CN109187061A - A kind of air conditioner test system and air conditioner test method - Google Patents

A kind of air conditioner test system and air conditioner test method Download PDF

Info

Publication number
CN109187061A
CN109187061A CN201810954407.6A CN201810954407A CN109187061A CN 109187061 A CN109187061 A CN 109187061A CN 201810954407 A CN201810954407 A CN 201810954407A CN 109187061 A CN109187061 A CN 109187061A
Authority
CN
China
Prior art keywords
test
voltage
module
withstand
station
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN201810954407.6A
Other languages
Chinese (zh)
Inventor
凌勇
向远汉
赵俊权
覃兆丹
刘爽
胡建辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gree Electric Appliances Inc of Zhuhai
Gree Wuhan Electric Appliances Co Ltd
Original Assignee
Gree Electric Appliances Inc of Zhuhai
Gree Wuhan Electric Appliances Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gree Electric Appliances Inc of Zhuhai, Gree Wuhan Electric Appliances Co Ltd filed Critical Gree Electric Appliances Inc of Zhuhai
Priority to CN201810954407.6A priority Critical patent/CN109187061A/en
Publication of CN109187061A publication Critical patent/CN109187061A/en
Withdrawn legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01MTESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
    • G01M99/00Subject matter not provided for in other groups of this subclass
    • G01M99/008Subject matter not provided for in other groups of this subclass by doing functionality tests
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01MTESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
    • G01M99/00Subject matter not provided for in other groups of this subclass
    • G01M99/005Testing of complete machines, e.g. washing-machines or mobile phones
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01MTESTING STATIC OR DYNAMIC BALANCE OF MACHINES OR STRUCTURES; TESTING OF STRUCTURES OR APPARATUS, NOT OTHERWISE PROVIDED FOR
    • G01M99/00Subject matter not provided for in other groups of this subclass
    • G01M99/007Subject matter not provided for in other groups of this subclass by applying a load, e.g. for resistance or wear testing

Abstract

The present invention relates to air-conditioning production technical field, in particular to a kind of air conditioner test system and air conditioner test method.The air conditioner test system includes: that workbench described in workbench is provided with for the voltage-withstand test module and multiple test stations to air-conditioning to be measured progress voltage-withstand test;Operating test module, connecting terminal and switching switch block are provided in each described test station, the operating test module is used to carry out operating test to the air-conditioning to be measured for being located at the test station, the connecting terminal is used to connect the air-conditioning to be measured positioned at the station to be measured with to the air-conditioning conveying signal to be measured, and the switching switch block is used to control the connecting terminal and is connecting with the voltage-withstand test module and switching between connecting with the operating test module.Air conditioner test system provided by the invention effectively integrates voltage-withstand test and operating test, reduces unnecessary repetitive operation, improves work efficiency.

Description

A kind of air conditioner test system and air conditioner test method
Technical field
The present invention relates to air-conditioning production technical field, in particular to a kind of air conditioner test system and air conditioner test method.
Background technique
General air-conditioning in factory in production process, the assembling that is near completion be packaged it is offline before require to carry out voltage-withstand test with And operating two test stages of test, the only test Jing Guo two above link just can ensure that the security performance and function of air-conditioning It can be normal.
Tooling is powered on used in voltage-withstand test and operating test in the station layout tested in the related technology air-conditioning Identical, in two test stages, there are a large amount of repeating parts, complex procedures and inefficiency.
Summary of the invention
The invention discloses a kind of air conditioner test device and air conditioner test methods, for surveying voltage-withstand test process and operating Trial work sequence effectively integrates, and solves the problems, such as two testing process complex procedures repetitions and inefficiency in the prior art.
In order to achieve the above objectives, the present invention the following technical schemes are provided:
A kind of air conditioner test system, comprising: workbench, the workbench are provided with for carrying out pressure-resistant survey to air-conditioning to be measured The voltage-withstand test module and multiple test stations of examination;
Operating test module, connecting terminal and switching switch block, the fortune are provided in each described test station Transfer to test module is used to carry out the air-conditioning to be measured for being located at the test station operating test, and the connecting terminal is used for connection position In the station to be measured air-conditioning to be measured to convey signal to the air-conditioning to be measured, the switching switch block is for described in controlling Connecting terminal is connecting with the voltage-withstand test module and is switching between connecting with the operating test module.
One voltage-withstand test module of above-mentioned air conditioner test system, workbench setting corresponds to multiple test stations, when a certain A test station starting test is in the air-conditioning to be measured of the test station, and the switching switch block of the test station controls the test The connecting terminal of station connects voltage-withstand test module, and voltage-withstand test module carries out voltage-withstand test to the air-conditioning to be measured, surveys to pressure resistance Examination is completed, and switching switch block control connecting terminal connects the operating test module of the test station, operates test module to this Testing air conditioner carries out operating test.As can be seen that air conditioner test system provided by the invention is not in the case where repeating patch Switch the company of corresponding wiring terminal with operating test module in voltage-withstand test module, corresponding test station by switching switch block It connects, reduces unnecessary repetitive operation, improve work efficiency.
Optionally, each described test station is provided with test instruction input module;The air conditioner test system is also wrapped It includes:
Main control module, the main control module and the voltage-withstand test module, each described operating test module, each The switching switch block and each described test instruction input module signal connection, for defeated when receiving test instruction Confirmation needs test station to be tested when entering module input test signal, judges the whether idle of the voltage-withstand test module, if The voltage-withstand test module is idle, controls the voltage-withstand test module and carries out pressure-resistant survey to the air-conditioning to be measured of corresponding test station Examination controls the switching switch block movement of corresponding test station and controls corresponding test station after the completion of voltage-withstand test The operating test module operating test is carried out to air-conditioning to be measured.
Optionally, the main control module includes main controller and the voltage-withstand test starting group being connected with the main controller Part;
The voltage-withstand test starting component is connected with the voltage-withstand test module, for starting the voltage-withstand test mould Block.
Optionally, the main control module further includes the monitoring assembly being connected with the main controller;
The monitoring assembly is used to monitor the operating condition of the voltage-withstand test module.
Optionally, each described switching switch block includes the first switching contactor being connected with the main control module With the second switching contactor;
The connecting terminal that first switching contactor is used to control corresponding test station connects the voltage-withstand test Module;
The connecting terminal that second switching contactor is used to control corresponding test station connects the operating test Module.
Optionally, the quantity of the test station is three.
A kind of air conditioner test method, using above-mentioned technical proposal provide it is any as described in air conditioner test system to air-conditioning It is tested, comprising the following steps:
Determine the test station for needing testing air conditioner;
The switching switch block of corresponding test station controls described in the connecting terminal connection of corresponding test station Voltage-withstand test module is to carry out voltage-withstand test to the air-conditioning to be measured for being located at corresponding test station;
After the completion of voltage-withstand test, the switching switch block of corresponding test station controls the described of corresponding test station and connects Line terminals connect the operating test module to carry out operating test to the air-conditioning to be measured for being located at corresponding test station.
Optionally, when the air conditioner test system includes main control module and each described test station is provided with test When instruction input module, the determination needs the test station of testing air conditioner to include:
The test instruction input module instructs for input test and test instruction is transmitted to the master control mould Block;
The main control module judges the corresponding test station of the test instruction.
Optionally, the switching switch block of the corresponding test station controls the terminals of corresponding test station Son connects the voltage-withstand test module to before carrying out voltage-withstand test positioned at the air-conditioning to be measured of corresponding test station, further includes:
Judge whether the voltage-withstand test module is idle by the main control module;
If the voltage-withstand test module is idle, the main control module controls the switching switch block of corresponding test station It controls the connecting terminal and connects the voltage-withstand test module;
If the voltage-withstand test module operating, the main control module are controlled after waiting the voltage-withstand test module idle and are corresponded to The switching switch block of test station controls the connecting terminal and connects the voltage-withstand test module.
Detailed description of the invention
Fig. 1 is a kind of main circuit schematic diagram of air conditioner test system provided in an embodiment of the present invention;
Fig. 2 is a kind of control circuit schematic diagram of air conditioner test system provided in an embodiment of the present invention;
Fig. 3 is a kind of process of air conditioner test method implemented using air conditioner test system provided in an embodiment of the present invention Figure.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
As shown in Figure 1 to Figure 2, the embodiment of the invention provides a kind of air conditioner test systems, comprising: workbench, workbench It is provided with the voltage-withstand test module 11 and multiple test stations for carrying out voltage-withstand test to air-conditioning to be measured;Each test work It is provided in and operates test module 12, connecting terminal 13 and switching switch block, operating test module 12 is used for positioned at survey The air-conditioning to be measured of trial work position carries out operating test, and connecting terminal 13, which is used to connect, is located at the air-conditioning to be measured of station to be measured with to be measured Air-conditioning conveys signal, and switching switch block is connecting with voltage-withstand test module 11 and testing with operating for controlling connecting terminal 13 It is switched between the connection of module 12.
Voltage-withstand test module 11 herein includes voltage resistant instrument, for carrying out voltage-withstand test to air-conditioning to be measured;Operating test mould Block 12 includes operating test equipment, for carrying out operating test to air-conditioning to be measured.
Wherein, the test used time of voltage-withstand test module 11 is shorter, and the test used time for operating test module 12 is longer, in air-conditioning Test jobs in, voltage-withstand test module 11 can be integrated with multiple operating test modules 12 and carry out voltage-withstand test and operating Test improves working efficiency to save process.
In the present embodiment, the voltage-withstand test module 11 on a workbench corresponds to multiple test stations, voltage-withstand test module 11 can carry out voltage-withstand test for the air-conditioning to be measured in any one test station.To 11 pairs of setting test stations of voltage-withstand test module On air-conditioning to be measured implement voltage-withstand test after the completion of, the operating test module 12 in the setting test station is in the test station Air-conditioning to be measured carry out operating test, air-conditioning to be measured saves work in the upper completion voltage-withstand test of a station and operating test Sequence.
Wherein, the connection of voltage-withstand test module 11 and operating test module 12 and air-conditioning to be measured is all by test station Connecting terminal 13 realize.The connecting terminal 13 for connecting air-conditioning to be measured is provided in each test station, in test station When placing the air-conditioning of test in need, connecting terminal 13 is connected air-conditioning to be measured by the human world that works.When needing to carry out voltage-withstand test, Connecting terminal 13 connects voltage-withstand test module 11 and air-conditioning to be measured, when carrying out operating test, the connection fortune of connecting terminal 13 Transfer to test module 12 and air-conditioning to be measured.Connecting terminal 13 is connect with voltage-withstand test module 11, connecting terminal 13 and operating test mould The state conversion that block 12 connects is controlled by switching switch block.In test job, switching switch block controls wiring Terminal 13 switches between connection voltage-withstand test module 11 and connection operating test module 12 as needed.
Referring now to Fig. 1, the course of work of air conditioner test system provided in this embodiment is done to be discussed in detail: multiple surveys Certain setting test station in trial work position is placed with air-conditioning to be measured, air-conditioning to be measured and staff connecing the setting test station Line terminals 13 connect air-conditioning to be measured, issue test starting signal, and switching switch block control voltage-withstand test module 11 connects wiring Terminal 13 connects voltage-withstand test module 11, and voltage-withstand test module 11 carries out voltage-withstand test to air-conditioning to be measured;It is completed to voltage-withstand test, Switching switch block control voltage-withstand test module 11 disconnects with connecting terminal 13 and is switched to operating test module 12 and connect Connecting terminal 13, operating test module 12 carry out operating test to air-conditioning to be measured, and after the completion of operating test, staff disconnects and connecing The connection of line terminals 13 and air-conditioning to be measured, a test step are completed.
It should be noted that the corresponding multiple operating test modules 12 of a voltage-withstand test module 11 in the present embodiment, when certain When the air-conditioning to be measured of a test station completes voltage-withstand test and carries out operating test, voltage-withstand test module 11 can be to other another Air-conditioning to be measured in test station carries out voltage-withstand test.
As can be seen that air conditioner test system provided by the invention passes through switching switching group in the case where not repeating patch Part switches the connection that test module 12 is operated in connecting terminal 13 and voltage-withstand test module 11 or each test station, reduces Unnecessary repetitive operation, improves work efficiency.
One kind is optionally in embodiment, each above-mentioned test station is provided with test instruction input module, for inputting Test instruction;Also, air conditioner test system provided in this embodiment further include: main control module, main control module and above-mentioned pressure resistance are surveyed Die trial block 11, each operating test module 12, each switching switch block and each test instruction input module letter Number connection, for when receiving test instruction input module input test signal confirmation need test station to be tested, judgement Voltage-withstand test module 11 it is whether idle, if voltage-withstand test module 11 is idle, control 11 pairs of voltage-withstand test module corresponding test works The air-conditioning to be measured of position carries out voltage-withstand test, after the completion of voltage-withstand test, the switching switch block movement of the corresponding test station of control, And the operating test module 12 for controlling corresponding test station carries out operating test to air-conditioning to be measured.
It tests instruction input module to instruct for staff's input test, test instruction input module instructs the test It is transferred to main control module, judges test instruction from which test station by main control module identification.Survey in the present embodiment Try the start button that instruction input module can be test station.The start button can connect in the connecting terminal 13 of test station Reception survey air-conditioning when from trend main control module send test instruction, can also by staff connecting test station terminals Son 13 sends test instruction to main control module with when air-conditioning to be measured.
The setting of main control module can be realized the automation control to entire air conditioner test system, and main control module can receive The test of the test instruction input module of each test station instructs, and receives which test station order judges according to signal first Starting test, then judges whether voltage-withstand test module 11 is idle, and when voltage-withstand test module 11 is idle, main control module control is tested It instructs the switching switch block in corresponding test station to control connecting terminal 13 and connects voltage-withstand test module 11, voltage-withstand test mould Block 11 connects air-conditioning to be measured to carry out voltage-withstand test to air-conditioning to be measured;When voltage-withstand test is completed, main control module control switching is switched Component controls the switching connection operating test module 12 of connecting terminal 13, and operating test module 12 connects air-conditioning to be measured to sky to be measured Transfer in row operating test;When voltage-withstand test module 11 is in operating condition, after main control module waits 11 free time of voltage-withstand test module Above-mentioned testing and control is carried out again.
The setting of main control module and test instruction input module improves the automation of entire test macro, realizes not The automatic switchover of voltage-withstand test and operating test, improves working efficiency in the case where repetition patch cord.
In a kind of optional embodiment, main control module includes main controller and the voltage-withstand test being connected with main controller starting Component, voltage-withstand test starting component are connected with voltage-withstand test module 11.
Wherein, main controller can be PLC (Programmable Logic Controller, programmable logic controller (PLC)), Main controller and above-mentioned voltage-withstand test module 11, each operating test module 12, each switching switch block and each Test instruction input module is connected.
Main controller starts component by voltage-withstand test and starts voltage-withstand test module 11, and after the completion of voltage-withstand test, main Control device controls connecting terminal 13 by control switching switch block and connect with operating test module 12, and operating test module 12 is automatic Starting carries out operating test to air-conditioning to be measured.
Specifically, the voltage-withstand test starting component in the present embodiment includes intermediate relay, and one end of intermediate relay is used In connection main controller, the other end is for connecting voltage-withstand test module 11.
It should be noted that the main control module in the present embodiment further includes the memory module being connected with main controller, it is used for Store voltage-withstand test data and operating test data.
In a kind of optional embodiment, main control module further includes the monitoring assembly being connected with main controller;Monitoring assembly is used In the operating condition of monitoring voltage-withstand test module 11.
Monitoring assembly forms monitoring circuit, and when voltage-withstand test module 11 operates, monitoring circuit is disconnected, when voltage-withstand test module 11 is idle, and monitoring circuit closure, the main controller of main control module judges whether the monitoring circuit of monitoring assembly is closed to judge pressure resistance Whether test module 11 is idle, if monitoring circuit is closed, main control module controls connecting terminal 13 and the pressure resistance of corresponding test station The connection of test module 11 carries out voltage-withstand test.
In a kind of optional embodiment, each switching switch block includes that the first switching being connected with main control module connects Tentaculum and the second switching contactor;The connecting terminal 13 that first switching contactor is used to control corresponding test station connects described resistance to Press test module 11;Second switching contactor is used to control the connection operating test mould of connecting terminal 13 of corresponding test station Block 12.
In the present embodiment, the corresponding multiple operating test modules 12 of a voltage-withstand test module 11, wherein multiple operating tests The quantity of module 12 is determined by voltage-withstand test and the duration of operating test, to realize efficient test work with optimal number proportion Make.As a kind of preferred embodiment, there are three the test station settings of a workbench in the present embodiment, i.e. a pressure resistance The corresponding three operatings test of test module 11, at work, as soon as the corresponding workbench of a staff, can test three Air-conditioning to be measured on station carries out supervision test, improves working efficiency.
Specifically, a kind of electrical principle main circuit diagram of the hollow commissioning test system of embodiment as shown in Figure 1, K1, K3, K5 are First switch controller, for controlling the connection of voltage-withstand test module 11 Yu connection terminal, K2, K4, K6 are the second switching control Device, for controlling the connection of operating test module 12 and connection terminal, K7 is that voltage-withstand test starts component, is used for voltage-withstand test mould The starting of block 11, K8 are monitoring assembly, for monitoring the closing or opening of monitoring circuit and feeding back signal to main control module.It is right The course of work of the air conditioner test system is illustrated, when to the first test station air-conditioning to be measured carry out voltage-withstand test, K1 closure connecting terminal 13 connect with voltage-withstand test module 11 (meanwhile other first switching contactors disconnection, i.e., K2, K3, K5 break Open), the starting of K7 closure voltage-withstand test module 11 (in the process, if the second test station is in the operating test of a upper circulation, K4 closure, if the second test station is idle, K4 is disconnected;If third test station is in the operating test of a upper circulation, K6 is closed, If third test station is idle, K4 is disconnected);When the air-conditioning to be measured to the first test station carries out operating test, K2 is closed wiring Terminal 13 is connect with operating test module 12, and K1 is disconnected, if the second test station or third test station start one at this time The test of new circulation instructs, K3 or K5 closure, the test of 11 second test station of voltage-withstand test module or third test station In circulation.
The control circuit part of the electrical principle of the hollow commissioning test system of above-described embodiment as shown in Figure 2, when pressing first The start button SB1 of test station, main controller first judge whether the signal X3 of monitoring assembly K8 is closed, just if it is closed state The test logic of the first test station, first main controller output signal Y0 can be started, connect the first switching contactor K1 coil, the The contact of one switching contactor K1 is by the connecting terminal 13 of the connection of voltage-withstand test module 11 to the first test station, master control Device exports Y6 pulse, connects voltage-withstand test and starts component K7, controls pressure resistance by the contact that voltage-withstand test in Fig. 1 starts component K7 Test module 11 starts voltage-withstand test, and the signal X3 of monitoring assembly is disconnected automatically at this time, completes monitoring assembly to voltage-withstand test For X3 signal by turn on automatically (voltage-withstand test module 11 enters the wait state of starting test next time), main controller judges automatically disconnection While Y0, Y1 is exported, the second switching contactor K2 coil is connected, by the contact of the second switching contactor K2 in Fig. 1 by the The connecting terminal 13 of one test station is switched in running testing system, and running testing system will start automatically, is completed operating and is surveyed Enter test next time after examination to wait.
As the start button SB2 for pressing the second test station, main controller first judges whether the signal X3 of monitoring assembly K8 closes It closes, the test logic of the first test station, first main controller output signal Y2 can be started if it is closed state, connect first The connection of voltage-withstand test module 11 to first is tested work by the contact of switching contactor K3 coil, the first switching contactor K3 The connecting terminal 13 of position, main controller export Y6 pulse, connect voltage-withstand test and start component K7, are started by voltage-withstand test in Fig. 1 The contact control voltage-withstand test module 11 of component K7 starts voltage-withstand test, and the signal X3 of monitoring assembly is disconnected automatically at this time, to resistance to By turn on automatically, (voltage-withstand test module 11 enters starting test next time and waits shape the X3 signal of pressure test completion monitoring assembly State), while main controller judges automatically disconnection Y2, Y3 is exported, the second switching contactor K4 coil is connected, and passes through in Fig. 1 second The connecting terminal 13 of first test station is switched in running testing system by the contact of switching contactor K4, running testing system It will start automatically, be waited after completing operating test into test next time.
As the start button SB3 for pressing third test station, main controller first judges whether the signal X3 of monitoring assembly K8 closes It closes, the test logic of the first test station, first main controller output signal Y4 can be started if it is closed state, connect first The connection of voltage-withstand test module 11 to first is tested work by the contact of switching contactor K5 coil, the first switching contactor K5 The connecting terminal 13 of position, main controller export Y6 pulse, connect voltage-withstand test and start component K7, are started by voltage-withstand test in Fig. 1 The contact control voltage-withstand test module 11 of component K7 starts voltage-withstand test, and the signal X3 of monitoring assembly is disconnected automatically at this time, to resistance to By turn on automatically, (voltage-withstand test module 11 enters starting test next time and waits shape the X3 signal of pressure test completion monitoring assembly State), while main controller judges automatically disconnection Y4, Y5 is exported, the second switching contactor K6 coil is connected, and passes through in Fig. 1 second The connecting terminal 13 of first test station is switched in running testing system by the contact of switching contactor K6, running testing system It will start automatically, be waited after completing operating test into test next time.
As follows to other label declarations in Fig. 1 and Fig. 2: L is firewire, and N is zero curve, and PE is ground wire, and SS is main controller (PLC) input polarity confirms terminal.
On the basis of the above embodiments, it as shown in figure 3, the embodiment of the present invention also provides a kind of air conditioner test method, adopts Air-conditioning is tested with any air conditioner test system provided by the above embodiment, comprising the following steps:
Step S1 determines the test station for needing testing air conditioner;
The switching switch block of step S2, corresponding test station control pressure resistance described in the connecting terminal 13 of corresponding test station Test module 11 is to carry out voltage-withstand test to the air-conditioning to be measured for being located at corresponding test station;
Step S3, after the completion of voltage-withstand test, the switching switch block control correspondence test station of corresponding test station is connect The connection of line terminals 13 operating test module 12 is to carry out operating test to the air-conditioning to be measured for being located at corresponding test station.
In step sl, if judging, voltage-withstand test module 11 is in operating condition, needs to wait voltage-withstand test module 11 empty Test jobs are carried out after spare time.Also, the judgement of test station can be and manually carry out being also possible to automatically control.
When the air conditioner test system includes main control module and each test station is provided with test instruction input module When, above-mentioned steps S1 determines that the test station for needing testing air conditioner includes:
Step S11, test instruction input module instruct for input test and test instruction are transmitted to main control module;
Step S12, the corresponding test station of main control module judgement test instruction.
On the basis of above-described embodiment, the switching switch block of corresponding test station controls connecing for corresponding test station Before line terminals 13 connect voltage-withstand test module 11 to carry out voltage-withstand test to the air-conditioning to be measured for being located at corresponding test station, also wrap It includes:
Step S10: judge whether voltage-withstand test module 11 is idle by main control module;
If voltage-withstand test module 11 is idle, the switching switch block that main control module controls corresponding test station controls terminals Son 13 connects voltage-withstand test module 11;
If voltage-withstand test module 11 operates, control module controls corresponding test station after waiting 11 free time of voltage-withstand test module Switch switch block control connecting terminal 13 and connects voltage-withstand test module 11.
With the air conditioner test method flow diagram that Fig. 3 is provided, the air-conditioning that air conditioner test system provided in this embodiment is implemented Test method is done to be discussed in detail.
When being placed with air-conditioning to be measured, and the connecting terminal 13 of the first test station in three the first test stations of test station It is connected with air-conditioning to be measured, presses the start button of the first test station, main controller judges that the state of voltage-withstand test module 11 is The no free time, when voltage-withstand test module 11 is idle, main controller starts the test logic of the first test station, sends instructions to first and cuts Changing-over tentaculum, the first switching contactor obtain it is electric, control connecting terminal 13 connect voltage-withstand test module 11, at this time main controller transmission refer to Enabling intermediate relay starting voltage-withstand test module 11, (at this point, the monitoring circuit of monitoring assembly disconnects, main controller judgement obtains resistance to Press test module 11 in running order), voltage-withstand test module 11 carries out pressure resistance to the air-conditioning to be measured in the first test station It tests, (at this point, the monitoring circuit of monitoring assembly is closed, main controller judgement obtains voltage-withstand test module 11 after the completion of voltage-withstand test It is in idle condition), voltage-withstand test module 11 enters test next time and waits;Main controller sends instructions to the second switching contact Device, the second switching contactor obtain it is electric, control connecting terminal 13 connection operating test module 12, operating test module 12 automatically start Operating test is carried out to air-conditioning to be measured.When main controller judges the state operating of voltage-withstand test module 11, whole system waits pressure resistance Test module carries out operation after 11 free time.
Above-mentioned first test station refers to test instruction at first by the received station of main controller, and main controller can only be at one Time point can only receive a test instruction, and multiple test instructions are sent, and main controller can be ranked up according to time order and function, example Such as, the first test station voltage-withstand test complete, the air-conditioning in the first test station also in operating test step in, master control Device can control voltage-withstand test module 11 and dock the second test station to the air-conditioning to be measured progress pressure resistance in the second test station Test.Such control mode, is utilized the time difference of voltage-withstand test and operating test, and a staff can monitor simultaneously Three test stations, have saved process and human cost, have improved work efficiency.
Obviously, those skilled in the art can carry out various modification and variations without departing from this hair to the embodiment of the present invention Bright spirit and scope.In this way, if these modifications and changes of the present invention belongs to the claims in the present invention and its equivalent technologies Within the scope of, then the present invention is also intended to include these modifications and variations.

Claims (9)

1. a kind of air conditioner test system characterized by comprising workbench, the workbench are provided with for air-conditioning to be measured Carry out the voltage-withstand test module and multiple test stations of voltage-withstand test;
Operating test module, connecting terminal and switching switch block, the operating is provided in each described test station to survey Die trial block is used to carry out the air-conditioning to be measured for being located at the test station operating test, and the connecting terminal is located at institute for connecting The air-conditioning to be measured of station to be measured is stated so as to the air-conditioning conveying signal to be measured, the switching switch block is for controlling the wiring Terminal is connecting with the voltage-withstand test module and is switching between connecting with the operating test module.
2. air conditioner test system according to claim 1, which is characterized in that each described test station is provided with test Instruction input module;The air conditioner test system further include:
Main control module, the main control module and the voltage-withstand test module, each described operating test module, described in each Switch switch block and each described test instruction input module signal connection, receives test instruction input mould for working as Confirmation needs test station to be tested when block input test signal, the whether idle of the voltage-withstand test module is judged, if described Voltage-withstand test module is idle, controls the voltage-withstand test module and carries out voltage-withstand test to the air-conditioning to be measured of corresponding test station, to After the completion of voltage-withstand test, controls the switching switch block movement of corresponding test station and control the institute of corresponding test station It states operating test module and operating test is carried out to air-conditioning to be measured.
3. air conditioner test system according to claim 2, which is characterized in that the main control module include main controller and with The voltage-withstand test that the main controller is connected starts component;
The voltage-withstand test starting component is connected with the voltage-withstand test module, for starting the voltage-withstand test module.
4. air conditioner test system according to claim 3, which is characterized in that the main control module further includes and the master control The monitoring assembly that device is connected;
The monitoring assembly is used to monitor the operating condition of the voltage-withstand test module.
5. air conditioner test system according to claim 2, which is characterized in that each described switching switch block include with The first switching contactor and the second switching contactor that the main control module is connected;
The connecting terminal that first switching contactor is used to control corresponding test station connects the voltage-withstand test module;
The connecting terminal that second switching contactor is used to control corresponding test station connects the operating test module.
6. air conditioner test system according to any one of claims 1-5, which is characterized in that the quantity of the test station It is three.
7. a kind of air conditioner test method, which is characterized in that using the air conditioner test system pair as described in any one of claim 1-6 Air-conditioning is tested, comprising the following steps:
Determine the test station for needing testing air conditioner;
The connecting terminal that the switching switch block of corresponding test station controls corresponding test station connects the pressure resistance Test module is to carry out voltage-withstand test to the air-conditioning to be measured for being located at corresponding test station;
After the completion of voltage-withstand test, the switching switch block of corresponding test station controls the terminals of corresponding test station The son connection operating test module is to carry out operating test to the air-conditioning to be measured for being located at corresponding test station.
8. air conditioner test method according to claim 7, which is characterized in that when the air conditioner test system includes master control mould When block and each described test station are provided with test instruction input module, the determination needs the test work of testing air conditioner Position includes:
The test instruction input module instructs for input test and test instruction is transmitted to the main control module;
The main control module judges the corresponding test station of the test instruction.
9. air conditioner test method according to claim 7, which is characterized in that the switching of the corresponding test station is opened It closes component and controls the connecting terminal connection voltage-withstand test module of corresponding test station to positioned at corresponding test station Air-conditioning to be measured carry out voltage-withstand test before, further includes:
Judge whether the voltage-withstand test module is idle by the main control module;
If the voltage-withstand test module is idle, the main control module controls the switching switch block control of corresponding test station The connecting terminal connects the voltage-withstand test module;
If the voltage-withstand test module operating, the main control module control corresponding test after waiting the voltage-withstand test module idle The switching switch block of station controls the connecting terminal and connects the voltage-withstand test module.
CN201810954407.6A 2018-08-21 2018-08-21 A kind of air conditioner test system and air conditioner test method Withdrawn CN109187061A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810954407.6A CN109187061A (en) 2018-08-21 2018-08-21 A kind of air conditioner test system and air conditioner test method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810954407.6A CN109187061A (en) 2018-08-21 2018-08-21 A kind of air conditioner test system and air conditioner test method

Publications (1)

Publication Number Publication Date
CN109187061A true CN109187061A (en) 2019-01-11

Family

ID=64919158

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810954407.6A Withdrawn CN109187061A (en) 2018-08-21 2018-08-21 A kind of air conditioner test system and air conditioner test method

Country Status (1)

Country Link
CN (1) CN109187061A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109781450A (en) * 2019-03-14 2019-05-21 格力电器(武汉)有限公司 For detecting the security performance of air-conditioning and the test macro of function
CN113251578A (en) * 2021-04-14 2021-08-13 格力电器(武汉)有限公司 Multifunctional test process line automatic switching method, electronic equipment and storage medium

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201489050U (en) * 2009-06-12 2010-05-26 福建捷联电子有限公司 Automatic distributor for power voltage-resistant earthing test instruments
CN101753227A (en) * 2008-11-28 2010-06-23 英华达(上海)科技有限公司 Radio frequency (RF) testing system and method for testing RF of multiple mobile communication devices
CN104569504A (en) * 2013-10-24 2015-04-29 珠海格力电器股份有限公司 Test device
CN107328592A (en) * 2017-06-26 2017-11-07 珠海格力电器股份有限公司 Air conditioner test method, device, system and processor, storage medium
CN108088696A (en) * 2017-12-15 2018-05-29 格力电器(武汉)有限公司 A kind of outdoor machine of air-conditioner tests system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101753227A (en) * 2008-11-28 2010-06-23 英华达(上海)科技有限公司 Radio frequency (RF) testing system and method for testing RF of multiple mobile communication devices
CN201489050U (en) * 2009-06-12 2010-05-26 福建捷联电子有限公司 Automatic distributor for power voltage-resistant earthing test instruments
CN104569504A (en) * 2013-10-24 2015-04-29 珠海格力电器股份有限公司 Test device
CN107328592A (en) * 2017-06-26 2017-11-07 珠海格力电器股份有限公司 Air conditioner test method, device, system and processor, storage medium
CN108088696A (en) * 2017-12-15 2018-05-29 格力电器(武汉)有限公司 A kind of outdoor machine of air-conditioner tests system

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109781450A (en) * 2019-03-14 2019-05-21 格力电器(武汉)有限公司 For detecting the security performance of air-conditioning and the test macro of function
CN113251578A (en) * 2021-04-14 2021-08-13 格力电器(武汉)有限公司 Multifunctional test process line automatic switching method, electronic equipment and storage medium

Similar Documents

Publication Publication Date Title
CN101566849B (en) Functional parameter test system for automobile electronic controller and test method thereof
CN109187061A (en) A kind of air conditioner test system and air conditioner test method
CN105807155A (en) Testing device and method for power cut and starting of electric devices
CN108632120A (en) Intelligent test device based on vehicle-mounted CAN network and test method
CN107544048B (en) Acquire fault identification module automatic detection device and detection method
CN111220827A (en) Automatic plugging and unplugging test method and control device
CN212568999U (en) Charging interface test structure, test device and test system
CN109655101B (en) Intelligent torque and rotation speed measurement and control system and test method
CN210668925U (en) Communication harness, simulation test equipment and system
CN115219250A (en) Motor train unit power vehicle IO loop test method
CN107885190A (en) A kind of electric automobile function test system
CN112834853A (en) Device and method for detecting electrical function of vehicle door
CN209894904U (en) New forms of energy electric automobile subassembly aging testing device that charges
CN105045198B (en) The automatic detection cabinet of the total wire box of integrated type elevator
CN209294018U (en) A kind of energy-saving control device for air compressor
CN102087527B (en) Backup auto-switching logic testing method for checking changeover manner of power transmission line
CN111551800A (en) Test device and test method
CN111123023A (en) Intelligent fault detector for vacuum excrement collector of railway carriage
CN218037773U (en) Fault test equipment of controller and fault test system of controller
CN105403792A (en) Solid state power distribution device reset function testing system and testing method
CN215180595U (en) ECU function test and aging test integrated test device
CN215449973U (en) Motor controller detection device
CN215932102U (en) Line testing device
CN214184118U (en) Testing device and assembly line system for electrical parts
CN114509656B (en) Intelligent detection system for IGBT driving single board

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20190111