CN109235729A - A kind of superimposed sheet installation check method in place - Google Patents
A kind of superimposed sheet installation check method in place Download PDFInfo
- Publication number
- CN109235729A CN109235729A CN201811109675.4A CN201811109675A CN109235729A CN 109235729 A CN109235729 A CN 109235729A CN 201811109675 A CN201811109675 A CN 201811109675A CN 109235729 A CN109235729 A CN 109235729A
- Authority
- CN
- China
- Prior art keywords
- superimposed sheet
- place
- light emitters
- receiver
- check method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/17—Floor structures partly formed in situ
-
- G—PHYSICS
- G01—MEASURING; TESTING
- G01C—MEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
- G01C15/00—Surveying instruments or accessories not provided for in groups G01C1/00 - G01C13/00
Abstract
The invention discloses a kind of superimposed sheets to install check method in place, it is therefore an objective to which existing error is larger when in place for the aobvious installation of superimposed sheet in the prior art, the slow problem of calibration speed.The present invention is the following steps are included: (1) installation positioning stirrup on all frame column reinforcing bars of each floor;(2) it by every benchmark control axis pilot measurement of bottom to each floor, and will make marks on corresponding Vierendeel girder according to the position of benchmark control axis described in every;(3) light emitters are set on this mark;(4) two center lines of the superimposed sheet are popped up on superimposed sheet;(5) receiver is set on corresponding position on centerline;(6) superimposed sheet is installed according to design requirement, when superimposed sheet installation site is accurate, receiver can receive the light issued in light emitters.Lifting of the present invention for superimposed sheet is in place.
Description
Technical field
The invention belongs to construction techniques, in particular to a kind of superimposed sheet installs Linear Positioning Accuracy Measurement Methods.
Background technique
With the continuous development of China's economy and the increasingly raising of living standards of the people, infrastructure construction especially building
The construction scale in house is increasing, for plane stiffness, anti-seismic performance and the leakage resistance energy for improving building, existing building
The structural system of object uses cast-in-situ steel reinforced concrete, but this cannot prevent armored concrete by the way of integral cast-in-situ
There is crack on plate, beam or column, it is right although these cracks not exclusively influence the integrally-built stability of building and safety
Consumer will cause the negative effect for worrying safety at cracking, while cast-in-situ reinforced concrete slab is needed since next floor
Build a large amount of brackets, be laid with pour mold, it is time-consuming and laborious, thus trend current in the industry be using superimposed sheet replace cast in place reinforced bar
Concrete slab overcomes aforementioned deficiency.
Superimposed sheet is the building slab that a kind of mode that prefabricated and cast-in-place concrete combines produces, prefabricated board with it is existing thereon
Pouring concrete layer is integrated into a whole superimposed sheet, and the main reinforcement of prefabricated board is the main reinforcement of superimposed sheet, top cast-in-place concrete layer
Negative reinforcement and distributing bar are only configured, prefabricated board is used as the bed die of cast-in-place concrete layer, it is not necessary to be cast-in-place concrete layer branch
Hold mode plate, prefabricated board bottom surface is smooth, and the ceiling (i.e. the bottom surface of superimposed sheet) of lower floor can no longer paint plastering;It is this folded
Plywood has the globality of cast-in-situ reinforced concrete slab, while it is big with rigidity, crack resistance is good, does not increase reinforcing bar consumption, section
About template, shorten the advantages that duration of entire engineering.But superimposed sheet in lifting since it is desired that primary lifting in place, is lifted into
It cannot be moved again behind position, therefore, and existing superimposed sheet is positioned by way of manually estimating.
The Chinese invention application of Publication No. CN106284787A discloses a kind of assembled overlapping board positioning method, including
Following steps:
I, installation positioning stirrup (2) on all frame column reinforcing bars (11) of each floor;
II, by every benchmark control axis (5) pilot measurement of bottom to each floor, and by the position of every axis (5)
It makes marks on the corresponding positioning stirrup (2);
III, all axis (5) are released, and check the distance between upper every of all frame columns (1) axis (5),
Angle is to meet design requirement;
IV, its two center lines (7) are popped up on having numbered every piece of prefabricated board (3);
It V, will be every according to the positional relationship of every in the design requirement center line (7) and the corresponding axis (5)
(7) bullet of center line described in item is on corresponding Vierendeel girder (4) side template;
VI, the prefabricated board (3) that reference numeral is installed according to design requirement, makes the center line (7) and frame thereon
The coincidence of the center line (7) snap the line is corresponded on beam (4) side template;
VII, fixed all prefabricated boards (3), the installation for completing prefabricated superimposed sheet are fixed.
Although the positioning of this method has used axis as benchmark, while being compareed using the center line of superimposed sheet, still,
This method is detected there is still a need for artificial using the mode of range estimation, and the error is very big, while artificial range estimation calibration is also deposited
In the disadvantage that calibration speed is slow.
Summary of the invention
It is an object of the invention to: existing error is larger when in place for the aobvious installation of superimposed sheet in the prior art, calibration
Slow-footed problem provides a kind of superimposed sheet installation check method in place.
The technical solution adopted by the invention is as follows:
A kind of superimposed sheet installation check method in place, comprising the following steps:
(1) the installation positioning stirrup on all frame column reinforcing bars of each floor;
(2) by every benchmark control axis pilot measurement of bottom to each floor, and will be according to benchmark control axis described in every
Position make marks on corresponding Vierendeel girder;
(3) light emitters are set on this mark;
(4) two center lines of the superimposed sheet are popped up on superimposed sheet;
(5) receiver is set on corresponding position on centerline;
(6) superimposed sheet is installed according to design requirement, when superimposed sheet installation site is accurate, receiver can receive light transmitting
The light issued on device.
Preferably, the light emitters are set as visible light formula laser emitter, are vertically installed on the receiver
Measure Board.
Preferably, institute's light emitters are provided with a, are respectively arranged on the connected both sides of Vierendeel girder, the reception
Device is set as two, respectively corresponds and is arranged on the center line.
Preferably, institute's light emitters are provided with a, are respectively arranged on the connected both sides of Vierendeel girder, the reception
Device is set to the point of intersection of two center lines, and the axis of the Measure Board and the angle of the benchmark control axis are °.
Preferably, institute's light emitters are set as one, and the recipient is set as reflecting mirror, the reflecting mirror
The angle of axis and the benchmark control axis is °, is additionally provided on adjacent label with the label that is provided with light emitters
Measure Board, when superimposed sheet installation site is accurate, Measure Board can receive the light that the light emitters of reflecting mirror reflection issue.
Preferably, the institute received block bottom is set as vacuum chuck.
In conclusion by adopting the above-described technical solution, the beneficial effects of the present invention are:
1, in the present invention, check method in place is installed with superimposed sheet of the present invention, the essence of superimposed sheet may be implemented
Quasi- installation positioning, improves the installation accuracy of superimposed sheet, also improves the speed of superimposed sheet installation accuracy check, improve construction
Speed reduces the duration, and then improves economic benefit.
Detailed description of the invention
Fig. 1 is the schematic top plan view of the embodiment of the present invention 1;
Fig. 2 is the schematic top plan view of the embodiment of the present invention 2;
Fig. 3 is the schematic top plan view of the embodiment of the present invention 3;
Fig. 4 is receiver schematic diagram of the invention;
Marked in the figure: 1- positioning stirrup, 2- benchmark control axis, 3- Vierendeel girder, 4- label, 5- light emitters, 6- are folded
Plywood, 7- center line, 8- receiver, 801- Measure Board, 802- vacuum chuck.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to the accompanying drawings and embodiments, right
The present invention is further elaborated.It should be appreciated that described herein, specific examples are only used to explain the present invention, not
For limiting the present invention.
Embodiment 1
A kind of superimposed sheet installation check method in place, comprising the following steps:
(1) the installation positioning stirrup 1 on all frame column reinforcing bars of each floor;
(2) by every 2 pilot measurement of benchmark control axis of bottom to each floor, and will be according to every benchmark control axis 2
Position makes marks 4 on corresponding Vierendeel girder 3;
(3) light emitters 5 are set on label 4;
(4) two center lines 7 of superimposed sheet 6 are popped up on superimposed sheet 6;
(5) receiver 8 is set on corresponding position on center line 7;
(6) superimposed sheet 6 is installed according to design requirement, when 6 installation site of superimposed sheet is accurate, receiver 8 can receive light
The light issued on transmitter (5).
Wherein, light emitters 5 are set as visible light formula laser emitter, are vertically installed with Measure Board on receiver 8
801.Light emitters 5 are provided with 2, are respectively arranged on the connected both sides of Vierendeel girder 3, and receiver 8 is set as two, respectively
It is correspondingly arranged on center line 7.
In the present embodiment, upper reinforcement is connected on each frame column reinforcing bar, each positioning stirrup is set on corresponding
On portion's reinforcing bar, and corresponding each positioning stirrup and upper reinforcement are fixedly connected with by spacer bar.In each edge of Vierendeel girder 3
The middle part of benchmark control axis 2 all done label 4, then visible light formula laser emitter is installed on label 4.It is overlapped in lifting
When plate 6, when superimposed sheet 6 hangs onto 60-80cm on Vierendeel girder 3 by tower crane, two receivers 8 are separately mounted to two by worker
On center line 7, then observe whether receive hot spot on the Measure Board 801 of recipient 8.It is carved with graduated scale on Measure Board 801, carves
Degree ruler is portrayed according to design installation requirement.During before below finally lifting and below lifting, and after the completion of lifting, work
Whether people can receive the position of hot spot and hot spot on Measure Board 801 by observation recipient to check the position of superimposed sheet 6
It is whether accurate.
Embodiment 2
A kind of superimposed sheet installation check method in place, comprising the following steps:
(1) the installation positioning stirrup 1 on all frame column reinforcing bars of each floor;
(2) by every 2 pilot measurement of benchmark control axis of bottom to each floor, and will be according to every benchmark control axis 2
Position makes marks 4 on corresponding Vierendeel girder 3;
(3) light emitters 5 are set on label 4;
(4) two center lines 7 of superimposed sheet 6 are popped up on superimposed sheet 6;
(5) receiver 8 is set on corresponding position on center line 7;
(6) superimposed sheet 6 is installed according to design requirement, when 6 installation site of superimposed sheet is accurate, receiver 8 can receive light
The light issued on transmitter (5).
Wherein, light emitters 5 are set as visible light formula laser emitter, and light emitters 5 are provided with 2, set respectively
It is placed on the connected both sides of Vierendeel girder 3, receiver 8 is set to the point of intersection of two center lines 7, the axis and benchmark of Measure Board 801
The angle of control axis 2 is 45 °.
In the present embodiment, upper reinforcement is connected on each frame column reinforcing bar, each positioning stirrup is set on corresponding
On portion's reinforcing bar, and corresponding each positioning stirrup and upper reinforcement are fixedly connected with by spacer bar.In each edge of Vierendeel girder 3
The middle part of benchmark control axis 2 all done label 4, then visible light formula laser emitter is installed on label 4, and be respectively set
At the label 4 on the both sides that Vierendeel girder 3 is connected.When lifting superimposed sheet 6, superimposed sheet 6 is hung on Vierendeel girder 3 by tower crane
When 60-80cm, two receivers 8 are separately mounted on the intersection point of two center lines 7 by worker, then observe the mark of recipient 8
Whether two hot spots are received on ruler plate 801, and ideally, two hot spots should be combined into one.It is carved on Measure Board 801
Spend ruler, graduated scale is portrayed according to design installation requirement, and preferred, also portrayed a rectangle frame on graduated scale, rectangle frame according to
Design installation requirement is portrayed.During before below finally lifting and below lifting, and after the completion of lifting, worker can lead to
Cross whether observation recipient receives hot spot, in the rectangle frame whether hot spot falls on Measure Board 801 and the quantity of hot spot comes school
Whether the position of core superimposed sheet 6 is accurate.
Embodiment 3
A kind of superimposed sheet installation check method in place, comprising the following steps:
(1) the installation positioning stirrup 1 on all frame column reinforcing bars of each floor;
(2) by every 2 pilot measurement of benchmark control axis of bottom to each floor, and will be according to every benchmark control axis 2
Position makes marks 4 on corresponding Vierendeel girder 3;
(3) light emitters 5 are set on label 4;
(4) two center lines 7 of superimposed sheet 6 are popped up on superimposed sheet 6;
(5) receiver 8 is set on corresponding position on center line 7;
(6) superimposed sheet 6 is installed according to design requirement, when 6 installation site of superimposed sheet is accurate, receiver 8 can receive light
The light issued on transmitter (5).
Wherein, light emitters 5 are set as one, and light emitters 5 are set as visible light formula laser emitter, receive
Device 8 is set as reflecting mirror, and the axis of reflecting mirror and the angle of benchmark control axis 2 are 45 °, and is provided with light emitters 5
It is additionally provided with Measure Board 801 on the adjacent label 4 of label 4, when 6 installation site of superimposed sheet is accurate, Measure Board 801 can be received instead
Penetrate the light that the light emitters 5 of mirror reflection issue.
In the present embodiment, upper reinforcement is connected on each frame column reinforcing bar, each positioning stirrup is set on corresponding
On portion's reinforcing bar, and corresponding each positioning stirrup and upper reinforcement are fixedly connected with by spacer bar.In each edge of Vierendeel girder 3
The middle part of benchmark control axis 2 all done label 4, then visible light formula laser emitter is installed wherein on a label 4.?
When lifting superimposed sheet 6, when superimposed sheet 6 hangs onto 60-80cm on Vierendeel girder 3 by tower crane, receiver 8 is mounted on two by worker
On the intersection point of center line 7, then observe on reflecting mirror whether receive hot spot, meanwhile, with the label for being provided with light emitters 5
It is also equipped with Measure Board 801 on 4 adjacent labels 4, in the ideal case, reflecting mirror should will be seen that light formula laser emitter is sent out
Light out is reflected on Measure Board 801.Graduated scale is carved on Measure Board 801, graduated scale is portrayed according to design installation requirement, and
Preferably, a rectangle frame has also been portrayed on graduated scale, rectangle frame is portrayed according to design installation requirement.Before below the final lifting with
And during lifting lower section, and after the completion of lifting, worker can be by observing whether Measure Board 801 receives hot spot, and hot spot is
Whether the position that superimposed sheet 6 is checked in the no rectangle frame fallen on Measure Board 801 is accurate.
Embodiment 4
On the basis of the above embodiments, receive seat 8 in order to facilitate worker's Fast Installation, 8 bottom of received block is set as true
Suction disk 802.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not intended to limit the invention, all in essence of the invention
Made any modifications, equivalent replacements, and improvements etc., should all be included in the protection scope of the present invention within mind and principle.
Claims (6)
1. a kind of superimposed sheet installs check method in place, which comprises the following steps:
(1) installation positioning stirrup (1) on all frame column reinforcing bars of each floor;
(2) by every benchmark control axis (2) pilot measurement of bottom to each floor, and will be according to benchmark control axis described in every
(2) position makes marks (4) on corresponding Vierendeel girder (3);
(3) light emitters (5) are set on the label (4);
(4) two center lines (7) of the superimposed sheet (6) are popped up on superimposed sheet (6);
(5) receiver (8) are set on corresponding position on center line (7);
(6) superimposed sheet (6) are installed according to design requirement, when superimposed sheet (6) installation site is accurate, receiver (8) can receive light
The light issued on line transmitter (5).
2. a kind of superimposed sheet according to claim 1 installs check method in place, it is characterised in that: the light emitters
(5) it is set as visible light formula laser emitter, is vertically installed with Measure Board (801) on the receiver (8).
3. a kind of superimposed sheet according to claim 2 installs check method in place, it is characterised in that: the light emitters
(5) 2 are provided with, is respectively arranged on Vierendeel girder (3) connected both sides, the receiver (8) is set as two, respectively corresponds
It is arranged on the center line (7).
4. a kind of superimposed sheet according to claim 2 installs check method in place, it is characterised in that: the light emitters
(5) 2 are provided with, is respectively arranged on Vierendeel girder (3) connected both sides, the receiver (8) is set to two center lines (7)
The angle of point of intersection, the axis of the Measure Board (801) and the benchmark control axis (2) is 45 °.
5. a kind of superimposed sheet according to claim 2 installs check method in place, it is characterised in that: the light emitters
(5) it is set as one, the recipient (8) is set as reflecting mirror, the axis of the reflecting mirror and the benchmark control axis (2)
Angle be 45 °, be additionally provided with Measure Board (801) on adjacent label (4) with the label (4) that is provided with light emitters (5),
When superimposed sheet (6) installation site is accurate, Measure Board (801) can receive the light that the light emitters (5) of reflecting mirror reflection issue
Line.
6. a kind of superimposed sheet according to claim 2 installs check method in place, it is characterised in that: the received block (8)
Bottom is set as vacuum chuck (802).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811109675.4A CN109235729A (en) | 2018-09-21 | 2018-09-21 | A kind of superimposed sheet installation check method in place |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811109675.4A CN109235729A (en) | 2018-09-21 | 2018-09-21 | A kind of superimposed sheet installation check method in place |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109235729A true CN109235729A (en) | 2019-01-18 |
Family
ID=65057368
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201811109675.4A Pending CN109235729A (en) | 2018-09-21 | 2018-09-21 | A kind of superimposed sheet installation check method in place |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109235729A (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111908375A (en) * | 2020-07-06 | 2020-11-10 | 中交武汉港湾工程设计研究院有限公司 | Automatic control device for loading and unloading heavy construction |
CN112629508A (en) * | 2020-12-30 | 2021-04-09 | 上海建工五建集团有限公司 | Z-axis positioning device and positioning method for stiff steel column |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1632449A (en) * | 2005-01-01 | 2005-06-29 | 武汉理工大学 | Laser vernier |
CN1912536A (en) * | 2006-08-31 | 2007-02-14 | 张奔牛 | Multi-point displacement/deflection detection and monitoring device and method |
CN105649332A (en) * | 2016-01-12 | 2016-06-08 | 广州机施建设集团有限公司 | Building beam and slab construction method |
CN106284787A (en) * | 2016-08-05 | 2017-01-04 | 成都市第四建筑工程公司 | Assembled superimposed sheet is installed and localization method |
CN107288158A (en) * | 2017-06-30 | 2017-10-24 | 上海建工集团股份有限公司 | A kind of vertical framing precast construction method of underpass open cut |
-
2018
- 2018-09-21 CN CN201811109675.4A patent/CN109235729A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1632449A (en) * | 2005-01-01 | 2005-06-29 | 武汉理工大学 | Laser vernier |
CN1912536A (en) * | 2006-08-31 | 2007-02-14 | 张奔牛 | Multi-point displacement/deflection detection and monitoring device and method |
CN105649332A (en) * | 2016-01-12 | 2016-06-08 | 广州机施建设集团有限公司 | Building beam and slab construction method |
CN106284787A (en) * | 2016-08-05 | 2017-01-04 | 成都市第四建筑工程公司 | Assembled superimposed sheet is installed and localization method |
CN107288158A (en) * | 2017-06-30 | 2017-10-24 | 上海建工集团股份有限公司 | A kind of vertical framing precast construction method of underpass open cut |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111908375A (en) * | 2020-07-06 | 2020-11-10 | 中交武汉港湾工程设计研究院有限公司 | Automatic control device for loading and unloading heavy construction |
CN112629508A (en) * | 2020-12-30 | 2021-04-09 | 上海建工五建集团有限公司 | Z-axis positioning device and positioning method for stiff steel column |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102433841B (en) | Method for installing abnormal-shape curve steel box girder | |
CN106284787B (en) | Assembled superimposed sheet is installed and localization method | |
CN109235729A (en) | A kind of superimposed sheet installation check method in place | |
CN104746884A (en) | Method for hoisting prefabricated parts of assembled building | |
CN105178604A (en) | Construction method of assembly type superimposed floor slab | |
CN102102444A (en) | Assembling and positioning construction method of large steel casting members | |
CN104573211B (en) | Steel construction detail drawing mask method based on BIM systems | |
CN112761292A (en) | Construction method for prefabricated ribbed cavity floor slab | |
CN103526930A (en) | Multi-directional intersection reinforced bare concrete inclined column construction method | |
CN110700083A (en) | Installation measurement control method for prefabricated bridge pier stud | |
CN103088843A (en) | Comprehensive pipe gallery pre-buried iron piece installing construction method | |
CN114319884A (en) | Construction method of glass curtain wall | |
CN110210166A (en) | A kind of prefabricated superimposed sheet method for splitting | |
CN105113418B (en) | A kind of bearing pad stone construction lofting method | |
CN109235730A (en) | A kind of overlapping method of plate installation | |
CN104563525B (en) | A kind of box steel arch beam Integral horizontal type group is to method | |
CN105040992B (en) | Reverse inverted-insertion type construction method for structural steel columns | |
CN111688003A (en) | Manufacturing and construction method of large curved surface special-shaped plate | |
CN114856195A (en) | Post-pouring construction method for floor slab at building pipe well | |
CN208595915U (en) | A kind of superimposed sheet fast leveling nucleus correcting system | |
CN212271652U (en) | High-speed railway simply supported case roof beam contact net built-in fitting positioner | |
CN101666145B (en) | Method for upward hanging projecting eave stones | |
CN203863275U (en) | Die frame for welding embedded bolts of railway box girder | |
CN106436735B (en) | A kind of installation method of blower foundation ring | |
CN207892083U (en) | Fabricated shear wall board bottom has height difference junction support system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190118 |
|