CN109403337A - Basalt fiber reinforced TRD (Top-grade direct-fired) underground continuous wall and construction method thereof - Google Patents

Basalt fiber reinforced TRD (Top-grade direct-fired) underground continuous wall and construction method thereof Download PDF

Info

Publication number
CN109403337A
CN109403337A CN201811190333.XA CN201811190333A CN109403337A CN 109403337 A CN109403337 A CN 109403337A CN 201811190333 A CN201811190333 A CN 201811190333A CN 109403337 A CN109403337 A CN 109403337A
Authority
CN
China
Prior art keywords
cement
trd
basalt fibre
mixed
basalt fiber
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811190333.XA
Other languages
Chinese (zh)
Inventor
吉宏
张龙
张鹏
刘东华
何鹏
纪源
陈荣刚
董志高
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Power Transmission And Distribution Co ltd
Nanjing Tech University
Original Assignee
Jiangsu Power Transmission And Distribution Co ltd
Nanjing Tech University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jiangsu Power Transmission And Distribution Co ltd, Nanjing Tech University filed Critical Jiangsu Power Transmission And Distribution Co ltd
Priority to CN201811190333.XA priority Critical patent/CN109403337A/en
Publication of CN109403337A publication Critical patent/CN109403337A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/02Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
    • C04B28/04Portland cements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F5/00Dredgers or soil-shifting machines for special purposes
    • E02F5/02Dredgers or soil-shifting machines for special purposes for digging trenches or ditches
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Paleontology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Inorganic Chemistry (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Mechanical Engineering (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The invention discloses a basalt fiber reinforced TRD (blast furnace top dead wall) construction method underground continuous wall and a construction method thereof, wherein the basalt fiber reinforced TRD construction method underground continuous wall comprises cement-soil stirring mixed slurry, and the cement-soil stirring mixed slurry comprises the following components in parts by mass: 25% of P.O42.5-grade ordinary portland cement, wherein the water cement ratio is 1.2-1.5; the mixing amount of the sodium bentonite is 100kg/m3The water-cement ratio is 3.3-20; basalt fiber, the mixing amount is 0.4%; the construction method of the basalt fiber reinforced and stirred TRD continuous wall comprises the following steps: mixing basalt fibers and sodium bentonite according to a ratio of 20: 1, carrying out dry mixing; after being uniformly mixed, adding the basalt fiber cement slurry into a cement slurry machine for mixing and stirring to form basalt fiber cement mixed slurry; and finally, pouring the mixed slurry into a pumping aggregate bin, and then performing stirring pile construction according to a normal TRD construction process. After the reinforcement, the tensile strength and the shear strength of the underground continuous wall material are greatly improved, and the hydraulic fracture resistance of the novel underground continuous wall under a high water head is effectively improved.

Description

A kind of basalt fibre reinforcement TRD engineering method diaphram wall and its construction method
Technical field
The invention belongs to geotechnical engineering pattern foundation pit supporting structure fields, and in particular to a kind of basalt fibre reinforcement TRD engineering method underground Diaphragm wall and its construction method.
Background technique
Traditional diaphram wall is constructed using framing, is the weak link of sealing at Construction Joint, working procedure mostly with week Phase is long, if cannot be combined into one with underground structure side wall, cost is excessively high, this also constrains what it was applied in general base pit engineering Restriction condition.TRD engineering method changes conventional soil cement stirring wall as equal thickness cement mixing wall Choice of Construction Technique of Water Stop Curtain Single solum horizontal stirring mode, but the vertical stirring mode of different soil is realized by cutting box, have construction depth is big (can Up to 60m), adapt to stratum is wide, mixing effect is good, seamless connection high at wall precision, suitable for height-limited operating environment.
Require impervious barrier should qualified barrier properties in the curtain leakage preventing structure of hypertonic pressure and high-moisture silt soil strata Can, while structure being required to have certain non-deformability, guarantee that hydraulic fracture effect does not occur inside impervious barrier.It is expected that by Soil cement mixes reinforcement material to improve the intensity of soil cement, and raising prevents hydraulic fracture and non-deformability.It is stirred in reinforcement At in wall construction technology, routinely under the conditions of that basalt fibre and cement slurry are directly stirred mixed effect is unsatisfactory, Basalt fibre reunion is distributed in the form of sheets, is easily precipitated, and fibre bundle is unsuitable fully dispersed, the basalt fibre that is formed in this way and The mixed serum of cement slurry is pumped directly to deep mixer and carries out bore forming, and the sheet basalt fibre of precipitating easily concentrates on Partial-depth position in wall, cut agitator tank stirring action can not make basalt fibre it is fully dispersed uniformly in wall not With depth position;And last precipitating and the basalt fibre concentrated easily block and pump out slurry mouth, cause construction operation without Method is normally carried out.All preparation methods and rational proportion for only changing basalt fiber cement soil mixed serum, could ensure Nodule or precipitating do not occur in mixed serum for basalt fibre, to just can guarantee that basalt fibre is equably stirred to ground In lower diaphragm wall body, basalt fibre tensile characteristics can be just given full play to, improve the anti-hydraulic fracture and resistance of diaphram wall Shape ability.
Summary of the invention
The present invention provides a kind of basalt fibre reinforcement TRD engineering method diaphram wall and its construction methods, solve ground Lower diaphragm wall non-deformability is weak, Yi Fasheng hydraulic fracture and Wu Yan fiber cannot be uniformly dispersed in the different depth portion of wall The problem of position.
In order to solve the above-mentioned technical problem, the technical scheme adopted by the invention is that: a kind of basalt fibre reinforcement TRD work Method diaphram wall, which is characterized in that including Soil-cement mixed serum, the Soil-cement mixed serum is according to quality The component of part meter includes: P.O42.5 grades of ordinary portland cements, volume 25%, the ratio of mud 1.2~1.5;Sodium bentonite is mixed Measure 100kg/m3, the ratio of mud 3.3~20;Basalt fibre, volume 0.4%.
Further, the basalt fibre is the pencil monofilament that fibre length is 6mm~24mm.
Further, it is 12mm that the basalt fibre, which selects fibre length,.
A kind of construction method of basalt fibre reinforcement TRD engineering method diaphram wall, which is characterized in that including following step It is rapid:
S1, basalt fibre is mixed according to 20:1 mass parts than carrying out dry mixing with sodium bentonite;
S2, it is to be mixed uniformly after, cement slurry is added and carries out mixing mix, forms the finely dispersed basalt fibre of fiber and cement Mixed serum is starched, mixed serum is poured into pumping aggregate bin;
S3, according to the design drawing of TRD diaphram wall, surveying setting-out;
After S4, cell wall reinforce center line setting-out, Reinforcement Measures are carried out to place, so that place is met mechanical equipment and ground is held Carry the requirement of power, it is ensured that the stability of stake machine;
S5, hang that stake machine is carried out after provided box is in place;
S6, cutting box is hung paragraph by paragraph into pre-buried cave with crane, is fixed using supporting table;It sets at TRD host mobility to pre-buried acupuncture point Cutting box is connected, host returns again to predetermined construction location progress cutting box and voluntarily squeezes into excavation to projected depth;
S7, it excavates in advance: mixed serum being injected as liquid, cutting box is excavated by mudjack and is pushed ahead, excavate and loosen original soil Layer, cutting grooving a trip;Withdraw excavation: according to operation work efficiency, after the completion of the grooving of a trip, cutting box withdraw again to Cut starting point;Stir at wall: cutting box exchanges slurries after withdrawing to cutting starting point, and it is solid to inject mixed serum by mudjack Change, cutting box is pushed ahead and is mixed with liquid mixing mud is excavated, and uniform thickness Soil-cement Wall is formed.
Further, it in the step S1 and S2, is mixed by rotary mixer.
Further, in the step S4, Reinforcement Measures include carrying out laying steel plate to construction site.
Further, in the step S2, the ratio of mud of cement slurry is 0.5.
Advantageous effects of the invention: the present invention passes through the rational proportion of Soil-cement mixed serum, water is realized Soil is mixed with the reinforcement of basalt fibre, its tension of the soil cement after reinforcement is remarkably reinforced with shearing strength, so that profound The fiber and steel bar reinforced TRD engineering method diaphram wall of Wu Yan resists waterpower under high water head relative to traditional TRD cement-earth underground continuous wall It cleaves and is greatly improved with the ability of resistance to deformation;By improve mixed serum preparation method, make military rock fiber can be uniformly dispersed in The different depth position of wall.
Specific embodiment
The invention will be further described below.Following embodiment is only used for clearly illustrating technical side of the invention Case, and not intended to limit the protection scope of the present invention.
1, the construction method of basalt fibre reinforcement TRD engineering method diaphram wall, comprising the following steps:
Step 1: it is mixed to be carried out dry mixing using rotary mixer according to 20:1 mass parts ratio for basalt fibre and sodium bentonite It closes;
Step 2: the cement slurry that the ratio of mud 0.5 is added carries out mixing mix using rotary mixer after mix is uniform, formed The finely dispersed basalt fibre of fiber and cement mixing slurries pour into mixed serum in pumping aggregate bin;
Step 3: according to the design drawing of TRD diaphram wall, surveying setting-out;
Step 4: carrying out being laid with the Reinforcement Measures such as steel plate to construction site, it is ensured that construction after cell wall reinforces center line setting-out Place meets requirement of the mechanical equipment to foundation bearing capacity, it is ensured that the stability of stake machine;
Step 5: hanging provided box;
Step 6: stake machine is in place;
Step 7: being hung cutting box into pre-buried cave paragraph by paragraph with crane, fixed using supporting table;TRD host mobility is to pre-buried cave Position connects cutting box, and host returns again to predetermined construction location progress cutting box and voluntarily squeezes into excavation to projected depth;
Step 8: excavating in advance: injecting mixed serum as liquid, cutting box is excavated by mudjack and push ahead, excavate and loosen Native soil layer, cutting grooving a trip.Withdraw excavation: according to operation work efficiency, after the completion of the grooving of a trip, cutting box returns again Withdraw cutting starting point to.Stir at wall: cutting box exchanges slurries after withdrawing to cutting starting point, injects mixing slurry by mudjack Liquid solidification, cutting box are pushed ahead and are mixed with liquid mixing mud is excavated, and uniform thickness Soil-cement Wall is formed.
The above is only a preferred embodiment of the present invention, it is noted that for the ordinary skill people of the art For member, without departing from the technical principles of the invention, several improvement and deformations can also be made, these improvement and deformations Also it should be regarded as protection scope of the present invention.

Claims (7)

1. a kind of basalt fibre reinforcement TRD engineering method diaphram wall, which is characterized in that including Soil-cement mixed serum, The Soil-cement mixed serum includes: P.O42.5 grades of ordinary portland cements, volume according to the component of mass parts meter 25%, the ratio of mud 1.2~1.5;Sodium bentonite, volume 100kg/m3, the ratio of mud 3.3~20;Basalt fibre, volume 0.4%。
2. a kind of basalt fibre reinforcement TRD engineering method diaphram wall according to claim 1, which is characterized in that described Basalt fibre is the pencil monofilament that fibre length is 6mm~24mm.
3. a kind of basalt fibre reinforcement TRD engineering method diaphram wall according to claim 2, which is characterized in that described It is 12mm that basalt fibre, which selects fibre length,.
4. a kind of construction party of basalt fibre reinforcement TRD engineering method diaphram wall according to any one of claims 1 to 3 Method, which comprises the following steps:
S1, basalt fibre is mixed according to 20:1 mass parts than carrying out dry mixing with sodium bentonite;
S2, it is to be mixed uniformly after, cement slurry is added and carries out mixing mix, forms the finely dispersed basalt fibre of fiber and cement Mixed serum is starched, mixed serum is poured into pumping aggregate bin;
S3, according to the design drawing of TRD diaphram wall, surveying setting-out;
After S4, cell wall reinforce center line setting-out, Reinforcement Measures are carried out to place, so that place is met mechanical equipment and ground is held Carry the requirement of power, it is ensured that the stability of stake machine;
S5, hang that stake machine is carried out after provided box is in place;
S6, cutting box is hung paragraph by paragraph into pre-buried cave with crane, is fixed using supporting table;It sets at TRD host mobility to pre-buried acupuncture point Cutting box is connected, host returns again to predetermined construction location progress cutting box and voluntarily squeezes into excavation to projected depth;
S7, it excavates in advance: mixed serum being injected as liquid, cutting box is excavated by mudjack and is pushed ahead, excavate and loosen original soil Layer, cutting grooving a trip;Withdraw excavation: according to operation work efficiency, after the completion of the grooving of a trip, cutting box withdraw again to Cut starting point;Stir at wall: cutting box exchanges slurries after withdrawing to cutting starting point, and it is solid to inject mixed serum by mudjack Change, cutting box is pushed ahead and is mixed with liquid mixing mud is excavated, and uniform thickness Soil-cement Wall is formed.
5. a kind of construction method of basalt fibre reinforcement TRD engineering method diaphram wall according to claim 4, feature It is, in the step S1 and S2, is mixed by rotary mixer.
6. a kind of construction method of basalt fibre reinforcement TRD engineering method diaphram wall according to claim 4, feature It is, in the step S4, Reinforcement Measures include carrying out laying steel plate to construction site.
7. a kind of construction method of basalt fibre reinforcement TRD engineering method diaphram wall according to claim 4, feature It is, in the step S2, the ratio of mud of cement slurry is 0.5.
CN201811190333.XA 2018-10-12 2018-10-12 Basalt fiber reinforced TRD (Top-grade direct-fired) underground continuous wall and construction method thereof Pending CN109403337A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811190333.XA CN109403337A (en) 2018-10-12 2018-10-12 Basalt fiber reinforced TRD (Top-grade direct-fired) underground continuous wall and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811190333.XA CN109403337A (en) 2018-10-12 2018-10-12 Basalt fiber reinforced TRD (Top-grade direct-fired) underground continuous wall and construction method thereof

Publications (1)

Publication Number Publication Date
CN109403337A true CN109403337A (en) 2019-03-01

Family

ID=65467784

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811190333.XA Pending CN109403337A (en) 2018-10-12 2018-10-12 Basalt fiber reinforced TRD (Top-grade direct-fired) underground continuous wall and construction method thereof

Country Status (1)

Country Link
CN (1) CN109403337A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424409A (en) * 2019-08-16 2019-11-08 上海建工集团股份有限公司 A kind of foundation pit enclosure method being adapted to high water level low clearance
CN111021338A (en) * 2019-12-30 2020-04-17 深圳市市政设计研究院有限公司 Occlusive pile and construction method thereof
CN111042249A (en) * 2019-12-27 2020-04-21 上海建工四建集团有限公司 Construction method of ultra-deep equal-thickness cement-soil mixing wall under complex geological condition
CN112299796A (en) * 2020-12-01 2021-02-02 宁波中淳高科股份有限公司 Wall pile inter-pile grouting material for building envelope and construction method thereof
CN112707692A (en) * 2021-01-06 2021-04-27 上海智平基础工程有限公司 Cutting fluid for TRD construction, preparation method and construction method
CN115286311A (en) * 2022-06-30 2022-11-04 西南大学 Seepage-proof anti-cracking cement mortar material and preparation method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203891540U (en) * 2014-05-29 2014-10-22 安徽筑新纤维复合材料科技有限公司 Basalt fiber wire pole
CN105386458A (en) * 2015-11-26 2016-03-09 中铁十一局集团第四工程有限公司 Method for constructing slot wall of underground diaphragm wall reinforced through embedded type plastic mixing piles
CN105970946A (en) * 2016-07-06 2016-09-28 南京工业大学 Basalt fiber reinforced cement soil mixing pile and construction method thereof
CN106866056A (en) * 2017-04-05 2017-06-20 中铁八局集团第四工程有限公司 A kind of mud for construction of diaphragm wall and preparation method thereof
RU2631272C1 (en) * 2016-09-19 2017-09-20 Олег Савельевич Кочетов Vibration-insulated foundation
CN108589699A (en) * 2018-04-20 2018-09-28 浙江大学城市学院 A kind of interpolation H profile steel TRD walls and its construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203891540U (en) * 2014-05-29 2014-10-22 安徽筑新纤维复合材料科技有限公司 Basalt fiber wire pole
CN105386458A (en) * 2015-11-26 2016-03-09 中铁十一局集团第四工程有限公司 Method for constructing slot wall of underground diaphragm wall reinforced through embedded type plastic mixing piles
CN105970946A (en) * 2016-07-06 2016-09-28 南京工业大学 Basalt fiber reinforced cement soil mixing pile and construction method thereof
RU2631272C1 (en) * 2016-09-19 2017-09-20 Олег Савельевич Кочетов Vibration-insulated foundation
CN106866056A (en) * 2017-04-05 2017-06-20 中铁八局集团第四工程有限公司 A kind of mud for construction of diaphragm wall and preparation method thereof
CN108589699A (en) * 2018-04-20 2018-09-28 浙江大学城市学院 A kind of interpolation H profile steel TRD walls and its construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
余平等: "TRD工法在深基坑工程中止水中的应用", 《地质装备》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110424409A (en) * 2019-08-16 2019-11-08 上海建工集团股份有限公司 A kind of foundation pit enclosure method being adapted to high water level low clearance
CN111042249A (en) * 2019-12-27 2020-04-21 上海建工四建集团有限公司 Construction method of ultra-deep equal-thickness cement-soil mixing wall under complex geological condition
CN111021338A (en) * 2019-12-30 2020-04-17 深圳市市政设计研究院有限公司 Occlusive pile and construction method thereof
CN112299796A (en) * 2020-12-01 2021-02-02 宁波中淳高科股份有限公司 Wall pile inter-pile grouting material for building envelope and construction method thereof
CN112707692A (en) * 2021-01-06 2021-04-27 上海智平基础工程有限公司 Cutting fluid for TRD construction, preparation method and construction method
CN115286311A (en) * 2022-06-30 2022-11-04 西南大学 Seepage-proof anti-cracking cement mortar material and preparation method thereof

Similar Documents

Publication Publication Date Title
CN109403337A (en) Basalt fiber reinforced TRD (Top-grade direct-fired) underground continuous wall and construction method thereof
CN106759473B (en) The constructing structure and its construction method of underground pipe gallery and road
CN204491626U (en) The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine
CN112323823B (en) Filling device and method for waste air-raid shelter of pile foundation construction site
CN105155541B (en) A kind of dual slurry closure construction method of catch pit
CN109098175A (en) A kind of tri-axes deep mixing pile construction method
CN206070508U (en) Device for reinforcing foundation
CN108571000A (en) The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river
CN105970946A (en) Basalt fiber reinforced cement soil mixing pile and construction method thereof
CN111636455A (en) Comprehensive construction method of TRD (Top gas recovery device) and rotary drilling lead hole depth waterproof curtain
CN110306531A (en) High water level erratic boulder stratum construction of diaphragm wall technique
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration
CN108842764A (en) A kind of Stirring formula anchor tube construction method
CN105386458A (en) Method for constructing slot wall of underground diaphragm wall reinforced through embedded type plastic mixing piles
CN111676987A (en) Construction method for backfilling construction of construction fertilizer tank by vibrating, slurry-flushing and ramming method
CN113605381A (en) Polypropylene fiber reinforced cement soil mixing pile and construction process thereof
CN201321614Y (en) Retaining structure of precast reinforced concrete beam cement-soil piling wall
CN110468828A (en) A kind of construction method of pattern foundation pit supporting structure water-stop continuous wall
CN206971247U (en) Concrete toe board foundation reinforcing structure arranged on unloading rock mass
CN1180118A (en) Construction method for building foundation pit stope support
CN111455976A (en) Construction method of self-setting mortar impervious wall by grooving method
CN110344394A (en) A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method
CN109881696A (en) A kind of HPPG back cover construction method
CN102605775B (en) Combination pile of flexible pile and rigid pile concentrically arranged at upper end and lower end and pile forming method
CN108612082A (en) One type shaped form TRD walls and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190301

RJ01 Rejection of invention patent application after publication