CN109270360A - A kind of method of the online line loss of high precision computation - Google Patents

A kind of method of the online line loss of high precision computation Download PDF

Info

Publication number
CN109270360A
CN109270360A CN201811398193.5A CN201811398193A CN109270360A CN 109270360 A CN109270360 A CN 109270360A CN 201811398193 A CN201811398193 A CN 201811398193A CN 109270360 A CN109270360 A CN 109270360A
Authority
CN
China
Prior art keywords
electric energy
time
energy meter
line loss
electric
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811398193.5A
Other languages
Chinese (zh)
Other versions
CN109270360B (en
Inventor
张杭
毛庆
韩玉霞
童辉
李�荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANJING INTELLIGENT APPARATUS CO Ltd
Original Assignee
NANJING INTELLIGENT APPARATUS CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NANJING INTELLIGENT APPARATUS CO Ltd filed Critical NANJING INTELLIGENT APPARATUS CO Ltd
Priority to CN201811398193.5A priority Critical patent/CN109270360B/en
Publication of CN109270360A publication Critical patent/CN109270360A/en
Application granted granted Critical
Publication of CN109270360B publication Critical patent/CN109270360B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R27/00Arrangements for measuring resistance, reactance, impedance, or electric characteristics derived therefrom
    • G01R27/02Measuring real or complex resistance, reactance, impedance, or other two-pole characteristics derived therefrom, e.g. time constant
    • G01R27/26Measuring inductance or capacitance; Measuring quality factor, e.g. by using the resonance method; Measuring loss factor; Measuring dielectric constants ; Measuring impedance or related variables
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01RMEASURING ELECTRIC VARIABLES; MEASURING MAGNETIC VARIABLES
    • G01R19/00Arrangements for measuring currents or voltages or for indicating presence or sign thereof

Landscapes

  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Remote Monitoring And Control Of Power-Distribution Networks (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a kind of methods of the online line loss of high precision computation, this method is based on power, voltage, electric current and a period of time electric degree cumulative amount at synchronization (being accurate within 5ms) measurement route both ends, provides accurately data for line loss analyzing.More electric energy meters in wide scope are configured by hardware and software, other external sync clocks can be received by numeral input mouth, when monitoring a pulse (transformation of the numeral input from OFF to ON), it just starts freezing procedures: freezing to calculate cycle data, current accurate power is calculated, and starts and calculates a period of time electricity.Triggering is also possible to communicate correcting delay signal triggering when this synchronization can be the school GPS.By freezing calculating and the integration of communication network back-end data inside electric energy meter, realize that accurately line loss calculates and load balance calculates.

Description

A kind of method of the online line loss of high precision computation
Technical field
The invention belongs to electric system to monitor field, the in particular to method of a kind of online line loss of high precision computation on-line.
Background technique
In the circuit on power system operational process of factory, line loss problem largely reflects the event of power circuit operation Barrier rate, therefore, the research of line loss calculation and decreasing loss method is the content of electric system primary study, and line loss research is one multiple Miscellaneous project, wherein overhead transmission line is bigger by effect of natural conditions, such as: rainwater, hail, the loss ratio that can all lead to route It is larger;Power cable is different from trolley wire, smaller by effect of natural conditions, but with cable resistance, line media, shield All there is certain relationship in set, steel band happy dress.
Regulation in " the evaluation enterprise's rational utilization of electricity fire protection technology " that China issues, enterprises grid bus loss rate (enterprise Receiving end is to electrical equipment) index that should reach are as follows: a transformation 3.5% hereinafter, secondary transformation 5.5% hereinafter, transformation three times 7% or less.But total line loss of China's factory and enterprise internal electric network be much higher than national standard requirement, and up to 10%, verifying Up to 14~15%, therefore, to often go carry out line loss monitoring, research and analysis, take reducing loss measure very necessary.
Line loss is primarily referred to as power cable line active loss part at present, the energy loss on route line loss, For line loss percentage shared in all conveying electric energy line loss per unit, it is the economic indicator for measuring enterprises power supply. Enterprise generally uses ac power supply method, is easy to produce skin effect and kindred effect by the conducting wire of alternating current.Skin effect Examining the current density ratio of conductor cross-section central part, the current density through conducting wire edge is small, this is equivalent to the effective cross-section of conducting wire Reduce, improve conductor resistance.
Traditional method generally installs measuring instrumentss in end of incoming cables and equipment side, and system reads measuring instrumentss for a period of time Then electric energy cumulative amount data carry out simple difference and calculate the loss for being considered as this route.Conventionally, inlet wire is read End and equipment side measuring instrumentss, either manual meter reading or communication mechanism are read, and will necessarily have time difference, the data of reading It is not the data of synchronization, the data of different moments is simply sought into difference in this way, there will certainly be biggish deviation.
Summary of the invention
In order to overcome above-mentioned defect existing in the prior art, the present invention provides a kind of side of online line loss of high precision computation Method can more accurately calculate the loss of route.
In order to achieve the above objectives, a kind of the technical solution adopted by the present invention are as follows: realization side of the online line loss of high precision computation Method, electric energy meter synchronized sampling in wide scope is synchronous to calculate storage, passes through communication management unit and reads the data latched, realizes Agonic line loss function of statistic analysis.
A kind of implementation method of the online line loss of high precision computation, comprising the following steps:
Step 1: collection in worksite electric energy meter realizes data-frozen function, and guarantees that electric energy meter is in same a period of time in wide scope Between point freeze;
Step 2: after electric energy meter CPU processor receives synchronization pulse triggering, mark is set in Sampling interrupt, and open It wards off independent sampled point record storage and latches area, 1 cycle complete sample point of front is all moved and freezes sampling buffer, together Shi Jilu latches the time.Subsequent electric energy meter CPU calculates three-phase current, three-phase voltage, active using the sampling point value of the latch Power, reactive power value;
Step 3: the electric energy meter in wide scope is in the same electric degree for freezing moment K1 point and starting calculating a period of time Consumption;
Step 4: has the communication management unit of breakpoint transmission function by communication interface, by the electric energy in wide scope Electric current, voltage, power, electric degree aggregate-value for freezing in table etc. are collected into together by the communication management unit in region;
Step 5: monitoring SCADA software systems are to collecting the data (being stored in MYSQL database) come according to freezing Time reads from database, utilization preset line topological relationship, can intuitively calculate route line loss, voltage drop, Real-time current difference etc..
Load balance calculates:
I is into=I1+I2+I3+I4+ ...+IN
P is into=P1+P2+P3+P4+ ...+PN
Voltage loss
△ U=UPower end-ULoad end
Line loss calculation
Line loss per unit=(W1-W2)/W1*100%
Further, the electric energy meter, the communication interface of module and routine when increasing the school GPS on hardware have on software It is standby to support two kinds of data latch modes: pulse starting and communication broadcasting command starting when internet GPS school.
The communication management unit is ordered when realizing regularly Web broadcast school automatically, itself supports to receive correcting delay signal, Have each analog quantity electricity information storage at least 31 days, breakpoint transmission function and the new storage of preferential calling is supported to freeze to calculate Power, electric degree, electric current, voltage calculated value function.
The method of above-mentioned calculating line loss, it is further characterized by:
In step 1, the data freezed include: power, electric current, voltage real value and the freeze-off time point of synchronization A period of time electric degree aggregate-value afterwards.
In step 2, the start command that electric energy meter receives need to be set as super objective, pass through the external interrupt (IO of CPU Mouth interrupts or communicating interrupt) directly stop low-level tasks, into interrupt processing task.
In step 3, the electric degree is the aggregate-value of a period of time power: W=P △ t;△ t=(K2-K1) time exists Electric energy meter time consistency in wide scope then ensure that each table cumulative time section is identical.
Further, the communication management unit point of interruption resumes the implementation method of function are as follows: in-site collecting module is periodically called Acquired electric energy meter information, and stored in a manner of XML file, concentrated collection module receives and parses through XML file, is determining format just File is saved in real-time area, backup area after really, is write data into MYSQL database later, and delete real-time area file.
The utility model has the advantages that the present invention is joined between electric energy meter, communication management unit in a kind of simple and practical method It is dynamic, it realizes each power loop, voltage, electric current, the synchronized sampling of electricity and the measurement of wide scope, ensure that line loss calculation Accuracy.
Detailed description of the invention
Fig. 1 is system wiring schematic diagram of the invention.
Fig. 2 is the schematic diagram that electric energy meter of the invention receives trigger pulse.
Fig. 3 is electric energy meter data buffer area schematic diagram of the invention.
Fig. 4 is the increased communication protocol point table of the present invention.
Specific embodiment
For the ease of the understanding of those skilled in the art, the present invention is made further below with reference to embodiment and attached drawing Bright, the content that embodiment refers to not is limitation of the invention.
A kind of implementation method of the online line loss of high precision computation of the present embodiment, specific technology realize that steps are as follows:
Step 1: the present invention relates to collection in worksite electric energy meter, pass through and increase specific hardware device and algorithm, it is real Existing data-frozen function, and guarantee that electric energy meter freezes at same time point in wide scope, freezing data includes: synchronization A period of time electric degree aggregate-value after power, electric current, voltage real value and freeze-off time point.
Field electric energy table, the communication interface of module and routine when increasing the school GPS on hardware have two kinds of support on software Data latch mode: pulse starting or communication broadcasting command starting when internet GPS school.The starting life that field electric energy table receives It enables, super objective need to be set as, low-level tasks are directly stopped by the external interrupt (I/O port interrupts or communicating interrupt) of CPU, into Enter interrupt processing task.
Step 2: after electric energy meter CPU processor receives synchronization pulse triggering, mark is set in Sampling interrupt, and open It wards off independent sampled point record storage and latches area, 1 cycle complete sample point of front is all moved and freezes sampling buffer, together Shi Jilu latches the time.Subsequent electric energy meter CPU calculates three-phase current, three-phase voltage, active using the sampling point value of the latch Power, reactive power value.Since each electric energy meter is latched in synchronization, the electric energy meter in this way in guarantee wide scope is calculated closely The analog quantity of synchronization.
Step 3: the electric energy meter in wide scope is in the same electric degree for freezing moment K1 point and starting calculating a period of time Consumption, this period can adjust, such as 10 minutes, 1 hour or 1 day.
Electric degree is the aggregate-value of a period of time power: W=P △ t;Electricity of △ t=(K2-K1) time in wide scope Energy table time consistency then ensure that each meter cumulative time section is identical.
Step 4: having the communication management unit of breakpoint transmission function by communication interface, by the electric energy meter in wide scope In the electric current, voltage, power, the electric degree aggregate-value that freeze etc. by the communication management unit in region be collected into together, due to Data are frozen, and the delay for communicating calling has been not considered.Communication management unit supports breakpoint transmission function and preferential calling new The power calculated, the function of electric degree, electric current, voltage calculated value are freezed in storage.Specific way are as follows: the communication management unit of website The data that will be read by communication, the file table of XML are saved as according to time tag, according to current storage size, Ke Yicun Store up a month data.Central station communication management unit and website communication management unit communications, since central station needs to access region Range is wide, data in the website communication management unit more than quantity, breaks if there is some website link, after link-recovery, Stored tables of data can be recruited again and arrive central station, central station communication management unit automatic discrimination goes out the number which is amended record According to, and according to fixed format amended record into MYSQL database.
Step 5: monitoring SCADA software systems are to collecting the data (being stored in MYSQL database) come according to freezing Time reads from database, utilization preset line topological relationship, can intuitively calculate route line loss, voltage drop, Real-time current difference etc..
Load balance calculates:
I is into=I1+I2+I3+I4+ ...+IN
P is into=P1+P2+P3+P4+ ...+PN
Voltage loss
△ U=UPower end-ULoad end
Line loss calculation
Line loss per unit=(W1-W2)/W1*100%.
Above embodiment is merely illustrative of the invention's technical idea, and this does not limit the scope of protection of the present invention, all It is any changes made on the basis of the technical scheme according to the technical idea provided by the invention, each falls within present invention protection model Within enclosing.The technology that the present invention is not directed to can be realized by existing technology.

Claims (8)

1. a kind of implementation method of the online line loss of high precision computation, it is characterised in that: the electric energy meter synchronized sampling in wide scope It is synchronous to calculate storage, the data latched are read by communication management unit, realize agonic line loss function of statistic analysis.
2. the method according to claim 1, wherein including:
Step 1: collection in worksite electric energy meter realizes data-frozen function, and guarantees that electric energy meter is at same time point in wide scope Freeze;
Step 2: after electric energy meter CPU processor receives synchronization pulse triggering, setting active flag in Sampling interrupt, and It opens up independent sampled point record storage and latches area, 1 cycle complete sample point of front is all moved and freezes sampling buffer, It records simultaneously and latches the time, subsequent electric energy meter CPU calculates three-phase current using the sampling point value of the latch, three-phase voltage, has Function power and reactive power value;
Step 3: the electric energy meter in wide scope is in the same electric degree consumption freezed moment K1 point and start calculating a period of time Amount;
Step 4: the communication management unit for having breakpoint transmission function passes through communication interface, will be in the electric energy meter in wide scope Electric current, voltage, power, electric degree aggregate-value for freezing etc. are collected into together by the communication management unit in multiple regions;
Step 5: monitoring SCADA software systems are to the next data (being stored in MYSQL database) of collection according to freeze-off time It is read from database, utilization preset line topological relationship, can intuitively calculate route line loss, voltage drop, in real time Current difference etc.,
Load balance calculates:
I is into=I1+I2+I3+I4+ ...+IN
P is into=P1+P2+P3+P4+ ...+PN
Voltage loss
△ U=UPower end-ULoad end
Line loss calculation
Line loss per unit=(W1-W2)/W1*100%.
3. according to the method described in claim 1, when increasing the school GPS it is characterized by: the electric energy meter, on hardware module and Conventional communication interface has on software and supports two kinds of data latch modes: pulse starting and communication broadcast life when internet GPS school Enable starting.
4. according to the method described in claim 1, it is characterized by: the communication management unit, automatic to realize regularly network It is ordered when broadcasting school, itself supports to receive correcting delay signal, had each analog quantity electricity information storage at least 31 days, support disconnected Point resumes function and the power calculated, the function of electric degree, electric current, voltage calculated value are freezed in the new storage of preferential calling.
5. according to the method described in claim 2, it is characterized in that, in step 1:
The data freezed include: synchronization power, electric current, voltage real value and freeze-off time point after a period of time electric degree Aggregate-value.
6. according to the method described in claim 2, it is characterized in that, in step 2:
The start command that the electric energy meter receives need to be set as super objective, by the external interrupt of CPU (I/O port interrupt or Communicating interrupt) directly stop low-level tasks, into interrupt processing task.
7. according to the method described in claim 2, it is characterized in that, in step 3:
The electric degree is the aggregate-value of a period of time power: W=P △ t;Electricity of △ t=(K2-K1) time in wide scope Energy table time consistency then ensure that each table cumulative time section is identical.
8. according to the method described in claim 4, it is characterized in that, the implementation method of the breakpoint transmission function are as follows: adopt on the spot Collection module periodically calls acquired electric energy meter information, and is stored in a manner of XML file, and concentrated collection module receives and parses through XML File saves file in real-time area, backup area after judgement format is correct, writes data into MYSQL database later, and delete Except real-time area file.
CN201811398193.5A 2018-11-22 2018-11-22 Method for calculating online line loss with high precision Active CN109270360B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811398193.5A CN109270360B (en) 2018-11-22 2018-11-22 Method for calculating online line loss with high precision

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811398193.5A CN109270360B (en) 2018-11-22 2018-11-22 Method for calculating online line loss with high precision

Publications (2)

Publication Number Publication Date
CN109270360A true CN109270360A (en) 2019-01-25
CN109270360B CN109270360B (en) 2020-10-02

Family

ID=65190724

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811398193.5A Active CN109270360B (en) 2018-11-22 2018-11-22 Method for calculating online line loss with high precision

Country Status (1)

Country Link
CN (1) CN109270360B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113419189A (en) * 2020-08-06 2021-09-21 为准(北京)电子科技有限公司 Line loss testing method, comprehensive tester and storage medium

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6757628B1 (en) * 1998-07-14 2004-06-29 Landis+Gyr Inc. Multi-level transformer and line loss compensator and method
CN102497030A (en) * 2011-12-28 2012-06-13 山东电力研究院 Line-loss actual-measurement and positioning method based on high-voltage electric energy meter and system thereof
CN103310116A (en) * 2013-06-30 2013-09-18 安徽中兴继远信息技术股份有限公司 Intelligent terminal for calculating line loss of platform area, and calculating method thereof
CN103336171A (en) * 2013-06-29 2013-10-02 国家电网公司 Line loss analysis platform of electric quantity system
CN103592881A (en) * 2013-11-28 2014-02-19 广西大学 Multi-path signal synchronous sampling control circuit based on FPGA
CN204330894U (en) * 2014-12-15 2015-05-13 咸亨国际(杭州)电气制造有限公司 A kind of transformer loss proving installation
CN105842653A (en) * 2016-06-13 2016-08-10 国网江苏省电力公司电力科学研究院 Simultaneous acquisition test circuit used for electric energy and clock pulses of electric energy meter

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6757628B1 (en) * 1998-07-14 2004-06-29 Landis+Gyr Inc. Multi-level transformer and line loss compensator and method
CN102497030A (en) * 2011-12-28 2012-06-13 山东电力研究院 Line-loss actual-measurement and positioning method based on high-voltage electric energy meter and system thereof
CN103336171A (en) * 2013-06-29 2013-10-02 国家电网公司 Line loss analysis platform of electric quantity system
CN103310116A (en) * 2013-06-30 2013-09-18 安徽中兴继远信息技术股份有限公司 Intelligent terminal for calculating line loss of platform area, and calculating method thereof
CN103592881A (en) * 2013-11-28 2014-02-19 广西大学 Multi-path signal synchronous sampling control circuit based on FPGA
CN204330894U (en) * 2014-12-15 2015-05-13 咸亨国际(杭州)电气制造有限公司 A kind of transformer loss proving installation
CN105842653A (en) * 2016-06-13 2016-08-10 国网江苏省电力公司电力科学研究院 Simultaneous acquisition test circuit used for electric energy and clock pulses of electric energy meter

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113419189A (en) * 2020-08-06 2021-09-21 为准(北京)电子科技有限公司 Line loss testing method, comprehensive tester and storage medium
CN113419189B (en) * 2020-08-06 2022-02-22 为准(北京)电子科技有限公司 Line loss testing method, comprehensive tester and storage medium

Also Published As

Publication number Publication date
CN109270360B (en) 2020-10-02

Similar Documents

Publication Publication Date Title
CN102969796B (en) Near-real-time electric quantity monitoring and dispatching management system for rural power grid
CN207895024U (en) A kind of medium voltage distribution network fault fast positioning device
CN202210151U (en) System for remote checking and monitoring for electric energy metering device
CN102043115B (en) Network on-line live line measurement method for line parameter of power system
CN104076321B (en) On-line monitoring and evaluating system and method for digital electric energy meter
CN102147268B (en) Integral panoramic data recording and analyzing system
CN107680368A (en) A kind of metering device on-line monitoring and intelligent diagnosing method based on gathered data
CN201368905Y (en) Power quality monitoring and recording device of power system
CN201368904Y (en) Real-time dynamic monitoring and recording device of power system
CN110907855B (en) Distribution network line fault detection method based on comprehensive distribution box and high-voltage sensor
CN112685885A (en) Transformer area line loss analysis method for comprehensive big data analysis
CN104200314A (en) Electric quantity and line loss concurrent statistic method based on data remote synchronous acquisition technology
CN102682197A (en) Monitoring method and monitoring device for predicating change trend of energy consumption of single equipment in real time
CN110007137A (en) A kind of intelligent electric energy meter merging multiple terminal monitoring function
CN102183685A (en) Flexible wide area power grid phasor measurement method
CN101645611A (en) Self-adaptive re-sampling method for digital relay protection device
CN103529327B (en) A kind of full station equipment for monitoring power quality and monitoring method being suitable for Intelligent transformer station
CN211579700U (en) Low-voltage transformer area intelligent sensing terminal
CN109270360A (en) A kind of method of the online line loss of high precision computation
Hu et al. Research on intelligent inspection technology of distribution network based on RFID
CN109991512A (en) Based on the synchronous low-tension distribution box user's phase big data discrimination method of sudden load change
CN110726872B (en) Intelligent wiring terminal strip
CN203587709U (en) Intelligent transformer station integrated monitoring system
Zheng et al. Research on smart metering infrastructure technology based on new generation multi-core module electric energy meter and comprehensive demonstration application
CN208125808U (en) A kind of synchronized phasor line protective devices based on IEC61850 standard

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant