CN109267540A CN201811383782.6A CN201811383782A CN109267540A CN 109267540 A CN109267540 A CN 109267540A CN 201811383782 A CN201811383782 A CN 201811383782A CN 109267540 A CN109267540 A CN 109267540A
Authority
CN
China
Prior art keywords
water
solid
flood control
liquid separation
river
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201811383782.6A
Other languages
Chinese (zh)
Other versions
CN109267540B (en
Inventor
刘学应
蒋伟林
向佳佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang University of Water Resources and Electric Power
Original Assignee
Zhejiang University of Water Resources and Electric Power
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University of Water Resources and Electric Power filed Critical Zhejiang University of Water Resources and Electric Power
Priority to CN201811383782.6A priority Critical patent/CN109267540B/en
Publication of CN109267540A publication Critical patent/CN109267540A/en
Application granted granted Critical
Publication of CN109267540B publication Critical patent/CN109267540B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/04Structures or apparatus for, or methods of, protecting banks, coasts, or harbours
    • E02B3/10Dams; Dykes; Sluice ways or other structures for dykes, dams, or the like
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/16Sealings or joints
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/02Arrangement of sewer pipe-lines or pipe-line systems

Abstract

The invention discloses a kind of river flood control monitoring device and its construction methods, including flood control barricade, sealing mechanism, solid-liquid separation device and water storage system, flood control barricade is located at the upstream face top on riverbank, sealing mechanism is connected on flood control barricade, water-flowing trough is provided on the top surface on riverbank, solid-liquid separation device is provided with below water-flowing trough, solid-liquid separation device connects water storage system by water inlet pipe, and water storage system is located at the inside on riverbank.Its construction method includes: surveying and locating, water storage system construction, solid-liquid separation device construction, the installation of flood control Retaining wall, sealing mechanism and flood control monitoring device trial operation.Construction method step of the invention is simple, practical, not only can satisfy the flood control monitoring in different in width river, but also directly can carry out quick shunting processing to river water, reduces the water level in river, prevents from causing urban waterlogging.

Description

A kind of river flood control monitoring device and its construction method
Technical field
The present invention relates to a kind of river flood control monitoring device and its construction methods.
Background technique
Flood control works are for control, defending flood to reduce or remit the engineering that flood loss is built.
Flood control works in the prior art mainly have water blocking, flood discharge and retain three categories, although these flood control measures are most Direct flood control means, but require to put into a large amount of human and material resources and financial resources, and effect might not be fine, simultaneously Due to cannot quickly reduce the water level in river, it is affected caused by urban waterlogging, influence time is long.
Summary of the invention
Present invention aims at provided for deficiency of the prior art a kind of river flood control monitoring device and its The design of the technical solution of construction method, sealing mechanism can be beaten in the case where flood occurring or river water level goes up too fast It opens, so that river water is entered water storage system after solid-liquid separation device separates, so that river water is rapidly entered water storage system and shunted, mitigate Granule foreign in river water can be separated, be prevented by water level rise pressure caused by flood control barricade, solid-liquid separation device Granule foreign results in blockage to flood control monitoring device, improves flood control effect, while the river water shunted through water storage system can follow Ring utilizes, and it is simple to reduce the waste of the water resource construction method step, practical, not only can satisfy different in width river Flood control monitoring, and quick shunting processing directly can be carried out to river water, the water level in river is reduced, prevents from causing urban waterlogging.
In order to solve the above-mentioned technical problem, the present invention adopts the following technical scheme:
A kind of river flood control monitoring device, it is characterised in that: including flood control barricade, sealing mechanism, solid-liquid separation device and Water storage system, flood control barricade are located at the upstream face top on riverbank, and sealing mechanism is connected on flood control barricade, set on the top surface on riverbank It is equipped with water-flowing trough, solid-liquid separation device is provided with below water-flowing trough, solid-liquid separation device connects water storage system by water inlet pipe, Water storage system is located at the inside on riverbank;By the design of flood control barricade, can when flood occurs by river water barrier in river In road, prevent river water reverse irrigation from causing urban waterlogging, the design of sealing mechanism can go up too fast in generation flood or river water level In the case where open, make river water after solid-liquid separation device separates enter water storage system, make river water rapidly enter water storage system into Row shunt, mitigate water level go up the pressure caused by flood control barricade, solid-liquid separation device can by the granule foreign in river water into Row separation, prevents granule foreign from resulting in blockage to flood control monitoring device, improves flood control effect, while being shunted through water storage system River water can recycle, and reduce the waste of water resource.
Further, flood control barricade includes baffle, stiffening plate and guide plate, and stiffening plate is vertically set in qually spaced in the outer of baffle On side, spaced set has at least three guide plates from top to bottom between two neighboring stiffening plate, and baffle can play blocking The effect of river water, stiffening plate improve the installation strength of baffle, can resist bigger flood impact, and guide plate can incite somebody to action on quickly The river water to rise is guided to water-flowing trough, improves the shunting efficiency of river water.
Further, first sensor and second sensor are provided on the lateral surface of baffle, first sensor is located at second The lower section of sensor, first sensor and second sensor are and control room, first sensor are used for the effect of monitoring and warning, the Two sensors then play alarm function, convenient for opening sealing mechanism at the first time, the shunting of river water are realized, to reduce in river Water level.
Further, guide plate side directed downwardly is provided with arc guide groove, and arc guide groove can play the role of water conservancy diversion, make river Water rapidly enters solid-liquid separation device, while after river water and baffle collide, and prevents river water from entering road surface, and then influence city The drainage system in city.
Further, sealing mechanism includes hydraulic cylinder, water fender and telescopic rod, and hydraulic cylinder is set in qually spaced in baffle On medial surface, it is equidistantly provided with positioning box on the lateral surface of baffle, is arranged fluted on riverbank, groove is connected to water-flowing trough, Water fender limits in groove, and water fender connects hydraulic cylinder by telescopic rod, and telescopic rod runs through positioning box, passes through hydraulic oil It is mobile that cylinder can drive telescopic rod, and then water fender can be driven mobile, makes the river water higher than sealing mechanism directly through solid-liquid point Structure of disembarking enters water storage system, and groove can play position-limiting action to water fender, move horizontally water fender.
Further, solid-liquid separation device includes being separated by solid-liquid separation bucket and training for sediment pipe, is separated by solid-liquid separation bucket and is uniformly arranged on water-flowing trough Bottom surface on, and be connected to water-flowing trough, be separated by solid-liquid separation that bucket is tilted to be arranged in parallel at least two filter screens, the connection of training for sediment pipe is met The water surface and separation of solid and liquid bucket, and training for sediment pipe is located at the height of upstream face lower than the height for being separated by solid-liquid separation bucket junction, separation of solid and liquid Bucket can converge river water, improve the speed of water flow, and the solid particle polluter in river water can be filtered by filter screen, And be discharged by training for sediment pipe, improve the shunting efficiency of river water.
Further, be separated by solid-liquid separation the bottom end connection water inlet pipe of bucket, be horizontally disposed between the two neighboring water inlet pipe in left and right have it is auxiliary Assistant director of a film or play's flow tube is provided with third valve on auxiliary draft tube, by the design of auxiliary draft tube can by adjacent water inlet pipe into Row shunts, and reduces the water delivery pressure of single water inlet pipe, extends the physical life of water-supply-pipe, third valve can control water inlet pipe it Between water flow distribution.
Further, the side that training for sediment pipe is located at upstream face is rotatably connected to capping, capping can solid-liquid separation device not Stopped when work, since the pressure of river water realizes the sealing of training for sediment pipe, when solid-liquid separation device work, due to solid-liquid point Pressure from water in struggling against is greater than the pressure of water in external river, therefore capping is opened, and training for sediment pipe is discharged in solid particle polluter.
Further, water storage system includes water tank, and water tank horizontal homogeneous is arranged in riverbank, two neighboring water tank it Between be provided with major flow duct, water inlet pipe is connected to above the trailing flank of water tank, is provided with municipal administration below the leading flank of water tank Drainpipe, municipal drain are connected to city planting ductwork, and the first valve is provided on municipal drain, is arranged on the bottom surface of water tank There is groundwater drain, groundwater drain is connected to ground water regime, and the second valve, water storage are provided on groundwater drain Case can store river water, and be allocated by major flow duct, improve the processing capacity of entire flood control monitoring device, storage River water after depositing can be shunted by municipal drain and groundwater drain, convenient for the recycling of river water, reduce water The waste of resource.
Such as a kind of construction method of above-mentioned river flood control monitoring device, it is characterised in that include the following steps:
1) surveying and locating
A, the construction location for determining flood control monitoring device according to the width of riverbank upstream face first, to the top of entire upstream face Face measures setting-out, and makes corresponding arrangement and method for construction;
B, water-stop sheet then is installed in upstream face, water-stop sheet is inserted into the soil body of upstream face, the insertion depth of water-stop sheet For the overall design height of flood control monitoring device, keep water-stop sheet vertical with water (flow) direction holding;
C, steel pipe support is then installed between water-stop sheet and riverbank, is fixedly connected water-stop sheet with riverbank, and examine The leakproofness between two neighboring water-stop sheet is looked into, is drained the water between water-stop sheet and riverbank upstream face by water pump;
D, construction area delineating finally is carried out to riverbank, and the weeds in construction area is purged;
2) water storage system is constructed
A, the installation site of water tank is determined first in construction area, and determines the fitting depth and adjacent two of water tank Horizontal space between a water tank, then excavated by excavator along construction area, divide 5~8 times and excavated, every time Soil after excavation is deposited in the position left and dig 3~5m of position, is excavated to set depth, and the length of excavation is flood control monitoring dress The design length set forms strip foundation pit;
B, compacting leveling processing then is carried out to strip foundation pit, and one layer of side wall and bottom surface casting to strip foundation pit With a thickness of the concrete layer of 5~10cm, the reserving installation hole on the bottom surface of strip foundation pit and side wall;
C, the underground water for having the second valve is then installed in the mounting hole of the bottom surface spaced set of strip foundation pit Drainpipe is connected to the bottom end of groundwater drain with ground water regime, and installs end cap, edge on the top of groundwater drain Equidistant installation municipal drain below the front side wall of strip foundation pit, connect one end of municipal drain and city planting ductwork Logical, the other end installs end cap, further along installation water inlet pipe equidistant above the rear wall of strip foundation pit, makes water inlet pipe and strip The connection of shape foundation pit, and will be connected between two neighboring water inlet pipe by auxiliary draft tube, carry out encapsulation process;
D, the water tank that after the installation is completed to all groundwater drains, municipal drain and water inlet pipe, will be processed Successively it is hoisted to the setting position of strip foundation pit by hoisting machine, and by the end cap on groundwater drain and municipal drain It removes, is attached respectively with water tank, and carry out encapsulation process, while water inlet pipe being connected to water tank, and carries out Encapsulation process is checked after being connected to all groundwater drains, municipal drain, water inlet pipe with water tank;
E, it will be finally connected between two adjacent water tanks of left and right by major flow duct, and carry out encapsulation process, Soil is backfilled in strip foundation pit by excavator, until flushing with the port height of water inlet pipe, and carries out compacting processing;
3) solid-liquid separation device is constructed
A, the installation number of solid-liquid separation device is determined according to the installation site of water inlet pipe and number first, while according to row The separation of solid and liquid bucket of the design requirement selection corresponding size of water, and it is being separated by solid-liquid separation the tilted parallel installation filter screen that struggles against, edge The low one end of filter screen open up through-hole on being separated by solid-liquid separation bucket, and training for sediment pipe is installed on through-hole, training for sediment pipe goes out husky port The capping of rotation connection is installed;
B, solid-liquid separation device is successively installed on each water inlet pipe, and carries out consolidation process;
C, finally soil is backfilled with excavator, be backfilled to be separated by solid-liquid separation bucket port height position, and with tamp Machine carries out compacting processing;
4) flood control Retaining wall
The length and height of baffle are selected according to the length of strip foundation pit first, and stiffening plate is determined according to flood control rank Size, the stiffening plate processed is successively equidistantly vertically fixed on the lateral surface of baffle, it is then two neighboring in left and right Guide plate is uniformly installed from top to bottom between stiffening plate, and first sensor and the second sensing are installed on the lateral surface of baffle Device is connected to first sensor, second sensor with control room, is finally equidistantly opened up on baffle according to Design Requirement Drawing Telescopic hole continues the design height for backfilling soil to stiffening plate, and carries out compacting processing;
5) sealing mechanism is installed
Length direction first on the top surface on riverbank along strip foundation pit opens up water-flowing trough in parallel, make water-flowing trough with it is each It is separated by solid-liquid separation bucket connection, and is poured the concrete layer that a layer thickness is 5~10cm in water-flowing trough, reaches setting to concrete layer After intensity, groove is opened up along the side of water-flowing trough, and water fender is installed in groove, connects the side of water fender flexible Each telescopic rod is extended through corresponding telescopic hole by bar, and then in the top of telescopic rod, installation positioning box is sealed, then Hydraulic cylinder is successively installed along the other end of telescopic rod, hydraulic cylinder is connected to external oil-servicing facilities, finally uses excavator Continue to backfill soil to design height along the medial surface of baffle, and carries out compacting processing, while removing water-stop sheet and steel pipe support;
6) flood control monitoring device trial operation
When water level reaches the position of first sensor, early warning is monitored by control room, when water level reaches the second biography When the position of sensor, hydraulic cylinder starting is controlled by control room, and drive water fender to open by telescopic rod, make river water through logical Sink enters in separation of solid and liquid bucket, and river water enters water tank by water inlet pipe after silt is filtered, and is divided river water by water tank It is assigned to city planting ductwork or ground water regime.
The present invention is by adopting the above-described technical solution, have the advantages that
1, by the design of flood control barricade, can when flood occurs by river water barrier in river, prevent river water Reverse irrigation causes urban waterlogging.
2, the design of sealing mechanism can be opened in the case where flood occurring or river water level goes up too fast, pass through river water Enter water storage system after solid-liquid separation device separation, so that river water is rapidly entered water storage system and shunted, mitigates water level rise pair Pressure caused by flood control barricade.
3, solid-liquid separation device can separate the granule foreign in river water, prevent granule foreign from monitoring to flood control and fill It sets and results in blockage, improve flood control effect, while the river water shunted through water storage system can recycle, and reduce the wave of water resource Take.
4, construction method step of the invention is simple, practical, not only can satisfy the flood control prison in different in width river It surveys, and quick shunting processing directly can be carried out to river water, reduce the water level in river, prevent from causing urban waterlogging.
Detailed description of the invention:
The present invention will be further explained below with reference to the attached drawings:
Fig. 1 is the structural representation of flood control monitoring device in a kind of riverbank flood control monitoring device of the present invention and its construction method Figure;
Fig. 2 is the structural schematic diagram of flood control barricade in the present invention;
Fig. 3 is the connection schematic diagram of solid-liquid separation device and water storage system in the present invention.
In figure: 1- water tank;The municipal drain 2-;3- groundwater drain;4- flood control barricade;5- hydraulic cylinder;6- is logical Sink;7- groove;8- water fender;9- telescopic rod;10- is separated by solid-liquid separation bucket;11- filter screen;12- training for sediment pipe;13- capping;14- into Water pipe;15- baffle;16- stiffening plate;17- guide plate;18- positioning box;19- first sensor;20- second sensor;21- One valve;The second valve of 22-;23- major flow duct;24- auxiliary draft tube;25- third valve.
Specific embodiment
It as shown in Figure 1 to Figure 3, is a kind of river flood control monitoring device of the present invention, including flood control barricade 4, sealing mechanism, solid Liquid separator structure and water storage system, flood control barricade 4 are located at the upstream face top on riverbank, and flood control barricade 4 includes baffle 15, stiffening plate 16 and guide plate 17, stiffening plate 16 be vertically set in qually spaced on the lateral surface of baffle 15, between two neighboring stiffening plate 16 from On down spaced set have at least three guide plates 17, baffle 15 can play the role of stopping river water, and stiffening plate 16 improves The installation strength of baffle 15 can resist bigger flood impact, and the river water quickly to go up can be guided to logical by guide plate 17 Sink 6 improves the shunting efficiency of river water, and first sensor 19 and second sensor 20 are provided on the lateral surface of baffle 15, the One sensor 19 is located at the lower section of second sensor 20, and and control room, first passes for first sensor 19 and second sensor 20 Sensor 19 is used for the effect of monitoring and warning, and second sensor 20 then plays alarm function, convenient for opening sealing mechanism at the first time, Realize the shunting of river water, to reduce the water level in river, the side directed downwardly of guide plate 17 is provided with arc guide groove, and arc guide groove can To play the role of water conservancy diversion, river water is made to rapidly enter solid-liquid separation device, while after river water and baffle 15 collide, prevented River water enters road surface, and then influences the drainage system in city.
Sealing mechanism is connected on flood control barricade 4, and sealing mechanism includes hydraulic cylinder 5, water fender 8 and telescopic rod 9, hydraulic Oil cylinder 5 is set in qually spaced on the medial surface of baffle 15, is equidistantly provided with positioning box 18 on the lateral surface of baffle 15, on riverbank It is arranged fluted 7, groove 7 is connected to water-flowing trough 6, and water fender 8 limits in groove 7, and water fender 8 is connected by telescopic rod 9 Hydraulic cylinder 5, telescopic rod 9 run through positioning box 18, and it is mobile to drive telescopic rod 9 by hydraulic cylinder 5, and then can drive gear Water plate 8 is mobile, so that the river water higher than sealing mechanism is directly entered water storage system through solid-liquid separation device, groove 7 can be to water blocking Plate 8 plays position-limiting action, moves horizontally water fender 8.
Water-flowing trough 6 is provided on the top surface on riverbank, the lower section of water-flowing trough 6 is provided with solid-liquid separation device, solid-liquid separating machine Structure includes being separated by solid-liquid separation bucket 10 and training for sediment pipe 12, is separated by solid-liquid separation bucket 10 and is uniformly arranged on the bottom surface of water-flowing trough 6, and and water-flowing trough 6 connections, separation of solid and liquid bucket 10 is tilted to be arranged in parallel at least two filter screens 11, and training for sediment pipe 12 is connected to upstream face and solid-liquid point From bucket 10, and training for sediment pipe 12 is located at the height of upstream face lower than the height for being separated by solid-liquid separation 10 junctions of bucket, and being separated by solid-liquid separation bucket 10 can To converge river water, the speed of water flow is improved, the solid particle polluter in river water can be filtered by filter screen 11, and It is discharged by training for sediment pipe 12, improves the shunting efficiency of river water, the bottom end for being separated by solid-liquid separation bucket 10 connects water inlet pipe 14, left and right adjacent two Being horizontally disposed between a water inlet pipe 14 has auxiliary draft tube 24, and third valve 25 is provided on auxiliary draft tube 24, passes through auxiliary The design of diversion pipe 24 can shunt adjacent water inlet pipe 14, reduce the water delivery pressure of single water inlet pipe 14, extend defeated The physical life of water pipe, third valve 25 can control the distribution of the water flow between water inlet pipe 14, and training for sediment pipe 12 is located at upstream face Side is rotatably connected to capping 13, and capping 13 can be stopped when solid-liquid separation device does not work, due to the pressure of river water The sealing for realizing training for sediment pipe 12, when solid-liquid separation device work, the pressure due to being separated by solid-liquid separation water in bucket 10 is greater than external river The pressure of water in road, therefore cover 13 and be opened, training for sediment pipe 12 is discharged in solid particle polluter.
Solid-liquid separation device connects water storage system by water inlet pipe 14, and water storage system is located at the inside on riverbank, water storage system Including water tank 1,1 horizontal homogeneous of water tank is arranged in riverbank, is provided with major flow duct 23 between two neighboring water tank 1, Water inlet pipe 14 is connected to above the trailing flank of water tank 1, and municipal drain 2, municipal administration row are provided with below the leading flank of water tank 1 Water pipe 2 is connected to city planting ductwork, and the first valve 21 is provided on municipal drain 2, is provided with underground water on the bottom surface of water tank 1 Drainpipe 3, groundwater drain 3 are connected to ground water regime, and the second valve 22, water tank 1 are provided on groundwater drain 3 River water can be stored, and be allocated by major flow duct 23, improve the processing capacity of entire flood control monitoring device, stored up River water after depositing can be shunted by municipal drain 2 and groundwater drain 3, convenient for the recycling of river water, be reduced The waste of water resource;By the design of flood control barricade 4, can when flood occurs by river water barrier in river, prevent River water reverse irrigation causes urban waterlogging, and the design of sealing mechanism can be beaten in the case where flood occurring or river water level goes up too fast It opens, so that river water is entered water storage system after solid-liquid separation device separates, so that river water is rapidly entered water storage system and shunted, mitigate Water level goes up to pressure caused by flood control barricade 4, and the granule foreign in river water can be separated, be prevented by solid-liquid separation device Granule foreign results in blockage to flood control monitoring device, improves flood control effect, while the river water shunted through water storage system can follow Ring utilizes, and reduces the waste of water resource.
Such as a kind of construction method of above-mentioned river flood control monitoring device, include the following steps:
1) surveying and locating
A, the construction location for determining flood control monitoring device according to the width of riverbank upstream face first, to the top of entire upstream face Face measures setting-out, and makes corresponding arrangement and method for construction;
B, water-stop sheet then is installed in upstream face, water-stop sheet is inserted into the soil body of upstream face, the insertion depth of water-stop sheet For the overall design height of flood control monitoring device, keep water-stop sheet vertical with water (flow) direction holding;
C, steel pipe support is then installed between water-stop sheet and riverbank, is fixedly connected water-stop sheet with riverbank, and examine The leakproofness between two neighboring water-stop sheet is looked into, is drained the water between water-stop sheet and riverbank upstream face by water pump;
D, construction area delineating finally is carried out to riverbank, and the weeds in construction area is purged;
2) water storage system is constructed
A, the installation site of water tank 1 is determined first in construction area, and determines the fitting depth of water tank 1 and adjacent Horizontal space between two water tanks 1, then excavated by excavator along construction area, divide 5~8 times and excavated, Soil after excavating every time is deposited in the position left and dig 3~5m of position, is excavated to set depth, and the length of excavation is flood control prison The design length of device is surveyed, strip foundation pit is formed;
B, compacting leveling processing then is carried out to strip foundation pit, and one layer of side wall and bottom surface casting to strip foundation pit With a thickness of the concrete layer of 5~10cm, the reserving installation hole on the bottom surface of strip foundation pit and side wall;
C, the underground for having the second valve 22 is then installed in the mounting hole of the bottom surface spaced set of strip foundation pit Water drainpipe 3 is connected to the bottom end of groundwater drain 3 with ground water regime, and in the top installation end of groundwater drain 3 Lid makes one end and the municipal administration of municipal drain 2 along installation equidistant below the front side wall of strip foundation pit municipal drain 2 Pipe network connection, the other end install end cap, further along installation water inlet pipe 14 equidistant above the rear wall of strip foundation pit, make into water Pipe 14 is connected to strip foundation pit, and is connected to auxiliary draft tube 24 is passed through between two neighboring water inlet pipe 14, is carried out at sealing Reason;
D, after the installation is completed to all groundwater drains 3, municipal drain 2 and water inlet pipe 14, the storage that will be processed Water tank 1 is successively hoisted to the setting position of strip foundation pit by hoisting machine, and by groundwater drain 3 and municipal drain 2 On end cap remove, be attached respectively with water tank 1, and carry out encapsulation process, while water inlet pipe 14 and water tank 1 being carried out Connection, and encapsulation process is carried out, it has been connected to all groundwater drains 3, municipal drain 2, water inlet pipe 14 with water tank 1 Bi Hou is checked;
E, it finally will pass through major flow duct 23 between two adjacent water tanks 1 of left and right to be connected to, and carry out at sealing Soil, is backfilled in strip foundation pit by reason by excavator, until flushing with the port height of water inlet pipe 14, and is tamped Processing;
3) solid-liquid separation device is constructed
A, the installation number of solid-liquid separation device, while basis are determined according to the installation site of water inlet pipe 14 and number first The separation of solid and liquid bucket 10 of the design requirement selection corresponding size of displacement, and it is being separated by solid-liquid separation the tilted parallel installation filtering of bucket 10 Net 11 opens up through-hole on being separated by solid-liquid separation bucket 10 along the low one end of filter screen 11, and installs training for sediment pipe 12, training for sediment on through-hole The capping 13 for going out husky port and being equipped with rotation connection of pipe 12;
B, solid-liquid separation device is successively installed on each water inlet pipe 14, and carries out consolidation process;
C, finally soil is backfilled with excavator, be backfilled to be separated by solid-liquid separation bucket 10 port height position, and with rammer Real machine carries out compacting processing;
4) flood control Retaining wall
The length and height of baffle 15 are selected according to the length of strip foundation pit first, and is determined and is reinforced according to flood control rank The stiffening plate 16 processed is successively equidistantly vertically fixed on the lateral surface of baffle 15 by the size of plate 16, then in left and right Guide plate 17 is uniformly installed from top to bottom, and the first sensing of installation on the lateral surface of baffle 15 between two neighboring stiffening plate 16 Device 19 and second sensor 20 are connected to first sensor 19, second sensor 20 with control room, are finally wanted according to layout design It asks and equidistantly opens up telescopic hole on baffle 15, continue the design height for backfilling soil to stiffening plate 16, and carry out compacting processing;
5) sealing mechanism is installed
Length direction first on the top surface on riverbank along strip foundation pit opens up water-flowing trough 6 in parallel, makes water-flowing trough 6 and each A 10 connection of separation of solid and liquid bucket, and the concrete layer that a layer thickness is 5~10cm is poured in water-flowing trough 6, it is reached to concrete layer To after setting intensity, groove 7 is opened up along the side of water-flowing trough 6, and water fender 8 is installed in groove 7, makes the one of water fender 8 Each telescopic rod 9 is extended through corresponding telescopic hole by side connection expansion link 9, then installs positioning box in the top of telescopic rod 9 18 are sealed, and successively install hydraulic cylinder 5 then along the other end of telescopic rod 9, by hydraulic cylinder 5 and external oil-servicing facilities Connection finally continues to backfill soil to design height along the medial surface of baffle 15 with excavator, and carries out compacting processing, tears open simultaneously Except water-stop sheet and steel pipe support;
6) flood control monitoring device trial operation
When water level reaches the position of first sensor 19, early warning is monitored by control room, when water level reaches second When the position of sensor 20, hydraulic cylinder 5 is controlled by control room and is started, and drives water fender 8 to open by telescopic rod 9, is made River water enters through water-flowing trough 6 to be separated by solid-liquid separation in bucket 10, and river water passes through water inlet pipe 14 into water tank 1 after silt is filtered, and by Water tank 1 distributes river water to city planting ductwork or ground water regime.
The above is only specific embodiments of the present invention, but technical characteristic of the invention is not limited thereto.It is any with this hair Based on bright, to realize essentially identical technical effect, made ground simple change, equivalent replacement or modification etc. are all covered Among protection scope of the present invention.

Claims (10)

1. a kind of river flood control monitoring device, it is characterised in that: including flood control barricade, sealing mechanism, solid-liquid separation device and storage Water system, the flood control barricade are located at the upstream face top on riverbank, and the sealing mechanism is connected on the flood control barricade, described It is provided with water-flowing trough on the top surface on riverbank, the solid-liquid separation device, the separation of solid and liquid are provided with below the water-flowing trough Mechanism connects the water storage system by water inlet pipe, and the water storage system is located at the inside on riverbank.
2. a kind of river flood control monitoring device according to claim 1, it is characterised in that: the flood control barricade includes gear Plate, stiffening plate and guide plate, the stiffening plate are vertically set in qually spaced on the lateral surface of the baffle, it is two neighboring described plus Spaced set has at least three guide plates from top to bottom between strong plate.
3. a kind of river flood control monitoring device according to claim 2, it is characterised in that: set on the lateral surface of the baffle It is equipped with first sensor and second sensor, the first sensor is located at the lower section of the second sensor, and described first passes Sensor and the second sensor are and control room.
4. a kind of river flood control monitoring device according to claim 2, it is characterised in that: the guide plate side directed downwardly It is provided with arc guide groove.
5. a kind of river flood control monitoring device according to claim 2, it is characterised in that: the sealing mechanism includes hydraulic Oil cylinder, water fender and telescopic rod, the hydraulic cylinder are set in qually spaced on the medial surface of the baffle, the outside of the baffle It is equidistantly provided with positioning box on face, is arranged fluted on the riverbank, the groove is connected to the water-flowing trough, the water blocking Plate limits in the groove, and the water fender connects the hydraulic cylinder by telescopic rod, and the telescopic rod is through described Positioning box.
6. a kind of river flood control monitoring device according to claim 1, it is characterised in that: the solid-liquid separation device includes Be separated by solid-liquid separation bucket and training for sediment pipe, separations of solid and liquid struggles against and is uniformly arranged on the bottom surface of the water-flowing trough, and with the water-flowing trough Connection, separations of solid and liquid bucket is tilted to be arranged in parallel at least two filter screens, and the training for sediment pipe is connected to upstream face and described It is separated by solid-liquid separation bucket, and the training for sediment pipe is located at the height of upstream face lower than the height for being separated by solid-liquid separation bucket junction.
7. a kind of river flood control monitoring device according to claim 6, it is characterised in that: the bottom end for being separated by solid-liquid separation bucket The water inlet pipe is connected, being horizontally disposed between the two neighboring water inlet pipe in left and right has auxiliary draft tube, the auxiliary draft tube On be provided with third valve.
8. a kind of river flood control monitoring device according to claim 6, it is characterised in that: the training for sediment pipe is located at upstream face Side be rotatably connected to capping.
9. a kind of river flood control monitoring device according to claim 1, it is characterised in that: the water storage system includes water storage Case, the water tank horizontal homogeneous are arranged in riverbank, are provided with major flow duct between the two neighboring water tank, it is described into Water pipe is connected to above the trailing flank of the water tank, is provided with municipal drain below the leading flank of the water tank, described Municipal drain is connected to city planting ductwork, and the first valve is provided on the municipal drain, is set on the bottom surface of the water tank It is equipped with groundwater drain, the groundwater drain is connected to ground water regime, and is provided on the groundwater drain Two valves.
10. a kind of construction method of river flood control monitoring device as described in claim 1, it is characterised in that including walking as follows It is rapid:
1) surveying and locating
A, the construction location for determining flood control monitoring device according to the width of riverbank upstream face first, to the top surface of entire upstream face into Row surveying and locating, and make corresponding arrangement and method for construction;
B, water-stop sheet then is installed in upstream face, by the soil body of water-stop sheet insertion upstream face, the insertion depth of water-stop sheet is anti- The overall design height of flood monitoring device keeps water-stop sheet vertical with water (flow) direction holding;
C, steel pipe support is then installed between water-stop sheet and riverbank, is fixedly connected water-stop sheet with riverbank, and check phase Leakproofness between adjacent two water-stop sheets, is drained the water between water-stop sheet and riverbank upstream face by water pump;
D, construction area delineating finally is carried out to riverbank, and the weeds in construction area is purged;
2) water storage system is constructed
A, the installation site of water tank, and the fitting depth of determining water tank and two neighboring storage are determined first in construction area Horizontal space between water tank, then excavated by excavator along construction area, divide 5~8 times and excavated, is excavated every time Soil afterwards is deposited in the position left and dig 3~5m of position, is excavated to set depth, and the length of excavation is flood control monitoring device Design length forms strip foundation pit;
B, compacting leveling processing then is carried out to strip foundation pit, and a layer thickness is poured to the side wall and bottom surface of strip foundation pit For the concrete layer of 5~10cm, the reserving installation hole on the bottom surface of strip foundation pit and side wall;
C, the ground water drainage for having the second valve is then installed in the mounting hole of the bottom surface spaced set of strip foundation pit Pipe, is connected to the bottom end of groundwater drain with ground water regime, and installs end cap on the top of groundwater drain, along length Equidistant installation municipal drain, is connected to one end of municipal drain with city planting ductwork, separately below the front side wall of bar shaped foundation pit End cap is installed in one end, further along installation water inlet pipe equidistant above the rear wall of strip foundation pit, makes water inlet pipe and strip base Hole connection, and will be connected between two neighboring water inlet pipe by auxiliary draft tube, carry out encapsulation process;
D, after the installation is completed to all groundwater drains, municipal drain and water inlet pipe, the water tank processed is passed through Hoisting machine is successively hoisted to the setting position of strip foundation pit, and the end cap on groundwater drain and municipal drain is torn open It removes, is attached respectively with water tank, and carry out encapsulation process, while water inlet pipe being connected to water tank, and carry out close Envelope processing, after being connected to all groundwater drains, municipal drain, water inlet pipe with water tank, is checked;
E, it will be finally connected between two adjacent water tanks of left and right by major flow duct, and carry out encapsulation process, passed through Soil is backfilled in strip foundation pit by excavator, until flushing with the port height of water inlet pipe, and carries out compacting processing;
3) solid-liquid separation device is constructed
A, the installation number of solid-liquid separation device is determined according to the installation site of water inlet pipe and number first, while according to displacement Design requirement selection corresponding size separation of solid and liquid bucket, and the tilted parallel installation filter screen of struggling against is being separated by solid-liquid separation, along mistake The low one end of strainer opens up through-hole on being separated by solid-liquid separation bucket, and training for sediment pipe is installed on through-hole, and training for sediment pipe goes out husky port installation There is the capping of rotation connection;
B, solid-liquid separation device is successively installed on each water inlet pipe, and carries out consolidation process;
C, finally soil is backfilled with excavator, be backfilled to be separated by solid-liquid separation bucket port height position, and with rammer compacter into Row compacting processing;
4) flood control Retaining wall
The length and height of baffle are selected according to the length of strip foundation pit first, and determines the ruler of stiffening plate according to flood control rank It is very little, the stiffening plate processed is successively equidistantly vertically fixed on the lateral surface of baffle, then in the two neighboring reinforcement in left and right Guide plate is uniformly installed from top to bottom between plate, and first sensor and second sensor are installed on the lateral surface of baffle, is made First sensor, second sensor are connected to control room, are finally equidistantly opened up on baffle according to Design Requirement Drawing flexible Continue the design height for backfilling soil to stiffening plate, and carry out compacting processing in hole;
5) sealing mechanism is installed
Length direction first on the top surface on riverbank along strip foundation pit opens up water-flowing trough in parallel, makes water-flowing trough and each solid-liquid Separating bucket connection, and the concrete layer that a layer thickness is 5~10cm is poured in water-flowing trough, reach setting intensity to concrete layer Afterwards, groove is opened up along the side of water-flowing trough, and water fender is installed in groove, make the side connection expansion link of water fender, it will Each telescopic rod extends through corresponding telescopic hole, and then in the top of telescopic rod, installation positioning box is sealed, then along The other end of telescopic rod successively installs hydraulic cylinder, hydraulic cylinder is connected to external oil-servicing facilities, finally with excavator along gear The medial surface of plate continues to backfill soil to design height, and carries out compacting processing, while removing water-stop sheet and steel pipe support;
6) flood control monitoring device trial operation
When water level reaches the position of first sensor, early warning is monitored by control room, when water level reaches second sensor Position when, by control room control hydraulic cylinder starting, and by telescopic rod drive water fender opening, make river water through water-flowing trough Into being separated by solid-liquid separation in bucket, river water enters water tank by water inlet pipe after silt is filtered, and by water tank by river water distribute to City planting ductwork or ground water regime.
CN201811383782.6A 2018-11-20 2018-11-20 River flood prevention monitoring device and construction method thereof Active CN109267540B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811383782.6A CN109267540B (en) 2018-11-20 2018-11-20 River flood prevention monitoring device and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811383782.6A CN109267540B (en) 2018-11-20 2018-11-20 River flood prevention monitoring device and construction method thereof

Publications (2)

Publication Number Publication Date
CN109267540A true CN109267540A (en) 2019-01-25
CN109267540B CN109267540B (en) 2020-09-15

Family

ID=65189508

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811383782.6A Active CN109267540B (en) 2018-11-20 2018-11-20 River flood prevention monitoring device and construction method thereof

Country Status (1)

Country Link
CN (1) CN109267540B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110206116A (en) * 2019-06-06 2019-09-06 水利部交通运输部国家能源局南京水利科学研究院 A kind of urban flood defence early warning assisted drainage system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892649A (en) * 2010-07-08 2010-11-24 高维海 Project and method for preventing and controlling flood and drought
CN104831682A (en) * 2015-05-15 2015-08-12 上海诺山工程设计咨询有限公司 Flood storage waterlogging prevention device capable of increasing urban river channel water storage
CN106587485A (en) * 2016-11-01 2017-04-26 浙江水利水电学院 Water purifying device of regenerated water supplied lakes and construction method thereof
CN107605010A (en) * 2017-10-23 2018-01-19 沈阳建筑大学 Flood control structure for sponge urban construction
CN107858998A (en) * 2017-10-18 2018-03-30 深圳市东深工程有限公司 A kind of barricade and construction method applied to engineering flood bank reinforcing of passing the flood period

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101892649A (en) * 2010-07-08 2010-11-24 高维海 Project and method for preventing and controlling flood and drought
CN104831682A (en) * 2015-05-15 2015-08-12 上海诺山工程设计咨询有限公司 Flood storage waterlogging prevention device capable of increasing urban river channel water storage
CN106587485A (en) * 2016-11-01 2017-04-26 浙江水利水电学院 Water purifying device of regenerated water supplied lakes and construction method thereof
CN107858998A (en) * 2017-10-18 2018-03-30 深圳市东深工程有限公司 A kind of barricade and construction method applied to engineering flood bank reinforcing of passing the flood period
CN107605010A (en) * 2017-10-23 2018-01-19 沈阳建筑大学 Flood control structure for sponge urban construction

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110206116A (en) * 2019-06-06 2019-09-06 水利部交通运输部国家能源局南京水利科学研究院 A kind of urban flood defence early warning assisted drainage system

Also Published As

Publication number Publication date
CN109267540B (en) 2020-09-15

Similar Documents

Publication Publication Date Title
CN109056761A (en) Channel cleanout method
CN109722964B (en) Drainage structure of municipal road and construction method thereof
CN106087953A (en) A kind of drainage and construction method preventing and treating large-scale spoil ground, mountain area mud-rock flow
CN105804047A (en) Water drainage device and method for increasing water drainage and consolidation speed of filled sludge
CN109267540A (en) A kind of river flood control monitoring device and its construction method
CN109056879A (en) A kind of riverway sludge cleaning plant and construction method
CN109056895A (en) A kind of subsurface stormwater recovery system and its construction method
CN106759645A (en) A kind of integral type rainwater recycle stores water transfer system and its method
CN211057828U (en) Interim drainage structures is dug to earthwork packing
CN208949951U (en) A kind of riverway sludge cleaning plant
CN208949967U (en) A kind of subsurface stormwater recovery system
CN207376562U (en) A kind of key water control project that can filter silt
CN110185051A (en) Deep narrow excavation water discharge method
CN205530633U (en) Excavation section of growing up cutting drainage device
KR100964741B1 (en) Intake structure for preventing underground water pollution
CN212835459U (en) Interim drainage system of foundation ditch
CN212270979U (en) Construction structure for excavation drainage blind ditch and water collection well of foundation pit of weakly permeable stratum
CN211256853U (en) Slope wall for hydraulic engineering
CN213773717U (en) Gutter inlet
CN212561230U (en) Water drainage culvert structure
CN113175050B (en) Sponge urban rainwater collection and utilization system
CN210562520U (en) Drainage ditch suitable for household garbage pile
CN108457237B (en) Desilting and desilting dam system arrangement system and working method thereof
CN214116866U (en) Multilayer composite drainage system of abandoned slag yard
CN210946691U (en) Hydrophobic reinforced structure of hydraulic engineering bank protection

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant