CN109409718A - A kind of highway green construction fuzzy matter element evaluation model and construction method - Google Patents

A kind of highway green construction fuzzy matter element evaluation model and construction method Download PDF

Info

Publication number
CN109409718A
CN109409718A CN201811207256.4A CN201811207256A CN109409718A CN 109409718 A CN109409718 A CN 109409718A CN 201811207256 A CN201811207256 A CN 201811207256A CN 109409718 A CN109409718 A CN 109409718A
Authority
CN
China
Prior art keywords
data
module
construction
acquisition module
highway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811207256.4A
Other languages
Chinese (zh)
Inventor
周马生
魏雪涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Road and Bridge Corp
Original Assignee
China Road and Bridge Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Road and Bridge Corp filed Critical China Road and Bridge Corp
Priority to CN201811207256.4A priority Critical patent/CN109409718A/en
Publication of CN109409718A publication Critical patent/CN109409718A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06393Score-carding, benchmarking or key performance indicator [KPI] analysis
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • General Physics & Mathematics (AREA)
  • Tourism & Hospitality (AREA)
  • Theoretical Computer Science (AREA)
  • Educational Administration (AREA)
  • Marketing (AREA)
  • Development Economics (AREA)
  • General Business, Economics & Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Physics & Mathematics (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of highway green construction fuzzy matter element evaluation model and construction methods, comprising: data acquisition module, the data acquisition module is used to acquire all data during construction of the highway, and provides data source for data analysis module;Data analysis module, the data analysis module are used to analyze the data information of data acquisition module transmitting, and integrate to each data, finally pass data to association analysis module;Association analysis module, the association analysis module is for analyzing influence of each evaluation index to whole green construction degree;Overall merit module, the result that the overall merit module is used to be obtained according to association analysis module calculates the comprehensive score of highway green construction degree, the evaluation model can more accurately reflect practice of construction situation, and more objective appraisal can be made, simultaneously, most reasonable optimization can be made according to evaluation result, so that the effect of evaluation model becomes apparent from.

Description

A kind of highway green construction fuzzy matter element evaluation model and construction method
Technical field
The present invention relates to construction of the highway field, specially a kind of highway green construction fuzzy matter element evaluation model and building side Method.
Background technique
Green construction refers in engineering construction, under the premise of guaranteeing the basic demands such as quality, safety, passes through scientific management And technological progress, it economizes on resources to the maximum extent and reduces the construction activities negatively affected to environment, realize four sections, one environmental protection (section Can, it save land, is water-saving, save material and environmental protection).Green construction should be sustainable development idea overall application in engineering construction It embodying, green construction not merely refers to implements closure construction in engineering construction, and without dusty, no noise disturbs residents, In building site, surrounding grows flowers, plants grass, implements these contents such as timing watering, it is related to the various aspects of sustainable development, such as raw State and the contents such as environmental protection, resource and using energy source, the development of society and economy.
Matter Analysis is research matter-element, inquires into a kind of method for how solving inconsistent problem.Matter Analysis is promoted with studying It is converted into things, solution inconsistent problem is core content.Generally, it is the rule for studying people " offer advice, try every possible means " The subject of rule.Its theoretical frame is by research matter-element and its matter-element theory of variation and establishes mathematics on the basis of Region place value Two parts of tool form.
When carrying out green construction to highway, it usually needs building evaluation model, it is existing for highway green construction Evaluation model and construction method are usually the evaluation index and evaluate collection in terms of determining each influence, then different by determining The weight of evaluation index, the evaluation result needed.
But the evaluation model and construction method of existing highway green construction have the following deficiencies:
(1) existing evaluation model is difficult to carry out the degree of green construction comprehensive evaluation, and evaluation result objectivity is not It is enough, it can not accurately reflect actual conditions;
(2) existing evaluation model is difficult to be closed according to evaluation result after the degree to green construction makes evaluation The construction optimization of reason can not play the effect of evaluation model.
Summary of the invention
In order to overcome the shortcomings of that prior art, the present invention provide a kind of highway green construction fuzzy matter element evaluation model And construction method, which can more accurately reflect practice of construction situation, and can make more objective appraisal, together When, most reasonable optimization can be made according to evaluation result so that the effect of evaluation model becomes apparent from can effectively solve background The problem of technology proposes.
The technical solution adopted by the present invention to solve the technical problems is:
A kind of highway green construction fuzzy matter element evaluation model, comprising:
Data acquisition module, the data acquisition module are used to acquire all data during construction of the highway, and are number Data source is provided according to analysis module;
Data analysis module, the data analysis module are used to analyze the data information of data acquisition module transmitting, and right Each data are integrated, and association analysis module is finally passed data to;
Association analysis module, the association analysis module is for analyzing each evaluation index to whole green construction degree It influences;
Overall merit module, it is green that the result that the overall merit module is used to be obtained according to association analysis module calculates highway The comprehensive score of color construction degree.
Further, the data acquisition module include energy consumption acquisition module, consumption ground acquisition module, water consumption acquisition module, Consumptive material acquisition module and environment influence acquisition module, and the acquisition module that consumes energy, consumption ground acquisition module, water consumption acquisition module, consumptive material Acquisition module, environment influence acquisition module and respectively correspond energy conservation, save land, is water-saving, section five material, environmental protection evaluation indexes.
Further, the association analysis module includes data association module and weighted associations module, the data correlation Module is used for analytical calculation for the data of analytical calculation acquisition and the degree of association of each evaluation index, the weighted associations module The weighted value of each evaluation index and whole green construction degree.
Further, the overall merit module is connected with construction optimization module.
In addition, the present invention also provides a kind of construction methods of highway green construction fuzzy matter element evaluation model, including such as Lower step:
S100, building fuzzy matter element;
S200, the opinion rating for determining each evaluation index of object to be evaluated;
S300, the weight for determining evaluation index;
S400, the comprehensive score for obtaining highway green construction simultaneously establish evaluation model.
Further, in the step s 100, the method for constructing fuzzy matter element is by highway green construction object T and its feature Object C, characterizing magnitudes v collectively form highway green construction matter-element R, i.e.,
R=(T, C, v),
Wherein, C is evaluation index, and evaluation index C can be n, i.e. C1, C2 ... Cn, v are evaluation index present worth, right That answers also has n, i.e. v1, v2 ... vn.
Further, if highway green construction object T there are m, compound fuzzy matter element Rmn can be established, i.e.,
Further, in step s 200, the specific steps of each evaluation index opinion rating are determined are as follows:
S201, it establishes each evaluation index and acquires the correlation function of data;
S202, the degree of association is determined;
S203, the opinion rating that each evaluation index is determined according to correlation function and the degree of association.
Further, in step S300, analytic hierarchy process (AHP), Principal Component Analysis, entropy assessment or Te Erfei can be passed through Method calculates the weight of each evaluation index.
Further, it in step S400, establishes after evaluation model, by the weight of each evaluation index and can also comment Valence grade establishes highway green construction Optimized model.
Compared with prior art, the beneficial effects of the present invention are:
(1) present invention can more accurately reflect practice of construction situation, and make more objective appraisal, advantageously ensure that green Color construction is gone on smoothly;
(2) present invention can make more reasonable construction optimization according to evaluation result, so that the effect of evaluation model is more prominent Out, be conducive to improve the effect of green construction.
Detailed description of the invention
Fig. 1 is overall structure diagram of the invention;
Fig. 2 is overall flow schematic diagram of the invention.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
As shown in Figure 1, the present invention provides a kind of highway green construction fuzzy matter element evaluation model, including data acquisition module Block, data analysis module, association analysis module and overall merit module.
Data acquisition module is used to acquire all data during construction of the highway, and provides data for data analysis module Source.
Data acquisition module include energy consumption acquisition module, consumption ground acquisition module, water consumption acquisition module, consumptive material acquisition module and Environment influences acquisition module, and the acquisition module that consumes energy, consumption ground acquisition module, water consumption acquisition module, consumptive material acquisition module, environment shadow Acquisition module is rung to respectively correspond energy conservation, save land, is water-saving, section five material, environmental protection evaluation indexes, it can by this five indexs The degree of objective effective judgement highway green construction, simultaneously as energy consumption acquisition module, consumption ground acquisition module, water consumption acquisition Module, consumptive material acquisition module and environment influence acquisition module data values collected and all have ambiguity, therefore can construct public affairs The fuzzy matter element of road green construction.
Data analysis module is used to analyze the data information of data acquisition module transmitting, and integrates to each data, Finally pass data to association analysis module.
Association analysis module is for analyzing influence of each evaluation index to whole green construction degree, association analysis module Including data association module and weighted associations module.
Data association module is for the data of analytical calculation acquisition and the degree of association of each evaluation index, due to the number of acquisition According to not being determining incidence relation between corresponding evaluation index, such as the data of effect on environment and being associated with very for environmental protection index It is abstract, it is therefore desirable to determine the degree of association, each evaluation index is enabled to determine opinion rating according to these data and the degree of association.
Weighted value of the weighted associations module for each evaluation index of analytical calculation and whole green construction degree, green are applied Work and energy conservation, save land, water-saving, section five material, environmental protection evaluation indexes are related, but each evaluation index is to green construction The influence of degree is different, it is therefore desirable to the weight for determining each evaluation index, just according to the opinion rating of weight and each index Complete green construction fuzzy matter element evaluation model can be established, and evaluation is more acurrate objective.
The result that overall merit module is used to be obtained according to association analysis module calculates the synthesis of highway green construction degree Scoring.
Overall merit module is connected with construction optimization module, due to that can understand in the fuzzy matter element evaluation model of foundation Influence of each evaluation index of understanding to whole green construction situation, and be able to know that target commenting in each evaluation index Valence grade, therefore be conducive to optimize construction later, the effect of highway green construction can be passed through.
In addition, as shown in Fig. 2, the present invention also provides a kind of building sides of highway green construction fuzzy matter element evaluation model Method includes the following steps:
Step 1: building fuzzy matter element.
In the step s 100, the method for constructing fuzzy matter element is by highway green construction object T and its feature object C, spy Sign magnitude v collectively forms highway green construction matter-element R, i.e.,
R=(T, C, v),
Wherein, C is evaluation index, and evaluation index C can be n, i.e. C1, C2 ... Cn, v are evaluation index present worth, right That answers also has n, i.e. v1, v2 ... vn, and when being directed to highway green construction, evaluation index is energy conservation, saves land, is water-saving, section material, ring Border protection, v are collected each corresponding data.
If highway green construction object T there are m, compound fuzzy matter element Rmn can be established, i.e.,
It is excellent in order to improve the accuracy of green construction degree evaluation, and convenient for later during green construction Changing improves, and construction of the highway section can be divided into multistage according to factors such as landform, length, and establish compound fuzzy matter element, so that Evaluation result can more precisely.
Step 2: determining the opinion rating of each evaluation index of object to be evaluated.
In step 2, the specific steps of each evaluation index opinion rating are determined are as follows:
S201, it establishes each evaluation index and acquires the correlation function of data.
S202, determine that the degree of association, correlation function and the degree of association can be determined by the methods of big data analysis, expert's guidance.
S203, the opinion rating that each evaluation index is determined according to correlation function and the degree of association, opinion rating can be according to demand Be divided into it is multiple, meanwhile, when determining the opinion rating of each evaluation index, should first determine choice threshold value, avoid evaluation etc. Grade, which divides, ambiguity or error.
Step 3: determining the weight of evaluation index.
In step 3, each evaluation can be calculated by analytic hierarchy process (AHP), Principal Component Analysis, entropy assessment or Delphi method The weight of index.
Step 4: obtaining the comprehensive score of highway green construction and establishing evaluation model.
It in step 4, establishes after evaluation model, can also be established by the weight and opinion rating of each evaluation index Highway green construction Optimized model, the construction optimization after being conducive to.
It is obvious to a person skilled in the art that invention is not limited to the details of the above exemplary embodiments, Er Qie In the case where without departing substantially from spirit or essential attributes of the invention, the present invention can be realized in other specific forms.Therefore, no matter From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the present invention is by appended power Benefit requires rather than above description limits, it is intended that all by what is fallen within the meaning and scope of the equivalent elements of the claims Variation is included within the present invention.Any reference signs in the claims should not be construed as limiting the involved claims.

Claims (10)

1. a kind of highway green construction fuzzy matter element evaluation model characterized by comprising
Data acquisition module, the data acquisition module are used to acquire all data during construction of the highway, and are data point It analyses module and data source is provided;
Data analysis module, the data analysis module are used to analyze the data information of data acquisition module transmitting, and to each Data are integrated, and association analysis module is finally passed data to;
Association analysis module, the association analysis module is for analyzing each evaluation index to the shadow of whole green construction degree It rings;
Overall merit module, the result that the overall merit module is used to be obtained according to association analysis module calculate highway green and apply The comprehensive score of engineering degree.
2. a kind of highway green construction fuzzy matter element evaluation model according to claim 1, it is characterised in that: the data Acquisition module includes that energy consumption acquisition module, consumption ground acquisition module, water consumption acquisition module, consumptive material acquisition module and environment influence acquisition Module, and the acquisition module that consumes energy, consumption ground acquisition module, water consumption acquisition module, consumptive material acquisition module, environment influence acquisition module point Not Dui Ying energy conservation, save land, be water-saving, section five material, environmental protection evaluation indexes.
3. a kind of highway green construction fuzzy matter element evaluation model according to claim 1, it is characterised in that: the association Analysis module includes data association module and weighted associations module, and the data association module is used for the data of analytical calculation acquisition With the degree of association of each evaluation index, the weighted associations module is for each evaluation index of analytical calculation and whole green construction The weighted value of degree.
4. a kind of highway green construction fuzzy matter element evaluation model according to claim 1, it is characterised in that: the synthesis Evaluation module is connected with construction optimization module.
5. a kind of construction method of highway green construction fuzzy matter element evaluation model, characterized by the following steps:
S100, building fuzzy matter element;
S200, the opinion rating for determining each evaluation index of object to be evaluated;
S300, the weight for determining evaluation index;
S400, the comprehensive score for obtaining highway green construction simultaneously establish evaluation model.
6. a kind of construction method of highway green construction fuzzy matter element evaluation model according to claim 5, feature exist In: in the step s 100, the method for constructing fuzzy matter element is by highway green construction object T and its feature object C, characterizing magnitudes V collectively forms highway green construction matter-element R, i.e.,
R=(T, C, v),
Wherein, C is evaluation index, and evaluation index C can be n, i.e. C1、C2…Cn, v is evaluation index present worth, corresponding There are n, i.e. v1、v2…vn
7. a kind of construction method of highway green construction fuzzy matter element evaluation model according to claim 6, feature exist In: if highway green construction object T there are m, compound fuzzy matter element R can be establishedmn, i.e.,
8. a kind of construction method of highway green construction fuzzy matter element evaluation model according to claim 5, feature exist In: in step s 200, determine the specific steps of each evaluation index opinion rating are as follows:
S201, it establishes each evaluation index and acquires the correlation function of data;
S202, the degree of association is determined;
S203, the opinion rating that each evaluation index is determined according to correlation function and the degree of association.
9. a kind of construction method of highway green construction fuzzy matter element evaluation model according to claim 5, feature exist In: in step S300, each evaluation can be calculated by analytic hierarchy process (AHP), Principal Component Analysis, entropy assessment or Delphi method and is referred to Target weight.
10. a kind of construction method of highway green construction fuzzy matter element evaluation model according to claim 5, feature exist In: it in step S400, establishes after evaluation model, highway can also be established by the weight and opinion rating of each evaluation index Green construction Optimized model.
CN201811207256.4A 2018-10-17 2018-10-17 A kind of highway green construction fuzzy matter element evaluation model and construction method Pending CN109409718A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811207256.4A CN109409718A (en) 2018-10-17 2018-10-17 A kind of highway green construction fuzzy matter element evaluation model and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811207256.4A CN109409718A (en) 2018-10-17 2018-10-17 A kind of highway green construction fuzzy matter element evaluation model and construction method

Publications (1)

Publication Number Publication Date
CN109409718A true CN109409718A (en) 2019-03-01

Family

ID=65468226

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811207256.4A Pending CN109409718A (en) 2018-10-17 2018-10-17 A kind of highway green construction fuzzy matter element evaluation model and construction method

Country Status (1)

Country Link
CN (1) CN109409718A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116451829A (en) * 2023-02-23 2023-07-18 葛洲坝集团交通投资有限公司 Expressway construction emission reduction optimization method and system based on principal component analysis

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102646160A (en) * 2012-02-21 2012-08-22 北京工业大学 Regional water pollution comprehensive evaluation and optimization method based on entropy weight fuzzy matter element method
CN104680308A (en) * 2014-09-26 2015-06-03 北京科技大学 Fuzzy matter element evaluation method for cavability of rock
US20160224922A1 (en) * 2015-02-02 2016-08-04 Korea Institute Of Civil Engineering And Building Technology System and method for evaluating performance of infrastructure
CN106780160A (en) * 2016-12-13 2017-05-31 广东环境保护工程职业学院 A kind of Green Construction Assessment method
CN106933175A (en) * 2017-03-21 2017-07-07 中建三局第建设工程有限责任公司 Green construction management system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102646160A (en) * 2012-02-21 2012-08-22 北京工业大学 Regional water pollution comprehensive evaluation and optimization method based on entropy weight fuzzy matter element method
CN104680308A (en) * 2014-09-26 2015-06-03 北京科技大学 Fuzzy matter element evaluation method for cavability of rock
US20160224922A1 (en) * 2015-02-02 2016-08-04 Korea Institute Of Civil Engineering And Building Technology System and method for evaluating performance of infrastructure
CN106780160A (en) * 2016-12-13 2017-05-31 广东环境保护工程职业学院 A kind of Green Construction Assessment method
CN106933175A (en) * 2017-03-21 2017-07-07 中建三局第建设工程有限责任公司 Green construction management system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
熊艳等: "高等级公路绿色施工评价模型研究", 《交通科技》 *
薛松等: "基于模糊物元的绿色施工评价体系研究", 《建筑技术》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116451829A (en) * 2023-02-23 2023-07-18 葛洲坝集团交通投资有限公司 Expressway construction emission reduction optimization method and system based on principal component analysis

Similar Documents

Publication Publication Date Title
WO2021184550A1 (en) Target soil property content prediction method based on soil transfer function
CN109636150A (en) A kind of method for building up and its system of smart city " more rule unifications " appraisement system
CN110413666A (en) A kind of multi-source heterogeneous data integration method of farmland quality
CN104537597A (en) A technical method of diagnosing rationality of city spatial patterns
Song et al. Ecological-hydrological processes in arid environment: Past, present and future
CN113822770A (en) Farmland construction area intelligent demarcation method and system
CN103455856B (en) A kind of technical method of city space identification of function
CN111199298A (en) Flood forecasting method and system based on neural network
Liu RETRACTED ARTICLE: Agricultural water management based on the Internet of Things and data analysis
Zhou Safety management of karst construction in railway tunnels and tunnel farming as compared to traditional farming
CN109409718A (en) A kind of highway green construction fuzzy matter element evaluation model and construction method
Long et al. On the effective organization of rural settlements spatial structure under the transformation and development of mountainous areas in Western China: evaluation measurement based on complex adaptability theory
CN113627819A (en) Intelligent platform for evaluating green construction of deep foundation pit based on CIM technology
Wen et al. Estimating seasonal aboveground biomass of a riparian pioneer plant community: An exploratory analysis by canopy structural data
Zhao et al. Key Technologies of forest resource examination system development in China
Zhang Application of Internet of Things technology in agricultural production
CN111537510A (en) Farmland protection forest wind-prevention effect metering method based on spatial information technology
Hu et al. [Retracted] Optimization and Simulation of Farmland Protection Dynamic Monitoring System Based on Internet of Things Technology
CN109934397A (en) A kind of Forecasting Methods for Agriculture and system
CN113435667B (en) Comprehensive evaluation method and system for water resource utilization in paddy field irrigation and drainage mode
CN113793006A (en) Agricultural water-saving potential analysis method and system based on scale effect
Luo et al. Two-stage grey cloud clustering model under the panel data and its application
Wu et al. Research on fine management of construction project based on BIM5D technology
Chen et al. Research on Location of Supply Chain Center of Natural Resources based on K-means Clustering Model
CN109034530A (en) A kind of piping lane planing method based on neural network algorithm

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190301