CN109322309A - The construction method that greater coasting area offshore concrete pours - Google Patents
The construction method that greater coasting area offshore concrete pours Download PDFInfo
- Publication number
- CN109322309A CN109322309A CN201811235337.5A CN201811235337A CN109322309A CN 109322309 A CN109322309 A CN 109322309A CN 201811235337 A CN201811235337 A CN 201811235337A CN 109322309 A CN109322309 A CN 109322309A
- Authority
- CN
- China
- Prior art keywords
- concrete
- ship
- feed bin
- pours
- crane
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
Abstract
The present invention relates to a kind of construction method that greater coasting area offshore concrete pours, construction site configures two ships, and one is crane ship, and one is cargo ship;It transports setting feed bin on the deck of boat and carries out transport concrete;Concrete is transported to harbour and is delivered in feed bin by concrete placement vehicle;Feed bin is filled on cargo ship from wharf crane by truck crane.Ship is rested in crane ship side to construction area by cargo ship transport concrete;Crane ship is lifted feed bin to template by cargo ship, after feed bin is stablized, is opened feed bin valve, is leaned on concrete gravity, concrete is fallen in template.The present invention can solve the problem of similar items offshore concretes such as greater coasting area anti-collision alarm pier pour;It guaranteeing concrete pouring quality and under the premise of controllable construction safety risk, generally uses that mixer ship pours or marine plate oceangoing ship ship voluntarily stirs and pours two ways and substantially reduces construction cost compared to marine concrete, and avoids ship machinery work holdup phenomenon;It can be applied in the similar engineerings such as anti-collision alarm pier.
Description
Technical field
The present invention relates to a kind of construction method of concreting, especially a kind of concreting at greater coasting area sea
Construction method.
Background technique
The effect of anti-collision alarm pier is warning shippping traffic, guarantees the structures safety within the scope of caution mound;Project is located at sea
In domain, there is a certain distance apart from land-based area, general offshore concrete is poured using mixer ship or marine plate oceangoing ship ship voluntarily stirs
And pour two ways;But since caution mound amount of concrete is typically small, and placement layer by layer is needed, poured often;Using stirring
Ship, which pours, or plate oceangoing ship ship is voluntarily stirred and poured causes construction cost high, and construction period due to concreting often,
It is not continuous placing, mixer ship or plate oceangoing ship ship work holdup phenomenon are serious, and ship machinery utilization rate is low.Therefore feed bin+cargo ship+
Crane ship sea concrete construction method can under the premise of guaranteeing concrete pouring quality and controllable construction safety risk
Construction cost is substantially reduced, and avoids ship machinery work holdup phenomenon.
Summary of the invention
The present invention is to provide for a kind of construction method that greater coasting area offshore concrete pours, and this method can solve neritic zone
Domain sea pours that a small amount of concrete construction is at high cost, the problem of ship machinery utilization rate low efficiency.
To solve the above problems, the technical scheme is that a kind of construction party that greater coasting area offshore concrete pours
Method, construction site configure two ships, and one is crane ship, and another is cargo ship;Setting feed bin is transported on the transport deck of boat
Defeated concrete, the steps include:
1) concrete mix slump-loss and setting time test data sheet and single cargo ship transport concrete are combined
The time that need to be consumed with crane ship casting concrete determines the amount of single cargo ship transport concrete;
2) concrete is transported to harbour and is delivered in feed bin by concrete placement vehicle;Feed bin is filled to fortune from wharf crane by truck crane
On defeated ship;
3) cargo ship is by feed bin inner concrete to construction area, and ship is rested in crane ship side, crane ship by feed bin by
Cargo ship is lifted to template, after feed bin is stablized, is opened feed bin valve, is leaned on concrete gravity, concrete is fallen in template;
4) cargo ship band sky feed bin is rapidly returned to harbour, and feed bin is hung to harbour by truck crane, repeats above step construction.
Further, the slump test data provided according to laboratory consider the selection of time transport of single fortune concrete
Feed bin volume on the deck of boat.
Further, the amount of the determining single cargo ship transport concrete is 7m3。
Further, the construction method that the greater coasting area offshore concrete pours is suitable for greater coasting area anti-collision alarm pier class
Like engineering, single casting concrete amount is few, pours operating condition often.
The beneficial effects of the present invention are:
The more conventional offshore concrete of construction method of the invention is poured using mixer ship or plate oceangoing ship ship is voluntarily stirred and poured
The construction method built:
1) guarantee that construction cost can be substantially reduced under the premise of concrete pouring quality and construction safety risk are controllable;
2) ship machinery work holdup phenomenon is avoided.
The present invention can solve the similar items offshore concretes such as greater coasting area anti-collision alarm pier (single casting concrete amount
It is few, and pour often) the problem of pouring;This construction method is guaranteeing that concrete pouring quality and construction safety risk are controllable
Under the premise of, generally use that mixer ship pours or marine plate oceangoing ship ship voluntarily stirs and pours two ways and drops significantly compared to marine concrete
Low construction cost, and avoid ship machinery work holdup phenomenon;It can be applied in the similar engineerings such as anti-collision alarm pier.
Detailed description of the invention
Fig. 1 is the construction method construction process figure of greater coasting area concreting of the invention.
Specific embodiment
The present invention is further illustrated with embodiment with reference to the accompanying drawing.
As shown in Figure 1, a kind of construction method of greater coasting area concreting, is suitable for greater coasting area anti-collision alarm pier class
Like engineering, single casting concrete amount is few, but pours operating condition often;Construction site configures two ships, and one is lifting
Ship, another is cargo ship;It transports setting feed bin on the deck of boat and carries out transport concrete, and tried according to the slump that laboratory provides
Data are tested, the feed bin volume on the selection of time transport deck of boat of single fortune concrete is considered, the steps include:
1) concrete mix slump-loss and setting time test data sheet and single cargo ship transport concrete are combined
The time that need to be consumed with crane ship casting concrete determines the amount 7m of single cargo ship transport concrete3(two 3.5m3Feed bin);
2) concrete is transported to harbour and is delivered in feed bin by concrete placement vehicle;Feed bin is hung on cargo ship by truck crane;
3) cargo ship is by feed bin inner concrete to construction area, and ship is rested in crane ship side, crane ship by feed bin by
Cargo ship is lifted to template, after feed bin is stablized, is opened feed bin valve, is leaned on concrete gravity, concrete is fallen in template;
4) cargo ship band sky feed bin is rapidly returned to harbour, and feed bin is hung to harbour by truck crane, repeats above step construction.
Application implementation example of the present invention
Engineering is nuclear power projects intake region anti-collision alarm pier, this engineering is on the outside of one phase of recirculated water~tri- phase intakes
Region creates 6 anti-collision alarm piers, and pier body divides two layers, upper layer pier body diameter 2m, high 3m, the high 8m of top mark, lower layer pier body diameter 7m,
High 2.5m, the high 5m of top mark, lower layer's pier body, which divides two layers, to be poured.Consider that stake top fills out core, this project cubic amount of concrete waterborne is a total of about
680m3, nearly 700m3.By using the present invention, this engineering adds up casting concrete 21 times, and during which safe condition is controllable, concrete
Pouring quality meets specification, design requirement;Calculated by project cost, using the present invention, is applied compared to mixer ship casting concrete
Work method reduces construction cost about 1,700,000;Compared to the construction method that plate oceangoing ship ship is voluntarily stirred and poured, construction cost is reduced
About 900,000;And when non-casting concrete, transport of the cargo ship for materials such as template, reinforcing bars, crane ship cooperation reinforcing bar,
The offshore lifting of template avoids the construction machineries work holdup phenomenon such as ship.
Claims (4)
1. a kind of construction method that greater coasting area offshore concrete pours, construction site configures two ships, and one is crane ship,
Another is cargo ship;It transports setting feed bin on the deck of boat and carries out transport concrete, which is characterized in that the steps include:
1) concrete mix slump-loss and setting time test data sheet and single cargo ship transport concrete are combined and is risen
The time that weight ship casting concrete need to consume, determine the amount of single cargo ship transport concrete;
2) concrete is transported to harbour and is delivered in feed bin by concrete placement vehicle;Feed bin is filled to cargo ship from wharf crane by truck crane
On;
3) ship is rested in crane ship side, crane ship is by feed bin by transporting by feed bin inner concrete to construction area by cargo ship
Ship is lifted to template, after feed bin is stablized, is opened feed bin valve, is leaned on concrete gravity, concrete is fallen in template;
4) cargo ship band sky feed bin is rapidly returned to harbour, and feed bin is hung to harbour by truck crane, repeats above step construction.
2. the construction method that greater coasting area offshore concrete according to claim 1 pours, it is characterised in that: according to experiment
The slump test data that room provides consider the feed bin volume on the selection of time transport deck of boat of single fortune concrete.
3. the construction method that greater coasting area offshore concrete according to claim 1 pours, it is characterised in that: the determination
The amount of single cargo ship transport concrete is 7m3。
4. the construction method that greater coasting area offshore concrete according to claim 1 to 3 pours, it is characterised in that: institute
It states the construction method that greater coasting area offshore concrete pours and is suitable for greater coasting area anti-collision alarm pier similar engineering, single pours mixed
Solidifying soil amount is few, pours operating condition often.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811235337.5A CN109322309A (en) | 2018-10-23 | 2018-10-23 | The construction method that greater coasting area offshore concrete pours |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811235337.5A CN109322309A (en) | 2018-10-23 | 2018-10-23 | The construction method that greater coasting area offshore concrete pours |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109322309A true CN109322309A (en) | 2019-02-12 |
Family
ID=65262780
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811235337.5A Pending CN109322309A (en) | 2018-10-23 | 2018-10-23 | The construction method that greater coasting area offshore concrete pours |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109322309A (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109914416A (en) * | 2019-04-04 | 2019-06-21 | 三门核电有限公司 | A kind of concreting technique of suitable marine construction of structures construction |
CN112265105A (en) * | 2020-10-15 | 2021-01-26 | 长江三峡集团福建能源投资有限公司 | Concrete pouring process suitable for offshore building construction |
CN112343057A (en) * | 2020-10-16 | 2021-02-09 | 长江三峡集团福建能源投资有限公司 | Construction method for offshore concrete pouring in offshore area |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101890756A (en) * | 2009-11-19 | 2010-11-24 | 宁波一中管桩有限公司 | Novel highly-efficiency, energy-saving and environmentally-friendly method and system for manufacturing centrifugal concrete pile |
CN204452842U (en) * | 2015-01-23 | 2015-07-08 | 中交第二航务工程局有限公司 | Ship is built in a kind of new concrete transport |
CN104481147B (en) * | 2014-10-30 | 2016-06-22 | 中交四航局第三工程有限公司 | A kind of offshore reinforced concrete frame structure rapid constructing method |
CN107882055A (en) * | 2017-11-13 | 2018-04-06 | 中交第三航务工程局有限公司宁波分公司 | A kind of construction method of blower fan cushion cap |
-
2018
- 2018-10-23 CN CN201811235337.5A patent/CN109322309A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101890756A (en) * | 2009-11-19 | 2010-11-24 | 宁波一中管桩有限公司 | Novel highly-efficiency, energy-saving and environmentally-friendly method and system for manufacturing centrifugal concrete pile |
CN104481147B (en) * | 2014-10-30 | 2016-06-22 | 中交四航局第三工程有限公司 | A kind of offshore reinforced concrete frame structure rapid constructing method |
CN204452842U (en) * | 2015-01-23 | 2015-07-08 | 中交第二航务工程局有限公司 | Ship is built in a kind of new concrete transport |
CN107882055A (en) * | 2017-11-13 | 2018-04-06 | 中交第三航务工程局有限公司宁波分公司 | A kind of construction method of blower fan cushion cap |
Non-Patent Citations (1)
Title |
---|
邓浪: "水上大直径桩施工关键技术", 《价值工程》 * |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109914416A (en) * | 2019-04-04 | 2019-06-21 | 三门核电有限公司 | A kind of concreting technique of suitable marine construction of structures construction |
CN112265105A (en) * | 2020-10-15 | 2021-01-26 | 长江三峡集团福建能源投资有限公司 | Concrete pouring process suitable for offshore building construction |
CN112343057A (en) * | 2020-10-16 | 2021-02-09 | 长江三峡集团福建能源投资有限公司 | Construction method for offshore concrete pouring in offshore area |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109322309A (en) | The construction method that greater coasting area offshore concrete pours | |
CN104260209B (en) | Waterborne mobile concrete stirring boat in inland waterway | |
CN100419164C (en) | Method for moving large-scale heavy member to launch and float on water, and member mounting method | |
CN106545031B (en) | Self-propulsion type semi-submerged ship long-distance transportation Immersed tunnel technique | |
CN109914416A (en) | A kind of concreting technique of suitable marine construction of structures construction | |
CN103233452B (en) | The pre-splicing 1/4 cylinder transportation resources of a kind of lattice steel sheet pile large cylinder nominative sheet pile | |
CN203345167U (en) | Movable jack-up artificial island | |
CN206635654U (en) | A kind of barging device of underwater narrow-bore tunnel super long type prefabricated case beam | |
CN103195039A (en) | Artificial island construction method for self-elevating straight-through deck platform | |
CN104493972B (en) | Preparation method for the floating concrete component of floating island construction | |
CN107709669A (en) | Scour protection structure and method that the safeguard structure is provided along the sub-bottom of dock wall | |
CN108341629A (en) | As bottom reinforcing regardless of aproll soil and its construction method | |
CN204322301U (en) | A kind of cruiseway Waterborne movable concrete mixer vessel | |
JP3276617B2 (en) | Marine landfill method using sea sand | |
JP3308958B2 (en) | Construction method and form carrier for landfill structures | |
CN201376655Y (en) | Concrete tank ship | |
JP4677622B2 (en) | Conveying method of mortar and concrete to the construction site of dam body | |
CN115897640B (en) | Construction method of permeable breakwater | |
CN2692022Y (en) | Concrete stirring ship | |
JPS60156826A (en) | Protection work of slope surface and net-bag used therefor | |
JP3231456B2 (en) | Mixing and casting equipment for soil and solidified material | |
JP2895595B2 (en) | Landfill work boat | |
JP3884247B2 (en) | Naval ship | |
JPH05148836A (en) | Manufacturing, carrying and placing system for marine concrete | |
BE1023964B1 (en) | MARINE METHOD AND APPARATUS FOR (RE) STABILIZING CAISSONS |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190212 |
|
RJ01 | Rejection of invention patent application after publication |