center to side wall minimum distance 0.9m, overhead line height 1.7m-2.2m, not satisfying 4.8m 2.1m 1.5m BQ-350 grouting pump orbit transportation requirement;
(2) the method comprises the following steps of 910, middle section 7# pithead, 2# inclined shaft, 670 transportation gallery, 670 middle section 114 line threading, grouting station and pit drilling position design, and has the following defects:
the section of the ① 2# inclined shaft is 2.4m x 2.6m, the track is eccentric, the minimum distance from the track center to the side wall is 0.9m, and the track transportation requirement of the BQ-350 grouting pump of 4.8m x 2.1m x 1.5m cannot be met;
② 670 middle section transportation drift section is 3m, orbit eccentricity, orbit center to side wall minimum distance 0.9m, overhead line height 1.6m-1.8m, not satisfying 4.8m 2.1m 1.5m BQ-350 grouting pump orbit transportation requirement;
the ③ 2# inclined shaft throwing track has a larger gradient and cannot meet the requirement of lowering and transporting the driving drill rod;
(3) the method comprises the following steps of (1) passing a 110-line through-connection road (trackless and without a throwing lane) from a 901 transportation main roadway to a 4# inclined shaft to a 670 middle section to (670) a 110-line through-connection road, designing a grouting station and drilling a pit, wherein the scheme has the following defects: no track or no throwing lane exists at the 110-line run-through connection lane position from the No. 4 inclined shaft to the 670 middle section, the equipment materials need to be transshipped and manually transported, the time consumption and the cost are high, and the lifting transportation time is long;
(4)901 transportation main lane-112 line blind mixed well (transformation) -670 middle section 112 line-design slip casting station, drill nest position, this scheme has following advantage:
① all the roadways and lifting equipment of the line meet the size transportation requirements of the largest pieces of equipment and materials;
② the channel is an independent channel, which does not affect the lifting transportation of the mine normal production;
to sum up: the scheme '901 transportation of a large roadway, 112 line blind mixed well, 670 middle section 112 line, design of a grouting station and drilling position' is an optimal scheme by comprehensively considering the lifting capacity of the existing equipment and the roadway transportation condition.
The equipment is transferred and is firstly transferred the non-detachable piece and the super-long material of the large drilling grouting equipment to the blind shaft well mouth from the earth surface storage yard by using a loader and a sledge, the equipment and the material are transferred by using a shaft lifting and transporting device, the equipment is transferred by using an electric scraper underground, and the equipment is assembled by using a lifting beam, an anchor rod and a winch.
In this scenario, a 112-string blind shaft is the key to the success of this large equipment setting.
3. Drilling grouting equipment selects different transportation methods according to different classifications
Because the 112-line blind shaft well head is arranged in a drift 650m away from the well head, the width of the drift near the well head is only enough for a single vehicle to pass, two continuous 90-degree turns are arranged in the drift at the well head, a large truck cannot directly convey equipment to the well head, and the simple crane beam at the well head is used for unloading. The equipment can only be unloaded to the pithead material yard and then somehow transported to the blind shaft wellhead.
(1) Transferring to a blind shaft well head from a material yard:
the transfer method of the first equipment comprises the following steps: carrying by shoveling the front end of a loader bucket; one end of the first type of equipment is arranged in a loader bucket, two corners of the other end of the first type of equipment are respectively bound by a steel wire rope, and the other end of the first type of equipment is fixed on the upper part of the bucket by a shackle after the steel wire rope is tensioned; after the loader lifts the bucket, the equipment is directly shoveled and transported to the blind shaft mouth;
the second type of equipment is transported by the following method: carrying by adopting a loader bucket; the second type of equipment is directly bound and fixed by respectively winding two ends of a long steel wire rope for one circle around two ends of the equipment, then the middle part of the steel wire rope is hung on a loader bucket, and after the steel wire rope is adjusted to be horizontal, the equipment is directly hung and transported to a blind shaft well mouth;
the transfer method of the third type of equipment comprises the following steps: hauling with a loader by means of a sledge; firstly, picking and transporting third equipment to the sledge by using a loader, and then firmly binding the third equipment with the sledge by using a steel wire rope, wherein the gravity centers of all the third equipment are slightly in front of the middle part of the sledge in order to ensure the balance and stability in the towing process; then, a long steel wire rope is wound around a third type of equipment from the top, two ends of the long steel wire rope are fixed on special fixing points on two sides of the front end of the sledge, and the middle part of the long steel wire rope is hung on a hook at the tail part of the loader; then the sledge is hauled to the blind shaft well mouth by a loader;
the sledge is formed by welding steel pipes, and the manufacturing method comprises the following steps: the two sides of the sledge are large steel pipes, the middle of the sledge is welded and fixed with the small steel pipes, and the pipe orifices at the two ends of the large steel pipes close to the ground are made into upward-warped arcs.
(2) Is lowered to 670 horse head door from blind shaft well mouth
A complete set of lifting and transporting system is used for transporting personnel and materials up and down during shaft digging construction in the 112-line blind shaft, and the bearing capacity of the system meets the requirement of equipment lowering. The blind shaft sealing plate meets the requirement of passing the maximum-size equipment. The blind shaft is dug and built to the elevation of 480m, and in order to ensure the safety of equipment lowering and the convenience of personnel operation, a hanging scaffold is arranged at the ground height of a ingate at the middle section of the shaft 670.
The lowering method of the first type of equipment comprises the following steps: binding two corners of the short side of the first type of equipment with two ends of a steel wire rope respectively, hanging the middle part of the steel wire rope on a large hook of a lifting system, and directly lowering the steel wire rope to a 670 horsehead door;
the lowering method of the second equipment comprises the following steps: binding and fixing two ends of a long steel wire rope around two ends of the second equipment respectively in a circle, hanging the middle part of the steel wire rope on a large hook of a lifting system, and directly lowering the steel wire rope to the 670 horsehead door;
the lowering method of the third equipment comprises the following steps: weaving 6 steel wire ropes with the length of 11m, enabling the 6 steel wire ropes to respectively penetrate through central holes of 6 third-class devices, stringing the 6 steel wire rope ends together by using shackles, enabling a thick steel wire rope to penetrate through the rope ends at the other ends of the 6 steel wire ropes and then be hung on a large hook of a lifting system, lifting the third-class devices to enable the third-class devices to be in a vertical stable state after the large hook is lifted, and directly lowering the third-class devices to 670 horsehead doors.
(3) And (5) carrying to each operation position from a 670 horsehead door:
and (3) simulating whether the passing capacity meets the requirement of the descending size of the equipment or not by using a pre-simulation, wherein the height of the underground 670 ingate is 5m, and as shown in figures 1 and 2. By simulation, both the drill pipe and the rig of the third type of equipment can pass through 670 ingate.
The first type of equipment, the second type of equipment and the third type of equipment are conveyed by the following methods: when the device is placed in the 670 ingate, the electric scraper is used for dragging the bottom end of the placed device, signals are sent while dragging, the hook is slowly placed, and when the gravity center of the device is completely positioned in the 670 ingate, the hook steel wire rope is released; after the position of the equipment is adjusted and the steel wire ropes are arranged, the equipment is transported to each operation position by a scraper.
Lowering from the blind shaft wellhead to the 670 horsehead door also requires: the arrangement is carried out according to the assembly sequence of the underground equipment and the space requirement.
The lowering sequence of the drilling machine is as follows: firstly, putting down chassis of 3 drilling machines, then putting down a core machine and a millstone of the drilling machine, and finally putting down a drilling tower; the lowering sequence of the grouting pump is as follows: the chassis of the grouting pump is firstly put down, and then the motor and the pump body of the grouting pump are put down.
(4) The equipment transferred to each working position is assembled
Slurry pump: the pump body and the motor are assembled after being directly transferred to an operation position by using the electric carry scraper;
grouting pump: directly installing a connecting bolt after a chassis of the grouting pump is directly transferred to an operation position by using an electric scraper; then the pump body of the grouting pump and the motor of the grouting pump are assembled after being directly transferred to the operation position by an electric scraper;
drilling machine: directly installing connecting bolts after 3 chassis of the drilling machine are directly transferred to an operation position by using an electric scraper; the grinding disc of the drilling machine and the core drilling machine of the drilling machine are assembled by using a 16# I-steel lifting beam pre-installed at the top of a drilling pit, a 10t pulley is hung on the lifting beam, an anchor rod is arranged on the edge of the bottom of the drilling pit to fix a winch, a winch steel wire rope penetrates through the pulley and then is connected with a steel wire rope tied on equipment to be lifted, and an electric scraper assists in ensuring the stability and safety of the equipment.
Aiming at the pre-grouting engineering of the 112-line blind shaft of the tarmac lead-zinc ore, the blind shaft is used as a transportation channel, and the problem of well descending of large grouting drilling equipment is solved smoothly. The TSJ-2000 type drilling machine and the 350 pump grouting pump are used for the first time of construction in the well in China. The large-scale equipment adopts the blind vertical shaft to transfer and transport the equipment, has the advantages of high transfer speed, low cost, high stability and the like, and can provide important reference significance for the well transfer of similar large-scale equipment.
It should be understood that the above examples are only for clarity of illustration and are not intended to limit the embodiments. Other variations and modifications will be apparent to persons skilled in the art in light of the above description. And are neither required nor exhaustive of all embodiments. And obvious variations or modifications are possible which remain within the scope of the appended claims.
Claims (5)
1. The method for conveying the large drilling grouting equipment is characterized by comprising the following steps of:
(1) disassembling and classifying drilling grouting equipment;
in the step (1), the drilling grouting equipment comprises a drilling machine, a grouting pump, a slurry pump, a drill pipe, a drill collar and a drill tower; the drilling machine can be disassembled into 3 chassis of the drilling machine, a core machine of the drilling machine and a grinding disc of the drilling machine; the grouting pump is disassembled into a grouting pump chassis, a grouting pump motor and a grouting pump body;
in step (1), the equipment disassembled into single pieces is divided into three categories:
the first type of equipment is a single large-size piece and comprises 3 chassis of a drilling machine and a chassis of a grouting pump;
the second type of equipment is a single piece with small volume and large mass and comprises a mud pump, a core machine of a drilling machine, a grinding disc of the drilling machine, a grouting pump motor and a grouting pump body;
the third kind of equipment is a single piece which is an elongated piece and comprises a drill rod, a drill collar and a drill tower;
(2) drilling grouting equipment selects different transportation methods according to different classifications;
(3) assembling drilling grouting equipment;
in the step (2), according to different classification methods, different transportation methods are selected in different transportation sections:
(2-1) transporting from a material yard to a blind shaft well head:
the transfer method of the first equipment comprises the following steps: carrying by shoveling the front end of a loader bucket; one end of the first type of equipment is arranged in a loader bucket, two corners of the other end of the first type of equipment are respectively bound by a steel wire rope, and the other end of the first type of equipment is fixed on the upper part of the bucket by a shackle after the steel wire rope is tensioned; after the loader lifts the bucket, the equipment is directly shoveled and transported to the blind shaft mouth;
the second type of equipment is transported by the following method: carrying by adopting a loader bucket; the second type of equipment is directly bound and fixed by respectively winding two ends of a long steel wire rope for one circle around two ends of the equipment, then the middle part of the steel wire rope is hung on a loader bucket, and after the steel wire rope is adjusted to be horizontal, the equipment is directly hung and transported to a blind shaft well mouth;
the transfer method of the third type of equipment comprises the following steps: hauling with a loader by means of a sledge; firstly, picking and transporting third equipment to the sledge by using a loader, and then firmly binding the third equipment with the sledge by using a steel wire rope, wherein the gravity centers of all the third equipment are slightly in front of the middle part of the sledge in order to ensure the balance and stability in the towing process; then, a long steel wire rope is wound around a third type of equipment from the top, two ends of the long steel wire rope are fixed on special fixing points on two sides of the front end of the sledge, and the middle part of the long steel wire rope is hung on a hook at the tail part of the loader; then the sledge is hauled to the blind shaft well mouth by a loader;
(2-2) lowering the blind shaft to 670 horse head door from the blind shaft mouth:
the lowering method of the first type of equipment comprises the following steps: binding two corners of the short side of the first type of equipment with two ends of a steel wire rope respectively, hanging the middle part of the steel wire rope on a large hook of a lifting system, and directly lowering the steel wire rope to a 670 horsehead door;
the lowering method of the second equipment comprises the following steps: binding and fixing two ends of a long steel wire rope around two ends of the second equipment respectively in a circle, hanging the middle part of the steel wire rope on a large hook of a lifting system, and directly lowering the steel wire rope to the 670 horsehead door;
the lowering method of the third equipment comprises the following steps: weaving 6 steel wire ropes with the length of 11m, wherein the 6 steel wire ropes respectively penetrate through central holes of 6 third-class devices, stringing the 6 steel wire rope ends together by using shackles, then penetrating the other end rope ends of the 6 steel wire ropes by using a thick steel wire rope, hanging the thick steel wire rope on a large hook of a lifting system, lifting the third-class devices to enable the third-class devices to be in an upright stable state after the large hook is lifted, and then directly lowering the third-class devices to 670 horsehead doors;
(2-3) carrying to each operation position through a 670 horsehead door:
the first type of equipment, the second type of equipment and the third type of equipment are conveyed by the following methods: when the device is placed in the 670 ingate, the electric scraper is used for dragging the bottom end of the placed device, signals are sent while dragging, the hook is slowly placed, and when the gravity center of the device is completely positioned in the 670 ingate, the hook steel wire rope is released; after the position of the equipment is adjusted and the steel wire ropes are arranged, the equipment is transported to each operation position by a scraper.
2. The method for conveying large drilling grouting equipment according to claim 1, wherein the sledge is formed by welding steel pipes and is manufactured by the following steps: the two sides of the sledge are large steel pipes, the middle of the sledge is welded and fixed with the small steel pipes, and the pipe orifices at the two ends of the large steel pipes close to the ground are made into upward-warped arcs.
3. The method for transporting large drilling grouting equipment according to claim 1, wherein in the step (2-2), the lowering sequence from the blind shaft mouth to the 670 horse head door is arranged according to the assembly sequence and space requirement of the underground equipment.
4. A method of conveying large drilling grouting equipment according to claim 3, characterized in that the lowering sequence of the drilling rig is: firstly, putting down chassis of 3 drilling machines, then putting down a core machine and a millstone of the drilling machine, and finally putting down a drilling tower; the lowering sequence of the grouting pump is as follows: the chassis of the grouting pump is firstly put down, and then the motor and the pump body of the grouting pump are put down.
5. Method for the transportation of large drilling grouting equipment according to claim 1, characterized in that in step (3) the equipment transported to the respective working location is assembled:
slurry pump: the pump body and the motor are assembled after being directly transferred to an operation position by using the electric carry scraper;
grouting pump: directly installing a connecting bolt after a chassis of the grouting pump is directly transferred to an operation position by using an electric scraper; then the pump body of the grouting pump and the motor of the grouting pump are assembled after being directly transferred to the operation position by an electric scraper;
drilling machine: directly installing connecting bolts after 3 chassis of the drilling machine are directly transferred to an operation position by using an electric scraper; the grinding disc of the drilling machine and the core drilling machine of the drilling machine are assembled by using a 16# I-steel lifting beam pre-installed at the top of a drilling pit, a 10t pulley is hung on the lifting beam, an anchor rod is arranged on the edge of the bottom of the drilling pit to fix a winch, a winch steel wire rope penetrates through the pulley and then is connected with a steel wire rope tied on equipment to be lifted, and an electric scraper assists in ensuring the stability and safety of the equipment.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811351274.XA CN109488304B (en) | 2018-11-14 | 2018-11-14 | Conveying method of large drilling grouting equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811351274.XA CN109488304B (en) | 2018-11-14 | 2018-11-14 | Conveying method of large drilling grouting equipment |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109488304A CN109488304A (en) | 2019-03-19 |
CN109488304B true CN109488304B (en) | 2020-04-10 |
Family
ID=65695692
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811351274.XA Active CN109488304B (en) | 2018-11-14 | 2018-11-14 | Conveying method of large drilling grouting equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109488304B (en) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103754589A (en) * | 2014-02-18 | 2014-04-30 | 中国水利水电第八工程局有限公司 | Method and system for transporting bulk materials through high-fall continuous shafts |
CN104858038A (en) * | 2015-06-03 | 2015-08-26 | 马鞍山聚力科技有限公司 | Transportation and mounting method of large fixed hydraulic crusher vertical shaft |
CN104858039A (en) * | 2015-06-03 | 2015-08-26 | 马鞍山聚力科技有限公司 | Construction method of suspending and transporting crusher by shaft cage |
CN107060795A (en) * | 2017-05-26 | 2017-08-18 | 安徽理工大学 | A kind of underground mine TBM assembly construction methods |
CN108275573A (en) * | 2018-01-30 | 2018-07-13 | 中铁二十二局集团第工程有限公司 | The construction method for hanging and lifting translation unit equipment of rock tunnel(ling) machine |
-
2018
- 2018-11-14 CN CN201811351274.XA patent/CN109488304B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103754589A (en) * | 2014-02-18 | 2014-04-30 | 中国水利水电第八工程局有限公司 | Method and system for transporting bulk materials through high-fall continuous shafts |
CN104858038A (en) * | 2015-06-03 | 2015-08-26 | 马鞍山聚力科技有限公司 | Transportation and mounting method of large fixed hydraulic crusher vertical shaft |
CN104858039A (en) * | 2015-06-03 | 2015-08-26 | 马鞍山聚力科技有限公司 | Construction method of suspending and transporting crusher by shaft cage |
CN107060795A (en) * | 2017-05-26 | 2017-08-18 | 安徽理工大学 | A kind of underground mine TBM assembly construction methods |
CN108275573A (en) * | 2018-01-30 | 2018-07-13 | 中铁二十二局集团第工程有限公司 | The construction method for hanging and lifting translation unit equipment of rock tunnel(ling) machine |
Also Published As
Publication number | Publication date |
---|---|
CN109488304A (en) | 2019-03-19 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106894817B (en) | A kind of mechanization Upward slicing wedging mixed filling mining codes | |
CN109083644B (en) | A kind of safe and efficient mining methods of gently inclined medium thick orebody | |
CN103696774B (en) | Aboveground down-hole parallel construction staple shaft frame development method | |
CN101775985B (en) | Deeply buried iron mineral resource underground mining and concentrating integration system | |
CN104989272B (en) | Upward inverse well drilling process | |
CN104265164B (en) | The creeping into draw to dig of plateau mountain foundation pit excavation construction equipment carries native device | |
CN106089205A (en) | A kind of room-and-pillar method filling mining method being applicable to very thin ore body under water body | |
CN108708726A (en) | A kind of double-layer double-direction horizontal slices open stope afterwards filling mining methods | |
CN111502745A (en) | Double-tunnel separately-repaired tunnel construction production vertical shaft bottom trackless transport vehicle yard structure and construction method | |
CN111322073A (en) | A combined mine development system based on vertical shaft and tape inclined shaft | |
CN109296374B (en) | TBM hoisting and translation method for deep well enclosed space | |
CN104265156B (en) | The drawing to dig of plateau mountain foundation pit excavation construction equipment carries native device | |
CN109555559B (en) | Water prevention and treatment technical method for thousand-meter-level blind shaft of metal mine | |
CN212837943U (en) | Double-hole separately-repaired tunnel construction production vertical shaft bottom trackless transport vehicle yard structure | |
CN108626482B (en) | Utilize the construction method of anti-well drilling machine installation vertical gas pipe | |
CN109488304B (en) | Conveying method of large drilling grouting equipment | |
CN104989402A (en) | Medium-deep hole room pillar mining method for limestone underground mine mining | |
CN204476407U (en) | A kind of pick anchor parallel operations construction equipment | |
CN117005886A (en) | Underground mining system for large-dip-angle multi-coal-seam coal mine | |
CN204492863U (en) | A kind of hydraulic pressure supports tunnel sectional shelf-unit from moving circulation | |
CN103276670B (en) | A kind of suspension bridge anchorage is holed comprehensive anchoring process | |
CN205297358U (en) | Rig and boring tower device thereof | |
CN115306471B (en) | Optimized construction method of blind mixed well sliding-breaking system | |
CN103711489B (en) | The exploitation method of narrow vein basin shape nugget | |
CN211779722U (en) | Foundation-free base of coal mining belt machine head driving part |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |